STF PALONG TIMUR REV.00 RUN ALL BS 21.04.2018 324.0d 155.0d -119.0d 02-Oct-17 08:00 AM 20-Oct-18 08:00 AM 91.99% 44.15%
A
Milestone 324.0d 0.0d -119.0d 02-Oct-17 08:00 AM A 20-Oct-18 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A 02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -119.0d 20-Oct-18 08:00 AM 20-Oct-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
Preliminary Works 22.0d 0.0d 11-Dec-17 08:00 AM A 25-Jan-18 05:00 PM A 100% 100%
Setting Up of Site 12.0d 0.0d 11-Dec-17 08:00 AM A 23-Dec-17 05:00 PM A 100% 100%
A1120 Site measurement & site survey 12.0d 0.0d 11-Dec-17 08:00 AM A 23-Dec-17 05:00 PM A 100% 100%
Earthwork 12.0d 0.0d 23-Dec-17 08:00 AM A 25-Jan-18 05:00 PM A 100% 100%
A1130 Site clearance & excavation works 12.0d 0.0d 23-Dec-17 08:00 AM A 25-Jan-18 05:00 PM A 100% 100%
Water Retaining Structure 155.0d 42.0d -23.0d 06-Dec-17 08:00 AM A 09-Jun-18 05:00 PM 100% 57.45%
Wash Water Collection & Sludge Balancing Tank 155.0d 42.0d -23.0d 06-Dec-17 08:00 AM A 09-Jun-18 05:00 PM 100% 57.45%
Substructure 34.0d 0.0d 06-Dec-17 08:00 AM A 12-Mar-18 05:00 PM A 100% 100%
A1140 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
A1150 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
A1160 Concreting work 5.0d 0.0d 11-Jan-18 08:00 AM A 12-Mar-18 05:00 PM A 100% 100%
Wall & Top Slab 115.0d 36.0d -23.0d 17-Jan-18 08:00 AM A 02-Jun-18 05:00 PM 100% 40%
A1170 Frame 24.0d 0.0d 17-Jan-18 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1180 External finishes 18.0d 18.0d -23.0d 22-Apr-18 08:00 AM 13-May-18 05:00 PM 100% 0%
A1190 Internal finishes 18.0d 18.0d -23.0d 14-May-18 08:00 AM 02-Jun-18 05:00 PM 100% 0%
Backfilling & Compaction 18.0d 18.0d -23.0d 14-May-18 08:00 AM 02-Jun-18 05:00 PM 100% 0%
A1210 Backfill, level & compact 18.0d 18.0d -23.0d 14-May-18 08:00 AM 02-Jun-18 05:00 PM 100% 0%
Testing 6.0d 6.0d -23.0d 03-Jun-18 08:00 AM 09-Jun-18 05:00 PM 100% 0%
A1200 Cleaning & Water Tighness Testing 6.0d 6.0d -23.0d 03-Jun-18 08:00 AM 09-Jun-18 05:00 PM 100% 0%
Platform Structure 204.0d 91.0d -102.0d 06-Dec-17 08:00 AM A 05-Aug-18 05:00 PM 100% 13.33%
Dewatering Container (Geotube) 204.0d 91.0d -102.0d 06-Dec-17 08:00 AM A 05-Aug-18 05:00 PM 100% 13.33%
Substructure (Drain & Slab) 144.0d 31.0d -102.0d 06-Dec-17 08:00 AM A 28-May-18 05:00 PM 100% 27.37%
A1220 Install reinforcement 26.0d 26.0d -102.0d 06-Dec-17 08:00 AM A 22-May-18 05:00 PM 100% 30%
A1230 Install formwork 26.0d 26.0d -102.0d 10-Dec-17 08:00 AM A 22-May-18 05:00 PM 100% 30%
A1240 Concreting work 5.0d 5.0d -102.0d 23-May-18 08:00 AM 28-May-18 05:00 PM 100% 0%
Ramp 24.0d 24.0d -102.0d 29-May-18 08:00 AM 24-Jun-18 05:00 PM 100% 0%
A1250 Formwork, reinforcement, concrete & cover 24.0d 24.0d -102.0d 29-May-18 08:00 AM 24-Jun-18 05:00 PM 100% 0%
Geotube 36.0d 36.0d -102.0d 25-Jun-18 08:00 AM 05-Aug-18 05:00 PM 100% 0%
