Professional Documents
Culture Documents
2014
Solved Problems in Facility Planning & Design 2014
Facility Planning: determines how an activity’s tangible fixed assets best support achieving the activity’s
objectives.
Facility Location: is the placement of a facility with respect to customers, suppliers, and other facilities
with which it interfaces.
Structural Design: consists of the building and services (e.g., gas, water, power, heat, light, air,
sewage).
Layout Design: consists of all equipment, machinery, and furnishings within the structure.
Handling System Design: consists of the mechanism by which all interactions required by the layout are
satisfied (e.g., materials, personnel, information, and equipment handling
systems).
FACILITY LOCATION
WS = WxS
Where:
WS = weighted score for each factor for each facility plan or location
W= appropriate weight to each factor (typically between 0 to 1) based on the relative importance of
each.
S= assigned score to each facility plan or location (typically between 0 to 100) with respect to each
factor identified.
Compute the sum of the weighted scores for each facility plan or location and choose a facility
plan or location with the highest score.
2|P a g e
Solved Problems in Facility Planning & Design 2014
Center-Of-Gravity Technique
n
X Wi i
i=1
X= _________________
n
W i
i=1
n
Y W i i
i=1
Y= _________________
n
W i
i=1
Where:
X, Y = coordinates of the new facility at the center of gravity.
Xi, Yi = coordinates of the existing facility i.
Wi = annual weight shipped from facility i.
Load-Distance Technique
n
LD = l d
i i
i=1
Where:
LD = the load distance value
li = the load expressed as a weight, number of trips, or units being shipped from the proposed site to
location i.
di = the distance between the proposed site and location i.
Where:
(x, y) = coordinates of the proposed site
(x i,yi) = coordinates of the existing facility
Scrap Estimate
Ok = Ik - PkIk
Ok = Ik (1 - Pk)
Ik = Ok/ (1- Pk)
I1 = On/ (1- P1) (1- P2)… (1- Pn)
Where:
Ok = desired output of non-defective product from operation k
Ik = production input to operation k
3|P a g e
Solved Problems in Facility Planning & Design 2014
Ok or Yield = (Total Input) (%Good Units) + (Total Input) (1 – %Good Units) (%Reworked)
Where
Equipment Fraction
F= SQ/ EHR
Where:
F= number of machines required per period
S= standard time per unit produced
Q= number of units to be produced period
E= efficiency or actual performance expressed as percentage of standard time
R= reliability of the machine expressed as percentage of ―up time‖
LAYOUT DESIGN
D = OT / CT
CT = OT / D
Where:
D= desired output rate
OT = operating time per period
CT = cycle time
N= __(D)(t)___
OT
Where:
N= minimum number of work stations
t = sum of task times
D= desired output rate
OT = operating time per period
E= __t___
N x CT
4|P a g e
Solved Problems in Facility Planning & Design 2014
Where:
E= efficiency of the assembly line
t = sum of task times
N= minimum number of work stations
CT = cycle time
Add tasks to a workstation in order of task precedence one at a time until utilization is 100% or is
observed to fall
Then the above procedure is repeated at the next workstation for the remaining tasks
Pro – Appropriate when one or more task times is equal to or greater than the cycle time
Con – Might create the need for extra equipment
Assign tasks to station 1, then 2, etc. in sequence. Keep assigning to a workstation ensuring that
precedence is maintained and total work is less than or equal to the cycle time. Use the following
rules to select tasks for assignment.
Primary: Assign tasks in order of the largest number of following tasks
Secondary (tie-breaking): Assign tasks in order of the longest operating time
5|P a g e
Solved Problems in Facility Planning & Design 2014
Where:
Z= the least value of the product between Lij and Dij
Lij = Load between departments i & j, often measured by the value of the vowel letter.
A = 4, E = 3, I = 2, O = 1, U = 0, X = -1 X = -2
Dij = Distance between departments i & j
Adjacent (Straight) – 1, Partial Adjacent (Diagonal) – 2, Non-Adjacent – 3
The first department placed in the layout is the one with the greatest TCR value. If a tie exists,
choose the one with more A’s.
If a department has an X relationship with the first one, it is placed last in the layout. If a tie
exists, choose the one with the smallest TCR value.
The second department is the one with an A relationship with the first one. If a tie exists, choose
the one with the greatest TCR value.
If a department has an X relationship with the second one, it is placed next-to-the-last or last in
the layout. If a tie exists, choose the one with the smallest TCR value.
The third department is the one with an A relationship with one of the placed departments. If a tie
exists, choose the one with the greatest TCR value.
The procedure continues until all departments have been placed.
Consider the figure below. Assume that a department is placed in the middle (position 0). Then,
if another department is placed in position 1, 3, 5 or 7, it is ―fully adjacent‖ with the first one. If it
is placed in position 2, 4, 6 or 8, it is ―partially adjacent‖.
For each position, Weighted Placement (WP) is the sum of the numerical values for all pairs of
adjacent departments.
The placement of departments is based on the following steps:
o The first department selected is placed in the middle.
6|P a g e
Solved Problems in Facility Planning & Design 2014
7|P a g e
Solved Problems in Facility Planning & Design 2014
ANSWER SHEET 1
10. _______ 30. _________ 50. _________ 70. _________ 90. _________
11. _______ 31. _________ 51. _________ 71. _________ 91. _________
12. _______ 32. _________ 52. _________ 72. _________ 92. _________
13. _______ 33. _________ 53. _________ 73. _________ 93. _________
14. _______ 34. _________ 54. _________ 74. _________ 94. _________
15. _______ 35. _________ 55. _________ 75. _________ 95. _________
16. _______ 36. _________ 56. _________ 76. _________ 96. _________
17. _______ 37. _________ 57. _________ 77. _________ 97. _________
18. _______ 38. _________ 58. _________ 78. _________ 98. _________
19. _______ 39. _________ 59. _________ 79. _________ 99. _________
20. _______ 40. _________ 60. _________ 80. _________ 100. _________
8|P a g e
Solved Problems in Facility Planning & Design 2014
1. Using this space determination method, the present space requirements are converted to those
required for the proposed layout.
2. It is the most complex Flexible Manufacturing System layout which allows material to move among the
machine centers in any order and typically includes several support stations such as tool interchange
stations, pallet or fixture build stations, inspection stations, and chip/ coolant collection systems.
a. 2 b. 3
c. 4 d. 5
6. What is the objective of designing the product, process, and schedule in relation to facilities planning?
7. A principle of material handling which a material handling facility should be the result of a cohesive and
structured unit of specific courses of action to determine what material needs to be moved, when, and
where it will be moved, and how it will be moved.
9|P a g e
Solved Problems in Facility Planning & Design 2014
10. The arrangement of all equipment, machinery, and furnishings within the structure.
12. A graph is ___________ if it can be drawn so that its vertices are points in the plane and each edge
can be drawn so that it intersects no other edges and passes through no other vertices.
a. Open b. Close
c. Planar d. Non-Planar
13. How many urinals do you need if a church has 401 to 700 members?
a. 2 b. 3
c. 4 d. 5
14. This program is used to generate and evaluate plant layout which does not restrict the final layout to
uniform shape, nor does it allow fixing departments to certain locations, resulting in unrealistic
layouts.
