THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,

SPAOH, BETONG DIVISION, SARAWAK

1.0 GENERAL REPORT INFORMATION

1.1 Introduction

This monthly report has been prepared with the objective of outlining the
progress of works for the construction and completion of the proposed
Kampung Bungin extension, Spaoh, Betong Division, Sarawak for the
contract period from 5th July 2018 to 25th July 2019.

1.2 Project Description

Jabatan Tanah Dan Servei Sarawak intents to extend the existing Kampung
Bungin at Spaoh, Betong Division, Sarawak. The project site (Kampung
Bungin) can be accessed by road from Betong Town.

The total length of the access road is approximately 1.75km. The carriageway
for the access road shall be 7.0m and 5.5m wide for two ways traffic with 3m
and 1.5m wide earth shoulders on both sides. The carriageway shall be of
stone surfacing. 0.9m wide earth drains to be constructed on both side of the
roads. An approximate length of 97m of HDPE culverts are also to be
constructed. The total length of the water supply pipeline is approximately
1.77 km, consisting of HDPE and DI pipes.

1.3 Scope of Works

The main works to be executed under this contract as described and


implied by the Specification and Drawing includes:
a) Site Clearing, Earthworks and Roadworks.
b) Grubbing of tree stumps if tree is encountered.
c) Supply and Laying Non-Woven Geotextile.
d) Supply, Delivery Spread And Compact To Formation Level
Imported Suitable Materials.
e) Supply and Construct Road Structure.
f) Supply and Erect Road Furniture and Road Marking.
g) Drainage and Drainage Structures Works.
1
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

h) Environment Management.
i) Provision and Maintenance of S.O Facilities
j) Any Works Incidental to and Necessary for Completion of The
Specified Works.

1.4 Contract Particulars

Project Tittle: The Construction and Completion of The


Proposed Kampung Bungin Extension,
Spaoh, Betong Division, Sarawak
LS/PJ/4/2018

Superintending Officer (S.O): Jabatan Tanah Dan Survei, Sarawak


S.O’s Representative (S.O.R): PU Engineering Sdn Bhd
Contractor: Great Singai Construction.
Site Office Address: 2nd floor, New Township Phase 3,
SL.49/21075, Jalan Assan, 95700,
Betong, Sarawak.
Original Contract Sum: RM 2,931,000.00
Contract Period: Fifteen (15) Months
Commencement Date: 05 July 2018
Completion Date: 04 October 2019
Defects Liability Period: Twelve (12) Months
Defects Liability Period: Two (2) Months
(For Remedial Works)
Liquidated & Ascertained Damages: At the rate of 0.0219% at Contract Sum
Minimum Amount of Interim Payment: RM 100,000.00

2
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

1.5 Project Organisation Chart

Project Director
Ir. Tan Kee Beng

Resident Engineer
(Part Time)
Nur Hisyam
013-8396465

Clerk of Work
(Full Time)
Jolly Ong Soon Keng
016-5895155

3
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

2.0 WORKS PROGRESS

2.1 Work Progress Generally


In this section of Progress Report No.1, the work progress for period
05.07.18 to 25.07.18 is herewith reported. The works carried out
during this period consist of the preliminaries and general works, site
clearing and surveyor works.

2.2 Preliminaries and General Works


i. Contract All Risk and Workman Compensation Insurance
policies have been submitted. (28/6/18)
ii. Works programme and project organization chart have been
submitted. (24/7/18 and 6/7/18)
iii. CIDB Levy has been paid. (22/6/18)
iv. Boundary and Topography survey, building pegs setting out by
licensed surveyor.

4
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

2.3 Financial Progress Report Table

5
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

2.4 Physical Progress Report Table

6
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

2.5 Progress Report Summary

2.5.1 Contract Time Lapsed:


Time Lapsed (Days) Percentage (%)
20 Days out of 376 Days 5.32%

2.5.2 Financial Progress


Progress End of This Period End of Last Period Ref. Programme &
Remarks
Scheduled = 2.59% - Rev.0 dd
Actual = 2.38% -
This Reporting = 2.38% -
Status = -0.21% -

2.5.3 Physical Progress


Progress End of This Period End of Last Period Ref. Programme &
Remarks
Scheduled = 0.34 % - Rev.0 dd
Actual = 0.11% -
This Reporting = 0.11% -
Status = -0.27% -

7
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

2.5.4 Itemised Work Progress

Item Description Work Done (%)


