3.01 SUMMARY OF BENDING MOMENTS AND SHEAR FORCES AT VARIOUS SECTIONS FOR PRECAST GIRDER
For Loading diagram refer Section 2.2(a) udl due to Selfweight = 1.870 t/m
Lifting Points Lifting Points
Secction d from Supports
Section L/3
R = 18.61 t R = 18.61 t
19.90 m
Section L/4
Section L/2 For Regular Supports For lifting points
PRECAST GIRDER
6 Bottom - Left - Tapper 1 A6 175 200 35000 0.5 17500.0 266.7 4.67E+06 1.40E+09 8.33E-02 1.17E+08 3.65E+08 4.81E+08 CORRECT AREA CODES
7 Bottom - Right - Tapper 1 A7 175 200 35000 0.5 17500.0 266.7 4.67E+06 1.40E+09 2.78E-02 3.89E+07 3.65E+08 4.03E+08
8 Bottom - Left - Rectangle 2 A8 0 150 0 1.0 0.0 275.0 0.00E+00 0.00E+00 2.78E-02 0.00E+00 0.00E+00 0.00E+00 A1
9 Bottom - Right - Rectangle 2 A9 0 150 0 1.0 0.0 275.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00
10 Top - Left - Fillet A10 0 0 0 0.5 0.0 630.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00
11 Top - Right - Fillet A11 0 0 0 0.5 0.0 630.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00 STANDARD
12 Top - Left - Rectangle 1 A12 187.5 150 28125 1.0 28125.0 805.0 2.26E+07 2.81E+04 131.0 3.68E+06 6.33E+08 2.78E-02 1.76E+07 4.37E+09 4.38E+09 CROSS SECTION
13 Top - Right - Rectangle 1 A13 187.5 150 28125 1.0 28125.0 805.0 2.26E+07 2.81E+04 131.0 3.68E+06 6.33E+08 2.78E-02 1.76E+07 4.37E+09 4.38E+09
14 Top - Left - Tapper 1 A14 187.5 100 18750 0.5 9375.0 696.7 6.53E+06 9.38E+03 -10.7 -1.00E+05 1.88E+08 8.33E-02 1.56E+07 7.65E+08 7.81E+08 A2 A3
A6 A7
15 Top - Right - Tapper 1 A15 187.5 100 18750 0.5 9375.0 696.7 6.53E+06 9.38E+03 -10.7 -1.00E+05 1.88E+08 8.33E-02 1.56E+07 7.65E+08 7.81E+08 A A
16 Top - Left - Rectangle 2 A16 0 100 0 1.0 0.0 680.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00 A4 8 9 A5
17 Top - Right - Rectangle 2 A17 0 100 0 1.0 0.0 680.0 0.00E+00 0.00E+00 2.78E-02 0.00E+00 0.00E+00 0.00E+00
-1000 -500 0 500 1000
18 Web - Top - ( @ Cover Plank) A18 1330 65 86450 1.0 86450.0 912.5 7.89E+07 3.65E+08 2.78E-02 1.01E+07 2.17E+10 2.18E+10 1500
19 Deck slab A19 1525 220 335500 1.0 335500.0 1055.0 3.54E+08 3.36E+05 316.0 1.06E+08 1.62E+10 8.33E-02 1.35E+09 4.82E+10 4.95E+10
20 Length of Girder ( in metre) 13.64 Precast alone S: 508450.0 6.30E+07 8.75E+06 5.58E+10
21 Thickness of Cover plank ( mm ) 0 Total section S: 843950.0 4.71E+08 1.15E+08 1.41E+11
RESULTS :
1000
SI NO DESCRIPTION UNIT PRECAST COMPOSITE
1 Weight of Girder tons 14.186 26.155
2 Area of Girder m2 0.4160 0.7670
3 C.G. -- Ybottom m 0.4110 0.6760 0.5260
4 C.G. -- Ytop (Girder) m 0.4690 0.2040
500
5 C.G. -- Ytop (Deck) m 0.4260 GIVEN CROSS SECTION
6 Moment of Inertia : IXX m4 0.0320 0.0973
7 Section Modulus :Zbottom m3 0.0779 0.1439
8 Section Modulus :Ztop (Girder) m3 0.0682 0.4770
9 Section Modulus :Ztop (Deck) m3 0.2284 0
I & T SECTIONS -SUPPORT SECTION PROPERTIES
Si.No. Description Area Breadth Depth Factor Area Y bot A * Y bot Acc ycg,cc aypcc
of Components Code (mm) (mm) (mm) (mm) (mm )
2
(mm) (mm3) (mm)
1 Web (Total Height) A1 650 880 572000 1.0 572000.0 440.0 2.52E+08 1.42E+05 109.0 1.54E+07 4.43E+11
2 Bottom - Left - Fillet A2 0 0 0 0.5 0.0 450.0 0.00E+00 0.00E+00
3 Bottom - Right - Fillet A3 0 0 0 0.5 0.0 450.0 0.00E+00 0.00E+00
4 Bottom - Left - Rectangle 1 A4 0 300 0 1.0 0.0 150.0 0.00E+00 0.00E+00
5 Bottom - Right - Rectangle 1 A5 0 300 0 1.0 0.0 150.0 0.00E+00 0.00E+00
6 Bottom - Left - Tapper 1 A6 0 150 0 0.5 0.0 350.0 0.00E+00 0.00E+00
7 Bottom - Right - Tapper 1 A7 0 150 0 0.5 0.0 350.0 0.00E+00 0.00E+00
8 Bottom - Left - Rectangle 2 A8 0 150 0 1.0 0.0 375.0 0.00E+00 0.00E+00
9 Bottom - Right - Rectangle 2 A9 0 150 0 1.0 0.0 375.0 0.00E+00 0.00E+00
10 Top - Left - Fillet A10 0 0 0 0.5 0.0 780.0 0.00E+00 0.00E+00
11 Top - Right - Fillet A11 0 0 0 0.5 0.0 780.0 0.00E+00 0.00E+00
12 Top - Left - Rectangle 1 A12 150 0 0 1.0 0.0 880.0 0.00E+00 0.00E+00 218.0 0.00E+00 0.00E+00
13 Top - Right - Rectangle 1 A13 150 0 0 1.0 0.0 880.0 0.00E+00 0.00E+00 218.0 0.00E+00 0.00E+00
14 Top - Left - Tapper 1 A14 150 0 0 0.5 0.0 880.0 0.00E+00 0.00E+00 218.0 0.00E+00 0.00E+00
15 Top - Right - Tapper 1 A15 150 0 0 0.5 0.0 880.0 0.00E+00 0.00E+00 218.0 0.00E+00 0.00E+00
16 Top - Left - Rectangle 2 A16 0 100 0 1.0 0.0 830.0 0.00E+00 0.00E+00
17 Top - Right - Rectangle 2 A17 0 100 0 1.0 0.0 830.0 0.00E+00 0.00E+00
18 Web - Top - ( @ Cover Plank) A18 350 65 22750 1.0 22750.0 912.5 2.08E+07 9.61E+07
19 Deck slab A19 1800 220 396000 1.0 396000.0 1055.0 4.18E+08 3.96E+05 328.0 1.30E+08 1.92E+10
20 Length of Girder ( in metre) 9 Precast alone S: 594750.0 1.05E+08 1.54E+07
21 Thickness of Cover plank ( mm ) 0 Total section S: 990750.0 6.17E+08 1.45E+08
RESULTS :
SI NO DESCRIPTION UNIT PRECAST COMPOSITE
1 Weight of Girder tons 12.510 21.488
2 Area of Girder m2 0.5560 0.9550
3 C.G. -- Ybottom m 0.4310 0.6630 0.5130
4 C.G. -- Ytop (Girder) m 0.4490 0.2170
5 C.G. -- Ytop (Deck) m 0.4380 1.1010
6 Moment of Inertia : IXX m4 0.0342 0.1089
7 Section Modulus :Zbottom m3 0.0794 0.1643
8 Section Modulus :Ztop (Girder) m3 0.0762 0.5018
9 Section Modulus :Ztop (Deck) m3 0.2486
4.42E+02 Bf
factor MISelf AYbot2 MI @ CG DECK SLAB
A19
(mm) (mm4) (mm4) (mm4)
8.33E-02 3.69E+10 4.63E+07 3.70E+10 COVER PLANK A18 A20
2.78E-02 0.00E+00 0.00E+00 0.00E+00 A12 A13
A16 A17
2.78E-02 0.00E+00 0.00E+00 0.00E+00
A14 A15
8.33E-02 0.00E+00 0.00E+00 0.00E+00 A10 A11
8.33E-02 0.00E+00 0.00E+00 0.00E+00
VIEW THE PICTURE @ 100 % TO GET
PRECAST GIRDER
8.33E-02 0.00E+00 0.00E+00 0.00E+00 CORRECT AREA CODES
1000
500
GIVEN CROSS SECTION
0
I & T SECTIONS -- MID SECTION PROPERTIES Bf
Si.No. Description Area Breadth Depth Factor Area Y bot A * Y bot factor MISelf AYbot2 MI @ CG DECK SLAB
A19
of Components Code (mm) (mm) (mm) (mm) (mm2) (mm) (mm3) (mm) (mm) (mm4) (mm4) (mm4)
1 Web (Total Height) A1 275 880 242000 1.0 242000.0 440.0 1.06E+08 1.02E+04 93.5 9.51E+05 1.87E+11 8.33E-02 1.56E+10 2.04E+08 1.58E+10 COVER PLANK A18 A20
2 Bottom - Left - Fillet A2 0 0 0 0.5 0.0 350.0 0.00E+00 0.00E+00 2.78E-02 0.00E+00 0.00E+00 0.00E+00 A12 A13
A16 A17
3 Bottom - Right - Fillet A3 0 0 0 0.5 0.0 350.0 0.00E+00 0.00E+00 2.78E-02 0.00E+00 0.00E+00 0.00E+00
A14 A15
4 Bottom - Left - Rectangle 1 A4 175 200 35000 1.0 35000.0 100.0 3.50E+06 1.40E+09 8.33E-02 1.17E+08 3.39E+09 3.50E+09 A10 A
5 Bottom - Right - Rectangle 1 A5 175 200 35000 1.0 35000.0 100.0 3.50E+06 1.40E+09 8.33E-02 1.17E+08 3.39E+09 3.50E+09 11
VIEW THE PICTURE @ 100 % TO GET
PRECAST GIRDER
6 Bottom - Left - Tapper 1 A6 175 200 35000 0.5 17500.0 266.7 4.67E+06 1.40E+09 8.33E-02 1.17E+08 3.65E+08 4.81E+08 CORRECT AREA CODES
7 Bottom - Right - Tapper 1 A7 175 200 35000 0.5 17500.0 266.7 4.67E+06 1.40E+09 2.78E-02 3.89E+07 3.65E+08 4.03E+08
8 Bottom - Left - Rectangle 2 A8 0 150 0 1.0 0.0 275.0 0.00E+00 0.00E+00 2.78E-02 0.00E+00 0.00E+00 0.00E+00 A1
9 Bottom - Right - Rectangle 2 A9 0 150 0 1.0 0.0 275.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00
10 Top - Left - Fillet A10 0 0 0 0.5 0.0 630.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00
11 Top - Right - Fillet A11 0 0 0 0.5 0.0 630.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00 STANDARD
12 Top - Left - Rectangle 1 A12 187.5 150 28125 1.0 28125.0 805.0 2.26E+07 2.81E+04 112.0 3.15E+06 6.33E+08 2.78E-02 1.76E+07 4.37E+09 4.38E+09 CROSS SECTION
13 Top - Right - Rectangle 1 A13 187.5 150 28125 1.0 28125.0 805.0 2.26E+07 2.81E+04 112.0 3.15E+06 6.33E+08 2.78E-02 1.76E+07 4.37E+09 4.38E+09
14 Top - Left - Tapper 1 A14 187.5 100 18750 0.5 9375.0 696.7 6.53E+06 9.38E+03 -29.7 -2.78E+05 1.88E+08 8.33E-02 1.56E+07 7.65E+08 7.81E+08 A2 A3
A6 A7
15 Top - Right - Tapper 1 A15 187.5 100 18750 0.5 9375.0 696.7 6.53E+06 9.38E+03 -29.7 -2.78E+05 1.88E+08 8.33E-02 1.56E+07 7.65E+08 7.81E+08 A A
16 Top - Left - Rectangle 2 A16 0 100 0 1.0 0.0 680.0 0.00E+00 0.00E+00 8.33E-02 0.00E+00 0.00E+00 0.00E+00 A4 8 9 A5
17 Top - Right - Rectangle 2 A17 0 100 0 1.0 0.0 680.0 0.00E+00 0.00E+00 2.78E-02 0.00E+00 0.00E+00 0.00E+00
-1000 -500 0 500 1000
18 Web - Top - ( @ Cover Plank) A18 1330 65 86450 1.0 86450.0 912.5 7.89E+07 3.65E+08 2.78E-02 1.01E+07 2.17E+10 2.18E+10 1500
19 Deck slab A19 1800 220 396000 1.0 396000.0 1055.0 4.18E+08 3.96E+05 297.0 1.18E+08 1.92E+10 8.33E-02 1.60E+09 5.19E+10 5.35E+10
20 Length of Girder ( in metre) 13.64 Precast alone S: 508450.0 6.30E+07 6.70E+06 5.58E+10
21 Thickness of Cover plank ( mm ) 0 Total section S: 904450.0 4.86E+08 1.24E+08 1.50E+11
RESULTS :
1000
SI NO DESCRIPTION UNIT PRECAST COMPOSITE
1 Weight of Girder tons 14.186 27.689
2 Area of Girder m2 0.4160 0.8120
3 C.G. -- Ybottom m 0.4110 0.6930 0.5430
4 C.G. -- Ytop (Girder) m 0.4690 0.1870
500
5 C.G. -- Ytop (Deck) m 0.4070 GIVEN CROSS SECTION
6 Moment of Inertia : IXX m4 0.0320 0.1017
7 Section Modulus :Zbottom m3 0.0779 0.1468
8 Section Modulus :Ztop (Girder) m3 0.0682 0.5439
9 Section Modulus :Ztop (Deck) m3 0.2499 0
FRICTION AND SLIP LOSSES CALCULATION
CALCULATION OF SLIP LOSSES FOR CABLES WITH PARABOLIC VERTICAL CURVE STRESSED FROM
ONE SIDE
CABLE NO : 1 Bearing center
0.150 m 10.900 m
4.827 ° CL of Symmetry
0.500 m
Y
X 0.155 m
0.500 m 7.170 m 3.500 m
Straight Profile Parabolic Profile Straight Profile
GENERAL DETAILS OF CABLE Diff. b/w start & end point of parabole in Y axis =
Ultimate Stress in Cable = 1860 MPa 0.437 - 0.155 = 0.303 m
Area of Cable = 1184.4 mm2 0.303 / 7.17^2 = 0.0058895
Stress in Cable = 1422.9 MPa 0.5 + 7.17 = 7.820 m
m= 0.17
k= 0.002
E = 1.95E+05 MPa
Elongation = 157.40 mm (with in girder)
Total Elongation = 162.67 mm
DL = S
Dq (Stres
Cable Actual Length of
Stress x sx
Sl. No X (m) Y (m) DX (m) DY (m) q (radian Stress Cable Cable with
Length Length
s) (MPa) Stress in girder
)/E
(mm)
(A) (B) (Xn+1-Xn)) (Yn+1-Yn)) ATAN(DY/DX) qn+1 - qn (A) (A) (A)
40 12.820 0.155 0.500 0.000 0.000 0.000 1367.6 308678.8 1.583 1334.4 12.680
41 13.320 0.155 0.500 0.000 0.000 0.000 1366.2 326339.0 1.674 1335.7 13.180
42 13.820 0.155 0.500 0.000 0.000 0.000 1364.8 344664.2 1.768 1337.1 13.680
43 14.320 0.155 0.500 0.000 0.000 0.000 1363.5 363653.2 1.865 1338.4 14.180
44 14.420 0.155 0.100 0.000 0.000 0.000 1363.2 367530.5 1.885 1339.7 14.280
45 14.520 0.155 0.100 0.000 0.000 0.000 1362.9 371434.4 1.905 1340.0 14.380
46 14.620 0.155 0.100 0.000 0.000 0.000 1362.7 375364.6 1.925 1340.3 14.480
47 14.720 0.155 0.100 0.000 0.000 0.000 1362.4 379321.4 1.945 1340.5 14.580
48 14.820 0.155 0.100 0.000 0.000 0.000 1362.1 383304.6 1.966 1340.8 14.680
49 15.640 0.159 0.820 0.004 0.005 0.005 1358.8 433792.6 2.225 1341.1 15.500
50 16.140 0.165 0.500 0.006 0.013 0.008 1355.6 483384.6 2.479 1344.4 16.000
51 16.640 0.175 0.500 0.009 0.018 0.006 1352.9 527392.0 2.705 1347.5 16.500
51 17.140 0.187 0.500 0.012 0.024 0.006 1350.2 572658.8 2.937 1350.2 17.001
52 17.640 0.202 0.500 0.015 0.030 0.006 1347.5 619177.8 1347.5 17.501
52 18.140 0.220 0.500 0.018 0.036 0.006 1344.8 666941.8 1344.8 18.001
53 18.640 0.241 0.500 0.021 0.042 0.006 1342.1 715943.5 1342.1 18.502
53 19.140 0.265 0.500 0.024 0.048 0.006 1339.4 766175.4 1339.4 19.002
54 19.640 0.292 0.500 0.027 0.054 0.006 1336.8 817630.1 1336.8 19.503
54 20.140 0.322 0.500 0.030 0.060 0.006 1334.1 870300.0 1334.1 20.004
55 20.640 0.354 0.500 0.033 0.066 0.006 1331.4 924177.3 1331.4 20.505
55 21.140 0.390 0.500 0.036 0.071 0.006 1328.8 979254.3 1328.8 21.006
56 21.640 0.429 0.500 0.039 0.077 0.006 1326.1 1035523.0 1326.1 21.508
56 21.990 0.458 0.350 0.029 0.082 0.005 1324.1 1079895.6 1324.1 21.859
57 22.040 0.462 0.050 0.004 0.084 0.002 1323.5 1092862.9 1323.5 21.909
57 22.090 0.466 0.050 0.004 0.084 0.000 1323.4 1095763.1 1323.4 21.959
58 22.140 0.470 0.050 0.004 0.084 0.000 1323.2 1098669.7 1323.2 22.009
58 22.190 0.475 0.050 0.004 0.084 0.000 1323.1 1101582.7 1323.1 22.059
59 22.240 0.479 0.050 0.004 0.084 0.000 1323.0 1104501.9 1323.0 22.110
59 22.290 0.483 0.050 0.004 0.084 0.000 1322.8 1107427.5 1322.8 22.160
60 22.340 0.487 0.050 0.004 0.084 0.000 1322.7 1110359.4 1322.7 22.210
60 22.390 0.492 0.050 0.004 0.084 0.000 1322.6 1113297.6 1322.6 22.260
61 22.440 0.496 0.050 0.004 0.084 0.000 1322.4 1116242.1 1322.4 22.310
61 22.490 0.500 0.050 0.004 0.084 0.000 1322.3 1119193.0 1322.3 22.361
1 0.500 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
2 1.380 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
3 5.870 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
4 7.614 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
5 11.320 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
6 14.808 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
7 16.770 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
8 21.260 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
