Professional Documents
Culture Documents
PV (Planned Value) = BCWS (Budgeted Cost of Work NPV (Net Present Value) = FV/(1+r)n
Scheduled FV= Future Value, r= interest rate, n= no. of time periods
EV (Earned Value) = BCWP (Budgeted Cost of Work Higher NPV is better
Performed) IRR (Internal Rate of Return) = Solve the NPV equation for
AC (Actual Cost) = ACWP (Actual Cost of Work Performed) “r”
SV = EV – PV (minus is behind schedule) Also called Hurdle Rate
CV = EV – AC (minus is over budget) Higher IRR percentage is better
SPI = EV/PV (Less than 1 is behind schedule) BCR (Benefit/Cost Ratio)
CPI = EV/AC (Less than 1 is over budget) Higher BCR is better.
EAC = AC + (BAC-EV) Use when variances are atypical Beware, exam can call it CBR, where lower is better
EAC = AC + [(BAC-EV)/CPI] Use when variances are ROI (Return on Investment) = Earnings/Investment
typical Higher ROI is better
(Note: This is the same as EAC = BAC/CPI) Payback Period = Time to recover cost of the project
VAC = BAC – EAC Lower payback period is better
ETC = BAC – EV Use when variances are atypical Cash Flow = Cash In – Cash Out
ETC = (BAC – EV)/CPI Use when variances are typical
ETC = EAC – AC Use when original estimates were flawed
Between Team Members = N(N-1)/2 Project is closed when administrative closure is complete.
Administrative closure is done at end of each Project Phase and
at the end of the Project.
Contract closure: verification that deliverables were
acceptable; it is done once at the end of the contract.
Contract Closure Procedure is produced under “Close Project”
SD = (P-O)/6
Mean – Average
Median – Center number/value or average of
center values