STF PALONG TIMUR REV.00 RUN ALL BS 28.08.

2018 Classic Schedule Layout 28-Aug-18 10:44 AM


Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF PALONG TIMUR REV.00 RUN ALL BS 28.08.2018 412.0d 133.0d -207.0d 02-Oct-17 08:00 AM A 30-Jan-19 08:00 AM 100% 93.58%

Milestone 412.0d 0.0d -207.0d 02-Oct-17 08:00 AM A 30-Jan-19 08:00 AM 0% 0%


ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A 02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -207.0d 30-Jan-19 08:00 AM 30-Jan-19 08:00 AM 100% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%

Documentation 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%


Preparation & Submission 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
A1000 Preparation of Performance Bond 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1010 Preparation of Insurance Policies / Public Liability / Workmen's Compensation
14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1020 Preparation & Submission of Levy of CIDB 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1030 Site Registration of JKKP (DOSH) 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1040 Submission Copy of SPAN Certificate 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1050 Preparation & Submission of Lithography Expenses 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1060 Preparation & Submission of PQP / Method Statements 14.0d 0.0d 02-Oct-17 08:00 AM A 17-Oct-17 05:00 PM A 100% 100%
A1070 Preparation of Works (Contractor Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
A1080 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
A1090 Preparation of Works (General Obligation, Project Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
A1100 Preparation of Works (Authorities Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
A1110 Preparation of Works (Environmental Protection & Enhancement) 18.0d 0.0d 18-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
Civil & Structure Works 205.0d 41.0d -132.0d 06-Dec-17 08:00 AM A 14-Oct-18 05:00 PM 100% 99.26%

Preliminary Works 22.0d 0.0d 11-Dec-17 08:00 AM A 30-Jan-18 05:00 PM A 100% 100%
Setting Up of Site 12.0d 0.0d 11-Dec-17 08:00 AM A 21-Dec-17 05:00 PM A 100% 100%
A1120 Site measurement & site survey 12.0d 0.0d 11-Dec-17 08:00 AM A 21-Dec-17 05:00 PM A 100% 100%
Earthwork 12.0d 0.0d 22-Dec-17 08:00 AM A 30-Jan-18 05:00 PM A 100% 100%
A1130 Site clearance & excavation works 12.0d 0.0d 22-Dec-17 08:00 AM A 30-Jan-18 05:00 PM A 100% 100%
Water Retaining Structure 141.0d 0.0d 06-Dec-17 08:00 AM A 27-Aug-18 05:00 PM A 100% 100%
Wash Water Collection & Sludge Balancing Tank 141.0d 0.0d 06-Dec-17 08:00 AM A 27-Aug-18 05:00 PM A 100% 100%
Substructure 53.0d 0.0d 06-Dec-17 08:00 AM A 10-Mar-18 05:00 PM A 100% 100%
A1140 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
A1150 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
A1160 Concreting work 5.0d 0.0d 03-Feb-18 08:00 AM A 10-Mar-18 05:00 PM A 100% 100%
Wall & Top Slab 68.0d 0.0d 22-Feb-18 08:00 AM A 28-Apr-18 05:00 PM A 100% 100%