9 22.140 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
FRICTION AND SLIP LOSSES CALCULATION
CALCULATION OF SLIP LOSSES FOR CABLES WITH PARABOLIC VERTICAL CURVE STRESSED FROM ONE
SIDE
CABLE NO : 2 Bearing center
0.150 m 10.900 m
0.000 ° CL of Symmetry
0.155 m
Y
X 0.155 m
0.500 m 7.170 m 3.500 m
Straight Profile Parabolic Profile Straight Profile
GENERAL DETAILS OF CABLE Diff. b/w start & end point of parabole in Y axis =
Ultimate Stress in Cable = 1860 MPa 0.155 - 0.155 = 0.000 m
Area of Cable = 1184.4 mm2 0 / 7.17^2 = 0
Stress in Cable = 1422.9 MPa 0.5 + 7.17 = 7.820 m
m= 0.17
k= 0.002
E = 1.95E+05 MPa
Elongation = 159.45 (with in girder)
Total Elongation = 164.80 mm2 0.0000
DL = S
(Stres
Dq Cable Actual Length of
Stress x sx
Sl. No X (m) Y (m) DX (m) DY (m) q (radian Stress Cable Cable with
Length Length
s) (MPa) Stress in girder
)/E
(mm)
(A) (B) (Xn+1-Xn)) (Yn+1-Yn)) ATAN(DY/DX) qn+1 - qn (A) (A) (A)
40 12.820 0.155 0.500 0.000 0.000 0.000 1387.3 224595.8 1.152 1344.6 12.670
41 13.320 0.155 0.500 0.000 0.000 0.000 1385.9 242510.7 1.244 1345.9 13.170
42 13.820 0.155 0.500 0.000 0.000 0.000 1384.5 261100.4 1.339 1347.3 13.670
43 14.320 0.155 0.500 0.000 0.000 0.000 1383.1 280363.3 1.438 1348.6 14.170
44 14.420 0.155 0.100 0.000 0.000 0.000 1382.9 284296.6 1.458 1350.0 14.270
45 14.520 0.155 0.100 0.000 0.000 0.000 1382.6 288256.7 1.478 1350.2 14.370
46 14.620 0.155 0.100 0.000 0.000 0.000 1382.3 292243.7 1.499 1350.5 14.470
47 14.720 0.155 0.100 0.000 0.000 0.000 1382.0 296257.5 1.519 1350.8 14.570
48 14.820 0.155 0.100 0.000 0.000 0.000 1381.8 300298.2 1.540 1351.0 14.670
49 15.640 0.155 0.820 0.000 0.000 0.000 1379.5 334442.7 1.715 1351.3 15.490
50 16.140 0.155 0.500 0.000 0.000 0.000 1378.1 356145.1 1.826 1353.5 15.990
51 16.640 0.155 0.500 0.000 0.000 0.000 1376.7 378514.5 1.941 1354.9 16.490
51 17.140 0.155 0.500 0.000 0.000 0.000 1375.4 401549.6 2.059 1356.2 16.990
52 17.640 0.155 0.500 0.000 0.000 0.000 1374.0 425249.0 2.181 1357.6 17.490
52 18.140 0.155 0.500 0.000 0.000 0.000 1372.6 449611.3 2.306 1359.0 17.990
53 18.640 0.155 0.500 0.000 0.000 0.000 1371.2 474635.3 2.434 1360.3 18.490
53 19.140 0.155 0.500 0.000 0.000 0.000 1369.9 500319.5 2.566 1361.7 18.990
54 19.640 0.155 0.500 0.000 0.000 0.000 1368.5 526662.7 2.701 1363.0 19.490
54 20.140 0.155 0.500 0.000 0.000 0.000 1367.1 553663.4 2.839 1364.4 19.990
55 20.640 0.155 0.500 0.000 0.000 0.000 1365.8 581320.4 2.981 1365.8 20.490
55 21.140 0.155 0.500 0.000 0.000 0.000 1364.4 609632.3 1364.4 20.990
56 21.640 0.155 0.500 0.000 0.000 0.000 1363.0 638597.7 1363.0 21.490
56 21.990 0.155 0.350 0.000 0.000 0.000 1362.1 659261.7 1362.1 21.840
57 22.040 0.155 0.050 0.000 0.000 0.000 1361.9 662239.7 1361.9 21.890
57 22.090 0.155 0.050 0.000 0.000 0.000 1361.8 665224.3 1361.8 21.940
58 22.140 0.155 0.050 0.000 0.000 0.000 1361.7 668215.3 1361.7 21.990
58 22.190 0.155 0.050 0.000 0.000 0.000 1361.5 671212.9 1361.5 22.040
59 22.240 0.155 0.050 0.000 0.000 0.000 1361.4 674217.0 1361.4 22.090
59 22.290 0.155 0.050 0.000 0.000 0.000 1361.3 677227.6 1361.3 22.140
60 22.340 0.155 0.050 0.000 0.000 0.000 1361.1 680244.7 1361.1 22.190
60 22.390 0.155 0.050 0.000 0.000 0.000 1361.0 683268.3 1361.0 22.240
61 22.440 0.155 0.050 0.000 0.000 0.000 1360.9 686298.4 1360.9 22.290
61 22.490 0.155 0.050 0.000 0.000 0.000 1360.7 689335.0 1360.7 22.340
1 0.500 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
2 1.380 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
3 5.870 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
4 7.614 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
5 11.320 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
6 14.388 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
7 16.350 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
8 21.260 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
9 22.140 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
FRICTION AND SLIP LOSSES CALCULATION CABLE - 3
CALCULATION OF SLIP LOSSES FOR CABLES WITH PARABOLIC VERTICAL CURVE STRESSED FROM ONE
SIDE
CABLE NO : 3 Bearing center
0.150 m 10.900 m
0.000 ° CL of Symmetry
0.155 m
Y
X 0.155 m
0.500 m 7.170 m 3.500 m
Straight Profile Parabolic Profile Straight Profile
GENERAL DETAILS OF CABLE Diff. b/w start & end point of parabole in Y axis =
Ultimate Stress in Cable = 1860 MPa 0.155 - 0.155 = 0.000 m
Area of Cable = 1184.4 mm2 0 / 7.17^2 = 0
Stress in Cable = 1422.9 MPa 0.5 + 7.17 = 7.820 m
m= 0.17
k= 0.002
E = 1.95E+05 MPa
Elongation = 159.45 (with in girder)
Total Elongation = 164.80 mm2 0.0000
DL = S
Dq (Stres
Cable Actual Length of
Stress x sx
Sl. No X (m) Y (m) DX (m) DY (m) q (radian Stress Cable Cable with
Length Length
s) (MPa) Stress in girder
)/E
(mm)
(A) (B) (Xn+1-Xn)) (Yn+1-Yn)) ATAN(DY/DX) qn+1 - qn (A) (A) (A)
40 12.820 0.155 0.500 0.000 0.000 0.000 1387.3 224595.8 1.152 1344.6 12.670
41 13.320 0.155 0.500 0.000 0.000 0.000 1385.9 242510.7 1.244 1345.9 13.170
42 13.820 0.155 0.500 0.000 0.000 0.000 1384.5 261100.4 1.339 1347.3 13.670
43 14.320 0.155 0.500 0.000 0.000 0.000 1383.1 280363.3 1.438 1348.6 14.170
44 14.420 0.155 0.100 0.000 0.000 0.000 1382.9 284296.6 1.458 1350.0 14.270
45 14.520 0.155 0.100 0.000 0.000 0.000 1382.6 288256.7 1.478 1350.2 14.370
46 14.620 0.155 0.100 0.000 0.000 0.000 1382.3 292243.7 1.499 1350.5 14.470
47 14.720 0.155 0.100 0.000 0.000 0.000 1382.0 296257.5 1.519 1350.8 14.570
48 14.820 0.155 0.100 0.000 0.000 0.000 1381.8 300298.2 1.540 1351.0 14.670
49 15.640 0.155 0.820 0.000 0.000 0.000 1379.5 334442.7 1.715 1351.3 15.490
50 16.140 0.155 0.500 0.000 0.000 0.000 1378.1 356145.1 1.826 1353.5 15.990
51 16.640 0.155 0.500 0.000 0.000 0.000 1376.7 378514.5 1.941 1354.9 16.490
51 17.140 0.155 0.500 0.000 0.000 0.000 1375.4 401549.6 2.059 1356.2 16.990
52 17.640 0.155 0.500 0.000 0.000 0.000 1374.0 425249.0 2.181 1357.6 17.490
52 18.140 0.155 0.500 0.000 0.000 0.000 1372.6 449611.3 2.306 1359.0 17.990
53 18.640 0.155 0.500 0.000 0.000 0.000 1371.2 474635.3 2.434 1360.3 18.490
53 19.140 0.155 0.500 0.000 0.000 0.000 1369.9 500319.5 2.566 1361.7 18.990
54 19.640 0.155 0.500 0.000 0.000 0.000 1368.5 526662.7 2.701 1363.0 19.490
54 20.140 0.155 0.500 0.000 0.000 0.000 1367.1 553663.4 2.839 1364.4 19.990
55 20.640 0.155 0.500 0.000 0.000 0.000 1365.8 581320.4 2.981 1365.8 20.490
55 21.140 0.155 0.500 0.000 0.000 0.000 1364.4 609632.3 1364.4 20.990
56 21.640 0.155 0.500 0.000 0.000 0.000 1363.0 638597.7 1363.0 21.490
56 21.990 0.155 0.350 0.000 0.000 0.000 1362.1 659261.7 1362.1 21.840
57 22.040 0.155 0.050 0.000 0.000 0.000 1361.9 662239.7 1361.9 21.890
57 22.090 0.155 0.050 0.000 0.000 0.000 1361.8 665224.3 1361.8 21.940
58 22.140 0.155 0.050 0.000 0.000 0.000 1361.7 668215.3 1361.7 21.990
58 22.190 0.155 0.050 0.000 0.000 0.000 1361.5 671212.9 1361.5 22.040
59 22.240 0.155 0.050 0.000 0.000 0.000 1361.4 674217.0 1361.4 22.090
59 22.290 0.155 0.050 0.000 0.000 0.000 1361.3 677227.6 1361.3 22.140
60 22.340 0.155 0.050 0.000 0.000 0.000 1361.1 680244.7 1361.1 22.190
60 22.390 0.155 0.050 0.000 0.000 0.000 1361.0 683268.3 1361.0 22.240
61 22.440 0.155 0.050 0.000 0.000 0.000 1360.9 686298.4 1360.9 22.290
61 22.490 0.155 0.050 0.000 0.000 0.000 1360.7 689335.0 1360.7 22.340
1 0.500 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
2 1.380 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
3 5.870 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
4 7.614 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
5 11.320 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
6 14.388 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
7 16.350 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
8 21.260 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
9 22.140 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 ### Err:511
FRICTION AND SLIP LOSSES CALCULATION
CALCULATION OF SLIP LOSSES FOR CABLES WITH PARABOLIC VERTICAL CURVE STRESSED FROM ONE
SIDE
CABLE NO : 4 Bearing center
0.150 m 10.90
0.000 ° CL of Symmetry
0.155 m
Y
X 0.155 m
0.500 m 7.170 m 3.500 m
Straight Profile Parabolic Profile Straight Profile
GENERAL DETAILS OF CABLE Diff. b/w start & end point of parabole in Y axis =
Ultimate Stress in Cable = 1860 MPa 0.155 - 0.155 = 0.000 m
Area of Cable = 1184.4 mm2 0 / 7.17^2 = 0
Stress in Cable = 1422.9 MPa 0.5 + 7.17 = 7.820 m
m= 0.17
k= 0.002
E = 1.95E+05 MPa
Elongation = 159.45 (with in girder)
Total Elongation = 164.805 mm2 0.0000
DL = S
Dq (Stress
Cable Actual Length of
Stress x x
Sl. No X (m) Y (m) DX (m) DY (m) q (radian Stress Cable Cable with
Length Length)
s) (MPa) Stress in girder
/E
(mm)
(A) (B) (Xn+1-Xn)) (Yn+1-Yn)) ATAN(DY/DX) qn+1 - qn (A) (A) (A)
37 11.320 0.155 0.500 0.000 0.000 0.000 1391.5 174913.0 0.897 1340.5 11.170
38 11.820 0.155 0.500 0.000 0.000 0.000 1390.1 190795.6 0.978 1341.9 11.670
39 12.320 0.155 0.500 0.000 0.000 0.000 1388.7 207357.0 1.063 1343.2 12.170
FRICTION AND SLIP LOSSES CALCULATION
40 12.820 0.155 0.500 0.000 0.000 0.000 1387.3 224595.8 1.152 1344.6 12.670
41 13.320 0.155 0.500 0.000 0.000 0.000 1385.9 242510.7 1.244 1345.9 13.170
42 13.820 0.155 0.500 0.000 0.000 0.000 1384.5 261100.4 1.339 1347.3 13.670
43 14.320 0.155 0.500 0.000 0.000 0.000 1383.1 280363.3 1.438 1348.6 14.170
44 14.420 0.155 0.100 0.000 0.000 0.000 1382.9 284296.6 1.458 1350.0 14.270
45 14.520 0.155 0.100 0.000 0.000 0.000 1382.6 288256.7 1.478 1350.2 14.370
46 14.620 0.155 0.100 0.000 0.000 0.000 1382.3 292243.7 1.499 1350.5 14.470
47 14.720 0.155 0.100 0.000 0.000 0.000 1382.0 296257.5 1.519 1350.8 14.570
48 14.820 0.155 0.100 0.000 0.000 0.000 1381.8 300298.2 1.540 1351.0 14.670
49 15.640 0.155 0.820 0.000 0.000 0.000 1379.5 334442.7 1.715 1351.3 15.490
50 16.140 0.155 0.500 0.000 0.000 0.000 1378.1 356145.1 1.826 1353.5 15.990
51 16.640 0.155 0.500 0.000 0.000 0.000 1376.7 378514.5 1.941 1354.9 16.490
51 17.140 0.155 0.500 0.000 0.000 0.000 1375.4 401549.6 2.059 1356.2 16.990
52 17.640 0.155 0.500 0.000 0.000 0.000 1374.0 425249.0 2.181 1357.6 17.490
52 18.140 0.155 0.500 0.000 0.000 0.000 1372.6 449611.3 2.306 1359.0 17.990
53 18.640 0.155 0.500 0.000 0.000 0.000 1371.2 474635.3 2.434 1360.3 18.490
53 19.140 0.155 0.500 0.000 0.000 0.000 1369.9 500319.5 2.566 1361.7 18.990
54 19.640 0.155 0.500 0.000 0.000 0.000 1368.5 526662.7 2.701 1363.0 19.490
54 20.140 0.155 0.500 0.000 0.000 0.000 1367.1 553663.4 2.839 1364.4 19.990
55 20.640 0.155 0.500 0.000 0.000 0.000 1365.8 581320.4 2.981 1365.8 20.490
55 21.140 0.155 0.500 0.000 0.000 0.000 1364.4 609632.3 1364.4 20.990
56 21.640 0.155 0.500 0.000 0.000 0.000 1363.0 638597.7 1363.0 21.490
56 21.990 0.155 0.350 0.000 0.000 0.000 1362.1 659261.7 1362.1 21.840
57 22.040 0.155 0.050 0.000 0.000 0.000 1361.9 662239.7 1361.9 21.890
57 22.090 0.155 0.050 0.000 0.000 0.000 1361.8 665224.3 1361.8 21.940
58 22.140 0.155 0.050 0.000 0.000 0.000 1361.7 668215.3 1361.7 21.990
58 22.190 0.155 0.050 0.000 0.000 0.000 1361.5 671212.9 1361.5 22.040
59 22.240 0.155 0.050 0.000 0.000 0.000 1361.4 674217.0 1361.4 22.090
59 22.290 0.155 0.050 0.000 0.000 0.000 1361.3 677227.6 1361.3 22.140
60 22.340 0.155 0.050 0.000 0.000 0.000 1361.1 680244.7 1361.1 22.190
60 22.390 0.155 0.050 0.000 0.000 0.000 1361.0 683268.3 1361.0 22.240
61 22.440 0.155 0.050 0.000 0.000 0.000 1360.9 686298.4 1360.9 22.290
61 22.490 0.155 0.050 0.000 0.000 0.000 1360.7 689335.0 1360.7 22.340
1 0.500 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
2 1.380 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
3 5.870 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 7.614 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 11.320 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 14.388 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 16.350 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
8 21.260 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 22.140 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
FRICTION AND SLIP LOSSES CALCULATION
CALCULATION OF SLIP LOSSES FOR CABLES WITH PARABOLIC VERTICAL CURVE STRESSED FROM ONE
SIDE
CABLE NO : DUMMY Bearing center
0.150 m 13.58
7.016 ° CL of Symmetry
1.713 m
Y
X 0.840 m
0.750 m 12.680 m 0.500 m
Straight Profile Parabolic Profile Straight Profile
GENERAL DETAILS OF CABLE Diff. b/w start & end point of parabole in Y axis =
Ultimate Stress in Cable = 1860 MPa 1.62 - 0.84 = 0.780 m
Area of Cable = 1200 mm2 0.78 / 12.68^2 = 0.0048525
Stress in Cable = 1422.9 MPa 0.75 + 12.68 = 13.580 m
m= 0.25
k = 0.0046
E = 1.95E+05 MPa
Elongation = 186.26 (with in girder)