Up to Current Total to
Last Report Date
Report
1.0 SITE CLEARING, EARTHWORK AND ROADWORKS
SURVEY AND SETTING OUT WORKS 0 20% 20%
SITE CLEARING, EARTHWORK AND ROADWORKS
1.1 SUPPLY AND LAYING NON-WOVEN GEOTEXTILE
ROAD 1
ROAD 5
ROAD 4
ROAD 2
ROAD 3
ROAD 6
ROAD 7
ROAD 8
1.2 SUPPLY, DELIVERY SPREAD AND COMPACT TO 0
SURCHARGE LEVEL IMPORTED SUITABLE MATERIALS
ROAD 1
ROAD 5
ROAD 4
ROAD 2
ROAD 3
ROAD 6
ROAD 7
ROAD 8
1.3 SUPPLY AND LAY 250MM THICK ROAD SUBBASE 0
ROAD 1
ROAD 5
ROAD 4
ROAD 2
ROAD 3

8
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

ROAD 6
ROAD 7
ROAD 8
1.4 SUPPLY AND LAY 150MM THICK ROAD SUBBASE 0
ROAD 1
ROAD 5
ROAD 4
ROAD 2
ROAD 3
ROAD 6
ROAD 7
ROAD 8
2.0 DRAINAGE AND DRAINAGE STRUCTURES 0
2.1 DRAINS
EARTH DRAIN
PILING WORKS
75MM DIA BAKAU PILE FOR CULVERT WING WALL
2.2 CULVERTS
CULVERT NO. 9 SINGLE 2.1M DIA HDPE PIPE CULVERT
CULVERT NO. 8 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 7 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 3 SINGLE 0.9M DIA HDPE PIPE CULVERT
CULVERT NO. 6 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 5 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 4 SINGLE 0.9M DIA HDPE PIPE CULVERT
CULVERT NO. 2 SINGLE 0.9M DIA HDPE PIPE CULVERT
CULVERT NO. 1 SINGLE 0.9M DIA HDPE PIPE CULVERT
3.0 WATER RETICULATION 0
WATER SUPPLY

9
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

3.0 CONTRACTUAL ISSUES

No contractual issues affecting the progress of project were encountered so


far.

4.0 CRITICAL ISSUES

No critical issues so far.

5.0 CONCLUSION

The contract period lapsed is 5.32%. The achieved financial progress is 2.38%
against the scheduled financial progress of 2.59% (0.21% delay). As for the
physical progress, the actual work done is 0.11% against the scheduled
physical progress of 0.34% (0.23% delay). The main cause of delay is due to
delay arrival of the excavators to site on 25th July 2018 when it is scheduled to
arrive on 16th July 2018.

10
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix A – Site and Locality Plan

11
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Figure 1: Site and Locality Plan

12
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix B – Work Programme

13
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix C – Financial S-Curve and


Detailed Breakdown

14
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

15
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix D – Physical S-Curve and


Detailed Breakdown

16
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

17
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix E – Contractor’s Manpower


Record

18
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Manpower Type Date 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25


Day Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Site Supervisor 1 1 1 1 1 1 1 1 1 1
3 Surveyor 1 1 1 1 1 1 1 1 1 1
4 Excavator Operator 1 1
5 Roller Operator
6 General Workers
7 Barbender
8 Carpenter
9 Concretor
10 Lorry Driver
11 Watchman 1 1 1 1 1 1 1 1 1 1

Legendary:
Sunday

Public Holiday

19
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix F – Contractor’s Plant and


Machinery Record

20
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

No. Manpower Type Date 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25


Day Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed
1 SK200 Excavator 1
No1
2 SK300 Excavator
No2
3 Dump Truck/Lorry
4 Concrete Mixer
5 20 Ton Compactor
Roller
6 Motor Grader
7 Bulldozer

Legendary:
Sunday

Public Holiday

21
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Appendix G - Photographs

22
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Figure 2: Site Office at Betong Town

Figure 3: Site Office at Betong Town

23
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Figure 4: Path Clearing for Surveyor Work on Site

Figure 5: Path Clearing for Surveyor Work on Site

24
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Figure 6: Transportation and Excavation Work on Site

Figure 7: Pegging Work by Surveyor on Site

25
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Figure 8: Points Marking by Surveyor on Site

Figure 9: Temporary Benchmark 1 Used on Site


26
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK

Figure 10: Temporary Benchmark 2 Used on Site

Figure 11: Intersection Point Pegging on Site