Professional Documents
Culture Documents
សររ ប S-0 $ -
S-I ករងរភបតតម នរ ង ផគ តក ផគ ងក
សររ ប S-I $ -
S-II ផផផ ក បគគ គ សតណ ងក
សររ ប S-II $ -
S-III ជនក ទគ ១
S-III-1 ភបតរងកតរលខអណណ Cu.m 63.00 - 50.00 - -
S-III-2 ភបតរងសសរ Cu.m 63.00 - 65.00 - -
S-III-3 ភបតរងធផគម Cu.m 63.00 - 50.00 - -
S-III-4 ភបតរងជភណណធរ Cu.m 63.00 - 70.00 - -
S-III-5 សលសរផដកកតរលខអណណ Ton 780.00 - 100.00 - -
S-III-6 សលសរផដកសសរ Ton 780.00 - 100.00 - -
S-III-7 សលសរផដកធផគម Ton 780.00 - 100.00 - -
S-III-8 សលសរផដកជភណណធរ Ton 780.00 - 100.00 - -
S-III-9 លរសចតណង Kg 1.50 - - - -
S-III-10 តតភឡធងនរងររគភរ ធពរមមកតរលខអណណ Sq.m 10.00 - 2.00 - -
S-III-11 តតភឡធងនរងររគភរ ធពរមមសសរ Sq.m 10.00 - 2.00 - -
S-III-12 តតភឡធងនរងររគភរ ធពរមមធផគម Sq.m 10.00 - 2.00 - -
S-III-13 តតភឡធងនរងររគភរ ធពរមមជភណណធរ Sq.m 10.00 - 2.00 - -
សររ ប S-III $ -
S-IV ជនក ទគ ២
សររ ប S-IV $ -
S-V ជនក ទគ ៣
សររ ប S-V $ -
S-VI ជនក ដត បប ល
សររ ប S-VI $ -
សររ ប ចត ណ យ ករងរភបគកងបងគរត សតណ ងក
ករបតក ប ងក 5%
បបកក ចត ភ ណញ 10%
ភផតភពញ.លថថទគ______/______2014 ភផតភពញ.លថថទគ______/______2014
យលកប ពមភដយ ភរបបភរបងភដយ
Project Name :
Company Name :
#WH 140 Eo-E1,Road 6,Sangkat Toul Sangkei,Khan Russey Keo,Phnom Penh City Project Location :
Job Tittle : BOQ Type : LUMP SUM
Meeting Building Prepared by : Phone :
BILL OF QUANTITY AND COST ESTIMATION OF STRUCTURE WORK
Material Cost (USD) Labor Cost (USD) Total Cost
Item Description Unit Quantity Remarks
Unit Cost Total Unit Cost Total (USD.)
S-0 Engineering and Management Fee
S-0-1 Construction Engineering Service and Consultant Ls 1.00 15,000.00
S-0-2 Management Fee including Salary of Engineers Ls 1.00 18,000.00
Sub-Total S-0
S-I Site Preparation and Temporary Works
S-I-1 Site Clearing and Center Line Survey for Building Sq.m 1.00
S-I-2 Tower Crane Hire and Foundation Ls 1.00
S-I-3 Lift Ls 1.00
S-I-4 Scaffolding Sq.m 10.00 5.00
S-I-5 Temporary Site Office and Store Ls 1.00
S-I-6 Temporary Water Supply Ls 1.00
S-I-7 Temporary Electrical Supply Ls 1.00
Sub-Total S-I AAA
S-II Foundation, Excavation and Soil Filling Works
S-II-1 Soil Test and Report Nos
S-II-2 Sheetpiles Driving Rental / 4month Month
S-II-3 Soil Excavation Work for Basement Cu.m - 3.00
S-II-4 Slop Protection Sq.m 25.00 15.00
S-II-5 Bored Pile Work (D=800mm x 35m ) m 80.00 45.00
S-II-6 Pile Load Test Nos 6,000.00 4,000.00
S-II-7 Breaking head for piling Nos 3.50 1.50
S-II-8 Soil Excavation Work for Pit lift Cu.m 3.00
S-II-9 Soil Excavation Work for Footing Cu.m - 3.00
S-II-10 Soil Filling Work for Footing,Pit Cu.m 3.00 3.00
Sand Filling with Compaction for Footings,
S-II-11 Cu.m
Foundation Beam,Pit and Slab 1.20 1.50
Crushed Stone 4x6cm with Compaction for
S-II-12 Cu.m
Footings,Foundation Beams,Pit and Slab 8.00 2.00
