You are on page 1of 1

AACE INTERNATIONAL PERFORMANCE AND PRODUCTIVITY MANAGEMENT

total scope of an activity consists of a number of equal or on some measure of production. It also can be used on
nearly equal parts, and status is logically determined by some tasks for which the start/finish method is appro-
counting parts completed and comparing that to the priate. Percent complete at any point in time is found by
total number of parts in the total activity. Ideally, each dividing hours (or dollars) spent to date by the current
unit is of relatively short duration. In engineering, a pos- estimate of hours (or dollars) at completion. This
sible application is in the writing of a number of specifi- method is useful on any project where non-production
cations of a given type where all specifications are con- accounts (such as overhead) must be statused individu-
sidered to have essentially equal weight. In construction ally and summarized with production accounts to deter-
it is useful in activities such as earthwork, concrete work, mine the overall percent complete.
and wire pulling.
5. Supervisor Opinion—This is a subjective evaluation of
2. Incremental Milestone—This method is appropriate for percent complete and should be used only where more
activities of significant duration that are composed of discrete methods cannot be used. There is a natural ten-
easily recognized, sequential subactivities. Percentage dency to over-estimate the level of completion of an
completion values are established based on the effort activity in its early stages.
estimated to be required at each milestone point relative
to the total for the activity. This method is ideal for con- 6. Weighted or Equivalent Units—This method is applica-
trol of engineering drawings and can be used in pro- ble where the task is a major effort involving a long peri-
curement. A typical example for drawing control is: od of time and composed of two or more overlapping
subtasks, each with a different unit of measurement (e.g.,
Start drafting 0 percent each, yd3). To set this up all subtasks are listed along
Drawn, not checked 20 percent with their respective units of measure and quantities.
Complete for office check 35 percent The subtasks are then weighted using relative work-
To owner for approval 70 percent hours as weighting standards—the total of all weights
First issue 90 percent equals 1.00 or 100 percent. The progress of each subtask
Final issue100 percent is reported using one of the five measurement tech-
niques described previously. When this percentage is
Vessel installation and assembly is a classic example in multiplied by that subtask's weighting factor, its contri-
construction. For example: bution to overall task completion is calculated. Those for
all subtasks are added to give the overall percent com-
Received and inspected 15 percent pletion of the major activity. A classic example is con-
Setting complete 35 percent crete placement, which is frequently estimated and
Alignment complete 50 percent reported in terms of cubic yards in place; it can be broken
Internals installed 75 percent up into the subtasks of base preparation, forming, resteel
Testing complete 90 percent installation, concrete placement, curing, form stripping,
Accepted by owner 100 percent and patching. Another example is steel erection, which
is traditionally estimated and controlled in terms of tons
3. Start/Finish Percentages—This method is applicable to of steel. The process is illustrated in Table 17.1.
activities that lack readily definable intermediate mile-
stones and/or the effort/time required is very difficult to Productivity Measurement of Individual Work Tasks
estimate. For these tasks, controllers credit 20-50 percent Owners and contractors are always interested in comparing
when the activity is started and 100 percent when fin- actual field productivity to that estimated and budgeted.
ished. The reason that a percentage is assigned for start- When dealing with a single work activity, the calculation of
ing is to compensate for the period between start and fin- productivity is very simple:
ish when no credit is being given. In engineering, this
method is appropriate for work such as planning, productivity = (number of units completed) ÷ (work-
designing, manual writing, model building, and studies. hours consumed)
It also can be used for specification writing. In construc-
tion it is appropriate in any situation where scheduling is What is more difficult is the calculation of productivity at a
detailed with multiple, short-term tasks. summary level or for an entire project.
4. Ratio—This method is applicable to tasks such as project
Productivity Analysis at a Summary Level
management, constructability studies, project controls,
While a comparison of earned to actual workhours is used by
and comparable activity that involve a long period of
some practitioners to provide an evaluation of productivity
time, have no particular end product, and are estimat-
at a summary level, that approach is valid only if actual
ed and budgeted on a bulk allocation basis rather than

17.9

You might also like