This case study asks the student to analyze three project networks and calculate the time and critical path for each. For the first network, the critical path is A->C->D->F->G->I->J->E->H->O->P->R->S with a total time of 27 days. For the second network, the critical path is A->B->G->I with a total time of 18 days. For the third network, the critical path is A->D->E->Q->R with a total time of 85 days.
This case study asks the student to analyze three project networks and calculate the time and critical path for each. For the first network, the critical path is A->C->D->F->G->I->J->E->H->O->P->R->S with a total time of 27 days. For the second network, the critical path is A->B->G->I with a total time of 18 days. For the third network, the critical path is A->D->E->Q->R with a total time of 85 days.
This case study asks the student to analyze three project networks and calculate the time and critical path for each. For the first network, the critical path is A->C->D->F->G->I->J->E->H->O->P->R->S with a total time of 27 days. For the second network, the critical path is A->B->G->I with a total time of 18 days. For the third network, the critical path is A->D->E->Q->R with a total time of 85 days.
Time: 1 Week 1. Describe the project network to build a house from the data below. Calculate the time and critical path.
Activity Description Predecessor Time (Days)
A Clear the location - 1 B Bring the tool to the location - 2 C Conducting excavations A 1 D Pour the foundation C 2 E Plumbing installation from outside B, C 6 F Create a home frame D 10 G Installation of electric wire F 3 H Install the floor G 1 I Installing the roof F 1 J Installation of plumbing from inside E, H 5 K Installing the roof I 2 L Installation of the outer wall layers F, J 1 M Installing windows and outside doors F 2 N Build a wall L, M 4 O Isolate the walls and ceiling G, J 2 P Close the walls and ceiling O 2 Q Isolate the roof I, P 1 R Finish the interior P 7 S Finish the exterior I, N 7 T Build a garden S 3 2. Calculate the time and critical path from the data below
Activity Predecessor Time (Days)
A - 3 B A 14 C A 1 D C 3 E C 1 F C 2 G D, E, F 1 H G 1 I H 3 J H 2 K I, J 2 L K 2 M L 4 N L 1 O B, M, N 3
3. Calculate the time and critical path from the data below
Activity Predecessor Time (Days)
A - 21 B A 14 C A 14 D B, C 3 E D 70 F D 70 G D 14 H G 1 I H 1 Activity Predecessor Time (Days) J D 1 K J 1 L D 7 M L 7 N D 7 O N 14 P O 1 Q E, F, P 1 R Q, I, K 1 S M, R 2