Total Elongation = 191.26 mm2 0.0062
DL = S
Dq (Stress
Cable Actual Length of
Stress x x
Sl. No X (m) Y (m) DX (m) DY (m) q (radian Stress Cable Cable with
Length Length)
s) (MPa) Stress in girder
/E
(mm)
(A) (B) (Xn+1-Xn)) (Yn+1-Yn)) ATAN(DY/DX) qn+1 - qn (A) (A) (A)
37 11.000 0.872 0.500 0.014 0.027 0.005 1321.9 558126.0 2.862 1309.5 10.887
38 11.250 0.866 0.250 0.006 0.024 0.004 1319.1 587969.8 3.015 1314.1 11.137
39 11.500 0.861 0.250 0.005 0.021 0.002 1316.8 613952.5 1316.8 11.387
FRICTION AND SLIP LOSSES CALCULATION
40 12.000 0.852 0.500 0.009 0.018 0.004 1312.6 662899.7 1312.6 11.888
41 13.580 0.840 1.580 0.012 0.008 0.010 1299.8 824551.3 1299.8 13.468
42 13.590 0.840 0.010 0.000 0.000 0.008 1297.3 858792.8 1297.3 13.478
43 13.630 0.840 0.040 0.000 0.000 0.000 1297.0 862005.3 1297.0 13.518
44 13.680 0.840 0.050 0.000 0.000 0.000 1296.7 866033.6 1296.7 13.568
45 13.780 0.840 0.100 0.000 0.000 0.000 1296.1 874132.2 1296.1 13.668
46 13.880 0.840 0.100 0.000 0.000 0.000 1295.5 882286.7 1295.5 13.768
47 13.980 0.840 0.100 0.000 0.000 0.000 1294.9 890496.9 1294.9 13.868
48 14.080 0.840 0.100 0.000 0.000 0.000 1294.3 898763.0 1294.3 13.968
49 14.180 0.840 0.100 0.000 0.000 0.000 1293.8 907084.8 1293.8 14.068
50 14.280 0.840 0.100 0.000 0.000 0.000 1293.2 915462.2 1293.2 14.168
51 14.380 0.840 0.100 0.000 0.000 0.000 1292.6 923895.3 1292.6 14.268
51 14.480 0.840 0.100 0.000 0.000 0.000 1292.0 932384.0 1292.0 14.368
52 14.530 0.840 0.050 0.000 0.000 0.000 1291.7 936649.1 1291.7 14.418
52 14.570 0.840 0.040 0.000 0.000 0.000 1291.4 940071.2 1291.4 14.458
53 14.580 0.840 0.010 0.000 0.000 0.000 1291.4 940928.1 1291.4 14.468
53 16.160 0.852 1.580 0.012 0.008 0.008 1279.6 1120624.8 1279.6 16.048
54 16.660 0.861 0.500 0.009 0.018 0.010 1273.4 1220727.4 1273.4 16.548
54 16.910 0.866 0.250 0.005 0.021 0.004 1270.8 1264309.4 1270.8 16.798
55 17.160 0.872 0.250 0.006 0.024 0.002 1268.6 1301960.9 1268.6 17.048
55 17.660 0.886 0.500 0.014 0.027 0.004 1264.5 1372116.2 1264.5 17.548
56 18.160 0.902 0.500 0.016 0.032 0.005 1260.1 1450849.7 1260.1 18.048
56 18.660 0.921 0.500 0.019 0.037 0.005 1255.6 1531507.3 1255.6 18.549
57 19.160 0.942 0.500 0.021 0.042 0.005 1251.2 1614072.7 1251.2 19.049
57 19.660 0.965 0.500 0.023 0.047 0.005 1246.9 1698529.8 1246.9 19.550
58 20.160 0.991 0.500 0.026 0.052 0.005 1242.5 1784862.3 1242.5 20.050
58 20.660 1.019 0.500 0.028 0.057 0.005 1238.1 1873053.9 1238.1 20.551
59 21.160 1.050 0.500 0.031 0.061 0.005 1233.8 1963088.5 1233.8 21.052
59 21.660 1.083 0.500 0.033 0.066 0.005 1229.5 2054949.8 1229.5 21.553
60 22.160 1.119 0.500 0.036 0.071 0.005 1225.2 2148621.6 1225.2 22.054
60 22.660 1.157 0.500 0.038 0.076 0.005 1220.9 2244087.8 1220.9 22.556
61 23.160 1.197 0.500 0.040 0.081 0.005 1216.6 2341332.1 1216.6 23.057
61 23.660 1.240 0.500 0.043 0.085 0.005 1212.4 2440338.5 1212.4 23.559
62 24.160 1.285 0.500 0.045 0.090 0.005 1208.1 2541090.7 1208.1 24.061
62 24.660 1.333 0.500 0.048 0.095 0.005 1203.9 2643572.7 1203.9 24.564
63 25.160 1.383 0.500 0.050 0.100 0.005 1199.7 2747768.4 1199.7 25.066
63 25.660 1.436 0.500 0.053 0.105 0.005 1195.5 2853661.7 1195.5 25.569
64 26.160 1.491 0.500 0.055 0.110 0.005 1191.3 2961236.5 1191.3 26.072
64 26.660 1.548 0.500 0.057 0.114 0.005 1187.2 3070476.9 1187.2 26.575
65 27.160 1.608 0.500 0.060 0.119 0.005 1183.0 3181366.9 1183.0 27.079
65 27.260 1.620 0.100 0.012 0.122 0.003 1181.6 3219034.7 1181.6 27.179
66 27.310 1.626 0.050 0.006 0.122 0.000 1181.2 3230239.3 1181.2 27.230
66 27.360 1.633 0.050 0.006 0.122 0.000 1180.9 3237624.0 1180.9 27.280
67 27.410 1.639 0.050 0.006 0.122 0.000 1180.7 3245020.6 1180.7 27.331
67 27.460 1.645 0.050 0.006 0.122 0.000 1180.4 3252429.1 1180.4 27.381
68 27.510 1.651 0.050 0.006 0.122 0.000 1180.1 3259849.4 1180.1 27.431
68 27.560 1.657 0.050 0.006 0.122 0.000 1179.9 3267281.6 1179.9 27.482
69 27.610 1.663 0.050 0.006 0.122 0.000 1179.6 3274725.7 1179.6 27.532
69 27.660 1.669 0.050 0.006 0.122 0.000 1179.3 3282181.6 1179.3 27.582
70 27.710 1.676 0.050 0.006 0.122 0.000 1179.0 3289649.4 1179.0 27.633
70 27.760 1.682 0.050 0.006 0.122 0.000 1178.8 3297129.0 1178.8 27.683
71 27.810 1.688 0.050 0.006 0.122 0.000 1178.5 3304620.4 1178.5 27.734
71 27.860 1.694 0.050 0.006 0.122 0.000 1178.2 3312123.7 1178.2 27.784
72 27.910 1.700 0.050 0.006 0.122 0.000 1178.0 3319638.8 1178.0 27.834
72 27.960 1.706 0.050 0.006 0.122 0.000 1177.7 3327165.7 1177.7 27.885
73 28.010 1.713 0.050 0.006 0.122 0.000 1177.4 3334704.4 1177.4 27.935
1 0.500 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
2 2.390 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
3 7.290 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 9.463 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 14.080 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 17.926 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 20.370 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
FRICTION AND SLIP LOSSES CALCULATION
8 25.770 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 27.660 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
SUMMARY OF CABLE STRESSES
STRESSES IN CABLE NO. 1
AT STRESSING AFTER SLIP LOSS LOSS
Distance Distance Angle
Stress Force Stress Force Stress Force
from from
(MPa) (kN) (MPa) (kN) (MPa) (kN)
origin base
0.500 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
1.380 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5.870 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7.614 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
11.320 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
14.808 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
16.770 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
21.260 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
22.140 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
X from
anchor X from
end center Y from base
CABLE 1 CABLE 2 CABLE 3 CABLE 4 DUMMY
13.930 0 Err:511 Err:511 Err:511 Err:511 Err:511
12.930 1000 Err:511 Err:511 Err:511 Err:511 Err:511
11.930 2000 Err:511 Err:511 Err:511 Err:511 Err:511
10.930 3000 Err:511 Err:511 Err:511 Err:511 Err:511
9.930 4000 Err:511 Err:511 Err:511 Err:511 Err:511
8.930 5000 Err:511 Err:511 Err:511 Err:511 Err:511
7.930 6000 Err:511 Err:511 Err:511 Err:511 Err:511
6.930 7000 Err:511 Err:511 Err:511 Err:511 Err:511
5.930 8000 Err:511 Err:511 Err:511 Err:511 Err:511
4.930 9000 Err:511 Err:511 Err:511 Err:511 Err:511
3.930 10000 Err:511 Err:511 Err:511 Err:511 Err:511
2.930 11000 Err:511 Err:511 Err:511 Err:511 Err:511
1.930 12000 Err:511 Err:511 Err:511 Err:511 Err:511
0.750 13180 Err:511 Err:511 Err:511 Err:511 Err:511
0.150 13930 Err:511 Err:511 Err:511 Err:511 Err:511
Exit Angle 4.827 0.000 0.000 0.000 7.016
ADILABAD EXPRESSWAY ROB@189.456
Impact factor for 70R Tracked loading = 1.100 As per clause 211.3 of IRC 6 - 2000
Impact factor for Class A loading = 1.1619 As per clause 211.2 of IRC 6 - 2000
Impact factor for 70R Wheeled loading = 1.125 As per clause 211.3 of IRC 6 - 2000
Distance from
SELF WEIGHT BM SF center of
Sl.No. Section End Interior End Interior bearing(m)
1 Support 0.00 0.00 12.42 12.42 0
2 d from sup. 9.83 9.83 11.27 11.27 0.83
3 0.25L 48.20 48.20 5.67 5.67 5.45
4 0.33L 56.49 56.49 3.86 3.86 7.19
5 0.5L 63.65 63.65 0.00 0.00 10.90
GREEN CONCRETE BM SF
Sl.No. Section End Interior End Interior
1 Support 0.00 0.00 38.62 38.62 0
2 d from sup. 10.47 13.18 33.25 33.25 1.89
3 0.25L 53.60 67.50 19.31 19.31 5.45
4 0.33L 63.19 79.57 13.13 13.13 7.19
5 0.5L 71.46 90.00 0.00 0.00 10.90
SIDL BM SF
Sl.No. Section End Interior End Interior
1 Support 0.27 -0.05 13.36 11.73 0
2 d from sup. 10.82 9.79 13.36 11.73 1.89
3 0.25L 52.37 50.93 6.94 6.70 5.45
4 0.33L 61.22 59.67 4.44 4.21 7.19
5 0.5L 69.19 67.48 0.63 0.60 10.90
DEAD LOAD BM SF
Sl.No. Section End Interior End Interior
1 Support 0.05 0.18 22.81 24.90 0.00
2 d from sup. 18.36 19.93 21.56 23.56 1.89
3 0.25L 94.20 100.39 11.87 12.56 5.45
4 0.33L 110.75 117.80 7.83 8.29 7.19
5 0.5L 125.28 133.09 0.51 0.52 10.90 0
0
0
LIVE LOAD Max BM Max SF 0
Sl.No. Section End Interior End Interior
1 Support -0.180 -0.700 12.75 16.68 0
2 d from sup. 10.760 13.140 12.75 16.68 1.89
3 0.25L 66.300 69.890 10.65 13.01 5.45
4 0.33L 81.470 88.520 7.52 9.89 7.19
5 0.5L 96.040 106.740 1.04 0.50 10.90
EXTERNAL INTERNAL
Location BM SF BM SF
Support 0.15 87.11 -1.63 96.29
Ultimate moment d from Sup 71.49 85.55 77.34 94.61
& Ultimate shear
1.25G+2SG+2.5Q L/4 388.24 55.34 402.07 61.63
L/3 464.55 37.47 487.89 43.51
L/2 535.08 4.50 568.17 3.10
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
I Properties of Precast section
A 0.556 0.556 0.416 0.416 0.416 0.416 0.416 0.556 0.556
Yb 0.431 0.431 0.411 0.411 0.411 0.411 0.411 0.431 0.431
Yt 0.449 0.449 0.469 0.469 0.469 0.469 0.469 0.449 0.449
Zb 0.079 0.079 0.078 0.078 0.078 0.078 0.078 0.079 0.079
Zt 0.076 0.076 0.068 0.068 0.068 0.068 0.068 0.076 0.076
Ix 0.034 0.034 0.032 0.032 0.032 0.032 0.032 0.034 0.034
H 0.8800 0.8800 0.8800 0.8800 0.8800 0.8800 0.8800 0.880 0.880
(Ay)p 1.79E+07 1.79E+07 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 1.79E+07 1.79E+07
II Properties of composite section 1 1 2 2 2 2 2 1 1
Ac 0.909 0.909 0.767 0.767 0.767 0.767 0.767 9.09E-01 0.909
Ybc 0.646 0.646 0.676 0.676 0.676 0.676 0.676 6.46E-01 0.646
Ytc 0.455 0.455 0.426 0.426 0.426 0.426 0.426 4.55E-01 0.455
Zbgc 0.160 0.160 0.144 0.144 0.144 0.144 0.144 1.60E-01 0.160
Ztgc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 4.43E-01 0.443
Zbsc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 4.43E-01 0.443
Ztsc 0.228 0.228 0.228 0.228 0.228 0.228 0.228 2.28E-01 0.228
Ixc 0.104 0.104 0.097 0.097 0.097 0.097 0.097 1.04E-01 0.104
Hc 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.10E+00 1.100
Slab thickness, t 0.220 0.220 0.220 0.220 0.220 0.220 0.220 2.20E-01 0.220
Effective flange width, Bf 1.525 1.53 1.53 1.53 1.53 1.53 1.53 1.53E+00 1.525
(Ay)c 1.34E+08 1.34E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.34E+08 1.34E+08
III Material Properties
Grade of concrete at 7th day (Mpa) 30.3 30.3 30.3 30.3 30.3 30.3 30.3 30.3 30.3
Grade of concrete at 28th day (Mpa) 45 45 45 45 45 45 45 45 45
Ec, initial = 5000 x sqrt(fck) (Mpa) 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66
Ec, final = 5000 x sqrt(fck) (Mpa) 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02
Young's modules of prestressing steel, Es (Mpa) 195000 195000 195000 195000 195000 195000 195000 195000 195000
IV Stressing Sequence
First stage stressing (N) @ Days 7 7 7 7 7 7 7 7 7
Second stage stressing (N1) @ Days 28 28 28 28 28 28 28 28 28
Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 2 & 3 (7th day)
1 No of strands 24 24 24 24 24 24 24 24 24
2 c/s area of strand 2368.8 2368.8 2368.8 2368.8 2368.8 2368.8 2368.8 2368.8 2368.8
3 Jacking force after Friction & slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 P, acting at a distance from base of girder (Yx) m Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 Moment, M = P x e Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
8 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
10 Final Stresses
11 Stress at bottom of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
12 Stress at top of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
13 Moment due to selfweight of girder ( KN-m) x 9.81 0.00 96.43 472.84 554.17 624.41 554.17 472.84 96.43 0.00
14 Stress at bottom of girder ( 13 / Zb ) 0.00 -1.22 -6.07 -7.12 -8.02 -7.12 -6.07 -1.22 0.00
15 Stress at top of girder ( 13 / Zt ) 0.00 1.27 6.93 8.12 9.15 8.12 6.93 1.27 0.00
DESIGN OF EXTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Resultant Stresses
16 Stress at bottom of girder (11 + 14) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
17 Stress at top of girder (12 + 15) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
18 Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
19 Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 3 (7th day)
20 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
21 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
22 Jacking force after slip losses, P (KN) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
23 Distance from base of girder, Yx Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
24 Eccentricity, e = Yb - Yx Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
25 Moment, M = P x e Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
26 Stress due to Axial force, sd = P / A Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
27 Stress due to Moment at bottom of girder, sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
