Company / Project Metric Measure Benefits Savings

Motorola (1992) In process defect levels 150-time reduction


Raytheon / aircraft integration Depot maintenance inspection 88% reduction measured in
system time. days
Business/ GE Railcar Lease Turnaround time in the shop Reductions up to 62%
Allied Signal Capacity cycle time inventory Up 50% Decrease 50% Decrease
(Honeywell)/Lamination plant in on-time delivery Increase approaching 100%
South Carolina
Allied Signal (Honeywell)/Bendix Concept -to-delivery cycle time Reduced from 18 months to 8
IQ Brake pads months
Hughes aircraft missile systems Finance Improved 1.000% / improved
group / wave solder operation 500%
General Electric Finance 2% billion in 1999
Motorola (1999) Finance $15 billion over 11 years
Dow Chemical Projects / Rail Finance Saving more than $2.45 million
Shipments for capital expenditure
DuPont plant / Yerkes in New Finance Savings more than $25 million
York (2000)
Telefonica de Espana (2001) Finance Savings and increased revenue
of 30 million euros in the first
10 months
Texas Instrument Finance $600 million
Johnson and Johnson Finance $500 Million
Honeywell Finance $1.2 Billion