CAPEX PROJECT
August 30, 2018 (WK # 33- August 9-15, 2018)
1.0 SAFE MAN-HOUR MONITORING
1.1 Average Manpower Week # 33 RJAC=28 HAMMER HEAD= 19 SL TEMP= 2 CME= 10 ARCGEN=7 TEEM= 2
RJAC 33 Ongoing manual chipping of the ground for construction of oil and water separator beside at EP area, continues CHB laying for
construction of oil and water separator at the motorpol, plastering of column inside coal storage, excavation at the V- canal and
installation of forms for construction of oil and water separator at the OLD warehouse.
HAMMER HEAD/EFK 22 Fabrication of cladding, installation of stiffener, stud, Rockwool fiber insulation and aluminum cladding on the ducting at the ID fan
and dismantling of scaffold.
CME 16 Installation of railings at the Pre-heater rice husk and installation of guarding at the pack house Silo.
ARCGEN 14 Dismantling of steel forms, spreading of base course, ongoing leveling and ground compaction for pavement the logistic parking.
TEEM INC 8 Full welding and installation of platform at the EP drag chain.
UPSKILL INC 2 Safety inspector and coordinator between the contractors and SCC technical Dept. and EHS Dept.
Weather Status:
Sunny Cloudy to Rainy Cloudy Rainy
CAPEX PROJECT activity:
Ongoing CHB laying for Ongoing installation of forms Full welding the installed Fabrication of cladding- Manual
construction of oil and water and rebar for construction of oil structural support and HAMMER HEAD (EFK) excavation/digging
separator at the motorpol-RJAC and water separator at the Old bracing on the platform-TEEM works for construction of
warehouse-RJAC INC oil and water separator
beside EP area-RJAC