28 Stress due to Moment at top of girder, st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
29 Stress at bottom of girder (16 + 27) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
30 Stress at top of girder (17 + 28) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
43 Stress at bottom of girder = (16 + 27 + 41) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
44 Stress at top of girder = (17 +28 + 42) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Pre-stress loss due to Initial shrinkage strain at 28th day
45 Strain due to residual shrinkage at 7th day (Table 3 IRC:18) 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035
46 Strain due to residual shrinkage at 28th day (Table 3 IRC:18) 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019
47 Net strain due to residual shrinkage 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160
48 Loss in cable force, P = Strain x Es x Cable area (kN) -110.86 -110.86 -110.86 -110.86 -110.86 -110.86 -110.86 -110.86 -110.86
49 Moment, M = P x e (kN-m) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
50 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) (N/mm2) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
51 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) (N/mm2) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
52 Stress at bottom of girder = (43+50) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
53 Stress at top of girder = (44+51) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
DESIGN OF EXTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Pre-stress loss due to Initial creep strain at 28th day
54 Maturity of concrete at 7th day 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00%
55 Strength of concrete at 7th day (Mpa) 35.00 35.00 35.00 35.00 35.00 35.00 35.00 35.00 35.00
56 Creep strain per 10 Mpa (Table 2 IRC:18) 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196
57 Maturity of concrete at 28th day 100.00% 110.00% 110.00% 110.00% 110.00% 110.00% 110.00% 110.00% 110.00%
58 Strength of concrete at 28th day (Mpa) 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00
59 Creep strain per 10 Mpa (Table 2 IRC:18) 0.00180 0.00162 0.00162 0.00162 0.00162 0.00162 0.00162 0.00162 0.00162
60 Net strain due to creep 0.00016 0.00034 0.00034 0.00034 0.00034 0.00034 0.00034 0.00034 0.00034
61 Stress at level of steel ((sb-st) x C.G. cable group / H) + st Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
62 Loss in force due to creep P = ( stress x (strain/10) x Es x (cable area) / 1000) kN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
63 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
64 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
65 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
66 Stress at bottom of girder = (52+64) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
67 Stress at top of girder = (53+65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
VI Second Stage Stressing of Cable 4 (28th day)
68 Permissible compressive stress 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
69 Permissible tensile stress -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00
70 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
71 c/s area of strand mm2 1184.4 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40
72 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
73 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
74 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
75 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
76 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
77 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
78 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
79 Stress at bottom of girder (43 + 54) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
80 Stress at top of girder (44 + 55) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
93 Stress at bottom of girder (66 + 77 + 91) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
94 Stress at top of girder (67 + 78 + 92) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
DESIGN OF EXTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
VII Second Stage Stressing of Cable 2 (28th day)
95 Permissible compressive stress 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
96 Permissible tensile stress -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00
97 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
98 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
99 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
100 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
101 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
102 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
103 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
104 Stress due to Moment at bottom of girder (sb = (P / Ac) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
105 Stress due to Moment at top of girder (st = (P / Ac) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
106 Stress at bottom of girder (70 + 81) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
107 Stress at top of girder (71 + 82) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
120 Stress at bottom of girder (93 + 104 + 118) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
121 Stress at top of girder (94 + 105 + 119) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Resultant stresses after concreting slab
128 Stress at bottom of girder (120 + 126) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
129 Stress at top of girder (121 + 127) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
XI Moment due to SIDL (KN-m) x 9.81 2.65 106.14 513.75 600.57 678.75 600.57 513.75 106.14 2.65
139 Stress due to Moment at bottom of girder (sb = (M / Zbgc) -0.02 -0.66 -3.57 -4.17 -4.72 -4.17 -3.57 -0.66 -0.02
140 Stress due to Moment at top of girder (st = (M / Ztgc) 0.01 0.24 1.08 1.26 1.42 1.26 1.08 0.24 0.01
141 Stress due to Moment at top of slab (sts = (M / Ztsc) 0.01 0.47 2.25 2.63 2.97 2.63 2.25 0.47 0.01
Resultant stresses after SIDL
142 Stress at bottom of girder (136 + 139) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
143 Stress at top of girder (137+ 140) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
145 Stress at top of slab (138+ 141) 2.80 3.42 5.20 5.58 5.92 5.58 5.20 3.42 2.80
Permissible Compressive stress at service = 0.33fck (Mpa) 14.85 14.85 14.85 14.85 14.85 14.85 14.85 14.85 14.85
XII Moment due to LL x 9.81 (kN-m) -1.77 105.56 650.40 799.22 942.15 799.22 650.40 105.56 -1.77
146 Stress due to Moment at bottom of girder (sb = (M / Zbc) 0.01 -0.66 -4.52 -5.55 -6.55 -5.55 -4.52 -0.66 0.01
147 Stress due to Moment at top of girder (st = (M / Ztc) 0.00 0.24 1.36 1.68 1.98 1.68 1.36 0.24 0.00
148 Stress due to Moment at top of slab (sts = (M / Ztsc) -0.01 0.46 2.85 3.50 4.12 3.50 2.85 0.46 -0.01
Final stresses after LL
149 Stress at bottom of girder (42 + 46) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
150 Stress at top of girder (43 + 47) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
151 Stress at top of slab (44+ 48) 2.79 3.88 8.05 9.08 10.05 9.08 8.05 3.88 2.79
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
165 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
166 Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Relaxation loss
167 Relaxation loss % for 0.765 fp (Ref Table 4A of IRC:18-2000) 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50%
168 Loss in force due to relaxation P = -(167 x 3.0 x (3+22+34+72+84+99+111)/100.0 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
169 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
170 Stress due to Moment at bottom of girder (sb = (P / Ac) - (M / Zbgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
171 Stress due to Moment at top of girder (st = (P / Ac) + (M / Ztgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
172 Stress due to Moment at top of slab (sts = (P / Ac) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant stresses after losses
173 Stress at bottom of girder (149 + 158 + 164 + 170) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
174 Stress at top of girder (150 + 159 + 165 + 171) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
175 Stress at top of slab (151 + 160 + 166 + 172) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Temporary actual compressive stress = Err:511 Temp. perm. Comp. stress at 7th day = 1544.73 MT / m2
Temporary actual tensile stress = -300.79 MT / m2 Temp. perm. Comp. stress at 28th day = 2040.00 MT / m2
Actual compressive stress = Err:511 Temp. perm. tensile stress 7th day = 154.47 MT / m2
Residual compressive stress at bottom = Err:511 Temp. perm. tensile stress 28th day = 204.00 MT / m2
(No tension is permitted) Permissible compressive stress = 1514.70 MT / m2
Ratio of span to Deflection = Err:511
DESIGN OF INTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
I Properties of Precast section
A 0.556 0.556 0.416 0.416 0.416 0.416 0.416 0.556 0.556
Yb 0.431 0.431 0.411 0.411 0.411 0.411 0.411 0.431 0.431
Yt 0.449 0.449 0.469 0.469 0.469 0.469 0.469 0.449 0.449
Zb 0.079 0.079 0.078 0.078 0.078 0.078 0.078 0.079 0.079
Zt 0.076 0.076 0.068 0.068 0.068 0.068 0.068 0.076 0.076
Ix 0.034 0.034 0.032 0.032 0.032 0.032 0.032 0.034 0.034
H 0.880 0.88 0.88 0.880 0.880 0.880 0.880 0.880 0.880
(Ay)p 1.79E+07 1.79E+07 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 1.79E+07 1.79E+07
II Properties of composite section 3 3 4 4 4 4 4 3 3
Ac 0.955 0.955 0.812 0.812 0.812 0.812 0.812 0.955 0.955
Ybc 0.663 0.663 0.693 0.693 0.693 0.693 0.693 0.663 0.663
Ytc 0.438 0.438 0.407 0.407 0.407 0.407 0.407 0.438 0.438
Zbgc 0.164 0.164 0.147 0.147 0.147 0.147 0.147 0.164 0.164
Ztgc 0.502 0.502 0.544 0.544 0.544 0.544 0.544 0.502 0.502
Zbsc 0.502 0.502 0.544 0.544 0.544 0.544 0.544 0.502 0.502
Ztsc 0.249 0.249 0.250 0.250 0.250 0.250 0.250 0.249 0.249
Ixc 0.109 0.109 0.102 0.102 0.102 0.102 0.102 0.109 0.109
Hc 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100
Slab thickness, t 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220
Effective flange width, Bf 1.800 1.80 1.80 1.800 1.800 1.800 1.800 1.800 1.800
(Ay)c 1.34E+08 1.34E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.34E+08 1.34E+08
III Material Properties
Grade of concrete at 7th day (Mpa) 35.00 35.00 35.00 35.00 35.00 35.00 35.00 35.00 35.00
Grade of concrete at 28th day (Mpa) 45 45 45 45 45 45 45 45 45
Ec, initial = 5000 x sqrt(fck) (Mpa) 29580.40 29580.40 29580.40 29580.40 29580.40 29580.40 29580.40 29580.40 29580.40
Ec, final = 5000 x sqrt(fck) (Mpa) 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02
Young's modules of prestressing steel, Es (Mpa) 195000 195000 195000 195000 195000 195000 195000 195000 195000
Stressing Sequence 7 7 7 7 7 7 7 7 7
First stage stressing (N) @ Days 28 28 28 28 28 28 28 28 28
IV Second stage stressing (N1) @ Days
Permissible compressive stress. clause 7.1.2 IRC:18-2000 17.50 17.50 17.50 17.50 17.50 17.50 17.50 17.50 17.50
Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75
Stressing of Cable 1 (7th day)
1 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
2 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
3 Jacking force after Friction & slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 P, acting at a distance from base of girder (Yx) m Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 Moment, M = P x e Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
8 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
10 Final Stresses
11 Stress at bottom of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
12 Stress at top of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
13 Moment due to selfweight of girder ( KN-m) x 9.81 0.00 96.43 472.84 554.17 624.41 554.17 472.84 96.43 0.00
14 Stress at bottom of girder ( 13 / Z b ) 0.00 -1.22 -6.07 -7.12 -8.02 -7.12 -6.07 -1.22 0.00
15 Stress at top of girder ( 13 / Zt ) 0.00 1.27 6.93 8.12 9.15 8.12 6.93 1.27 0.00
DESIGN OF INTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Resultant Stresses
16 Stress at bottom of girder (11 + 14) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
17 Stress at top of girder (12 + 15) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
18 Permissible compressive stress. clause 7.1.2 IRC:18-2000 17.50 17.50 17.50 17.50 17.50 17.50 17.50 17.50 17.50
19 Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75 -1.75
Stressing of Cable 3 (7th day)
20 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