S-II-13 Lean Concrete Pit Footings,Foundation Beam &Slab Cu.m 50.00 25.00
S-II-14 Concrete for Footings Cu.m 63.00 50.00
S-II-15 Concrete for Columns Cu.m 63.00 65.00
S-II-16 Concrete for Basement wall Cu.m 63.00 65.00
S-II-17 Concrete for Pit Life Cu.m 63.00 65.00
S-II-18 Concrete for Foundation Beams Cu.m 63.00 50.00
S-II-19 Concrete for Slab Cu.m 63.00 30.00
S-II-20 Concrete for Stair case Cu.m 63.00 70.00
S-II-21 Steel Bars for Footings Ton 780.00 100.00
S-II-22 Steel Bars for Columns Ton 780.00 100.00
S-II-23 Steel Bars for Basement wall Ton 780.00 100.00
S-II-24 Steel Bars for Pit Ton 780.00 100.00
S-II-25 Steel Bars for Foundation Beams Ton 780.00 100.00
S-II-26 Steel Bars for Slab Ton 780.00 100.00
S-II-27 Steel Bars for Stair case Ton 780.00 100.00
S-II-28 Wire ties Kgf 1.50 -
S-II-29 Water stop m 7.50 3.00
S-II-30 Masonry Cu.m 50.00 30.00
S-II-31 Water proofing (Mambrane) wall,footing & slab Sq.m 10.00 2.00
S-II-32 Form Works for Footings Sq.m 10.00 2.50
S-II-33 Form Works For Columns Sq.m 10.00 2.50
S-II-34 Form Works For Basement wall Sq.m 10.00 2.50
S-II-35 Form Works For Pit Sq.m 10.00 2.50
S-II-36 Form Works For Foundation Beams Sq.m 10.00 2.50
S-II-37 Form Works for Stairs Sq.m 10.00 2.50
Sub-Total S-II AAA
S-III First Floor Plan
S-III-1 Concrete for Slab Cu.m 63.00 50.00
S-III-2 Concrete for Columns Cu.m 63.00 65.00
S-III-3 Concrete for Beams Cu.m 63.00 50.00
S-III-4 Concrete for Stair case Cu.m 63.00 70.00
S-III-5 Steel Bars for Slabs Ton 780.00 100.00
S-III-6 Steel Bars for Columns Ton 780.00 100.00
S-III-7 Steel Bars for Beams Ton 780.00 100.00
S-III-8 Steel Bars for Stair case Ton 780.00 100.00
S-III-9 Wire ties Kgf 1.50 -
S-III-10 Form Works for Slabs Sq.m 10.00 2.50
S-III-11 Form Works for Columns Sq.m 10.00 2.50
S-III-12 Form Works for Beams Sq.m 10.00 2.50
S-III-13 Form Works for Stairs Sq.m 10.00 2.50
Sub-Total S-III AAA
S-IV Second Floor Plan
S-IV-1 Concrete for Slab Cu.m 63.00 50.00
S-IV-2 Concrete for Columns Cu.m 63.00 65.00
S-IV-3 Concrete for Beams Cu.m 63.00 50.00
S-IV-4 Concrete for Stair Cu.m 63.00 70.00
S-IV-5 Steel Bars for Slabs Ton 780.00 100.00
S-IV-6 Steel Bars for Columns Ton 780.00 100.00
S-IV-7 Steel Bars for Beams Ton 780.00 100.00
S-IV-8 Steel Bars for Stairs Ton 780.00 100.00
S-IV-9 Wire ties Kgf 1.50 -
S-IV-10 Form Works for Slabs Sq.m 10.00 2.50
S-IV-11 Form Works for Columns Sq.m 10.00 2.50
S-IV-12 Form Works for Beams Sq.m 10.00 2.50
S-IV-13 Form Works for Stairs Sq.m 10.00 2.50
Sub-Total S-IV AAA
S-V Third Floor Plan
S-V-1 Concrete for Slab Cu.m 63.00 50.00
S-V-2 Concrete for Columns Cu.m 63.00 65.00
S-V-3 Concrete for Beams Cu.m 63.00 50.00