A1260 Preparation & installation 36.0d 36.0d -102.0d 25-Jun-18 08:00 AM 05-Aug-18 05:00 PM 100% 0%
Building 204.0d 91.0d -72.0d 06-Dec-17 08:00 AM A 05-Aug-18 05:00 PM 100% 7.54%
Polymer Plant 204.0d 91.0d -72.0d 06-Dec-17 08:00 AM A 05-Aug-18 05:00 PM 100% 7.54%
Substructure (Footing, Stump, Ground Beam & Slab) 144.0d 31.0d -72.0d 06-Dec-17 08:00 AM A 28-May-18 05:00 PM 100% 27.37%
A1270 Install reinforcement 26.0d 26.0d -72.0d 06-Dec-17 08:00 AM A 22-May-18 05:00 PM 100% 30%
A1280 Install formwork 26.0d 26.0d -72.0d 10-Dec-17 08:00 AM A 22-May-18 05:00 PM 100% 30%
A1290 Concreting work 5.0d 5.0d -72.0d 23-May-18 08:00 AM 28-May-18 05:00 PM 100% 0%
Frame (Upper Beam & Column) 24.0d 24.0d -72.0d 29-May-18 08:00 AM 24-Jun-18 05:00 PM 100% 0%
A1300 Scaffold, stagging, formwork, reinforcement, t-prox, soffit & concrete
24.0d 24.0d -72.0d 29-May-18 08:00 AM 24-Jun-18 05:00 PM 100% 0%
Ramp & Drain 18.0d 18.0d -72.0d 25-Jun-18 08:00 AM 15-Jul-18 05:00 PM 100% 0%
A1310 Excavation, levelling, formwork, reinforcement & concrete 18.0d 18.0d -72.0d 25-Jun-18 08:00 AM 15-Jul-18 05:00 PM 100% 0%
Roof 18.0d 18.0d -72.0d 25-Jun-18 08:00 AM 15-Jul-18 05:00 PM 100% 0%
A1320 Install roof truss & covering 18.0d 18.0d -72.0d 25-Jun-18 08:00 AM 15-Jul-18 05:00 PM 100% 0%
Wall 18.0d 18.0d -72.0d 25-Jun-18 08:00 AM 15-Jul-18 05:00 PM 100% 0%
A1330 Scaffold, stagging, formwork, reinforcement & concrete 18.0d 18.0d -72.0d 25-Jun-18 08:00 AM 15-Jul-18 05:00 PM 100% 0%
Drawing & Material Approval 24.0d 0.0d 22-Nov-17 08:00 AM A 19-Dec-17 05:00 PM A 100% 100%
A1440 Submission of Drawing / Material for approval 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A1450 Review & approval for Drawing / Material 12.0d 0.0d 06-Dec-17 08:00 AM A 19-Dec-17 05:00 PM A 100% 100%
Wash Water Collection & Sludge Balancing Tank 155.0d 42.0d -17.0d 06-Dec-17 08:00 AM A 09-Jun-18 05:00 PM 95.24% 61.9%
Procurement 102.0d 30.0d -23.0d 06-Dec-17 08:00 AM A 27-May-18 05:00 PM 100% 92.86%
A1460 Horizontal Screw Pump, Subermisble Supernatant Pump 72.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1470 FAT Wash Water Recovery Pumpset 6.0d 0.0d 05-Mar-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
A1480 Pipes, Fittings & Valves 30.0d 0.0d 05-Mar-18 08:00 AM A 31-Mar-18 05:00 PM A 100% 100%
A1490 Submersible Mixer 30.0d 0.0d 05-Mar-18 08:00 AM A 31-Mar-18 05:00 PM A 100% 100%
A1500 Crane / Lifting Equipment, High Pressure Rubber Hose 30.0d 30.0d -23.0d 05-Mar-18 08:00 AM A 27-May-18 05:00 PM 100% 60%
Installation 42.0d 42.0d -17.0d 22-Apr-18 08:00 AM 09-Jun-18 05:00 PM 80.95% 0%
A1510 Construction of Horizontal Screw Pump Pit 24.0d 24.0d -17.0d 22-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1520 Horizontal Screw Pump, Subermisble Supernatant Pump 18.0d 18.0d -17.0d 21-May-18 08:00 AM 09-Jun-18 05:00 PM 61.11% 0%
A1530 Pipes, Fittings & Valves 18.0d 18.0d -17.0d 21-May-18 08:00 AM 09-Jun-18 05:00 PM 61.11% 0%