21 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
22 Jacking force after slip losses, P (KN) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
23 Distance from base of girder, Yx Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
24 Eccentricity, e = Yb - Yx Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
25 Moment, M = P x e Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
26 Stress due to Axial force, sd = P / A Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
27 Stress due to Moment at bottom of girder, sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
28 Stress due to Moment at top of girder, st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
29 Stress at bottom of girder (16 + 27) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
30 Stress at top of girder (17 + 28) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
43 Stress at bottom of girder = (16 + 27 + 41) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
44 Stress at top of girder = (17 +28 + 42) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Pre-stress loss due to Initial shrinkage strain at 28th day
45 Strain due to residual shrinkage at 7th day (Table 3 IRC:18) 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035 0.00035
46 Strain due to residual shrinkage at 28th day (Table 3 IRC:18) 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019 0.00019
47 Net strain due to residual shrinkage 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160 0.000160
48 Loss in cable force, P = Strain x Es x Cable area (kN) -73.91 -73.91 -73.91 -73.91 -73.91 -73.91 -73.91 -73.91 -73.91
49 Moment, M = P x e (kN-m) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
50 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) (N/mm2) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
51 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) (N/mm2) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
52 Stress at bottom of girder = (43+50) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
53 Stress at top of girder = (44+51) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
DESIGN OF INTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Pre-stress loss due to Initial creep strain at 28th day
54 Maturity of concrete at 7th day 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00%
55 Strength of concrete at 7th day (Mpa) 35.00 35.00 35.00 35.00 35.00 35.00 35.00 35.00 35.00
56 Creep strain per 10 Mpa (Table 2 IRC:18) 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196 0.00196
57 Maturity of concrete at 28th day 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
58 Strength of concrete at 28th day (Mpa) 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00 45.00
59 Creep strain per 10 Mpa (Table 2 IRC:18) 0.00180 0.00162 0.00162 0.00162 0.00162 0.00162 0.00162 0.00162 0.00162
60 Net strain due to creep 0.00016 0.00034 0.00034 0.00034 0.00034 0.00034 0.00034 0.00034 0.00034
61 Stress at level of steel ((sb-st) x C.G. cable group / H) + st Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
62 Loss in force due to creep P = ( stress x (strain/10) x Es x (cable area) / 1000) kN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
63 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
64 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
65 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
66 Stress at bottom of girder = (52+64) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
67 Stress at top of girder = (53+65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
VI Second Stage Stressing of Cable 4 (28th day)
68 Permissible compressive stress 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
69 Permissible tensile stress -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00
70 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
71 c/s area of strand mm2 1184.4 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40
72 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
73 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
74 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
75 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
76 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
77 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
78 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
79 Stress at bottom of girder (43 + 54) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
80 Stress at top of girder (44 + 55) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
93 Stress at bottom of girder (66 + 77 + 91) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
94 Stress at top of girder (67 + 78 + 92) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
DESIGN OF INTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
VII Second Stage Stressing of Cable 2 (28th day)
95 Permissible compressive stress 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
96 Permissible tensile stress -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00
97 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
98 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
99 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
100 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
101 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
102 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
103 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
104 Stress due to Moment at bottom of girder (sb = (P / Ac) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
105 Stress due to Moment at top of girder (st = (P / Ac) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
106 Stress at bottom of girder (70 + 81) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
107 Stress at top of girder (71 + 82) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant Stresses
120 Stress at bottom of girder (93 + 104 + 118) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
121 Stress at top of girder (94 + 105 + 119) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
X Differential Shrinkage (Composite section)
130 Restraining force (kN) 2242.67 2242.67 2242.67 2242.67 2242.67 2242.67 2242.67 2242.67 2242.67
131 Moment due to restraning force (kN-m) 729.99 664.95 664.95 664.95 664.95 664.95 664.95 664.95 729.99
132 Stress at bottom of girder (N/mm2 ) -2.08 -1.70 -1.70 -1.70 -1.70 -1.70 -1.70 -1.70 -2.08
133 Stress at top of girder 4.12 4.32 4.32 4.32 4.32 4.32 4.32 4.32 4.12
135 Stress at top of slab 2.79 1.43 1.43 1.43 1.43 1.43 1.43 1.43 2.79
XI Moment due to SIDL (KN-m) x 9.81 -0.49 96.04 499.62 585.36 661.98 585.36 499.62 96.04 -0.49
139 Stress due to Moment at bottom of girder (sb = (M / Zbgc) 0.00 -0.58 -3.40 -3.99 -4.51 -3.99 -3.40 -0.58 0.00
140 Stress due to Moment at top of girder (st = (M / Ztgc) 0.00 0.19 0.92 1.08 1.22 1.08 0.92 0.19 0.00
141 Stress due to Moment at top of slab (sts = (M / Ztsc) 0.00 0.39 2.00 2.34 2.65 2.34 2.00 0.39 0.00
Resultant stresses after SIDL
142 Stress at bottom of girder (136 + 139) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
143 Stress at top of girder (137+ 140) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
145 Stress at top of slab (138+ 141) 2.78 1.82 3.43 3.77 4.08 3.77 3.43 1.82 2.78
Permissible Compressive stress at service = 0.33fck (Mpa) 14.85 14.85 14.85 14.85 14.85 14.85 14.85 14.85 14.85
XII Moment due to LL x 9.81 (kN-m) -6.87 128.90 685.62 868.38 1047.12 868.38 685.62 128.90 -6.87
146 Stress due to Moment at bottom of girder (sb = (M / Zbc) 0.04 -0.78 -4.67 -5.92 -7.14 -5.92 -4.67 -0.78 0.04
147 Stress due to Moment at top of girder (st = (M / Ztc) -0.01 0.26 1.26 1.60 1.93 1.60 1.26 0.26 -0.01
148 Stress due to Moment at top of slab (sts = (M / Ztsc) -0.03 0.52 2.74 3.48 4.19 3.48 2.74 0.52 -0.03
Final stresses after LL
149 Stress at bottom of girder (42 + 46) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
150 Stress at top of girder (43 + 47) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
151 Stress at top of slab (44+ 48) 2.76 2.34 6.18 7.25 8.27 7.25 6.18 2.34 2.76
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Relaxation loss
167 Relaxation loss % for 0.765 fp (Ref Table 4A of IRC:18-2000) 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50%
168 Loss in force due to relaxation P = -(167 x 3.0 x (3+22+34+72+84+99+111)/100.0 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
169 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
170 Stress due to Moment at bottom of girder (sb = (P / Ac) - (M / Zbgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
171 Stress due to Moment at top of girder (st = (P / Ac) + (M / Ztgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
172 Stress due to Moment at top of slab (sts = (P / Ac) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Resultant stresses after losses
173 Stress at bottom of girder (149 + 158 + 164 + 170) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
174 Stress at top of girder (150 + 159 + 165 + 171) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
175 Stress at top of slab (151 + 160 + 166 + 172) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Assuming failure by Yield of steel,
196 fck M45 M45 M45 M45 M45 M45 M45 M45 M45
197 Width of web 650 650 275 275 275 275 275 650 650
198 Thickness of slab, t 220 220 220 220 220 220 220 220 220
199 Bf 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
200 db (Hc -152) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
201 fp 1860 1860 1860 1860 1860 1860 1860 1860 1860
202 c/s area of cables ( 2 + 21+ 71 + 97) 4738 4738 4738 4738 4738 4738 4738 4738 4738
203 Mult = (0.9 x 200 x 1000.0 x 202 x 201) / 10^6 (Ref IRC : 18-2000) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Assuming failure by crushing of concrete,
Mult =((0.176 x 197 x (200 x 1000)^2 x fck)+(2 x 0.8 x ((199x1000)-197) x ((200 x
204
1000)-(198/2)x 198 x fck)) / 10^6 (Ref IRC : 18-2000) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl.No. Description Prestress BM at top of slab at top of girder at bottom of girder Deflection (mm)
1 Pre-stress effect I Stage (Cable 1 & 3) Err:511 Err:511 - Err:511 Err:511 Err:511
2 Self weight of girder - 63.65 - 933.45 -818.01 23.467
Resultant after first stage pre-stress Err:511 Err:511 - Err:511 Err:511 Err:511
3 Instant losses of Stage I Err:511 Err:511 - Err:511 Err:511
Resultant Err:511 Err:511 - Err:511 Err:511
4 Pre-stress effect II Stage Err:511 Err:511 - Err:511 Err:511 Err:511
Instant losses of Stage II (including losses in I stage due
5 to II stage pre-stress) Err:511 Err:511 - Err:511 Err:511
6 Long term losses in I stage Err:511 Err:511 - Err:511 Err:511
Resultant after second stage pre-stress Err:511 Err:511 - Err:511 Err:511 Err:511
7 Effect of deck slab - 61.63 - 127.76 -473.47 5.3
Resultant Err:511 Err:511 - Err:511 Err:511 Err:511
8 Effect of Differential shrinkage - 56.71 146.04 440.45 -172.98
Resultant Err:511 Err:511 146.04 Err:511 Err:511
9 Super imposed dead loads - 69.19 270.22 124.16 -460.10 3.129
Resultant Err:511 Err:511 416.26 Err:511 Err:511 Err:511
10 Long term losses in II stage Err:511 Err:511 Err:511 Err:511 Err:511
Resultant (Stress at service condition w/o LL) Err:511 Err:511 Err:511 Err:511 Err:511
11 Vehicular live load - 96.04 427.43 196.39 -727.79 6.943
Resultant (Stress at service condition) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
12 Additional 20% long term losses Err:511 Err:511 Err:511 Err:511 Err:511
Stresses at service condition considering 20%
additional losses. Err:511 Err:511 Err:511 Err:511 Err:511
Temporary actual compressive stress = Err:511 Temp. perm. Comp. stress at 7th day = 1785.00 MT / m2
Temporary actual tensile stress = -146.04 MT / m2 Temp. perm. Comp. stress at 28th day = 2040.00 MT / m2
Actual compressive stress = Err:511 Temp. perm. tensile stress 7th day = 178.50 MT / m2
Residual compressive stress at bottom = Err:511 Temp. perm. tensile stress 28th day = 204.00 MT / m2
(No tension is permitted) Permissible compressive stress = 1514.70 MT / m2
Ratio of span to Deflection = Err:511
Effect of Differential Shrinkage @ Support section
Force due to differential shrinkage is calculated as per BS 5400 PART 4 - 1990
At the time of casting deck slab, the girder is at full strength with no moisture content.
And girder has been already attained maximum shrinkage when casting of deck slab over it.
Deck slab starts shrinking at 2nd day from date of casting. (i.e. age at shrinkage starts = 1 day)
Deck slab attains a maximum shrinkage at 28 days from the date of casting the deck slab.
