International Symposium on Underground Excavation and Tunnelling

2-4 February 2006, Bangkok, Thailand

Application of Top-down Construction Method for Deep


Excavations in Urban Area of Bangkok
1 1 1 1
Narong Thasnanipan , Zaw Zaw Aye , Chanchai Submaneewong , Thayanan Boonyarak
1
Seafco Public Company Limited, Bangkok, Thailand

ABSTRACT

Top-down construction method was used for construction of deep underground structures of
major projects in Bangkok, including 18 subway stations of the M.R.T Chaloem
Ratchamongkhon Line, the first underground mass transit system project in Bangkok. This paper
presents authors’ experiences in application of top-down construction method including different
stanchion installation techniques in Bangkok. The problems encountered during the actual
installation of the stanchions are also discussed. Application of top-down method in recently
completed deep basement structure is also reported highlighting the benefits offered by the
method in comparison with conventional bottom-up method. This paper demonstrates that the
top-down method is the most appropriate solution in construction of the deep underground
structures for protecting the sensitive urban environment.

REFERENCES

Arz P. 1989. Foundations of the Ko-Galerie in Dusseldorf Using Top-down Building


Technologies, Proceedings of the International Conference on Piling and Deep
Foundations, London, 15-18 May 1989 : 185-192. Rotterdam: Balkema.
Crawley J.D. & Stones C. S. 1996. Westminister Station – Deep Foundation and Top-Down
Construction in Central London, Geotechnical Aspects of Underground Construction in
Soft Ground, London : 93-97. Rotterdam : Balkema.
Findlay J. D., Wren G.E. 1989. Review of the Methods Used to Construct Large Diameter Bored
Piles for Top Down Construction. Proceedings of the International Conference on Piling
and Deep Foundations, London, 15-18 May 1989 : 199-210. Rotterdam: Balkema.
Finsted J. A. 1991. Royal Christiana Hotel : Basement with Permanent Sheet Pile Wall, “Up-and-
th
down” Method, 4 International DFI Conference : 387-392. Rotterdam: Balkema.
Hollingsworth J.R. 1991. Diaphragm Walls, Load Bearing Piles and Piled Soil Reinforcement for
th
a Deep Top-down Basement Construction, 4 International DFI Conference : 79-84.
Rotterdam : Balkema.
Manoharn S. & Aye Z. Z. (1994) , Bored Pile with King-post and Secant Pile Wall Construction
for Top-Down Method – Central Sukhothai Hotel Haddyai, Latest Technology in
Construction Technology Conference, Bangkok, Thailand
Thasnanipan N., Maung A. W. & Z. Z. Aye, (2000) Practical Installation of Stanchions for Top-
Down Construction in Bangkok Subsoil, Year 2000 Geotechnics, Geotechnical
Engineering Conference, The Imperial Queen’s Park Hotel, Bangkok, Thailand, 27-30
November 2000
Yong K.S., Tsen C.N. & Tang S.K. 1998. Performance of a Deep Excavation with Top-down
th
Construction, 13 Southeast Asian Geotechnical Conference, 16-20 November 1998.
Taipei, Taiwan ROC : 587-593