16. It is an analog model of the operations and inspections required in assembling a product.
18. Which of the following assumptions is not associated with planar location models?
10 | P a g e
Solved Problems in Facility Planning & Design 2014
19. The algorithm in Relationship Diagramming for determining the placement of the new activity begins
at the ____________ of the partial layout and evaluates all possible locations in counterclockwise
order.
21. An approach to scoring models in computerized layout evaluation which attempts to approximate the
―cost‖ of flow between activities.
23. In a __________________ layout, work stations are arranged according to the general function they
perform without regard to any particular product.
a. Product b. Process
c. Fixed Position d. Group Technology
24. A layout procedure which is based on the space relationship diagram, modifying considerations, and
practical limitations, a number of alternative layouts are designed and evaluated.
25. It is a form of flow pattern that is applicable when it is desired to terminate the flow very near the point
where the flow originated.
26. It determines how an activity’s tangible fixed assets best support achieving the activity’s objectives.
a. Jib b. Gantry
c. Hoist d. Stacker
11 | P a g e
Solved Problems in Facility Planning & Design 2014
28. A type of layout used when the product is too large or cumbersome to move through the various
processing steps. Consequently, rather than take the product to the processes, the processes are
brought to the product.
29. It allows the storage location for a particular product to change or ―float‖ over time.
30. It is the design verification phase of product development and is used to demonstrate or prove
aspects of a design.
31. Typically, layout design problems do not have well-defined, unique, and optimum solutions. We are
interested in obtaining a/ an ___________________.
32. How many lavatories do you need if a school has 101 to 200 students?
a. 2 b. 3
c. 4 d. 5
33. This method evaluates different locations based on the load being transported and the distance. A
single set of location coordinates is not identified. Instead, various locations are evaluated using a
value that is measure of weight and distance.
34. A programmable equipment connected by an automated material handling system and controlled by a
central computer.
35. A layout construction program that uses the total closeness rating, which is the sum of all numerical
values, assigned to the closeness relationships in a relationship chart between a department and all
other departments.
12 | P a g e
Solved Problems in Facility Planning & Design 2014
36. It is the sum of the weighted ratings between the new activity to be placed in the layout and its
neighbors in the layout.
a. Faces b. Edges
c. Adjacents d. Duals
39. A scale plan or model on which a thread is used to trace and measure the path of workers, materials
or equipment during a specified sequence of events.
40. What is the recommended range of stall width for standard car use?
a. Pallet b. Skid
c. Tote Pan d. Stretchwrap
42. It involves the assignment of specific storage locations or storage addresses for each product stored.
43. The arrangement of desired machinery of a plant, established or contemplated, in the way which will
permit the easiest flow of materials, at the lowest cost and with the minimum of handling, in processing
the product from the receipt of raw materials to the dispatch of the finished product.
44. A tabular record for presenting quantitative data about the movements of workers, materials or
equipment between any number of places over any given period of time.
13 | P a g e
Solved Problems in Facility Planning & Design 2014
46. A layout procedure composed of three simple steps, which can be applied to any type of layout
problem. These steps are: put the problem on paper, show lines of the flow, and convert flow lines to
machine lines.
a. Open b. Close
c. Line d. Circle
48. How many water closets do you need if a business organization has 51 to 80 employees?
a. 2 b. 3
c. 4 d. 5
49. What is the preferred area requirement of partitioned open for space—supervisor or manager?
50. A method of determining space requirements where each work station is a production facility having
its own receiving, shipping, production, and storage space requirements.
51. How much space area requirements do you need if you will serve meals to 200 to 400 employees?
53. It summarizes whether a part will be purchased or produced, how the production of a part will be
achieved, what equipment will be used, and how long it will take to perform each operation.
54. A principle of material handling which material handling flow should be as low as possible within the
requirements for effectiveness and efficiency of a material handling system.
55. A type of layout used when production volumes for individual products are not sufficient thereby
grouping products into logical product families.
14 | P a g e
Solved Problems in Facility Planning & Design 2014
56. It provides information about the component parts of the product, make or buy decisions, part
number, number of parts per product, and drawing references.
57. It consists of mechanism by which all interactions required by the layout are satisfied.
58. This a space determination method where templates or models are placed on the layout to obtain an
estimate of the general configuration and space requirements.
59. A type of layout used when processes are located according to the processing sequence for the
product. Material flows directly from a workstation to the adjacent workstation.
60. This location policy is referred to as _______________ if one particular time, different products use
the same storage slot, albeit only one product occupies the slot when it is occupied.
61. It identifies the significant material flows and their corresponding paths.
62. It is the simplest form of flow pattern which when employed in a plant, separate receiving and
shipping crews are normally required.
a. Function b. Material
c. Manufacturing d. All of these
15 | P a g e
Solved Problems in Facility Planning & Design 2014
66. It depicts the probable movement of materials by corresponding lines superimposed on the floor plan
of the area under study.
68. It consists of the mechanism by which all interactions required by the layout are satisfied e.g.
materials, personnel, information, and equipment handling systems.
69. Which of the following tools is used primarily in determining machine location for a product layout?
74. This drawing provides part specifications and dimensions in sufficient detail for manufacturing.
16 | P a g e
Solved Problems in Facility Planning & Design 2014
75. It establishes the prerequisite assembly steps that must be completed before performing a given
assembly step.
76. It refers to the overall design concepts or morphologies embedded within the facilities plan
77. What is the recommended range of stall width for luxury and elderly car use?
78. A principle of material handling which you try to reduce the ratio of equipment weight to product
weight and suggest not to buy equipment that is bigger than necessary.
79. How much space area requirements do you need if you will serve meals to 401 to 800 employees?
80. What is the recommended reception area that can accommodate a reception and 6 – 8 people?
81. It is obtained by dividing the usable cube by the exterior envelope of the container.
82. It is determined by dividing the overall container height by the nested height.
84. The total number of containers along the length and width of the trailer and the container stacked
vertically.
17 | P a g e
Solved Problems in Facility Planning & Design 2014
85. A space determination method consists of a single machine plus all the associated equipment and
space required for its operation. Work space, additional maintenance space, and storage space are
added to the space requirements for the machine.
88. It is a quantitative method of locating a facility at the center of the movement in a geographic area
based on weight and distance. It identifies a set of coordinates designating a central location on a
map relative to all other locations.
89. Are physical restrictions on the order in which operations are performed on the assembly line?
90. It is generally agreed that effective facilities planning can reduce material handling costs by ---
a. 5 – 10% b. 10 – 30%
c. 30 – 40% d. 50 – 70%
92. Which of the following is/ are way/s that we can accommodate a 20 second task in an 18 second
cycle time?
93. The term _____________ is used as a measure of the number of storages and retrievals performed
per time period.
a. Space b. Cost
c. Size d. Throughput
18 | P a g e
Solved Problems in Facility Planning & Design 2014
94. It takes a load summary chart and block diagram as input and then makes pair wise exchanges of
departments until no improvements in cost or non-adjacency score can be found.
95. It is an adaptation of the familiar mileage chart appearing on most road maps which normally contains
numbers representing some measure of the material flow between two machines, departments,
buildings, or sites.
96. It is the placement of a facility with respect to customers, suppliers, and other facilities with which it
interfaces.
