SOP for Calibration of Infrared Moisture Balance
Standard operating procedure to calibrate the infrared moisture balance comparing with LOD at 105 deg.C.
1.0  OBJECTIVE 

       To calibrate the equipment for reliable and accurate results.

2.0  SCOPE

       This procedure is applicable to infrared moisture balance, installed in quality control department.   

3.0  RESPONSIBILITY

3.1  Doing      : Technical Assistant


3.2  Checking : Executive /Manager

4.0  ACCOUNTABILITY

       Head of the Department

5.0  PROCEDURE

       Frequency : Once in a three month

5.1  Operate the instrument as per SOP.


5.2  Set the temperature by ‘voltage regulator knob’.
5.3  After fifteen minute, observe the temperature and record it in annexure.
5.4  Select any raw material like starch or any inprocess granules sample. Carry out LOD at 105oC. Calculate and record % LOD in annexure‐I
5.5  For same sample perform its LOD in the infrared moisture balance at the same temperature and record  the result in annexure.
5.6  The performance of the instrument is satisfactory if  the observed % L.O.D. difference between the oven and I.R.balance is within the tolerance limit of
10 % of  the % LOD observed in oven, otherwise follow the S.O.P.

6.0  ABBREVIATIONS

6.1  %  = Percentage
6.2  LOD = Loss on drying
6.3  I.R. = Infra red

Ankur Choudhary is India's first professional pharmaceutical blogger, author and founder of Pharmaceutical Guidelines, a widely‐read pharmaceutical
blog since 2008. Sign‐up for the free email updates for your daily dose of pharmaceutical tips.
Email: info@pharmaguideline.com. Need Help: Ask Question

© 2015 All rights reserved to Ankur Choudhary and data may not be reproduced on other websites. Designed by Pharmaceutical Guidelines.
Privacy Policy Disclaimer

http://www.pharmaguideline.com/2011/10/sop­for­calibration­of­infrared.html 1/1

You might also like