(Table 29 - BS 5400-4:1990)
Force, F = h.A.E.esh
Where, h = 0.43 Reduction coefficient as per clause 7.4.3.4 BS 5400 PART 4 -1990
Area of deck slab, A = 0.777 m 2
C/S Area of deck slab (3m width x 259mm average depth)
E = 3421184.01 MT/m Young's modules of deck slab concrete at 28 days
2
esh = 0.0002
This force will act at a distance of 129.5 mm. above top of Girder.( i.e at centre of Deck slab )
M 45
Outer Girder-Left
Section properties (Composite girder properties used)
Composite area of girder, Ac = 0.909 m2
Ybc = 0.646 m
Ytc = 0.455 m
Zbgc = 0.160 m3
Ztgc = 0.443 m3
Zbsc = 0.443 m3
Ztsc = 0.228 m3
Hc = 1.101 m
Differential shrinkage Force, F = -2242.67 kN
Moment, M = -729.99 kNm
Stress calculation
Top of Slab = 2.787 N/mm2
Junction of slab & girder = 1.230 N/mm2
Top of girder = 4.116 N/mm2
Effect of Differential Shrinkage @ Mid section
Force due to differential shrinkage is calculated from BS 5400 PART 4 - 1990
Force, F = h.A.E.esh
h = 0.43 Reduction coefficient as per clause 7.4.3.4 BS 5400 PART 4 -1990
A = 0.777 m2 C/S Area of deck slab
E = 3421184.01 MT/m2 Young's modules of deck slab concrete at 28 days
esh = 0.0002 Differential shrinkage strain as per Appendix C of BS 5400 PART 4 - 1990
This force will act at a distance of 129.5 mm. above top of Girder.( i.e at centre of Deck slab )
Stress Calculations
Outer Girder-Left
Section properties
Ac = 0.767 m2
Ybc = 0.676 m
Ytc = 0.426 m
Zbgc = 0.144 m3
Ztgc = 0.477 m3
Zbsc = 0.477 m3
Ztsc = 0.228 m3
Hc = 1.102 m
Force, F = -2242.67 kN
Moment, M = -664.95 kNm
Stress calculation
Top (N/mm2) of Slab = 2.949 N/mm2
Junction of slab & girder = 1.432 N/mm2
Top (N/mm2) of girder = 4.318 N/mm2
Stress Calculations for Temperature Rise (Support section)
h= 1101 mm h2 = 250 mm
h1 = 150 mm h3 = 150 mm
Summary of stresses:
Outer Girder-
Distance Left
Depth m 1.101
Area (m )2
0.909
Yt (m) 0.455
Yb (m) 0.646
Zt (m3) 0.228
Zbs (m )3
0.443
Ztg (m )3
0.443
Zb (m )3
0.160
CG of Moment
Stress due Total force Force of force
Dist. Of fiber from Temp. at Width of temp. between from top about Top
Fiber No the top fiber fiber resistance Force fibers of slab of Slab
units m o
c m Mpa MN/m MN m MN-m
Summary of stresses:
Outer
Girder-
Distance Left
Depth (m) 1.101
Area (m )
2
0.909
Yt (m) 0.455
Yb (m) 0.646
Icg (m )
4
0.104
Zt (m3) 0.228
Zbs (m )
3
0.443
Ztg (m )
3
0.443
Zb (m3) 0.160
Force (kN) -854
Eigen Moment (kN-m) -1066
Secondary Moment (kN-m)
Moment kNm -1066
Stress due to resisting force (N/mm2)
Top of slab -4.160
Bottom of Slab 0.251
Top of Girder 0.251
Bottom of Girder -2.590
Outer
Girder-
Distance Left
Stress due to equivalent force (N/mm2)
Top of slab 0.939
Bottom of Slab 0.939
Top of Girder 0.939
Bottom of Girder 0.939
Stress due to Eigen Moment (N/mm2)
Top of slab 4.683
Bottom of Slab 2.409
Top of Girder 2.409
Bottom of Girder -6.649
Stress (N/mm2) due to Secondary Moment
Top of slab 0.000
Bottom of Slab 0.000
Top of Girder 0.000
Bottom of Girder 0.000
Combined Stress (N/mm )2
h= 1102 mm h2 = 250 mm
h1 = 150 mm h3 = 150 mm
Summary of stresses:
Outer Girder-
Distance Left
Depth m 1.102
Area (m )2
0.767
Yt (m) 0.426
Yb (m) 0.676
Zt (m3) 0.228
Zbs (m )3
0.523
Ztg (m )3
0.523
Zb (m )3
0.144
CG of Moment
Stress due Total force Force of force
Dist. Of fiber from Temp. at Width of temp. between from top about Top
Fiber No the top fiber fiber resistance Force fibers of slab of Slab
units m o
c m Mpa MN/m MN m MN-m
Summary of stresses:
Outer
Girder-
Distance Left
Depth (m) 1.102
Area (m )
2
0.767
Yt (m) 0.426
Yb (m) 0.676
Icg (m )
4
0.097
Zt (m3) 0.228
Zbs (m )
3
0.523
Ztg (m )
3
0.523
Zb (m3) 0.144
Force (kN) -884
Eigen Moment (kN-m) -1022
Secondary Moment (kN-m)
Moment kNm -1022
Stress due to resisting force (N/mm2)
Top of slab -4.160
Bottom of Slab 0.251
Top of Girder 0.251
Bottom of Girder -2.590
Outer
Girder-
Distance Left
Stress due to equivalent force (N/mm2)
Top of slab 1.152
Bottom of Slab 1.152
Top of Girder 1.152
Bottom of Girder 1.152
Stress due to Eigen Moment (N/mm2)
Top of slab 4.474
Bottom of Slab 1.954
Top of Girder 1.954
Bottom of Girder -7.100
Stress (N/mm2) due to Secondary Moment
Top of slab 0.000
Bottom of Slab 0.000
Top of Girder 0.000
Bottom of Girder 0.000
Combined Stress (N/mm )2
A B D E G H J
C F I
0
Distence from Mid 1 Mid 2 Mid 3
3m 3m 3m
MAIN REINFORCEMENT
Note : The Max. BM are obtained from STAAD-Pro.
DISTRIBUTION REINFORCEMENT
Note : The Max. BM for distribution steel from as per IRC-21 ( Page No:56)
Max MB= 0.3 (LL-BM) + 0.2 (DL-BM)
Distence
Bending from 'o' Dead Load Live Load Max BM (d)eff req (d)eff act Ast req
nature Location in m BM BM in KN-m in mm in mm in mm2
Hog A 1.1 10.141 17.10 7.16 50.98 194 215.27
Hog B 1.9 11.129 26.95 10.31 61.18 194 310.06
Sag C Mid 1 1.77 51.19 15.71 75.52 194 472.51
Hog D 4.1 1.25 25.49 7.90 53.55 194 237.52
Hog E 4.9 0.545 31.78 9.64 59.17 194 290.02
Sag F Mid 2 4.964 43.95 14.18 71.74 194 426.42
Hog G 7.1 0.545 25.31 7.70 52.88 194 231.64
Hog H 7.9 1.251 25.80 7.99 53.86 194 240.30
Sag I Mid 3 1.77 50.43 15.48 74.97 194 465.61
Sag J 10.1 11.129 6.09 4.05 38.36 194 121.90
Hog K 10.9 10.141 0.00 2.03 27.13 194 61.00
spacing
Area of req
Dia of bars each bar in mm
16 201.0619 242.9
16 201.0619 173.8
16 201.0619 124.9
16 201.0619 247.4
16 201.0619 204.7
16 201.0619 135.3
16 201.0619 255.9
16 201.0619 244.6
16 201.0619 126.8
16 201.0619 384.2
16 201.0619 652.5
spacing
Area of req
Dia of bars each bar in mm
12 113.0973 525.4
12 113.0973 364.8
12 113.0973 239.4
12 113.0973 476.2
12 113.0973 390
12 113.0973 265.2
12 113.0973 488.3
12 113.0973 470.7
12 113.0973 242.9
12 113.0973 927.8
12 113.0973 1854.2
Analysis and Design of cantilever Deck Slab
Load calculation:
self weight = 1 t/m or 10 KN/m
wearing coat = 0.165 t/m or 1.65 KN/m
Live load
Type of load 70R (Bogi). 70R(Track) 70R (Wheel) ClassA
Load in single wheel 100 KN 77 KN/m 85 KN 57 KN
Moment calculation:
Moveing direction
C Contact area on slab
A 378
400 mm thick of slab
360
0.853 m
w= 378 mm
1.25 m D= 400 mm
dwc= 75 mm
Impact factor = 1.25
840
….. Effective length of dispersion is leff= w+ 2(D+dwc)
= 1.328 m
410 410
Actual disparsion length on slab= 0.853 m
b1= breadth of tyre over the road surface of the slab in the direction
parallel to supporting edge plus twice the thickness of wearing coat
= 0.51 m
100 x1.25
.'. Equalent load=
0.853 1.98
= 74.08 KN
MAIN REINFORCEMENT
(d)eff spacing
Bending Max BM req (d)eff act Ast req Area of req
nature Location in KN-m in mm in mm in mm2 Dia of bars each bar in mm
Hog A 64.93 153.52 352 1076.14 16 201.062 186.8
DISTRIBUTION REINFORCEMENT
Note : The Max. BM for distribution steel from as per IRC-21 ( Page No:56)
Max MB= 0.3 (LL-BM) + 0.2 (DL-BM)
(d)eff spacing
Bending Max BM req (d)eff act Ast req Area of req
nature Location in KN-m in mm in mm in mm2 Dia of bars each bar in mm
Hog A 18.19 81.26 346 306.70 12 113.097 368.8
200
12 @ 200 c/c
300
246
VL = 133.21 MT/m
= 1306.83 kN/m
Shear connector provided / m length of Girder
16 mm dia @ 200 mm c/c
Number of shear connector per meter of Girder = 1000/100 + 1 = 11 nos.
SQu = 1000/Spacing x 2 x As fu
As = Area of shear connector = 2 * PI * 12^2/4 = 402.12 mm2
fu = Ultimate tensile strength of shear connector = 415 N/mm2
SQu = 834407 N = 834.41 KN
Provided 5 Nos. of shear connecter
= ΣQu / VL for spacing of shear connector provided = 0.638 >1
Hence OK
Check for deflection @ MID SPAN
Deflections due to prestress
Grade of concrete = M 45
Span length , l = 27160 mm e1 =Eccentricity @ mid span
Girder depth = 1962.5 mm e2 =Eccentricity @ anchorage
Girder length = 28160 mm
Mod. of elasticity of concrete E= 33.5 kN/mm2
Cable - 4
Moment of Inertia,I = 97300000000 mm4
Load P = Err:511 kN 696
Eccentricity, e1 = 926 mm 926
Eccentricity, e2 = 696 mm 1046
120
Cable - 3
Moment of Inertia,I = 97300000000 mm4
Load P = Err:511 kN 346
Eccentricity, e1 = 746 mm 746
Eccentricity, e2 = 346 mm
1046 300
Cable - 2
Moment of Inertia,I = 97300000000 mm4
Load P = Err:511 kN 4
Eccentricity, e1 = 566 mm
Eccentricity, e2 = 4 mm
566
1046
480
Deflection δ = Err:511
δ= Err:511 mm
Cable - 1
Moment of Inertia,I = 97300000000 mm4
Load P = Err:511 kN
Eccentricity, e1 = 386 mm
Eccentricity, e2 = 354 mm 354
386
1046
660
Deflection δ = Err:511
δ= Err:511 mm
Total deflection due to prestress
Total deflection, δ = Err:511
δ1= Err:511 mm Upward
External Internal
Girders,(mm) Girders,(mm)
Deflection due to DL= 11.978 11.884
Deflection due to SIDL= 3.77 3.129
Deflection due to LL= 8.528 6.943
Total deflection , δ2 = 24.276 21.956
(Downword)
Net deflection (Short term)
For External girder = Err:511
Err:511 mm Downward
For internal girder = Err:511
Err:511 mm Downward
Hence
Err:511 Err:511 77.60 Err:511 External Girders
Err:511 Err:511 77.60 Err:511 Internal Girders
Longterm Deflections
δ = (δ2 - δ1 x Pt/Pi) x (1+ φ)
Deflection due to Prestress δ1 = Err:511 mm
Deflection due to DL,SIDL,&LL δ2 = 24.276 mm External Girders
Deflection due to DL,SIDL,&LL δ2 = 21.956 mm Internal Girders
Creep coefficient φ = 1.8
Grade of concrete = M 45
Grade of steel = Fe 415
Allowable stress in concrete = 15 MPa
Allowable stress in steel = 200 MPa
Modular ratio = 10
k= 0.429
j= 0.857
Q= 2.755
Width of diaphragm = 350mm
Height of diaphragm = 1570mm
Clear cover = 40mm
Dia of bar = 25mm
Effective cover = 53mm
Dia of stirrup provided = 10mm
Effective depth provided = 1508mm
Service condition results
For END diaphragm HM SM SF
Dead load case 0.3600 0.1200 1.6400
SIDL case 9.2100 2.0300 5.5100
Live load case 12.2200 11.4300 12.3900
Design moment 21.7900 13.5800 19.5400
Shear Check:
Shear force = 27.96 ton
Actual shear stress = 0.47 MPa
Total Ast provided = 3220.13mm2
Pt provided = 0.54
Permissible shear stress = 0.31 MPa Design shear reft.
Dia of stirrup = 10 Vs = V -tc bd
No of legs = 2 9.35 MT
Asw = 157.08mm2
Spacing of stirrup = 300mm
Design of precast slab:
Data:
Grade of concrete = M45
m= 10
sbc = 15.00Mpa
Permissible stress in steel = 200.00Mpa
k= 0.4286
j= 0.8571
Q= 2.7551
c/c distance between girders = 3.00m
Width of top flange = 0.80m
Clear distance between flanges of girders = 2.20m
Thickness of deck slab = 0.24m
Selfweight of slab = 0.576t/m2
Construction live load = 0.080t/m2
Total load on precast slab = 0.656t/m2
Assume bearing of slab inside the flange = 0.100m
Effective span = 2.400m
This bridge is falling in curve road geometry, and needs to be analysed for centrifugal force.
Analysis for exact effect due to centrifugal force involves more rigorous analysis procedure.
To cater for the effect due to centrifugal force on longitudinal stress in deck cross section,
an impact percentage has been added to the usual impact factor.
pe
s urfac e 5.55 % sloslope
road surface 5.55 % 3.177° Horizontal line
road
Percentage of W acting to increase longitudinal stress in deck is given as
2 Change in length due to long term Creep as per IRC18 -2000 Table-2 Page No16
3 Change in length due to long term Shrinkage as per IRC18 -2000 Table-3 Page No17
Pocket 350
300 300
Yo Yo
fcj = Grade of Concrete of Girder when stressing 1st cable = 35.0 Mpa
A1 = 0.245*0.245 = 0.060025 m2
A2 = 0.35*0.35 = 0.1225 m2
Hence OK
Hence allowable stress behind anchorage has been suitably increased by providing hoop
reinforcement. CEB-FIPmodel code has been used to calculate the increase in permissible
bearing stress.