Page 1 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 28.08.2018 Classic Schedule Layout 28-Aug-18 10:44 AM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1170 Frame 24.0d 0.0d 22-Feb-18 08:00 AM A 21-Apr-18 05:00 PM A 100% 100%
A1180 External finishes 18.0d 0.0d 22-Apr-18 08:00 AM A 28-Apr-18 05:00 PM A 100% 100%
A1190 Internal finishes 18.0d 0.0d 22-Apr-18 08:00 AM A 28-Apr-18 05:00 PM A 100% 100%
Backfilling & Compaction 18.0d 0.0d 28-Apr-18 08:00 AM A 27-Aug-18 05:00 PM A 100% 100%
A1210 Backfill, level & compact 18.0d 0.0d 28-Apr-18 08:00 AM A 27-Aug-18 05:00 PM A 100% 100%
Testing 6.0d 0.0d 19-May-18 08:00 AM A 12-Jul-18 05:00 PM A 100% 100%
A1200 Cleaning & Water Tighness Testing 6.0d 0.0d 19-May-18 08:00 AM A 12-Jul-18 05:00 PM A 100% 100%
Platform Structure 150.0d 41.0d -162.0d 06-Dec-17 08:00 AM A 14-Oct-18 05:00 PM 100% 96.92%
Dewatering Container (Geotube) 150.0d 41.0d -162.0d 06-Dec-17 08:00 AM A 14-Oct-18 05:00 PM 100% 96.92%
Substructure (Drain & Slab) 137.0d 5.0d -162.0d 06-Dec-17 08:00 AM A 02-Sep-18 05:00 PM 100% 100%
A1220 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM A 26-May-18 05:00 PM A 100% 100%
A1230 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM A 26-May-18 05:00 PM A 100% 100%
A1240 Concreting work 5.0d 5.0d -162.0d 15-May-18 08:00 AM A 02-Sep-18 05:00 PM 100% 100%
Ramp 24.0d 0.0d 22-Apr-18 08:00 AM A 11-Jun-18 05:00 PM A 100% 100%
A1250 Formwork, reinforcement, concrete & cover 24.0d 0.0d 22-Apr-18 08:00 AM A 11-Jun-18 05:00 PM A 100% 100%
Geotube 36.0d 36.0d -162.0d 23-Apr-18 08:00 AM A 14-Oct-18 05:00 PM 100% 90%
A1260 Preparation & installation 36.0d 36.0d -162.0d 23-Apr-18 08:00 AM A 14-Oct-18 05:00 PM 100% 90%
Building 205.0d 0.0d 06-Dec-17 08:00 AM A 06-Aug-18 05:00 PM A 100% 100%
Polymer Plant 205.0d 0.0d 06-Dec-17 08:00 AM A 06-Aug-18 05:00 PM A 100% 100%
Substructure (Footing, Stump, Ground Beam & Slab) 127.0d 0.0d 06-Dec-17 08:00 AM A 08-May-18 05:00 PM A 100% 100%
A1270 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM A 07-May-18 05:00 PM A 100% 100%
A1280 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM A 07-May-18 05:00 PM A 100% 100%
A1290 Concreting work 5.0d 0.0d 03-May-18 08:00 AM A 08-May-18 05:00 PM A 100% 100%
Frame (Upper Beam & Column) 24.0d 0.0d 23-Apr-18 08:00 AM A 15-May-18 05:00 PM A 100% 100%
A1300 Scaffold, stagging, formwork, reinforcement, t-prox, soffit & concrete 24.0d 0.0d 23-Apr-18 08:00 AM A 15-May-18 05:00 PM A 100% 100%
Ramp & Drain 18.0d 0.0d 23-Apr-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
A1310 Excavation, levelling, formwork, reinforcement & concrete 18.0d 0.0d 23-Apr-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
Roof 18.0d 0.0d 05-May-18 08:00 AM A 20-Jul-18 05:00 PM A 100% 100%
A1320 Install roof truss & covering 18.0d 0.0d 05-May-18 08:00 AM A 20-Jul-18 05:00 PM A 100% 100%
Wall 18.0d 0.0d 23-Apr-18 08:00 AM A 08-Jun-18 05:00 PM A 100% 100%
A1330 Installation of Brickwall 18.0d 0.0d 23-Apr-18 08:00 AM A 08-Jun-18 05:00 PM A 100% 100%
Accessories 18.0d 0.0d 13-Jun-18 08:00 AM A 21-Jul-18 05:00 PM A 100% 100%
A1340 Install frame, doors, windows, roller shutter & lockset 18.0d 0.0d 13-Jun-18 08:00 AM A 21-Jul-18 05:00 PM A 100% 100%