98. It is a mechanized device to move materials in relatively large quantities between specific locations
over a fixed path.
99. It is a way to visualize the amount of movement that occurs between departments.
100. It covers the system’s ability to be changed to produce new product types and ability to change the
order of operations executed on a part.
19 | P a g e
Solved Problems in Facility Planning & Design 2014
1. Using this space determination method, the present space requirements are converted to those
required for the proposed layout.
2. It is the most complex Flexible Manufacturing System layout which allows material to move among the
machine centers in any order and typically includes several support stations such as tool interchange
stations, pallet or fixture build stations, inspection stations, and chip/ coolant collection systems.
a. 2 b. 3
c. 4 d. 5
Answer: b. 3
6. What is the objective of designing the product, process, and schedule in relation to facilities planning?
7. A principle of material handling which a material handling facility should be the result of a cohesive and
structured unit of specific courses of action to determine what material needs to be moved, when, and
where it will be moved, and how it will be moved.
20 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: b. Groups machines into small assembly lines that produce families of parts.
10. The arrangement of all equipment, machinery, and furnishings within the structure.
12. A graph is ___________ if it can be drawn so that its vertices are points in the plane and each edge
can be drawn so that it intersects no other edges and passes through no other vertices.
a. Open b. Close
c. Planar d. Non-Planar
Answer: c. Planar
13. How many urinals do you need if a church has 401 to 700 members?
a. 2 b. 3
c. 4 d. 5
Answer: c. 4
14. This program is used to generate and evaluate plant layout which does not restrict the final layout to
uniform shape, nor does it allow fixing departments to certain locations, resulting in unrealistic
layouts.
21 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: b. PLANET
16. It is an analog model of the operations and inspections required in assembling a product.
18. Which of the following assumptions is not associated with planar location models?
Answer: d. Travel costs are indirectly proportional to the planar distance used.
19. The algorithm in Relationship Diagramming for determining the placement of the new activity begins
at the ____________ of the partial layout and evaluates all possible locations in counterclockwise
order.
21. An approach to scoring models in computerized layout evaluation which attempts to approximate the
―cost‖ of flow between activities.
22 | P a g e
Solved Problems in Facility Planning & Design 2014
23. In a __________________ layout, work stations are arranged according to the general function they
perform without regard to any particular product.
a. Product b. Process
c. Fixed Position d. Group Technology
Answer: a. Product
24. A layout procedure which is based on the space relationship diagram, modifying considerations, and
practical limitations, a number of alternative layouts are designed and evaluated.
25. It is a form of flow pattern that is applicable when it is desired to terminate the flow very near the point
where the flow originated.
26. It determines how an activity’s tangible fixed assets best support achieving the activity’s objectives.
a. Jib b. Gantry
c. Hoist d. Stacker
Answer: c. Hoist
28. A type of layout used when the product is too large or cumbersome to move through the various
processing steps. Consequently, rather than take the product to the processes, the processes are
brought to the product.
23 | P a g e
Solved Problems in Facility Planning & Design 2014
29. It allows the storage location for a particular product to change or ―float‖ over time.
30. It is the design verification phase of product development and is used to demonstrate or prove
aspects of a design.
Answer: a. Prototyping
31. Typically, layout design problems do not have well-defined, unique, and optimum solutions. We are
interested in obtaining a/ an ___________________.
32. How many lavatories do you need if a school has 101 to 200 students?
a. 2 b. 3
c. 4 d. 5
Answer: a. 2
33. This method evaluates different locations based on the load being transported and the distance. A
single set of location coordinates is not identified. Instead, various locations are evaluated using a
value that is measure of weight and distance.
34. A programmable equipment connected by an automated material handling system and controlled by a
central computer.
35. A layout construction program that uses the total closeness rating, which is the sum of all numerical
values, assigned to the closeness relationships in a relationship chart between a department and all
other departments.
24 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: c. CORELAP
36. It is the sum of the weighted ratings between the new activity to be placed in the layout and its
neighbors in the layout.
a. Faces b. Edges
c. Adjacents c. Duals
Answer: a. Faces
39. A scale plan or model on which a thread is used to trace and measure the path of workers, materials
or equipment during a specified sequence of events.
40. What is the recommended range of stall width for standard car use?
a. Pallet b. Skid
c. Tote Pan d. Stretchwrap
Answer: d. Stretchwrap
42. It involves the assignment of specific storage locations or storage addresses for each product stored.
25 | P a g e
Solved Problems in Facility Planning & Design 2014
43. The arrangement of desired machinery of a plant, established or contemplated, in the way which will
permit the easiest flow of materials, at the lowest cost and with the minimum of handling, in processing
the product from the receipt of raw materials to the dispatch of the finished product.
44. A tabular record for presenting quantitative data about the movements of workers, materials or
equipment between any number of places over any given period of time.
46. A layout procedure composed of three simple steps, which can be applied to any type of layout
problem. These steps are: put the problem on paper, show lines of the flow, and convert flow lines to
machine lines.
a. Open b. Close
c. Line d. Circle
Answer: b. Close
48. How many water closets do you need if a business organization has 51 to 80 employees?
a. 2 b. 3
c. 4 d. 5
Answer: c. 4
49. What is the preferred area requirement of partitioned open for space—supervisor or manager?
26 | P a g e
Solved Problems in Facility Planning & Design 2014
50. A method of determining space requirements where each work station is a production facility having
its own receiving, shipping, production, and storage space requirements.
51. How much space area requirements do you need if you will serve meals to 200 to 400 employees?
53. It summarizes whether a part will be purchased or produced, how the production of a part will be
achieved, what equipment will be used, and how long it will take to perform each operation.
54. A principle of material handling which material handling flow should be as low as possible within the
requirements for effectiveness and efficiency of a material handling system.
55. A type of layout used when production volumes for individual products are not sufficient thereby
grouping products into logical product families.
56. It provides information about the component parts of the product, make or buy decisions, part
number, number of parts per product, and drawing references.
27 | P a g e
Solved Problems in Facility Planning & Design 2014
57. It consists of mechanism by which all interactions required by the layout are satisfied.
58. This a space determination method where templates or models are placed on the layout to obtain an
estimate of the general configuration and space requirements.
59. A type of layout used when processes are located according to the processing sequence for the
product. Material flows directly from a workstation to the adjacent workstation.
60. This location policy is referred to as _______________ if one particular time, different products use
the same storage slot, albeit only one product occupies the slot when it is occupied.
61. It identifies the significant material flows and their corresponding paths.
62. It is the simplest form of flow pattern which when employed in a plant, separate receiving and
shipping crews are normally required.
28 | P a g e
Solved Problems in Facility Planning & Design 2014
a. Function b. Material
c. Manufacturing d. All of these
66. It depicts the probable movement of materials by corresponding lines superimposed on the floor plan
of the area under study.
68. It consists of the mechanism by which all interactions required by the layout are satisfied e.g.
materials, personnel, information, and equipment handling systems.
69. Which of the following tools is used primarily in determining machine location for a product layout?
29 | P a g e
Solved Problems in Facility Planning & Design 2014
74. This drawing provides part specifications and dimensions in sufficient detail for manufacturing.
75. It establishes the prerequisite assembly steps that must be completed before performing a given
assembly step.