A1540 Submersible Mixer 12.0d 12.0d -17.0d 21-May-18 08:00 AM 02-Jun-18 05:00 PM 91.67% 0%
A1550 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -23.0d 28-May-18 08:00 AM 09-Jun-18 05:00 PM 91.67% 0%
Existing Sedimentation Tank 161.0d 48.0d -29.0d 06-Dec-17 08:00 AM A 16-Jun-18 05:00 PM 100% 65.22%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
Installation 48.0d 48.0d -29.0d 22-Apr-18 08:00 AM 16-Jun-18 05:00 PM 100% 0%
A1580 Submersible Sludge Pump 24.0d 24.0d -29.0d 22-Apr-18 08:00 AM 20-May-18 05:00 PM 100% 0%
A1590 Pipes, Fittings & Valves 24.0d 24.0d -29.0d 21-May-18 08:00 AM 16-Jun-18 05:00 PM 100% 0%
Polymer Plant 245.0d 132.0d -113.0d 06-Dec-17 08:00 AM A 22-Sep-18 05:00 PM 86.33% 25.86%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 60.0d -53.0d 06-Dec-17 08:00 AM A 30-Jun-18 05:00 PM 100% 60%
A1610 Metering Pumps (Diaphragm type) 60.0d 60.0d -113.0d 06-Dec-17 08:00 AM A 30-Jun-18 05:00 PM 100% 60%
A1620 Crane / Lifting Equipment 30.0d 30.0d -23.0d 06-Dec-17 08:00 AM A 27-May-18 05:00 PM 100% 60%
A1630 Static Mixer & Sludge Blender 30.0d 30.0d -23.0d 06-Dec-17 08:00 AM A 27-May-18 05:00 PM 100% 60%
Fabrication 36.0d 36.0d -89.0d 01-Jul-18 08:00 AM 11-Aug-18 05:00 PM 100% 0%
A1640 Mixing & Service Tank 36.0d 36.0d -113.0d 01-Jul-18 08:00 AM 11-Aug-18 05:00 PM 100% 0%
A1650 Hopper, Feeder & Pump Skid 36.0d 36.0d -113.0d 01-Jul-18 08:00 AM 11-Aug-18 05:00 PM 100% 0%
A1660 Local Control Panel 30.0d 30.0d -83.0d 01-Jul-18 08:00 AM 04-Aug-18 05:00 PM 100% 0%
Installation 36.0d 36.0d -113.0d 12-Aug-18 08:00 AM 22-Sep-18 05:00 PM 47.22% 0%
A1670 Mixing & Service Tank 24.0d 24.0d -113.0d 12-Aug-18 08:00 AM 08-Sep-18 05:00 PM 70.83% 0%
A1680 Hopper, Feeder & Pump Skid 24.0d 24.0d -113.0d 12-Aug-18 08:00 AM 08-Sep-18 05:00 PM 70.83% 0%
A1690 Dosing Pipeworks 24.0d 24.0d -113.0d 12-Aug-18 08:00 AM 08-Sep-18 05:00 PM 70.83% 0%
A1700 Local Control Panel 12.0d 12.0d -113.0d 09-Sep-18 08:00 AM 22-Sep-18 05:00 PM 0% 0%
A1710 Crane / Lifting Equipment 12.0d 12.0d -113.0d 09-Sep-18 08:00 AM 22-Sep-18 05:00 PM 0% 0%
A1720 Static Mixer & Sludge Blender 12.0d 12.0d -113.0d 09-Sep-18 08:00 AM 22-Sep-18 05:00 PM 0% 0%
Pipeworks 155.0d 30.0d -18.0d 20-Dec-17 08:00 AM A 23-Jun-18 05:00 PM 100% 30.77%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
A1730 To procure & deliver 200mm Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A1870 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM A 21-Nov-17 05:00 PM A 100% 100%
A1880 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
Switchboard / MCC Panel 224.0d 99.0d -80.0d 22-Nov-17 08:00 AM A 14-Aug-18 05:00 PM 89.21% 44.35%
A1890 Procurement & fabrication of Panel 84.0d 84.0d -119.0d 22-Nov-17 08:00 AM A 28-Jul-18 05:00 PM 100% 60%
A1900 FAT Electrical Control & Swicthboards 1.0d 1.0d -80.0d 27-Mar-18 08:00 AM A 01-Jul-18 05:00 PM 100% 60%