Page 2 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 28.08.2018 Classic Schedule Layout 28-Aug-18 10:44 AM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

External Finishes 18.0d 0.0d 09-Jul-18 08:00 AM A 05-Aug-18 05:00 PM A 100% 100%
A1350 External plastering & painting 18.0d 0.0d 09-Jul-18 08:00 AM A 05-Aug-18 05:00 PM A 100% 100%
Internal Floor & Wall Finishes 18.0d 0.0d 04-Jul-18 08:00 AM A 06-Aug-18 05:00 PM A 100% 100%
A1360 Floor rendering, install tiles, install GI tray, internal plastering & painting 18.0d 0.0d 04-Jul-18 08:00 AM A 06-Aug-18 05:00 PM A 100% 100%
Ceiling Finishes 18.0d 0.0d 17-Jul-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
A1370 Install frame, ceiling & painting 18.0d 0.0d 17-Jul-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
Pipeworks 176.0d 18.0d -109.0d 20-Dec-17 08:00 AM A 17-Sep-18 05:00 PM 100% 97%

Procurement 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%


A1380 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
Installation 46.0d 18.0d -109.0d 01-Apr-18 08:00 AM A 17-Sep-18 05:00 PM 100% 96%
A1390 Excavation & backfilling works 24.0d 0.0d 25-Apr-18 08:00 AM A 10-Jul-18 05:00 PM A 100% 100%
A1400 Pipe laying & jointing 24.0d 0.0d 26-Apr-18 08:00 AM A 10-Jul-18 05:00 PM A 100% 100%
A1410 Connection to existing Chamber / Pipes 24.0d 0.0d 26-Apr-18 08:00 AM A 30-Apr-18 05:00 PM A 100% 100%
A1420 Miscellaneous works 18.0d 18.0d -109.0d 01-Apr-18 08:00 AM A 17-Sep-18 05:00 PM 100% 80%
Testing 6.0d 0.0d 11-Jul-18 08:00 AM A 25-Jul-18 05:00 PM A 100% 100%
A1430 Cleaning & testing works 6.0d 0.0d 11-Jul-18 08:00 AM A 25-Jul-18 05:00 PM A 100% 100%
Mechanical Works 277.0d 42.0d -116.0d 22-Nov-17 08:00 AM A 15-Oct-18 05:00 PM 100% 98.21%

Drawing & Material Approval 24.0d 0.0d 22-Nov-17 08:00 AM A 19-Dec-17 05:00 PM A 100% 100%
A1440 Submission of Drawing / Material for approval 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A1450 Review & approval for Drawing / Material 12.0d 0.0d 06-Dec-17 08:00 AM A 19-Dec-17 05:00 PM A 100% 100%
Wash Water Collection & Sludge Balancing Tank 265.0d 42.0d -133.0d 06-Dec-17 08:00 AM A 15-Oct-18 05:00 PM 100% 92.26%
Procurement 102.0d 30.0d -133.0d 06-Dec-17 08:00 AM A 01-Oct-18 05:00 PM 100% 95.54%
A1460 Horizontal Screw Pump, Subermisble Supernatant Pump 72.0d 0.0d 06-Dec-17 08:00 AM A 03-May-18 05:00 PM A 100% 100%
A1470 FAT Wash Water Recovery Pumpset 6.0d 0.0d 05-Mar-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
A1480 Pipes, Fittings & Valves 30.0d 0.0d 05-Mar-18 08:00 AM A 21-Apr-18 05:00 PM A 100% 100%
A1490 Submersible Mixer 30.0d 0.0d 05-Mar-18 08:00 AM A 30-Mar-18 05:00 PM A 100% 100%
A1500 Lifting Davit, High Pressure Rubber Hose 30.0d 30.0d -133.0d 05-Mar-18 08:00 AM A 01-Oct-18 05:00 PM 100% 75%
Installation 89.0d 12.0d -133.0d 04-Jul-18 08:00 AM A 15-Oct-18 05:00 PM 100% 85.71%
A1510 Construction of Horizontal Screw Pump Pit 24.0d 0.0d 05-Jul-18 08:00 AM A 15-Jul-18 05:00 PM A 100% 100%
A1520 Horizontal Screw Pump, Subermisble Supernatant Pump 18.0d 0.0d 04-Jul-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
A1530 Pipes, Fittings & Valves 18.0d 0.0d 04-Jul-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
A1540 Submersible Mixer 12.0d 0.0d 04-Jul-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%