76. It refers to the overall design concepts or morphologies embedded within the facilities plan
77. What is the recommended range of stall width for luxury and elderly car use?
Answer: c. 9 to 10 ft.
30 | P a g e
Solved Problems in Facility Planning & Design 2014
78. A principle of material handling which you try to reduce the ratio of equipment weight to product
weight and suggest not to buy equipment that is bigger than necessary.
79. How much space area requirements do you need if you will serve meals to 401 to 800 employees?
80. What is the recommended reception area that can accommodate a reception and 6 – 8 people?
81. It is obtained by dividing the usable cube by the exterior envelope of the container.
82. It is determined by dividing the overall container height by the nested height.
84. The total number of containers along the length and width of the trailer and the container stacked
vertically.
31 | P a g e
Solved Problems in Facility Planning & Design 2014
85. A space determination method consists of a single machine plus all the associated equipment and
space required for its operation. Work space, additional maintenance space, and storage space are
added to the space requirements for the machine.
88. It is a quantitative method of locating a facility at the center of the movement in a geographic area
based on weight and distance. It identifies a set of coordinates designating a central location on a
map relative to all other locations.
89. Are physical restrictions on the order in which operations are performed on the assembly line?
90. It is generally agreed that effective facilities planning can reduce material handling costs by ---
a. 5 – 10% b. 10 – 30%
c. 30 – 40% d. 50 – 70%
Answer: b. 10 – 30%
32 | P a g e
Solved Problems in Facility Planning & Design 2014
92. Which of the following is/ are way/s that we can accommodate a 20 second task in an 18 second
cycle time?
93. The term _____________ is used as a measure of the number of storages and retrievals performed
per time period.
a. Space b. Cost
c. Size d. Throughput
Answer: d. Throughput
94. It takes a load summary chart and block diagram as input and then makes pair wise exchanges of
departments until no improvements in cost or non-adjacency score can be found.
Answer: d. CRAFT
95. It is an adaptation of the familiar mileage chart appearing on most road maps which normally contains
numbers representing some measure of the material flow between two machines, departments,
buildings, or sites.
96. It is the placement of a facility with respect to customers, suppliers, and other facilities with which it
interfaces.
98. It is a mechanized device to move materials in relatively large quantities between specific locations
over a fixed path.
33 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: a. Conveyor
99. It is a way to visualize the amount of movement that occurs between departments.
100. It covers the system’s ability to be changed to produce new product types and ability to change the
order of operations executed on a part.
34 | P a g e
Solved Problems in Facility Planning & Design 2014
ANSWER SHEET 2
10. _______ 30. _________ 50. _________ 70. _________ 90. _________
11. _______ 31. _________ 51. _________ 71. _________ 91. _________
12. _______ 32. _________ 52. _________ 72. _________ 92. _________
13. _______ 33. _________ 53. _________ 73. _________ 93. _________
14. _______ 34. _________ 54. _________ 74. _________ 94. _________
15. _______ 35. _________ 55. _________ 75. _________ 95. _________
16. _______ 36. _________ 56. _________ 76. _________ 96. _________
17. _______ 37. _________ 57. _________ 77. _________ 97. _________
18. _______ 38. _________ 58. _________ 78. _________ 98. _________
19. _______ 39. _________ 59. _________ 79. _________ 99. _________
20. _______ 40. _________ 60. _________ 80. _________ 100. _________
35 | P a g e
Solved Problems in Facility Planning & Design 2014
1. Belinda Fashion Wear is a small chain of stores specializing in fashion clothing. The company currently
has five stores in Manila, Quezon City, and Caloocan, and it wants to open new store in of four new
mall locations in the other nearby cities. A consulting firm has been hired to help the company decide
where to locate new store. The company has indicated five factors that are important to its decision,
including proximity of a college, community median income, mall vehicle traffic flow and parking,
quality and number of stores in the mall, and proximity of other malls or shopping areas. The
consulting firm had the company weight the importance of each factor. The consultant had visited each
potential location and rated them according to each factor, as follows:
Given that all sites have basically the same leasing cost and labor and operating cost, what is the
recommended location based on rating factors?
a. Mall 1 b. Mall 2
c. Mall 3 d. Mall 4
2. Zachtech Computers manufacture computer components such as chips, circuit boards, motherboards,
keyboards, LCD panels, and the like and sells them around the world. It wants to construct a new
warehouse/distribution center in Asia to serve emerging Asian markets. It has identified sites in
Shanghai, Hong Kong and Singapore and has rated the important location factors for each site as
follows:
Recommend a site including its total score rating based on these location factors and ratings.
a. Hongkong, 72 b. Hongkong, 82
c. Singapore, 81 d. Shanghai, 79
36 | P a g e
Solved Problems in Facility Planning & Design 2014
3. Cradle University is going to construct a new student center and athletic complex that will include a
bookstore, post office, theaters, markets, mini-mall, meeting rooms, swimming pool, and weight and
exercise rooms. The university administration has hired a site selection specialist has identified four
sites on campus and has rated important location factors for each site as follows:
4. Zhan Electronics is going to construct new P1.2 billion semi-conductor plant and has selected four
Export Processing Zone Areas as potential sites. The important location factors and ratings for each
town are as follows:
37 | P a g e
Solved Problems in Facility Planning & Design 2014
5. Joehanna Drug Store Chain wishes to build a new warehouse to serve the whole Quezon. At the
moment, it is looking at three possible locations. The factors, weights, and ratings being considered
are given below:
Ratings
Factor Weights Candelaria Lucena Lukban
Nearness to markets 20 4 7 5
Labor cost 5 8 8 4
Taxes 15 8 9 7
Nearness to suppliers 10 10 6 10
6. The Charlie Forwarding Company wants to build a new distribution center in Central Luzon. The center
needs to be in the vicinity of uncongested Aurora, Bataan, and Nueva Ecija. The coordinates of this sites
and the number of weekly packages that flow to each are as follows:
7. James Company is attempting to determine the location for a new outlet mall. The region where the
outlet mall will be constructed includes four towns, which together have a sizable population base. The
grid map coordinates of the four towns in Cavite and the populations of each are as follows:
Determine best location for the outlet mall using the center-of-gravity method.
8. Ray-Mart, a discount store chain, wants to build a new superstore in an area in Batangas near four
small towns with population between 8,000 and 42,000. The coordinates (in miles) of these four towns
and the market population in each are as follows:
38 | P a g e
Solved Problems in Facility Planning & Design 2014
Determine the coordinates of the best site using the center of gravity technique.
9. Caloy Distribution Center in Quezon City is due to be replaced with a much larger, more modern facility
that can handle the tremendous needs that have developed with the city’s growth. Fresh produce
travels to the seven store locations several times a day making site selection critical for efficient
distribution. Using the data in the following table, determine the map coordinates for the proposed
new distribution center.