A1910 Installation works 30.0d 30.0d -80.0d 11-Jul-18 08:00 AM 14-Aug-18 05:00 PM 43.33% 0%
Submain Cabling Works for MCC-SDP-Palong 179.0d 54.0d -119.0d 05-Mar-18 08:00 AM A 29-Sep-18 05:00 PM 80.3% 26.67%
A1920 Procurement & delivery of Cable 24.0d 24.0d -119.0d 05-Mar-18 08:00 AM A 25-Aug-18 05:00 PM 100% 60%
A1930 Installation & cabling works 30.0d 30.0d -119.0d 26-Aug-18 08:00 AM 29-Sep-18 05:00 PM 56.67% 0%
Distribution & Earthing System 179.0d 54.0d -119.0d 05-Mar-18 08:00 AM A 29-Sep-18 05:00 PM 80.3% 26.67%
A1940 Procurement & delivery 24.0d 24.0d -119.0d 05-Mar-18 08:00 AM A 25-Aug-18 05:00 PM 100% 60%
A1950 Installation & cabling works 30.0d 30.0d -119.0d 26-Aug-18 08:00 AM 29-Sep-18 05:00 PM 56.67% 0%
Compound Lighting System 179.0d 54.0d -119.0d 05-Mar-18 08:00 AM A 29-Sep-18 05:00 PM 80.3% 26.67%
A1960 Procurement & delivery 24.0d 24.0d -119.0d 05-Mar-18 08:00 AM A 25-Aug-18 05:00 PM 100% 60%
A1970 Installation & cabling works 30.0d 30.0d -119.0d 26-Aug-18 08:00 AM 29-Sep-18 05:00 PM 56.67% 0%
Relocation of Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM A 31-Dec-17 05:00 PM A 56.67% 100%
A1980 To relocate existing Cable 30.0d 0.0d 11-Dec-17 08:00 AM A 31-Dec-17 05:00 PM A 56.67% 100%
Miscellaneous Works 30.0d 30.0d -119.0d 26-Aug-18 08:00 AM 29-Sep-18 05:00 PM 56.67% 0%
A1990 Any other neccessary works 30.0d 30.0d -119.0d 26-Aug-18 08:00 AM 29-Sep-18 05:00 PM 56.67% 0%
Instrumentation Works 251.0d 114.0d -97.0d 08-Nov-17 08:00 AM A 01-Sep-18 05:00 PM 91.21% 54.24%
Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A2000 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM A 21-Nov-17 05:00 PM A 100% 100%
A2010 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
Procurement & Fabrication 84.0d 84.0d -97.0d 22-Nov-17 08:00 AM A 28-Jul-18 05:00 PM 100% 60.47%
A2020 To procure & fabricate Instrument Panel 84.0d 84.0d -97.0d 22-Nov-17 08:00 AM A 28-Jul-18 05:00 PM 100% 60%
A2030 FAT 1.0d 0.0d 07-Feb-18 08:00 AM A 01-Mar-18 05:00 PM A 100% 100%
Installation 30.0d 30.0d -97.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 43.33% 0%
A2040 Installation & signal cabling works 30.0d 30.0d -97.0d 29-Jul-18 08:00 AM 01-Sep-18 05:00 PM 43.33% 0%
Infrastructure Works 24.0d 24.0d -102.0d 13-Aug-18 08:00 AM 09-Sep-18 05:00 PM 62.72% 0%
Training, Testing, Commissioning & Maintenance 17.0d 17.0d -119.0d 30-Sep-18 08:00 AM 18-Oct-18 05:00 PM 0% 0%
A2070 Preparation of testing & report 12.0d 12.0d -119.0d 30-Sep-18 08:00 AM 13-Oct-18 05:00 PM 0% 0%
A2080 Pre-commissioning 6.0d 6.0d -119.0d 30-Sep-18 08:00 AM 06-Oct-18 05:00 PM 0% 0%
A2090 Setting to work 3.0d 3.0d -119.0d 07-Oct-18 08:00 AM 09-Oct-18 05:00 PM 0% 0%
A2100 Commissioning & training 7.0d 7.0d -119.0d 10-Oct-18 08:00 AM 17-Oct-18 05:00 PM 0% 0%
A2110 Handing over to Client 1.0d 1.0d -119.0d 18-Oct-18 08:00 AM 18-Oct-18 05:00 PM 0% 0%