Page 3 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 28.08.2018 Classic Schedule Layout 28-Aug-18 10:44 AM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1550 Lifting Davit, High Pressure Rubber Hose 12.0d 12.0d -133.0d 02-Oct-18 08:00 AM 15-Oct-18 05:00 PM 100% 0%
Existing Sedimentation Tank 212.0d 0.0d 06-Dec-17 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM A 21-Apr-18 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM A 30-Mar-18 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM A 21-Apr-18 05:00 PM A 100% 100%
Installation 40.0d 0.0d 30-Jun-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
A1580 Submersible Sludge Pump 24.0d 0.0d 18-Jul-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
A1590 Pipes, Fittings & Valves 24.0d 0.0d 30-Jun-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
Polymer Plant 234.0d 0.0d 06-Dec-17 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 0.0d 06-Dec-17 08:00 AM A 23-Jul-18 05:00 PM A 100% 100%
A1610 Metering Pumps (Diaphragm type) 60.0d 0.0d 06-Dec-17 08:00 AM A 21-Jul-18 05:00 PM A 100% 100%
A1620 Crane / Lifting Equipment 30.0d 0.0d 06-Dec-17 08:00 AM A 23-Jul-18 05:00 PM A 100% 100%
A1630 Static Mixer & Sludge Blender 30.0d 0.0d 06-Dec-17 08:00 AM A 14-Jul-18 05:00 PM A 100% 100%
Fabrication 36.0d 0.0d 02-May-18 08:00 AM A 12-Jun-18 05:00 PM A 100% 100%
A1640 Mixing & Service Tank 36.0d 0.0d 02-May-18 08:00 AM A 12-Jun-18 05:00 PM A 100% 100%
A1650 Hopper, Feeder & Pump Skid 36.0d 0.0d 02-May-18 08:00 AM A 12-Jun-18 05:00 PM A 100% 100%
A1660 Local Control Panel 30.0d 0.0d 02-May-18 08:00 AM A 12-Jun-18 05:00 PM A 100% 100%
Installation 50.0d 0.0d 14-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
A1670 Mixing & Service Tank 24.0d 0.0d 23-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
A1680 Hopper, Feeder & Pump Skid 24.0d 0.0d 23-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
A1690 Dosing Pipeworks 24.0d 0.0d 23-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
A1700 Local Control Panel 12.0d 0.0d 27-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
A1710 Jib Crane 12.0d 0.0d 24-Jul-18 08:00 AM A 25-Jul-18 05:00 PM A 100% 100%
A1720 Static Mixer & Sludge Blender 12.0d 0.0d 14-Jul-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
Pipeworks 188.0d 0.0d 20-Dec-17 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
A1730 To procure & deliver Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
Installation 24.0d 0.0d 04-Jul-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
A1740 Excavation & backfilling works 24.0d 0.0d 04-Jul-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
A1750 Pipe laying & jointing 24.0d 0.0d 04-Jul-18 08:00 AM A 24-Jul-18 05:00 PM A 100% 100%
Testing 6.0d 0.0d 21-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%

Page 4 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 28.08.2018 Classic Schedule Layout 28-Aug-18 10:44 AM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

