You are on page 1of 3

Case Study

(Individual Assignment)

Topic: Project Management


Time: 1 Week
1. Describe the project network to build a house from the data below. Calculate the time and
critical path.

Activity Description Predecessor Time (Days)


A Clear the location - 1
B Bring the tool to the location - 2
C Conducting excavations A 1
D Pour the foundation C 2
E Plumbing installation from outside B, C 6
F Create a home frame D 10
G Installation of electric wire F 3
H Install the floor G 1
I Installing the roof F 1
J Installation of plumbing from inside E, H 5
K Installing the roof I 2
L Installation of the outer wall layers F, J 1
M Installing windows and outside doors F 2
N Build a wall L, M 4
O Isolate the walls and ceiling G, J 2
P Close the walls and ceiling O 2
Q Isolate the roof I, P 1
R Finish the interior P 7
S Finish the exterior I, N 7
T Build a garden S 3
2. Calculate the time and critical path from the data below

Activity Predecessor Time (Days)


A - 3
B A 14
C A 1
D C 3
E C 1
F C 2
G D, E, F 1
H G 1
I H 3
J H 2
K I, J 2
L K 2
M L 4
N L 1
O B, M, N 3

3. Calculate the time and critical path from the data below

Activity Predecessor Time (Days)


A - 21
B A 14
C A 14
D B, C 3
E D 70
F D 70
G D 14
H G 1
I H 1
Activity Predecessor Time (Days)
J D 1
K J 1
L D 7
M L 7
N D 7
O N 14
P O 1
Q E, F, P 1
R Q, I, K 1
S M, R 2