You are on page 1of 8

Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A.

The
NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the project is -
$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76 (plus or
minus $10) D. The NPV of the project is not within $10 of any of the numbers cited
in answers A, B, and C E. The NPV of the project can not be computed because the
cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] +
[4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $)
-9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or minus
$10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV of the
project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not within
$10 of any of the numbers cited in answers A, B, and C E. The NPV of the project
can not be computed because the cash flows are not conventional (Fall 2009, quiz 3,
question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3
Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -
$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000
-7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The
NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -
$5,303.76 (plus or minus $10) D. The NPV of the project is not within $10 of any of
the numbers cited in answers A, B, and C E. The NPV of the project can not be
computed because the cash flows are not conventional (Fall 2009, quiz 3, question
6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected
cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34
(plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C.
The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project
is not within $10 of any of the numbers cited in answers A, B, and C E. The NPV of
the project can not be computed because the cash flows are not conventional (Fall
2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from
today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the
project is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00
(plus or minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D.
The NPV of the project is not within $10 of any of the numbers cited in answers A,
B, and C E. The NPV of the project can not be computed because the cash flows are
not conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] +
[-7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus
or minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The
NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is
not within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus
or minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The
NPV of the project is not within $10 of any of the numbers cited in answers A, B,
and C E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0 1 2 3 Expected cash flow
(in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project is -$5,823.34 (plus or
minus $10) B. The NPV of the project is -$5,500.00 (plus or minus $10) C. The NPV
of the project is -$5,303.76 (plus or minus $10) D. The NPV of the project is not
within $10 of any of the numbers cited in answers A, B, and C E. The NPV of the
project can not be computed because the cash flows are not conventional (Fall 2009,
quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-7,000/1.0Years from today 0
1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000 6,500 A. The NPV of the project
is -$5,823.34 (plus or minus $10) B. The NPV of the project is -$5,500.00 (plus or
minus $10) C. The NPV of the project is -$5,303.76 (plus or minus $10) D. The NPV
of the project is not within $10 of any of the numbers cited in answers A, B, and C
E. The NPV of the project can not be computed because the cash flows are not
conventional (Fall 2009, quiz 3, question 6) NPV = [-9,000] + [4,000/1.037] + [-
7,000/1.0Years from today 0 1 2 3 Expected cash flow (in $) -9,000 4,000 -7,000
6,500 A. The NPV of the project is -$5,823.34 (plus or minus $10) B. The NPV of the
project is -$5,500.00 (plus or minus $10) C. The NPV of the project is -$5,303.76
(plus or minus $10) D. The NPV of the project is not within $10 of any of the
numbers cited in answers A, B, and C E. The NPV of the project can not be computed
because the cash flows are not conventional (Fall 2009, quiz 3, question 6) NPV =
[-9,000] + [4,000/1.037] + [-7,000/1.0

You might also like