Store Locations Map Coordinates (x,y) Truck Round Trips per Day
Timog Avenue (10, 5) 3
Banawe St. (3, 8) 3
West Avenue (4, 7) 2
Tomas Morato St. (15, 10) 6
Visayas Avenue (13, 3) 5
Libis (1, 12) 3
Cubao (5, 5) 10
a. (8, 7) b. (9, 7)
c. (7, 9) d. (7, 8)
10. The following table gives the map coordinates and the shipping loads for a set of cities that we wish to
connect though a central ―hub.‖ Near what map coordinates should the hub be located?
a. (7, 5) b. (8, 4)
c. (4, 8) d. (5, 7)
11. The Inah Burger restaurant chain uses a distribution center to prepare the food ingredients it provides
its individual restaurants. The company is attempting to determine the location for new distribution
center that will service five restaurants. The grid-map coordinates of the five restaurants and the annual
numbers of 40-foot trailer trucks transported to each restaurant are as follows:
39 | P a g e
Solved Problems in Facility Planning & Design 2014
12. The Inah Burger restaurant chain in the previous problem is considering three potential sites. With the
following grid-map coordinates for its new distribution center: A(350, 300). B. (150, 250), and C (250,
300). Determine the best location using the load-distance formula.
13. Marla Homes, a home improvement/ building supply chain, is going to build a new warehouse facility
to serve its stores in six Metro Manila Cities - Taguig, Pasig, Mandaluyong, Makati, Pasay, and
Quezon City. The coordinates of this cities (in miles), using Manila, as the origin (0,0) of a set of
coordinates, and the annual truck loads that supply each city as shown as follows. Determine the best
site using the center- gravity technique.
14. Refer to problem no. 13, Marla Homes base has two parcel of land, Site A & B in Metro Manila. Use
the load-distance technique to determine which would be the best site with its load-distance value.
Given:
Site X Y
A 88 80
B 13 127
15. Roy Automobile Accessories, a manufacturer of automobile fan belts is considering three locations—
Subic, Clark, and Laguna for a new plant. Cost studies indicate that fixed costs per year at the sites
are P30,000.00, P60,000.00, and P110,000.00, respectively; and variable cost are P75.00 per unit,
P45.00 per unit, and P25.00 per unit, respectively. The expected selling price of the fan belt produced
is P120.00. The company wishes to find the most economical location for an expected volume of
2,000 units per year.
16. A plastic firm has four work centers (A, B, C, and D) in series with individual capacities (units per day) and
actual output as shown.
A B C D
450 390 360 400 actual output = 306/ day
a. 306 b. 360
c. 450 d. 1,600
40 | P a g e
Solved Problems in Facility Planning & Design 2014
a. 19% b. 22.5%
c. 68% d. 85%
18. Dennis Furniture Company manufactures four-drawer oak cabinets in six stages. In the first stage, the
boards forming the walls of the cabinets are cut; in the second stage the front drawer panels are
woodworked; in the third stage the boards are sanded and finished; in the fourth stage the boards are
cleaned, stained, and painted with a clear finish; in the fifth stage the hardware for pulls, runners, and
fittings is installed; and in the final stage the cabinets are assembled. Inspection occurs at each stage
of the process, and the average percentages of good-quality units are as follows:
The cabinets are produced in weekly production runs with a product input for 300 units. Determine
the weekly product yield of good-quality cabinets.
a. 186 b. 288
c. 312 d. 486
19. Refer to problem no. 18, what would weekly product input have to be in order to achieve a final
weekly product yield of 300 cabinets?
a. 186 b. 288
c. 312 d. 486
20. The Jelo Motor Company, motors are produced in a three-stage process. Motors are inspected
following each stage with percentage yields of good quality in process units as follows:
3 0.95
The company wants to know the daily product yield for product input of 250 units per day.
a. 263 b. 238
c. 223 d. 280
21. Refer to problem no. 20, how many input units it would have to start with each day to result in a final
daily yield of 250 good quality units?
a. 263 b. 238
c. 223 d. 280
41 | P a g e
Solved Problems in Facility Planning & Design 2014
22. Rafael Metals Company manufactures of wood burning stove. What is the product input for 15,000
stoves if the good quality of each stove is 88%?
a. 13,200 b. 1,800
c. 125,000 d. 17,045
23. Lara Company operates a small telephone order system for a catalog of its clothing products. The
catalog orders are processed in four stages. Errors can be made in orders at any of these stages,
and the average percentages of errors that occur at each stage are as follows.
Stage %Error
1 19%
2 16%
3 10%
4 8%
If an average of 460 telephone orders is processed each day, how many errorless orders will result?
a. 112 b. 259
c. 244 d. 129
24. Liam Manufacturing Company has a weekly product input of 2,800 units. The average percentage of
good-quality product is 87 percent. Of the poor quality products 60 percent can be reworked and sold
as good-quality products. Determine the weekly product output?
a. 2,654 b. 5,364
c. 1,462 d. 3,218
25. Assume that production volume is 1,600 pieces per day, the standard time is 0.004 hour per piece, 8
working hours per day, setup time at 0.2 hr per day, and scrap rate of 0.10. Find the fractional
machine number.
a. 1.12 b. 0.85
c. 0.91 d. 1.21
26. A product requires two sequential machine operations. The first takes 3.5 minutes and the defect
percentage is 12. The second takes 6.0 minutes and the defect percentage is 7. In another similar
plant belonging to the same company, past annual data on identical operations and working
conditions indicate that a total of 2,198 hours due to set up of machines and 2,052 hours due to
machine unavailability due to maintenance per year. Assuming 250 work days per year and a daily
shift of 10 hours, it is desired to determine the minimum fractional number of machines to
manufacture 50,000 units per year.
a. 4 b. 5
c. 6 d. 7
27. Eric Explosives Company is considering the expansion of a solid-propellant manufacturing process by
adding more 1-ton capacity curing furnaces. Each batch (1 ton) of propellant must undergo 30 minutes of
furnace time, including load and unload operations. However, the furnace is used only 80 percent of the
time due to power restrictions in the other parts of the system. The required output for the new layout is to
be 16 tons per shift (8 hours). Plant (system) efficiency is estimated at 50 percent of system capacity.
Determine the number of furnaces required.
a. 3 b. 4
c. 1 d. 5
42 | P a g e
Solved Problems in Facility Planning & Design 2014
28. Refer to problem no. 27, estimate the percentage of time the furnaces will be idled.
a. 20% b. 25%
c. 33% d. 67%
29. Charmz Developing Agency must determine how many photo-enlarger cubicles are required to maintain
an output of 200 good prints per hour. The set-up and exposure time can theoretically be done in 2
minutes per print, but operators are on the average only 90 percent efficient and, in addition, 5 percent of
the prints must be scrapped and redone. Also, the cubicles can be utilized for enlarging only 70 percent of
the time. What is the required process capacity in prints per hour?
a. 212 b. 250
c. 211 d. 200
30. Refer to problem no. 29, what average output per hour can be expected from each cubicle, taking its use
factor and efficiency into account?
a. 211 b. 30
c. 19 d. 200
31. Refer to problem no. 29, how many enlarger cubicles are required?
a. 14 b. 10
c. 16 d. 12
32. Dason Plastics manufacturer must acquire some molding machines capable of producing 160,000 good
parts per year. They will be installed in a production line that normally produces 20 percent rejects
because of the tight aerospace specifications. Assume that it takes 90 seconds to mold each part and the
plant operates 2,000 hours per year. If the molding machines are used only 50 percent of the time and
are 90 percent efficient, what actual (usable) molding machine output per hour would be achieved?