S-V-4 Steel Bars for Slabs Ton 780.00 100.00
S-V-5 Steel Bars for Columns Ton 780.00 100.00
S-V-6 Steel Bars for Beams Ton 780.00 100.00
S-V-7 Wire ties Kgf 1.50 -
S-V-8 Form Works for Slabs Sq.m 10.00 2.50
S-V-9 Form Works for Columns Sq.m 10.00 2.50
S-V-10 Form Works for Beams Sq.m 10.00 2.50
Sub-Total S-V AAA
S-VI Roof Structure
S-VI-1 Concrete for Beam and Roof Beams Cu.m 63.00 50.00
S-VI-2 Concrete for Roof Columns Cu.m 63.00 65.00
S-VI-3 Concrete for Slab Cu.m 63.00 50.00
S-VI-4 Steel Bars for Slabs Ton 780.00 100.00
S-VI-5 Steel Bars for Roof Columns Ton 780.00 100.00
S-VI-6 Steel Bars for Beam and Roof Beams Ton 780.00 100.00
S-VI-7 Wire ties Kgf 1.50 -
S-VI-8 Form Works for Roof Slabs Sq.m 10.00 2.50
S-VI-9 Form Works for Roof Columns Sq.m 10.00 2.50
S-VI-10 Form Works for Beam and Roof Beams Sq.m 10.00 2.50
S-VI-11 Roofing Tile Sq.m 7.00 1.00
S-VI-12 Steel Framing including Gutter Sq.m 20.00 4.00
Sub-Total S-VI AAA
Sub total for Structural work
Wastage 5%
Grand Total Including Benefit 10%
House Area
Unit Price Per 1m²
Excavation
No Description a (m) b (m) c (m) H (m) N V (cu-m)
1 P1 3.000 4.500 1.50 1.50 10 84.38
2 P2 4.000 5.500 3.00 1.50 14 299.25
W(ton)
1.450
1.450 3.3352 86.4
Slab Form
24
Slab Re-Bars
Top Re-Bars in short direction
In short direction X= 3.4
Type Speacing(m) Distribute (m) n T.Distribute (m) Diameter(m) Steel Area
Whole of 1/3L 0.300 1.133 2 2.267 0.010 0.00008
1/3L 0.300 1.133 4 4.533 0.010 0.00008
2/3L 0.150 3.333 2 6.667 0.010 0.00008
Total
2.856 19.04
Ground Beam Re-bars
Longitudinal Re-bars
1 1B1=(0.3mx0.50m) Diameter(m) n Steel Area L(m) L1(m) N E(ton)
Top Rebar
whole 0.020 2 0.00063 6.00 6.50 2 7.85
0.3L 0.020 3 0.00094 4.00 4.25 2 7.85
Side Rebar
whole 0.012 2 0.00023 6.00 6.50 2 7.85
Bottom Rebar
whole 0.020 2 0.00063 6.00 6.50 2 7.85
0.7L 0.020 2 0.00063 4.50 4.50 2 7.85
Total
Concrete Section
W(ton)+20% b(m) h(m) L(m) N V(cu-m) Speacing(m)
Support Ssup(m)
0.064 0.25 0.50 6.00 2 1.500 3.00 0.15
0.063 0.25 0.15 6.00 2 Midspan Smid(m)
0.45 3.00 0.2
0.023 Total Num
0.064
0.044
0.310 1.050 Total
Stirrups Lean Concrete
Diameter(m) Steel Area L1(m) L2(m) N E(ton) W(ton) b(m) h(m)
0.45 0.05
0.010 0.00157 1.360 1.000 20.00 7.85 0.02910
(+)15%
0.11713
Lean Concrete Girder forms Sand filling
L(m) N V(cu-m) b (m) h (m) L (m) N S (sq-m) b(m) h(m)
6.00 2 0.270 0.25 0.50 6.00 2 12.000 0.45 0.1
0.270 12.000
Sand filling
L(m) N V(cu-m)
6.00 2 0.540
0.540
Column forms
No Description a (m) b (m) H (m) N S (sq-m)
1 Colmn C1 0.30 4.00 4.00 5 172.00
2 Colmn C2 0.40 0.40 4.00 5 32.00
Concrete Main ba
Story
Column Length of
No Stories Height Total
Marks a (m) b(m) h(m) Rebars
(m) (m3)
(m)
Diameter