Where,
u = perimeter of hoop = pi*(0.3 + 0.016) = 0.993 m
s = hoop spacing = 0.060 m
As = Cross sectional area of hoop reinforcement = 201 mm2
fyd = design strength of hoop = 0.87 * 415 = 361.05 N/mm2
Ac1=245×245 = 60025 mm2
AC2 = Area of concrete within hoop reinforcement
= pi/4 * 0.24^2 = 45238.9 mm2
fcd = 0.8 * fcj / 1.5 = 18.67 N/mm2
Msdu = Maximum moment in hoop reinforcement zone = 0.00
Hence OK
2Ypo = = 350
2Yo = = 245
Ypo / Yo = = 0.7000
Fbst = = 18.9 KN
Allowable stress in steel = 0.87fy = 0.87*415 = 361.1 N/mm2
Ast required = 18.897* 1000 / 361.05 = 52 mm2
Provide Nos. 6
Dia. 16
legged 2
OK
This reinforcement shall be provided in a zone 0.2 Yo = 35 mm from face to
2Yo = 350 mm
0.3659
0.1500 Err:511 Err:511 Err:511 0.3756 girder length 17.05
0.4000 Err:511 Err:511 Err:511 C1 C2 C3 8.525
1.2125 Err:511 Err:511 Err:511 E1 1.3608 0.9852 0.6193
2.0250 Err:511 Err:511 Err:511 E2 0.4600 0.2900 0.1200
2.8375 Err:511 Err:511 Err:511 E3 1.3608 0.9852 0.6193
3.6500 Err:511 Err:511 Err:511 ST 0.7500 0.7500 0.7500
4.4625 Err:511 Err:511 Err:511 L1 0.0000 0.0000 0.0000
5.2750 Err:511 Err:511 Err:511 L2 7.2750 6.7750 6.2750
6.0875 Err:511 Err:511 Err:511 MID 1.0000 2.0000 3.0000
6.9000 Err:511 Err:511 Err:511 L3 7.2750 6.7750 6.2750
7.7125 Err:511 Err:511 Err:511 L4 0.0000 0.0000 0.0000
8.5250 Err:511 Err:511 Err:511 ST 0.7500 0.7500 0.7500
9.3375 Err:511 Err:511 Err:511
10.1500 Err:511 Err:511 Err:511 Err:511 Err:511
10.9625 Err:511 Err:511 Err:511 1.4650
11.7750 Err:511 Err:511 Err:511 1.1650
12.5875 Err:511 Err:511 Err:511 0.8050
13.4000 Err:511 Err:511 Err:511 0.4450
14.2125 Err:511 Err:511 Err:511
15.0250 Err:511 Err:511 Err:511
15.8375 Err:511 Err:511 Err:511
16.6500 Err:511 Err:511 Err:511
16.9000 Err:511 Err:511 Err:511
16.90
DESIGN OF EXTERNAL PSC GIRDER & CHECK FOR STRESSES: SUPPORT D FROM SUP. 0.25L 0.33L L/2 0.66L 0.75L D FROM SUP. SUPPORT
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
I Properties of Precast section
A 0.556 0.556 0.416 0.416 0.416 0.416 0.416 0.416 0.416
Yb 0.431 0.431 0.411 0.411 0.411 0.411 0.411 0.411 0.411
Yt 0.449 0.449 0.469 0.469 0.469 0.469 0.469 0.469 0.469
Zb 0.079 0.079 0.078 0.078 0.078 0.078 0.078 0.078 0.078
Zt 0.076 0.076 0.068 0.068 0.068 0.068 0.068 0.068 0.068
Ix 0.034 0.034 0.032 0.032 0.032 0.032 0.032 0.032 0.032
H 0.8800 0.8800 0.8800 0.8800 0.8800 0.8800 0.8800 0.8800 0.8800
(Ay)p 1.79E+07 1.79E+07 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06
II Properties of composite section
Ac 0.909 0.909 0.767 0.767 0.767 0.767 0.767 0.767 0.767
Ybc 0.646 0.646 0.676 0.676 0.676 0.676 0.676 0.676 0.676
Ytc 0.455 0.455 0.426 0.426 0.426 0.426 0.426 0.426 0.426
Zbgc 0.160 0.160 0.144 0.144 0.144 0.144 0.144 0.144 0.144
Ztgc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 0.477 0.477
Zbsc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 0.477 0.477
Ztsc 0.228 0.228 0.228 0.228 0.228 0.228 0.228 0.228 0.228
Ixc 0.104 0.104 0.097 0.097 0.097 0.097 0.097 0.097 0.097
Hc 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100
Slab thickness 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220
Effective flange width 1.525 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53
(Ay)c 1.34E+08 1.34E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08
III Material Properties
Grade Initial 30.29 30.29 30.29 30.29 30.29 30.29 30.29 30.29 30.29
Grade Final 45 45 45 45 45 45 45 45 45
Ec, initial 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66
Ec, final 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02
Es 195000 195000 195000 195000 195000 195000 195000 195000 195000
First stage stressing (N) @ 7 7 7 7 7 7 7 7 7
Second stage stressing (N1) @ 28 28 28 28 28 28 28 28 28
IV Stressing Sequence
Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 1 (7th day)
1 No of strands (Ref Page No ) 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
2 c/s area of strand (Ref Page No ) 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
3 Jacking force after slip losses (P) KN (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 Distance from base of girder (Yx) (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
8 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
10 Final Stresses
11 Stress at bottom of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
12 Stress at top of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
13 Moment due to selfweight of girder ( KN-m) 0.00 96.43 472.84 554.17 624.41 554.17 472.84 96.43 0.00
14 Stress at bottom of girder ( 13 / Zb ) 0.00 -1.22 -6.07 -7.12 -8.02 -7.12 -6.07 -1.24 0.00
15 Stress at top of girder ( 13 / Zt ) 0.00 1.27 6.93 8.12 9.15 8.12 6.93 1.41 0.00
Final Stresses
16 Stress at bottom of girder (11 + 14) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
17 Stress at top of girder (12 + 15) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
18 Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
19 Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 3 (7th day)
20 No of strands (Ref Page No ) 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
21 c/s area of strand (Ref Page No ) 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
22 Jacking force after slip losses (P) KN (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
23 Distance from base of girder (Yx) (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
24 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
25 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
26 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
27 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
28 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
29 Stress at bottom of girder (16 + 27) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
30 Stress at top of girder (17 + 28) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
44 Stress at bottom of girder (29 + 42) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
45 Stress at top of girder (30 + 43) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Moment due to SIDL (KN-m) 2.65 106.14 513.75 600.57 678.75 600.57 513.75 106.14 2.65
64 Stress due to Moment at bottom of girder (sb = (M / Zbgc) -0.02 -0.66 -3.57 -4.17 -4.72 -4.17 -3.57 -0.74 -0.02
65 Stress due to Moment at top of girder (st = (M / Ztgc) 0.01 0.24 1.08 1.26 1.42 1.26 1.08 0.22 0.01
66 Stress due to Moment at bot of slab (sbs = (M / Zbsc) 0.01 0.24 1.08 1.26 1.42 1.26 1.08 0.22 0.01
67 Stress due to Moment at top of slab (sts = (M / Ztsc) 0.01 0.47 2.25 2.63 2.97 2.63 2.25 0.46 0.01
Final stresses after SIDL
68 Stress at bottom of girder (60 + 64) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
69 Stress at top of girder (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
70 Stress at bottom of slab (61+ 65) -1.67 -1.29 -0.46 -0.27 -0.11 -0.27 -0.46 -1.31 -1.67
71 Stress at top of slab (61+ 65) -0.54 0.30 2.09 2.47 2.81 2.47 2.09 0.30 -0.54
72 Permissible compressive stress 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
73 Permissible tensile stress -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00
74 No of strands (Ref Page No ) 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
75 c/s area of strand (Ref Page No ) 1184.4 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40
76 Jacking force after slip losses (P) KN (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
77 Distance from base of girder (Yx) (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
78 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
79 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
80 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
81 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zbgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
82 Stress due to Moment at top of girder (st = (P / A) - (M / Ztgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
83 Stress due to Moment at bot of slab (sbs=(P / A) - (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
84 Stress due to Moment at top of slab (sts =(P / A) - (M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
85 Stress at bottom of girder (47 + 58) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
86 Stress at top of girder (48 + 59) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
87 Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
88 Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
104 Stress at bottom of girder (60 + 73) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
105 Stress at top of girder (61 + 74) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
106 Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
107 Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
121 Stress at bottom of girder (47 + 58) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
122 Stress at top of girder (48 + 59) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
123 Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
124 Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
138 Stress at bottom of girder (60 + 73) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
139 Stress at top of girder (61 + 74) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
IX Moment due to LL (Ref Page No x 10) -1.77 105.56 650.40 799.22 942.15 799.22 650.40 105.56 -1.77
155 Stress due to Moment at bottom of girder (sb = (M / Zbc) 0.01 -0.66 -4.52 -5.55 -6.55 -5.55 -4.52 -0.73 0.01
156 Stress due to Moment at top of girder (st = (M / Ztc) 0.00 0.24 1.36 1.68 1.98 1.68 1.36 0.22 0.00
Stress due to Moment at bot of slab (sbs= (M / Zbsc) 0.00 0.24 1.36 1.68 1.98 1.68 1.36 0.22 0.00
Stress due to Moment at top of slab (sts = (M / Ztsc) -0.01 0.46 2.85 3.50 4.12 3.50 2.85 0.46 -0.01
157 Final stresses after LL
158 Stress at bottom of girder (90 + 92) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
159 Stress at top of girder (91 + 93) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
X Longterm losses
160 cg of cable group (( 1x 4) + (20 x 23) + (51 x 54)) / (1+20+51) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
161 Eccentricty e = (Ybc -97) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
162 Creep loss
163 Creep strain (Ref Page No of IRC:18-2000) 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044
164 Stress at level of steel ((95-96) x 97 / Hc) + 96 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
165 Loss in force due to creep P = ( 101 x (100 / 10) x Es x (2 + 21+ 52) / 1000) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
166 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
167 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
168 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at bot of slab (sbs= (P / A) + (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
169 Shrinkage loss
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
170 Shrinkage strain (Ref Page No of IRC:18-2000) 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020
171 Loss in force due to shrinkage P = (107 X Es x( 2 + 21 + 52 ) / 1000) -184.77 -184.77 -184.77 -184.77 -184.77 -184.77 -184.77 -184.77 -184.77
172 Moment Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
173 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
174 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at bot of slab (sbs= (P / A) + (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
175 Relaxation loss
176 Relaxation loss (Ref Page No of IRC:18-2000) 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50%
177 Loss in force due to relaxation P = ( 113 x 3 x (3 + 22 + 35 + 53 + 66)/1000 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
178 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
179 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
180 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at bot of slab (sbs= (P / A) + (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
181 Final stresses after losses
182 Stress at bottom of girder ( 95 + 104 + 110 + 116) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
183 Stress at top of girder ( 96 + 105 + 111 + 117) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
215 Longitudinal reinforcement (mm2) = (0.18 x A X 10^6 / 10^2) 1000.8 1000.8 748.8 748.8 748.8 748.8 748.8 748.8 748.8
216 Vertical Reinforcement (@ mid)(mm2) = (0.18 x 600 x 1000)/100 1080 1080 1080 1080 1080 1080 1080 1080 1080
217 Vertical Reinforcement(@ sup)(mm2)= (0.18 x 450x1000)/100 810 810 810 810 810 810 810 810 810
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
I Properties of Precast section
A 0.556 0.556 0.416 0.416 0.416 0.416 0.416 0.416 0.416
Yb 0.431 0.431 0.411 0.411 0.411 0.411 0.411 0.411 0.411
Yt 0.449 0.449 0.469 0.469 0.469 0.469 0.469 0.469 0.469
Zb 0.079 0.079 0.078 0.078 0.078 0.078 0.078 0.078 0.078
Zt 0.076 0.076 0.068 0.068 0.068 0.068 0.068 0.068 0.068
Ix 0.034 0.034 0.032 0.032 0.032 0.032 0.032 0.032 0.032
H 0.880 0.88 0.88 0.88 0.8800 0.88 0.88 0.88 0.88
(Ay)p 1.79E+07 1.79E+07 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06
II Properties of composite section
Ac 0.909 0.909 0.767 0.767 0.767 0.767 0.767 0.767 0.767
Ybc 0.646 0.646 0.676 0.676 0.676 0.676 0.676 0.676 0.676
Ytc 0.455 0.455 0.426 0.426 0.426 0.426 0.426 0.426 0.426
Zbgc 0.160 0.160 0.144 0.144 0.144 0.144 0.144 0.144 0.144
Ztgc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 0.477 0.477
Zbsc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 0.477 0.477
Ztsc 0.228 0.228 0.228 0.228 0.228 0.228 0.228 0.228 0.228
Ixc 0.104 0.104 0.097 0.097 0.097 0.097 0.097 0.097 0.097
Hc 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100
Slab thickness 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220
Effective flange width 1.525 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53
(Ay)c 1.34E+08 1.34E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08
III Material Properties
Grade Initial 30.29 30.29 30.29 30.29 30.29 30.29 30.29 30.29 30.29
Grade Final 45 45 45 45 45 45 45 45 45
Ec, initial 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66
Ec, final 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02
Es 195000 195000 195000 195000 195000 195000 195000 195000 195000
First stage stressing (N) @ 7 7 7 7 7 7 7 7 7
Second stage stressing (N1) @ 35 35 35 35 35 35 35 35 35
IV Stressing Sequence
Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 1 (7th day)
1 No of strands (Ref Page No ) 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
2 c/s area of strand (Ref Page No ) 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
3 Jacking force after slip losses (P) KN (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 Distance from base of girder (Yx) (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
8 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
10 Final Stresses
11 Stress at bottom of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
12 Stress at top of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
13 Moment due to selfweight of girder (Ref Page No x 9.81 0.00 96.43 472.84 554.17 624.41 554.17 472.84 96.43 0.00
14 Stress at bottom of girder ( 13 / Zb ) 0.00 -1.22 -6.07 -7.12 -8.02 -7.12 -6.07 -1.24 0.00
15 Stress at top of girder ( 13 / Zt ) 0.00 1.27 6.93 8.12 9.15 8.12 6.93 1.41 0.00
Final Stresses
16 Stress at bottom of girder (11 + 14) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
17 Stress at top of girder (12 + 15) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
18 Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
19 Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 3 (7th day)
20 No of strands (Ref Page No ) 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
21 c/s area of strand (Ref Page No ) 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
22 Jacking force after slip losses (P) KN (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
23 Distance from base of girder (Yx) (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
24 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
25 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
26 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
27 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
28 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
29 Stress at bottom of girder (16 + 27) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
30 Stress at top of girder (17 + 28) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
44 Stress at bottom of girder (29 + 42) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
45 Stress at top of girder (30 + 43) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
VI Stressing of Cable 4 (7th day)
68 Permissible compressive stress 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
69 Permissible tensile stress -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
70 No of strands (Ref Page No ) 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
71 c/s area of strand (Ref Page No ) 1184.4 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40