a. 40 b. 18
c. 45 d. 20
33. Refer to problem no. 32, how many molding machines would be required?
a. 4 b. 8
c. 6 d. 12
34. Given:
Year Demand (units)
i. 220,000
ii. 275,000
iii. 380,000
iv. 420,000
v. 565,000
% Scrap: 3%
Standard Time: 2 minutes per unit
Target Machine Efficiency: 90%
Machine Breakdown: 30 minutes per day
Operation Schedule: 8am – 4pm daily schedule/ 20 working days per month
a. 5 b. 7
c. 2 d. 9
43 | P a g e
Solved Problems in Facility Planning & Design 2014
35. Refer to problem 34, how many machines you will acquire/ buy on Year 2?
a. 5 b. 7
c. 1 d. 9
36. Refer to problem no. 34, how many machines you will acquire/ buy on Year 3?
a. 5 b. 7
c. 3 d. 9
37. Refer to problem no. 34, how many machines you will acquire/ buy on Year 4?
a. 1 b. 10
c. 2 d. 9
38. Refer to problem no. 34, how many machines you will acquire/ buy on Year 5?
a. 1 b. 10
c. 3 d. 13
39. A team of Industrial Engineers conducted a work sampling of identical machines being used for a
manufacturing company and they have observed the following:
% Idleness
Machine 1 20%
Machine 2 35%
Machine 3 15%
Machine 4 55%
The machines are running based on the schedule of operation per shift.
Shift Schedule: 6am – 2pm/ 2pm – 10pm/ 10pm – 6am
Break Time: 1-hr meal break and 15 minutes coffee or short break per shift.
a. 1 b. 2
c. 3 d. 4
40. Mandy Garments produces T-shirts for road races. They need to acquire some new stamping
machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but
the new machines will be used for T-shirts only 60 percent of the time and the output usually includes
5 percent that are ―seconds‖ and unusable. The stamping operation takes 1 minute per T-shirt, and
the stamping machines are expected to have 90 percent efficiency when considering adjustments,
changeover of patterns, and unavoidable downtime. How many machines are required?
a. 5 b. 6
c. 7 d. 8
41. During one-8-hour shift, 770 non-defective parts are desired from a fabrication operation. The
standard time for the operation is 12 minutes. Because the machine operators are unskilled, the
actual time it takes to perform the operation is 25 minutes and, on the average, one-sixth of the parts
that begin fabrication are scrapped. Assuming that each of the machines used for this operation will
not be available for 45 minutes each shift and there is a probability of 0.05 that each machine will
breakdown, determine the number of machines required.
a. 50 b. 52
c. 54 d. 56
44 | P a g e
Solved Problems in Facility Planning & Design 2014
42. Nestor Briefcases is an exclusive producer of handcrafted, stylish cases. Priding itself on its earlier
reputation, the company assembles each case with care and attention to detail. This laborious
process requires the completion of six primary work elements, which are listed here.
If the demand is 50 cases per 40-hour week, compute the cycle time for the process.
a. 30 b. 40
c. 46 d. 48
43. Refer to problem no. 42, compute the lead time required for assembling one briefcase.
a. 30 b. 48
c. 80 d. 45
44. Refer to problem no. 42, calculate the theoretical minimum number of workstations.
a. 3 b. 2
c. 4 d. 1
45. Refer to problem no. 42, balance the line based on the most number of followers.
a.
35 45
AD BCEF
b.
45 35
AB CDEF
c.
30 30 20
A BCD EF
45 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
30 25 25
A BC DEF
a. 89% b. 83%
c. 81% d. 93%
47. Refer to problem no. 42, suppose the demand for briefcases increases to 80 cases per week.
Calculate a new cycle time.
a. 30 b. 35
c. 50 d. 45
48. Refer to problem no. 47, balance the line based on the longest task time
a.
35 45
AD BCEF
b.
45 35
AB CDEF
c.
30 30 20
A BCD EF
d.
30 25 25
A BC DEF
49. Refer to problem no. 47, calculate the new efficiency of the manufacturing process.
a. 89% b. 83%
c. 81% d. 93%
46 | P a g e
Solved Problems in Facility Planning & Design 2014
50. Refer to problem no. 47, calculate the theoretical minimum number of workstations.
a. 3 b. 2
c. 4 d. 1
51. Pepper & Mys Bakeshop has set a production quota of 600 party cakes per 40-hour workweek. Use
the following information to compute for the cycle time.
a. 3 b. 16
c. 4 d. 13
52. Refer to problem no. 51, compute the theoretical minimum number of workstations.
a. 5 b. 3
c. 2 d. 4
53. Refer to problem no. 51, balance the line using incremental utilization method
a.
b.
c.
3 3.25 3.25 3.25
3.25
47 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
3.0 3.0 3.25 3.25 3.25
54. Refer to problem no. 51, calculate the efficiency of the assembly line.
a. 95% b. 90%
c. 80% d. 83%
55. The Hanzel Pizza is revamping its order processing and pizza-making procedures. In order to deliver
fresh pizza fast, six elements must be completed.
If the demand is 120 pizzas per night (5:00 p.m. to 1:00 a.m.), compute the cycle time for the process.
a. 4 b. 3
c. 14 d. 13
56. Refer to problem no. 55, compute the lead time for the process.
a. 4 b. 3
c. 14 d. 13
57. Refer to problem no. 55, Calculate the theoretical minimum number of workstations.
a. 2 b. 3
c. 4 d. 5
58. Refer to problem no. 55, balance the line using the most number of followers method.
a.
3 5 3 3
AB CD E F
b.
3 2 3 3 3
AB C D E F
48 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
4 1 3 3 3
AC B D E F
d.
4 4 3 3
AC BD E F
59. Refer to problem no. 55, compute the efficiency of the line.
a. 88% b. 91%
c. 89% d. 93%
60. Refer to problem no. 55, suppose demand increases to 160 pizzas per night. What is the new cycle
time?
a. 4 b. 3
c. 14 d. 13
61. Refer to problem no. 60, balance the line based on the longest task time method.
a.
3 5 3 3
AB CD E F
b.
3 2 3 3 3
AB C D E F
c.
4 1 3 3 3
AC B D E F
49 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
4 4 3 3
AC BD E F
62. Refer to problem no. 60, calculate the new theoretical minimum number of workstations.
a. 2 b. 3
c. 4 d. 5
63. Neren’s Eye Care, Inc., is a full-service optical supplier that sells eyeglasses, contact lenses,
protective eye apparel to opticians. Bogs’ job is to assemble custom-ordered lenses into eyeglasses
for customers. Sales have been good lately, and Bogs has been assembling 100 glasses a day. The
manager of Neren’s asked Bogs to write down the precedence requirements and approximate
assembly times for each step in the assembly process. The data are shown here.