A1760 Cleaning & testing works 6.0d 0.0d 21-Jul-18 08:00 AM A 27-Jul-18 05:00 PM A 100% 100%
Miscellaneous Works 201.0d 0.0d 20-Dec-17 08:00 AM A 25-Aug-18 05:00 PM A 100% 100%
Engineering Design 18.0d 0.0d 20-Dec-17 08:00 AM A 11-Jan-18 05:00 PM A 100% 100%
A1770 Engineering design for Motive Water System & Air Compressor 18.0d 0.0d 20-Dec-17 08:00 AM A 11-Jan-18 05:00 PM A 100% 100%
Procurement 61.0d 0.0d 13-Jan-18 08:00 AM A 21-Jul-18 05:00 PM A 100% 100%
A1780 Booster Pump 30.0d 0.0d 13-Jan-18 08:00 AM A 21-Jul-18 05:00 PM A 100% 100%
A1790 Air Compressor Set (2 units) 30.0d 0.0d 13-Jan-18 08:00 AM A 03-May-18 05:00 PM A 100% 100%
A1800 Submersible Pump (Portable & Gasoline Engine) 30.0d 0.0d 13-Jan-18 08:00 AM A 21-May-18 05:00 PM A 100% 100%
A1810 Portable Water jet 12.0d 0.0d 13-Jan-18 08:00 AM A 21-Apr-18 05:00 PM A 100% 100%
A1820 Penstock & Valves 60.0d 0.0d 13-Jan-18 08:00 AM A 24-May-18 05:00 PM A 100% 100%
A1830 FAT Penstock / Valves 1.0d 0.0d 26-Mar-18 08:00 AM A 26-Mar-18 05:00 PM A 100% 100%
Installation 40.0d 0.0d 01-Jul-18 08:00 AM A 25-Aug-18 05:00 PM A 100% 100%
A1840 Booster Pump Set 18.0d 0.0d 21-Jul-18 08:00 AM A 25-Jul-18 05:00 PM A 100% 100%
A1850 Air Compressor Set (2 units) 18.0d 0.0d 26-Jul-18 08:00 AM A 25-Aug-18 05:00 PM A 100% 100%
A1860 Penstock / Valves 30.0d 0.0d 01-Jul-18 08:00 AM A 16-Jul-18 05:00 PM A 100% 100%
Electrical Works 249.0d 30.0d -104.0d 08-Nov-17 08:00 AM A 01-Oct-18 05:00 PM 100% 95.84%

Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A1870 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM A 21-Nov-17 05:00 PM A 100% 100%
A1880 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
Switchboard / MCC Panel 237.0d 0.0d 22-Nov-17 08:00 AM A 14-Aug-18 05:00 PM A 100% 100%
A1890 Procurement & fabrication of Panel 84.0d 0.0d 22-Nov-17 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
A1900 FAT Electrical Control & Switchboards 1.0d 0.0d 27-Mar-18 08:00 AM A 24-May-18 05:00 PM A 100% 100%
A1910 Installation works 30.0d 0.0d 26-Jul-18 08:00 AM A 14-Aug-18 05:00 PM A 100% 100%
Submain Cabling Works for MCC-SDP-Palong 75.0d 0.0d 05-Mar-18 08:00 AM A 09-Jun-18 05:00 PM A 100% 100%
A1920 Procurement & delivery of Cable 24.0d 0.0d 05-Mar-18 08:00 AM A 07-Jun-18 05:00 PM A 100% 100%
A1930 Installation & cabling works 30.0d 0.0d 26-Apr-18 08:00 AM A 09-Jun-18 05:00 PM A 100% 100%
Distribution & Earthing System 75.0d 0.0d 05-Mar-18 08:00 AM A 13-Aug-18 05:00 PM A 100% 100%
A1940 Procurement & delivery 24.0d 0.0d 05-Mar-18 08:00 AM A 18-Jul-18 05:00 PM A 100% 100%
A1950 Installation & cabling works 30.0d 0.0d 26-Apr-18 08:00 AM A 13-Aug-18 05:00 PM A 100% 100%
Compound Lighting System 75.0d 30.0d -104.0d 05-Mar-18 08:00 AM A 01-Oct-18 05:00 PM 100% 72.22%
A1960 Procurement & delivery 24.0d 0.0d 05-Mar-18 08:00 AM A 19-Jul-18 05:00 PM A 100% 100%
A1970 Installation & cabling works 30.0d 30.0d -104.0d 26-Apr-18 08:00 AM A 01-Oct-18 05:00 PM 100% 50%