72 Jacking force after slip losses (P) KN (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
73 Distance from base of girder (Yx) (Ref Page No ) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
74 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
75 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
76 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
77 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zbgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
78 Stress due to Moment at top of girder (st = (P / A) - (M / Ztgc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
79 Stress at bottom of girder (47 + 58) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
80 Stress at top of girder (48 + 59) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
94 Stress at bottom of girder (60 + 73) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
95 Stress at top of girder (61 + 74) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Moment due to SIDL (Ref Page No x 9.81) 2.65 106.14 513.75 600.57 678.75 600.57 513.75 106.14 2.65
64 Stress due to Moment at bottom of girder (sb = (M / Zbgc) -0.02 -0.66 -3.57 -4.17 -4.72 -4.17 -3.57 -0.74 -0.02
65 Stress due to Moment at top of girder (st = (M / Ztgc) 0.01 0.24 1.08 1.26 1.42 1.26 1.08 0.22 0.01
Stress due to Moment at bot of slab (sbs = (M / Zbsc) 0.01 0.24 1.08 1.26 1.42 1.26 1.08 0.22 0.01
Stress due to Moment at top of slab (sts = (M / Ztsc) 0.01 0.47 2.25 2.63 2.97 2.63 2.25 0.46 0.01
Final stresses after SIDL
66 Stress at bottom of girder (60 + 64) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
67 Stress at top of girder (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) -1.67 -1.29 -0.46 -0.27 -0.11 -0.27 -0.46 -1.31 -1.67
Stress at top of slab (61+ 65) -0.54 0.30 2.09 2.47 2.81 2.47 2.09 0.30 -0.54
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
Final Stresses
107 Stress at bottom of girder (47 + 58) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
108 Stress at top of girder (48 + 59) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
122 Stress at bottom of girder (60 + 73) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
123 Stress at top of girder (61 + 74) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
IX Moment due to LL (Ref Page No x 10) -1.77 105.56 650.40 799.22 942.15 799.22 650.40 105.56 -1.77
139 Stress due to Moment at bottom of girder (sb = (M / Zbc) 0.01 -0.66 -4.52 -5.55 -6.55 -5.55 -4.52 -0.73 0.01
140 Stress due to Moment at top of girder (st = (M / Ztc) 0.00 0.24 1.36 1.68 1.98 1.68 1.36 0.22 0.00
Stress due to Moment at bot of slab (sbs= (M / Zbsc) 0.00 0.24 1.36 1.68 1.98 1.68 1.36 0.22 0.00
Stress due to Moment at top of slab (sts = (M / Ztsc) -0.01 0.46 2.85 3.50 4.12 3.50 2.85 0.46 -0.01
141 Final stresses after LL
142 Stress at bottom of girder (90 + 92) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
143 Stress at top of girder (91 + 93) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
X Longterm losses
144 cg of cable group (( 1x 4) + (20 x 23) + (51 x 54)) / (1+20+51) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
145 Eccentricty e = (Ybc -97) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
146 Creep loss
147 Creep strain (Ref Page No of IRC:18-2000) 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044 0.00044
148 Stress at level of steel ((95-96) x 97 / Hc) + 96 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
149 ce due to creep P = ( 101 x (100 / 10) x Es x (2 + 21+ 52) / 1000) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
150 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
151 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
152 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at bot of slab (sbs= (P / A) + (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
153 Shrinkage loss
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
154 Shrinkage strain (Ref Page No of IRC:18-2000) 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020 0.00020
155 in force due to shrinkage P = (107 X Es x( 2 + 21 + 52 ) / 1000) -184.77 -184.77 -184.77 -184.77 -184.77 -184.77 -184.77 -184.77 -184.77
156 Moment Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
157 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
158 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at bot of slab (sbs= (P / A) + (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
159 Relaxation loss
160 Relaxation loss (Ref Page No of IRC:18-2000) 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50% 3.50%
161 rce due to relaxation P = ( 113 x 3 x (3 + 22 + 35 + 53 + 66)/1000 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
162 Moment (M = P X e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
163 Stress due to Moment at bottom of girder (sb = (P / A) - (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
164 Stress due to Moment at top of girder (st = (P / A) + (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at bot of slab (sbs= (P / A) + (M / Zbsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress due to Moment at top of slab (sts = (P / A) +(M / Ztsc) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
165 Final stresses after losses
166 Stress at bottom of girder ( 95 + 104 + 110 + 116) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
167 Stress at top of girder ( 96 + 105 + 111 + 117) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at bottom of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Stress at top of slab (61+ 65) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
199 Longitudinal reinforcement (mm2) = (0.18 x A X 10^6 / 10^2) 1000.8 1000.8 748.8 748.8 748.8 748.8 748.8 748.8 748.8
Vertical Reinforcement (@ mid)(mm2) = (0.18 x 600 x
200 1000)/100 1080 1080 1080 1080 1080 1080 1080 1080 1080
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
A B C D E F G H I
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
I Properties of Precast section
A 0.556 0.556 0.416 0.416 0.416 0.416 0.416 0.416 0.416
Yb 0.431 0.431 0.411 0.411 0.411 0.411 0.411 0.411 0.411
Yt 0.449 0.449 0.469 0.469 0.469 0.469 0.469 0.469 0.469
Zb 0.079 0.079 0.078 0.078 0.078 0.078 0.078 0.078 0.078
Zt 0.076 0.076 0.068 0.068 0.068 0.068 0.068 0.068 0.068
Ix 0.034 0.034 0.032 0.032 0.032 0.032 0.032 0.032 0.032
H 0.880 0.88 0.88 0.88 0.8800 0.88 0.88 0.88 0.88
(Ay)p 1.79E+07 1.79E+07 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06 8.75E+06
II Properties of composite section
Ac 0.909 0.909 0.767 0.767 0.767 0.767 0.767 0.767 0.767
Ybc 0.646 0.646 0.676 0.676 0.676 0.676 0.676 0.676 0.676
Ytc 0.455 0.455 0.426 0.426 0.426 0.426 0.426 0.426 0.426
Zbgc 0.160 0.160 0.144 0.144 0.144 0.144 0.144 0.144 0.144
Ztgc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 0.477 0.477
Zbsc 0.443 0.443 0.477 0.477 0.477 0.477 0.477 0.477 0.477
Ztsc 0.228 0.228 0.228 0.228 0.228 0.228 0.228 0.228 0.228
Ixc 0.104 0.104 0.097 0.097 0.097 0.097 0.097 0.097 0.097
Hc 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100
Slab thickness, t 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220 0.220
Effective flange width, Bf 1.525 1.53 1.53 1.53 1.53 1.53 1.53 1.53 1.53
(Ay)c 1.34E+08 1.34E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08 1.15E+08
III Material Properties
Grade Initial 30.29 30.29 30.29 30.29 30.29 30.29 30.29 30.29 30.29
Grade Final 45 45 45 45 45 45 45 45 45
Ec, initial 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66 27517.66
Ec, final 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02 33541.02
Es 195000 195000 195000 195000 195000 195000 195000 195000 195000
First stage stressing (N) @ Days 7 7 7 7 7 7 7 7 7
Second stage stressing (N1) @ Days 28 28 28 28 28 28 28 28 28
IV Stressing Sequence
Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 1 (7th day)
1 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
2 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
3 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
4 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
5 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
6 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
7 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
8 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
9 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
10 Final Stresses
11 Stress at bottom of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
12 Stress at top of girder Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
13 Moment due to selfweight of girder ( KN-m) x 9.81 0.00 96.43 472.84 554.17 624.41 554.17 472.84 96.43 0.00
14 Stress at bottom of girder ( 13 / Z b ) 0.00 -1.22 -6.07 -7.12 -8.02 -7.12 -6.07 -1.24 0.00
15 Stress at top of girder ( 13 / Zt ) 0.00 1.27 6.93 8.12 9.15 8.12 6.93 1.41 0.00
Final Stresses
16 Stress at bottom of girder (11 + 14) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
17 Stress at top of girder (12 + 15) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
18 Permissible compressive stress. clause 7.1.2 IRC:18-2000 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14 15.14
19 Permissible tensile stress. clause 7.1.4 IRC:18-2000 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51 -1.51
Stressing of Cable 3 (7th day)
20 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
21 c/s area of strand 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4 1184.4
22 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
23 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
24 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
25 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
26 Stress due to Axial force (sd = P / A) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
27 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
28 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
29 Stress at bottom of girder (16 + 27) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
30 Stress at top of girder (17 + 28) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
43 Stress at bottom of girder (29 + 41) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
44 Stress at top of girder (30 + 42) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
VI Second Stage Stressing of Cable 4 (28th day)
45 Permissible compressive stress 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
46 Permissible tensile stress -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00 -2.00
47 No of strands 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844 11.844
48 c/s area of strand 1184.4 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40 1184.40
49 Jacking force after slip losses (P) KN Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
50 Distance from base of girder (Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
51 Eccentricity e = (Yb - Yx) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
52 Moment (M = P x e) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
53 Stress due to Axial force (sd = P / Ac) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
54 Stress due to Moment at bottom of girder (sb = (P / A) + (M / Zb) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
55 Stress due to Moment at top of girder (st = (P / A) - (M / Zt) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
56 Stress at bottom of girder (43 + 54) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
57 Stress at top of girder (44 + 55) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
70 Stress at bottom of girder (56 + 68) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
71 Stress at top of girder (57 + 69) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
83 Stress at bottom of girder (70 + 81) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
84 Stress at top of girder (71 + 82) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
Final Stresses
97 Stress at bottom of girder (83 + 95) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
98 Stress at top of girder (84 + 96) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
XI Moment due to SIDL (KN-m) x 9.81 2.65 106.14 513.75 600.57 678.75 600.57 513.75 106.14 2.65
116 Stress due to Moment at bottom of girder (sb = (M / Zbgc) -0.02 -0.66 -3.57 -4.17 -4.72 -4.17 -3.57 -0.74 -0.02
117 Stress due to Moment at top of girder (st = (M / Ztgc) 0.01 0.24 1.08 1.26 1.42 1.26 1.08 0.22 0.01
Sl no Description 0.500 1.380 5.870 7.614 11.320 14.808 16.770 21.260 22.140
118 Stress due to Moment at top of slab (sts = (M / Ztsc) 0.01 0.47 2.25 2.63 2.97 2.63 2.25 0.46 0.01
Final stresses after SIDL
119 Stress at bottom of girder (113 + 116) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
120 Stress at top of girder (114+ 117) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
122 Stress at top of slab (115+ 118) -0.54 0.30 2.09 2.47 2.81 2.47 2.09 0.30 -0.54
XII Moment due to LL x 9.81 -1.77 105.56 650.40 799.22 942.15 799.22 650.40 105.56 -1.77
123 Stress due to Moment at bottom of girder (sb = (M / Zbc) 0.01 -0.66 -4.52 -5.55 -6.55 -5.55 -4.52 -0.73 0.01
124 Stress due to Moment at top of girder (st = (M / Ztc) 0.00 0.24 1.36 1.68 1.98 1.68 1.36 0.22 0.00
125 Stress due to Moment at top of slab (sts = (M / Ztsc) -0.01 0.46 2.85 3.50 4.12 3.50 2.85 0.46 -0.01
Final stresses after LL
126 Stress at bottom of girder (90 + 92) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
127 Stress at top of girder (91 + 93) Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511 Err:511
128 Stress at top of slab (61+ 65) -0.55 0.77 4.94 5.97 6.94 5.97 4.94 0.77 -0.55
F = 0.4 Ec A ( r s xs - rg xg )
No. of Girders = 4
3000
220
950 0
0
150
880
880
0
650
0
650
The differential strain = Residual shrinkage strain in deck slab - Residual shrikage strain in girder
2
Fictitious thickness = dm = 660000 = 261 mm
2525
From Table 3 of IRC : 22 - 1966
26 X 30 - 20
30 0.525 = 0.583
Main steel in Deck slab will be about 1.25% to 1.4% and generally distribution steel will be about 30%
of main steel.
... fs = 0.4 %
Calculation of xs
xs = yas b ( 1 - 0.1 fs )
Where, y = 6.00E-04 for relative humidity within 30%
µs = 0.583 b = 1 fs = 0.4
xs = 6.00E-04 x 0.583 x 1 ( 1 - 0.1 x 0.4 )
= 3.36E-04
Calculation of xg
= 2710 mm
50% of exposed perimeter = 2710 = 1355 mm
2
Fictitious thickness = 556000 = 410 mm
1355
From Table 3 of IRC : 22 - 1966
20 0.675
41.03 X
30 0.525 = 0.525
= 3.09E-04
F = 0.4 Ec A ( r s xs - r g xg )
rs = 1.0 ( As per cl. 608.1 of IRC : 22 - 1966 )
rg = 0.53 ( As per Table 1 of IRC : 22 - 1966 )
r g xg = 0.53 X 3.09E-04 = 1.64E-04
r s xs - r g xg = 3.36E-04 - 1.64E-04 = 1.72E-04
= 1521 kN
This force will act at a distance of 110 mm. above top of Girder.( i.e at centre of Deck slab )
Outer Girder-Left
Flange Area (m )
2
0.336
Yt (m) 0.455
Yb (m) 0.646
Icg (m )
4
0.104
Zts (m )
3
0.228
Zbs (m )
3
0.443
Zbg (m3) 0.160
Force (kN) -1521
Eigen Moment (kN-m) -525
Secondary Moment (kN-m)
Moment kNm -525
Stress due to resisting force
Top (N/mm2) of Slab -4.535
Bottom (N/mm2) of Slab -4.535
Stress due to equivalent force
Top (N/mm2) of Slab 1.674
Bottom (N/mm2) of Slab 1.674
Top (N/mm2) of Girder 1.674
Bottom (N/mm2) of girder 1.674
Stress due to Eigen Moment
Top (N/mm2) of Slab 2.305
Bottom (N/mm2) of Slab 1.186
Top (N/mm2) of Girder 1.186
Bottom (N/mm2) of girder -3.273
Secondary Moment (kN-m)
Top (N/mm2) of Slab 0.000
Bottom (N/mm2) of Slab 0.000
Top (N/mm2) of Girder 0.000
Bottom (N/mm2) of girder 0.000
Combined stress
Top (N/mm2) of Slab -0.556
Bottom (N/mm2) of Slab -1.675
Top (N/mm2) of Girder 2.859
No. of Girders = 4
3000
240
650 150
100
213
880
230
266
200
275
200
625
The differential strain = Residual shrinkage strain in deck slab - Residual shrikage strain in girder
27 X 30 - 20
30 0.525 = 0.571
Main steel in Deck slab will be about 1.25% to 1.4% and generally distribution steel will be about 30%
of main steel.
... fs = 0.4 %
Calculation of xs
xs = yas b ( 1 - 0.1 fs )
Where, y = 6.00E-04 for relative humidity within 30%
µs = 0.571 b = 1 fs = 0.4
xs = 6.00E-04 x 0.571 x 1 ( 1 - 0.1 x 0.4 )
= 3.29E-04
Calculation of xg
= 2742 mm
50% of exposed perimeter = 2742 = 1371 mm
2
Fictitious thickness = 416000 = 303 mm
1371
From Table 3 of IRC : 22 - 1966
20 0.675
30.35 X
30 0.525 = 0.525
= 3.09E-04
F = 0.4 Ec A ( rs xs - rg xg )
rs = 1.0 ( As per cl. 608.1 of IRC : 22 - 1966 )
rg = 0.53 ( As per Table 1 of IRC : 22 - 1966 )
rg xg = 0.53 X 3.09E-04 = 1.64E-04
rs x s - rg xg = 3.29E-04 - 1.64E-04 = 1.65E-04
This force will act at a distance of 120 mm. above top of Girder.( i.e at centre of Deck slab )
Outer Girder-Left
Depth (m) 1.102
Flange Area (m )
2
0.366
Yt (m) 0.426
Yb (m) 0.676
Icg (m )
4
0.097
Zts (m )
3
0.228
Inner bearings
Vertical
Node Env Fy Mton
54 +ve 60.897 LOAD #203, (15 of 47)
54 -ve 0 -
82 +ve 59.478 LOAD #221, (33 of 47)
82 -ve -0.349 LOAD #282, (47 of 47)
85 +ve 37.657 LOAD #302, (20 of 47)
85 -ve 0 -
113 +ve 43.367 LOAD #315, (33 of 47)
113 -ve -0.053 LOAD #48, (1 of 47)
Maximum 60.897
ding Reaction in other bearings
85 113