Assuming an 8-hour workday, how long does it take Bogs to assemble one pair of glasses?
a. 2 b. 2.4
c. 4 d. 4.8
64. Refer to problem no. 63, Neren’s anticipates a surge in demand with the opening of its own retail
outlets. If the assembly process is set up as an assembly line, what is the maximum number of
eyeglasses that can be assembled in one day, regardless of the number of workers hired?
a. 200 b. 240
c. 100 d. 480
65. Refer to problem no. 64, what is the efficiency of the line?
a. 80% b. 91%
c. 100% d. 95%
50 | P a g e
Solved Problems in Facility Planning & Design 2014
66. Prof. Jone has assigned 15 cases in his Seminar class to be completed in a 15 week semester. The
students, of course, are moaning and groaning that the caseload cannot possibly be completed in the
time allotted. Prof. Jone sympathetically suggests that the students work in groups and learn to
organize their work efficiently. Knowing when a situation is hopeless, the students make a list of the
tasks that have to be completed in preparing a case. These tasks are listed here, along with
precedence requirements and estimated time in days. Assuming students will work 5 days a week on
this assignment, how many students should be assigned to each group?
a. 3 b. 4
c. 5 d. 6
67. The precedence diagram and task times (in minutes) for assembling Reyson’s Stamp Pad are shown
here. Set up an assembly line to produce 125 stamp pads in a 40-hour week. What is the cycle time?
8 5
A B F 4 J 9
C D E H 7 K 3
6 10 2
G I
5 2
a. 10 b. 19.2
c. 61 d. 2
68. Refer to problem no. 67, balance the line based on the most number of followers.
a.
19 19 11 12
b.
19 19 18 5
51 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
19 17 13 12
d.
19 16 14 12
69. The work elements, precedence requirements, and time requirements to assemble a picture frame
are shown here. What is the cycle time capable of producing 1,600 frames per 40-hour week?
a. 1.5 b. 0.70
c. 0.10 d. 3.4
70. Refer to problem no. 69, balance the assembly line based on the computed cycle time using
incremental utilization method
a.
1.4 1.2 .80
b.
1.30 1.40 0.70
DABI CEF GH
52 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
1.40 1.40 0.60
ABC DEFG HI
d.
1.45 1.45 0.50
DEAI BCFG H
71. Refer to Problem No. 70, what is the maximum output per week?
a. 1,600 b. 1,715
c. 1,750 d. 1,656
72. Refer to problem no. 69, balance the assembly line based on the computed cycle time using most
number of followers method.
a.
1.4 1.2 .80
b.
1.30 1.40 0.70
DABI CEF GH
c.
1.40 1.40 0.60
ABC DEFG HI
d.
1.45 1.45 0.50
DEAI BCFG H
73. Refer to Problem No. 72, what is the maximum output per week?
a. 1,600 b. 1,715
c. 1,750 d. 1,656
53 | P a g e
Solved Problems in Facility Planning & Design 2014
74. Refer to problem no. 69, balance the assembly line based on the computed cycle time using longest
task time method.
a.
1.4 1.2 .80
b.
1.30 1.40 0.70
DABI CEF GH
c.
1.40 1.40 0.60
ABC DEFG HI
d.
1.45 1.45 0.50
DEAI BCFG H
75. Refer to Problem No. 74, what is the maximum output per week?
a. 1,600 b. 1,715
c. 1,750 d. 1,656
76. Refer to problem no. 69, calculate the maximum number of frames that can be assembles each week.
a. 2,557 b. 2,452
c. 3,567 d. 3,429
77. Refer to problem no. 76, rebalance the line for maximum production. Assuming one worker per
workstation. How many workers would be required?
a. 5 b. 4
c. 6 d. 3
78. Refer to problem no. 76, assume the company can sell as many frames as can be produced. If
workers are paid P60.00 an hour. What is the total cost per frame?
a. 1.67 b. 1.47
c. 6.17 d. 7.14
54 | P a g e
Solved Problems in Facility Planning & Design 2014
79. The Racela Finance Corporation has set a processing quota of 80 insurance claims per 8-hour day.
The claims process consists of five elements, which are detailed in the following table. Racela has
decided to use an assembly line arrangement to process the forms and would like to make sure they
have set up the line in the most efficient fashion. Calculate the cycle time required to meet the
processing quota.
a. 5 b. 6
c. 15 d. 16
80. Refer to problem no. 79, determine how many claims can actually be processed on your line.
81. A firm must produce 40 units/day during an 8-hour workday. Tasks, times, and predecessor activities
are given below.
a. 10 b. 38
c. 12 d. 20
82. Thomas Santos, manager of a metropolitan branch office of the state department of motor vehicles,
attempted to perform an analysis of the driver’s license renewal operations. He identified the steps
and associated times required to perform each step as follows:
Santos found that each step was assigned to a different person. Santos also found that jobs A, B, C,
and D were handled by general clerks who were each paid P270.00 per hour. Job E was by a
photographer paid P360.00 per hour. Job F, the issuing of temporary licenses, was required by state
55 | P a g e
Solved Problems in Facility Planning & Design 2014
policy to be handled by a uniformed motor vehicle officer. Officers were paid P405.00 per hour, but
they could be assigned to any job except photography.
A review of the jobs indicated that job A, reviewing the application for correctness, had to be
performed before any other step could be taken. Similarly, job F, issuing the temporary license, could
not be performed until all the other steps were completed. The checking of file violations and
restrictions could be performed while the applicant is having his eye test. The branch offices were
charged P450.00 per hour for each camera to perform photography.
Determine the maximum number of applications per hour that can be handled by the present
configuration of the process?
a. 60 b. 90
c. 120 d. 180
83. Refer to problem no. 82, how many applications can be processed per hour if a second clerk is added
to check for violations?
a. 60 b. 90
c. 120 d. 180
84. In addition to problem no. 83, assuming one more clerk is added to job D, what is the maximum
number of applications the process can handle?
a. 60 b. 90
c. 120 d. 180
85. Refer to problem no. 82, what is the required cycle time of the process to accommodate 180
applications per hour?
a. 15 b. 20
c. 40 d. 60
86. Refer to problem no. 82, compute for the costs per application per hour involved in the current
process.
a. 30.60 b. 18.90
c. 23.40 d. 38.25
87. Refer to problem no. 84, for the costs per application per hour involved in the alternative process.
a. 30.60 b. 18.90
c. 23.62 d. 38.25
88. Given:
From/To A B C D E F
A 15 50 125
B 20 75
C 50 120 120
D
E 50 100
F 110 100
56 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
A B C
D E F
b.
C B E
F A D
c.
B A F
E C D
d.
D B E
C F A
89. Given:
57 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
1 2 6
4 3 5
b.
5 2 1
4 3 6
c.
2 6 5
3 4 1
d.
6 3 4
1 5 2
90. Given:
58 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
4 1 2
6 5 3
b.
3 6 4
2 5 1
c.
1 5 4
3 6 2
d.
6 3 2
5 1 4
91. Given:
Loads/day
From/To A B C D E
A 30 60 20
B 30 30
C 80
D 40
E
59 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
C A
D E
b.
C B
D A
c.
B D
E A
d.
A E
C B
60 | P a g e
Solved Problems in Facility Planning & Design 2014
92. Matthew Design Company has been asked to design the layout for a newly constructed office
building of one of its clients. The closeness matrix showing the daily trips between its six department
offices is given below.
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
3 1 5
6 4 2
b.
2 5 3
4 1 6
c.
5 1 4
3 6 2
d.