Diameter Area of Total Length of Length of
Quantity of of
of Rebars Weight down mid up Stirrups out Stirrups in
Rebars Rebars
Rebars (m) (m2) (kg) (m) (m)
(mm)
1.2070 24.00
0.5740 3.20
Footing forms short
No Description a (m) b (m) H (m) N S (sq-m)
1 Footing 1 1.000 1.500 0.400 10 20.00
2 Footing 2 2.000 3.000 0.400 14 56.00
Footing Re-Bars
Section Bottom Rebars in
No Describtion Area of
Total Length Diameter
a (m) b (m) h (m) Rebars
(m3) (m)+0.75 (mm)
(m2)
Total
Total Area of Total Rebars
Spacing Length Diameter
Quantity Weight Rebars Quantity Weight (ton)
(m) (m)+0.75 (mm)
(kg) (m2) (kg)
10 0.947 6.00
14 4.773 33.60
Concrete Wall and
Bottom Re-Bars in short direction
In Short direction = 3.5
Type Speacing(m) Distribute (m) Diameter(m) Steel Area Length(m) nos Layer
Whole 0.150 12.000 0.014 0.00015 3.80 80.00 2
Total
E(ton) W(ton) Rebar (ton) (+)20% N B(m) L(m) t(m) N V(cu-m) B(m)
7.85 0.735 1.12 1.34 1 3.50 12.00 0.2 1 8.4 3.5
0.735
E(ton) W(ton)
7.85 0.382
0.382 1.340 8.400
WALL Form
L(m) N S(sq-m)
12 2 84
84
ភលខភរបងរ កលបរ រភចចទរ
ភឈមគគតភរងរ
ភឈមគសសបអនរ
#WH 140 Eo-E1,Road 6,Sangkat Toul Sangkei,Khan Russey Keo,Phnom Penh City ទគតតងគតភរងរ
បបភភទ BOQ:
ភឈម គករងរ
ភរបបរងភដយរ ទបរសអពផរ
A-I-05 ករងរពរ ដ ន
ពរដនបតភបតរងធមមត(ឆប,ខតក) Sq.m 2.00 2.00
ពរដនមផងសរលលតធមមតនរងលបថផតសភត រច Sq.m 7.50 2.50
ពរដនមផងសរលលតមនបសទបកករពរជតរប(បនផបកទគក) Sq.m 8.50 2.50
ពរដនមផងសរលកកចកនរងលបថផតសភត រច Sq.m 10.00 4.00
A-I-06 ករងរជភណណធ រ
ករងរចបកបជជងនរងបបកបយអរសតភរចកតភផណក,កតឈរ M 3.00 2.00
ករងរចបកបជជងនរងបបកបយអរសតភរចថសជភណណធរ Sq.m 3.00 2.00
បនផគជអរមរខជភណណធរ(ទបករអរល) M 1.50 1.00
បងងនកលដផដកបរទភឈធពគភលធនរងបញកថផតសភត រច M 38.00 6.50
ចបកបជជងនរងបបកបយអរបតជភណណធរ Sq.m 4.00 3.50
ចបកបជជងនរងបបកបយអរសតភរចភជធងជញញ តងតមកតជភណណធ M 3.00 2.00
A-I-07 ករងរទស នរ ង បងសរ ច
A-I-08 ប នផ បក ទគ ក
ករបតក ប ងក 5%
បបកក ចត ភ ណញ 10%
លផផ អគរ
តត ល លសត ណ ងក ករ ផ ង 1m²
ចត ណត
ពរតមនករបតពកកបបពអនដមរសរគនបតជកកនរងមរ សរគនបតជកក
ពរតមនករតរបផតងលតអរខងកផរងផផគដបចជសឡរង,ភកអគ,ទបរទសតនណ,ផបគ
ភផតភពញ.លថថទគ______/______2014 ភផតភពញ.លថថទគ______/______2014
យលកប ពមភដយ ភរបបភរបងភដយ
សតរបក………..
A- សស បតខកមម
Date: 19/Sep/2014
តតលលសតភររ (USD) តតលលពលកមម (USD)
ល.រ បបភភទករងរ ឯកត បរ រមណ សររបររម
តតលលឯកត សររប តតលលឯកត សររប
A-I ជនក ទគ ១
A-I-1 ញរមនរងកញញកកសរ
ត បកបងសរច(Laminate 8mm) m² 85.00 - 7.50 - -
A-I-2 ញរមនរងកញញកកសរ
ត បកទស១សនឃគក(Laminate 8mm) set 200.00 - 30.00 - -
A-I-3 ញរមនរងកញញកកសរ
ត បកទស២សនឃគក(Laminate 8mm) set 400.00 - 60.00 - -
A-I-4 ទសភឈធ១សនឃគក(0.9m x 2.2m) set 120.00 - 40.00 - -
A-I-5 ទសភឈធ២សនឃគក(1.8m x 2.2m) set 240.00 - 80.00 - -
A-I-6 ភសរមបលនរងគនឃគគសតរបកទសភឈធ១សនឃគក set 60.00 - 5.00 - -
A-I-7 ភសរកចកនរងគនឃគគសតរបកទសភឈធ២សនឃគក set 90.00 - 10.00 - -
A-I-8 ភសសតរបកទសកញញកក set 50.00 - 5.00 - -
A-I-9 លដទសកញញកក nos 30.00 - 5.00 - -
A-I-10 បតភចបកទសកញញកក nos 10.00 - 3.00 - -
