You are on page 1of 4

New Tower Crane Review Performance Standard

Now In Effect – What It Means To You!


On July 1, 2016, regulatory amendments by the Professional Engineers Ontario (PEO) came into effect
that require engineers performing tower crane inspections to follow a new Performance Standard called
“Review of Tower Cranes As Required By The Occupational Health And Safety Act”.

The PEO regulatory amendments were supposed to become effective at the same time as amendments
to the OHSA Regulations for Construction Projects. But that didn’t happen. The PEO Regulation came
out first and is now in effect, while the amendment to the OHSA Regulation is still waiting to pass and
may take another year or so to come into effect. So now the two regulations that were supposed to
work together in harmony are now somewhat inconsistent.

The expected revisions to the OHSA include new requirements for the engineer to verify that the entire
crane is safe for use – not just the structure, as is currently specified in the Construction Regulations. In
response, the new engineering Performance Standard dictates the steps needed to complete a full
review of the crane’s structural, mechanical, electrical, and controls components.

QUICK FACT:

 Performance Standards included in the regulations under the Professional Engineers Act are a
minimum standard that engineers must follow in carrying out their duties. Failure to do so can
be considered Professional Misconduct and is subject to discipline by the PEO, up to and
including possible suspension or revocation of the engineer’s license.

So What Does This Mean?


Until the tower crane amendments to the Construction Regulations pass and take force, the law still
requires that only the crane structure be inspected by the engineer.

While the engineer does have to follow the Performance Standard when carrying out the work, that only
pertains to the scope of work that the engineer is undertaking. So, to meet current requirements under
sections 158 and 159 of the Construction Regulations, the engineer need only cover the structural
elements of the crane as laid out in the Performance Standard.

The engineer would only have to carry out all the other elements of the Performance Standard (ie.
mechanical, electrical, and controls) if the scope of the review covered the entire crane. This can
happen, for example, if there is an order by the Ministry of Labour for an engineer to provide a report
stating that the tower crane “is unlikely to endanger a worker”. In this case, the engineer would be
required to verify all elements of the crane, not just the structure, and the Performance Standard would
need to be fully met.
How Will This Be Enforced?
Given the current disconnect between the OHSA Regulation and the PEO Regulation, there is a question
of how the MOL and the PEO will enforce violations of the new Performance Standard by an engineer.

We wanted to be sure, so we contacted high ranking individuals within both bodies to verify our own
conclusions. We will keep our sources anonymous as we haven’t asked permission to quote anyone.

Our source at PEO confirmed that violations of the Performance Standard would be enforced if a
complaint was made and the engineer was found guilty of failing to comply with the Standard. Simple
and understandable.

Our source at MOL indicated that they had not yet come to any conclusions but expected that they
would not be enforcing the Performance Standard as it is not part of the OHSA regulations and
therefore, not part of their jurisdiction. We then asked whether MOL was likely to make a complaint to
PEO if they felt that an engineer violated the Performance Standard. The answer was yes, that was a
possibility.

Both bodies agreed that the scope of work would dictate how much of the Performance Standard
needed to be met. Thus the engineer would not be guilty of a violation if electrical and control systems
were not checked where the job was only to inspect the structure.

So the next question was, where does structural end and mechanical begin. To that, the MOL source
was not clear. The tone of the message was that it depends on whether there is an incident and the
particulars of the incident.

For example, the Performance Standard has very specific requirements for the engineer to review bolt
torqueing on the turntable bolts and the tower mast bolts. These include the use of calibrated
torqueing equipment, something that is not common on all job sites right now. If a turntable bolt failure
were to occur, the argument could be made that this is a structural element, not a mechanical element,
and thus failure to review it as stipulated in the Performance Standard is a violation of PEO’s regulations.
In this circumstance, MOL may choose to make a complaint to PEO, possibly resulting in discipline for
the engineer.

Similar arguments could be made for other elements covered in the Performance Standard. This puts
the engineer in an uncertain position right now while the two regulations are not aligned. Some
engineers may consider the bolts to be structural parts of the crane, others not. Same with the
foundation, tie in’s to the building, wire ropes, etc.

Does This Mean Any Changes For The Tower Crane Owner / Operator?
Well, yes and no.

The Construction Regulations don’t change yet, and the MOL’s enforcement of them won’t change yet.
So there isn’t any direct OHSA change on constructors yet.

You still only have to call the engineer in to do structural NDT inspections prior to erection, and
structural visual inspections post erection and annually thereafter.
However, the engineer may want to do things a little differently to ensure compliance with the
Performance Standard and that may mean some changes, depending on your engineer and what they
were doing before July 1.

What Changes For The Structural Review?


The Performance Standard provides requirements for an extensive document review prior to any review
work by the engineer. These are to include a review of the manufacturer’s manual, structural inspection
criteria and repair procedures by the manufacturer, the crane log book and maintenance records, bolt
torque records, manufacturer bulletins, etc. Thus, you may find your engineer will want to review these
documents in greater detail as part of the structural inspection from now on.

The Standard then breaks down requirements for review prior to erection, after erection, and when
climbing a crane. The last item should not have any effect until implementation of the OHSA regulatory
amendments.

Prior to erection, the requirement is to perform a visual inspection of all structural components and also
a NDT inspection where deemed necessary by the engineer. Any NDT performed as part of the
structural review will now have to be performed by CGSB certified technicians under the Performance
Standard requirements. This closes a loophole in the OHSA Regulation where NDT is specified as a
requirement, but only “methods approved by CGSB” needed to be used, effectively allowing unqualified
personnel to perform NDT work.

Quick Fact:

 The engineer’s report must now include the name and qualifications of the personnel
performing NDT inspections. This personnel must be CGSB certified to comply with the
Performance Standard.

When it comes to the Post Erection inspection, the engineer is now required to verify verticality of the
tower crane and review the erector’s report, including bolt torqueing data.

The engineer must climb the crane and access any areas with suitable access platforms and guardrails as
part of the post erection inspection. Long distance inspections using binoculars from the parking lot will
not be acceptable!

The Performance Standard makes a point of the fact that an engineer can designate a competent person
to do any of the tasks in the review provided it is prudent to do so and there is adequate supervision by
the engineer. The method of supervision is not defined though.

Summary
The new engineering Performance Standard largely doesn’t affect the construction industry directly as
yet, however, it will have some effect through possible changes in the way engineers carry out their
reviews.

If and when the amendments to the Regulations for Construction Projects pass and become effective,
the review of tower cranes will become more demanding, covering the mechanical, electrical, and
controls components of tower cranes in addition to the structure. Some cranes out there right now may
not be able to pass without extensive work and/or engineering. Implementation of this Performance
Standard is the only a first step towards tightening up tower crane safety. Tower crane owners and
operators would be wise to review the engineers Performance Standard as well as stay on top of
upcoming legislation so as to stay ahead of the curve.

The engineer’s Performance Standard for “Review of Tower Cranes as Required by the Occupational
Health and Safety Act” can be found by following this link:

http://www.peo.on.ca/index.php/ci_id/29691/la_id/1.htm

About the author:

Dennis Domenichini, P.Eng. participated on the Tower Crane Legislative Review Committee throughout
its activity and contributed to the development of PEO’s Performance Standard for the review of tower
cranes.