Page 5 of 6 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.00 RUN ALL BS 28.08.2018 Classic Schedule Layout 28-Aug-18 10:44 AM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Relocation of Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM A 09-Jan-18 05:00 PM A 100% 100%
A1980 To relocate existing Cable 30.0d 0.0d 11-Dec-17 08:00 AM A 09-Jan-18 05:00 PM A 100% 100%
Miscellaneous Works 30.0d 0.0d 01-Apr-18 08:00 AM A 14-Aug-18 05:00 PM A 100% 100%
A1990 Any other neccessary works 30.0d 0.0d 01-Apr-18 08:00 AM A 14-Aug-18 05:00 PM A 100% 100%
Instrumentation Works 361.0d 114.0d -207.0d 08-Nov-17 08:00 AM A 07-Jan-19 05:00 PM 100% 63.31%

Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A2000 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM A 21-Nov-17 05:00 PM A 100% 100%
A2010 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
Procurement & Fabrication 84.0d 84.0d -207.0d 22-Nov-17 08:00 AM A 03-Dec-18 05:00 PM 100% 75.29%
A2020 To procure & fabricate Instrument Panel 84.0d 84.0d -207.0d 22-Nov-17 08:00 AM A 03-Dec-18 05:00 PM 100% 75%
A2030 FAT 1.0d 0.0d 27-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
Installation 30.0d 30.0d -207.0d 04-Dec-18 08:00 AM 07-Jan-19 05:00 PM 100% 0%
A2040 Installation & signal cabling works 30.0d 30.0d -207.0d 04-Dec-18 08:00 AM 07-Jan-19 05:00 PM 100% 0%
Infrastructure Works 24.0d 24.0d -162.0d 22-Oct-18 08:00 AM 18-Nov-18 05:00 PM 100% 0%

Roadworks 24.0d 24.0d -162.0d 22-Oct-18 08:00 AM 18-Nov-18 05:00 PM 100% 0%


A2050 Site clearance, levelling & compaction 18.0d 18.0d -162.0d 22-Oct-18 08:00 AM 11-Nov-18 05:00 PM 100% 0%
A2060 Lay of crusher-run & premix 24.0d 24.0d -162.0d 22-Oct-18 08:00 AM 18-Nov-18 05:00 PM 100% 0%
Site Handover Work 203.0d 17.0d -207.0d 07-Jun-18 08:00 AM A 29-Jan-19 05:00 PM 100% 20.69%

Training, Testing, Commissioning & Maintenance 203.0d 17.0d -207.0d 07-Jun-18 08:00 AM A 29-Jan-19 05:00 PM 100% 20.69%
A2070 Preparation of testing & report 12.0d 12.0d -207.0d 07-Jun-18 08:00 AM A 23-Jan-19 05:00 PM 100% 50%
A2080 Pre-commissioning 6.0d 6.0d -207.0d 10-Jan-19 08:00 AM 16-Jan-19 05:00 PM 100% 0%
A2090 Setting to work 3.0d 3.0d -207.0d 17-Jan-19 08:00 AM 20-Jan-19 05:00 PM 100% 0%
A2100 Commissioning & training 7.0d 7.0d -207.0d 21-Jan-19 08:00 AM 28-Jan-19 05:00 PM 100% 0%
A2110 Handing over to Client 1.0d 1.0d -207.0d 29-Jan-19 08:00 AM 29-Jan-19 05:00 PM 100% 0%

Page 6 of 6 TASK filter: All Activities


© Oracle Corporation