A-I-11 បតភចបកទសភឈធ nos 12.00 - 3.00 - -
A-I-12 បបដបកទបកទសនរងឪបករណណបរទភបធកទសសសយ
អ បបវតណរ nos 60.00 - 6.00 - -
A-I-13 សងកជញញ តងឥដដកតរសក20cm m² 10.00 - 3.00 - -
A-I-14 សងកជញញ តងឥដដកតរសក10cm m² 5.00 - 1.75 - -
A-I-15 ករងរឡមបបភហងខខលក m² 10.00 - 3.00 - -
A-I-16 ករងរបបកកផរងនរងភបកកតរសក2cm m² 2.00 - 1.50 - -
A-I-17 ករងរលបថផតករ ផង m² 2.00 - 1.00 - -
A-I-18 ករងរលបថផតភបក m² 2.50 - 1.00 - -
A-I-19 ករងរពរដននរងលបថផត m² 10.00 - 3.00 - -
A-I-20 បកលករប រ m² 7.80 - 3.00 - -
A-I-21 ភរបបករបរ ភជធងជញញ តង(H=12cm) m 7.80 - 1.50 - -
A-I-22 បកលករប
ប រ នផបកទគក m² 7.80 - 3.00 - -
A-I-23 ភរបបករបរ ជញញ តងបនផបកទគក(H=2.2m) m² 7.80 - 3.00 - -
A-I-24 បកលមរ បជភណណធរ m² 20.00 - 4.00 - -
A-I-25 ភរបបករបរ ភជធងជញញ តងជភណណធរ(H=12cm) m² 20.00 - 4.00 - -
A-I-26 បងងនកលដជភណណធរភធសធពគផដកបរតភឈធពគភលធ m 50.00 - 7.00 - -
សតភ រគបនផ បក ទគ ក
បបកក ចត ភ ណញ 10%
លផផ អគរ
តត ល លសត ណ ងក ករ ផ ង 1m²
ចត ណត
ពរតមនករបតពកកបបពអនដមរសរគនបតជកកនរងមរ សរគនបតជកក
ពរតមនករតរបផតងលតអរខងកផរងផផគដបចជសឡរង,ភកអគ,ទបរទសតនណ,ផបគ
ភផតភពញ.លថថទគ______/______2014 ភផតភពញ.លថថទគ______/______2014
យលកប ពមភដយ ភរបបភរបងភដយ
ភផតងៗ
_____2014
BILL OF QUANTITY AND COST ESTIMATION
FOR
PART 2.1
A-IV First and Second floor
A-IV-01 Slab Finishing
Tiles floor work (80x80)
Tiles floor work (30x30) for bathroom
Water proofing in bathroom
A-IV-01 Brick wall instalation
Hollow brick wall 20cm
Hollow brick wall 10cm
A-IV-01 Brick wall Finishing
Wall tile in bathroom (30x60)
Wall plastering for interior
Wall plastering for exterior
Painting for interior
Shieler for exterior
Painting for exterior
Marble for Lift
Skirt tiles work sq.m
A-IV-01 Ceiling work
Normal ceiling with finishing paint
Ceiling with Water proof protiction (Bath room)
Ceiling Art with finishing paint
A-IV-01 Staircase
Marble for rise and run
Step Nosing trims
Steel handrail with wood handle and sprayed
Bottom of stair plastering
Skirt marble for staircase
Door and Window
Glass window with Aluminum frame (Laminate 5+5)
Glass window with Aluminum frame (Normal 5mm)
Single swing door (Tember 10mm)
Double swing door (Tember 10mm)
Aluminum door
Single swing wooden door
Double swing wooden door
Double swing wooden door
Knob & Latch for Single swing door
Lever lock & Latch for Double swing door
Hing for wooden door
Door stopper or Door closer
Sanitary work
Toilet and jet-spray
Urinal
Lavatory and faucet
Marble for lavatory
Shower and faucet
Mirror
Towel Bar
Paper Holder
Soap Dish
Floor Drain
Partition for WC
Other Work
Mortar cemen
Concrete plate for Lavatory
ON
Date: 15/07/2014
Labor Cost (USD) Total Cost
Remarks
Total (USD.)
BILL OF QUANTITY AND MATERIAL DETAIL
FOR Twin Villa, Area 290m², (4 Unit)
បររមណ
ល.រ បបភភទករងរ ឯកត តតលលសតភរគ តតលលសររប
តតលលឯកត សររប