1 6 2
3 5 4
61 | P a g e
Solved Problems in Facility Planning & Design 2014
93. Given:
Flow between Departments (Number of Moves)
Departments 1 2 3 4 5 6 7 8
1. Shipping and receiving 175 150 80 20 75
2. Plastic molding stamping 90 100 125 120
3. Metal forming 350
4. Sewing department 25 25
5. Small toy assembly 180 187
6. Large toy assembly 374 103
7. Painting 7
8. Mechanism assembly
Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
5 1
2 6 4
3 7 8
b.
1 7
5 2 6
3 8 4
62 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
4 5
6 1 3
2 8 7
d.
6 4
7 8 2
5 1 3
94. Given:
Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
Press Warehouse
Stores Turning
63 | P a g e
Solved Problems in Facility Planning & Design 2014
b.
Turning Stores
Plate Assembly
c.
Assembly Warehouse
Assembly Stores
d.
Milling Assembly
Stores Press
64 | P a g e
Solved Problems in Facility Planning & Design 2014
a.
4 6
1 5
2 3
b.
6 4
1 5
3 2
c.
2 3 6
1 5
d.
6 3 2
5 1
96. Based on the relationship chart below, what is its recommended layout?
65 | P a g e
Solved Problems in Facility Planning & Design 2014
a.
5 3 1
2 4
6 7
b. 1 3
4 2
5 6 7
c.
3 1
6 2 4
7 5
d.
1 3
6 2 4
5 7
97. Given:
66 | P a g e
Solved Problems in Facility Planning & Design 2014
a. 10,000 b. 11,000
c. 12,000 d. 14,000
98. In reference to problem no. 97, what activity is the first to be placed on the grid?
a. 7 b. 2
c. 5 d. 6
a.
10 5 6
1 3 7
2 8 4 9
b.
10 1 7
3 5 6
4 8 9 2
67 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
10 1 4
8 9 2
7 3 5 6
d.
10 5 6
8 4 7
2 1 3 9
100. Given:
Parts-Machines Matrix
Parts
1 2 3 4 5 6 7 8
A x x x
B x x
C x x
D x x x x
E x
Machines F x x
G x x
H x x x
I x x
J x x
K x
L x x x
Using Digital Clustering Algorithm (DCA), prepare the final cell formation with additional machines, if
needed.
68 | P a g e
Solved Problems in Facility Planning & Design 2014
a. 5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L X X X
G X X
K X
C X X
F X X
I X X
E X
b. 5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L1 X X
G X X
K X
L2 X
C X X
F X X
I X X
E X
c. 5 6 1 4 7 3 2 8
D X X X X
A X X X
H X X X
B X X
J X X
C X X
F X X
I X X
E X X X
L X X
G X X
K X
d. 5 6 1 4 7 3 2 8
D X X X X
A X X X
H X X X
B X X
J X X
C X X
F X X
I X X
E1 X
E2 x x
L X X
G X X
K X
69 | P a g e
Solved Problems in Facility Planning & Design 2014
1. Belinda Fashion Wear is a small chain of stores specializing in fashion clothing. The company currently
has five stores in Manila, Quezon City, and Caloocan, and it wants to open new store in of four new
mall locations in the other nearby cities. A consulting firm has been hired to help the company decide
where to locate new store. The company has indicated five factors that are important to its decision,
including proximity of a college, community median income, mall vehicle traffic flow and parking,
quality and number of stores in the mall, and proximity of other malls or shopping areas. The
consulting firm had the company weight the importance of each factor. The consultant had visited each
potential location and rated them according to each factor, as follows:
Given that all sites have basically the same leasing cost and labor and operating cost, what is the
recommended location based on rating factors?
a. Mall 1 b. Mall 2
c. Mall 3 d. Mall 4
Answer: d. Mall 4
2. Zachtech Computers manufacture computer components such as chips, circuit boards, motherboards,
keyboards, LCD panels, and the like and sells them around the world. It wants to construct a new
warehouse/distribution center in Asia to serve emerging Asian markets. It has identified sites in
Shanghai, Hong Kong and Singapore and has rated the important location factors for each site as
follows:
70 | P a g e
Solved Problems in Facility Planning & Design 2014
Recommend a site including its total score rating based on these location factors and ratings.
a. Hongkong, 72 b. Hongkong, 82
c. Singapore, 81 d. Shanghai, 79
Answer: c. Singapore, 81
3. Cradle University is going to construct a new student center and athletic complex that will include a
bookstore, post office, theaters, markets, mini-mall, meeting rooms, swimming pool, and weight and
exercise rooms. The university administration has hired a site selection specialist has identified four
sites on campus and has rated important location factors for each site as follows:
Answer: d. East
71 | P a g e
Solved Problems in Facility Planning & Design 2014
4. Zhan Electronics is going to construct new P1.2 billion semi-conductor plant and has selected four
Export Processing Zone Areas as potential sites. The important location factors and ratings for each
town are as follows:
Answer: b. Lipa
72 | P a g e
Solved Problems in Facility Planning & Design 2014
5. Joehanna Drug Store Chain wishes to build a new warehouse to serve the whole Quezon. At the
moment, it is looking at three possible locations. The factors, weights, and ratings being considered
are given below:
Ratings
Factor Weights Candelaria Lucena Lukban
Nearness to markets 20 4 7 5
Labor cost 5 8 8 4
Taxes 15 8 9 7
Nearness to suppliers 10 10 6 10
6. The Charlie Forwarding Company wants to build a new distribution center in Central Luzon. The center
needs to be in the vicinity of uncongested Aurora, Bataan, and Nueva Ecija. The coordinates of this sites
and the number of weekly packages that flow to each are as follows:
73 | P a g e
Solved Problems in Facility Planning & Design 2014
7. James Company is attempting to determine the location for a new outlet mall. The region where the
outlet mall will be constructed includes four towns, which together have a sizable population base. The
grid map coordinates of the four towns in Cavite and the populations of each are as follows:
Determine best location for the outlet mall using the center-of-gravity method.
8. Ray-Mart, a discount store chain, wants to build a new superstore in an area in Batangas near four
small towns with population between 8,000 and 42,000. The coordinates (in miles) of these four towns
and the market population in each are as follows:
Determine the coordinates of the best site using the center of gravity technique.
74 | P a g e
Solved Problems in Facility Planning & Design 2014
9. Caloy Distribution Center in Quezon City is due to be replaced with a much larger, more modern facility
that can handle the tremendous needs that have developed with the city’s growth. Fresh produce
travels to the seven store locations several times a day making site selection critical for efficient
distribution. Using the data in the following table, determine the map coordinates for the proposed
new distribution center.
Store Locations Map Coordinates (x,y) Truck Round Trips per Day
Timog Avenue (10, 5) 3
Banawe St. (3, 8) 3
West Avenue (4, 7) 2
Tomas Morato St. (15, 10) 6
Visayas Avenue (13, 3) 5
Libis (1, 12) 3
Cubao (5, 5) 10
a. (8, 7) b. (9, 7)
c. (7, 9) d. (7, 8)
Answer: a. (8, 7)
10. The following table gives the map coordinates and the shipping loads for a set of cities that we wish to
connect though a central ―hub.‖ Near what map coordinates should the hub be located?
a. (7, 5) b. (8, 4)
c. (4, 8) d. (5, 7)
Answer: d. (5, 7)
75 | P a g e
Solved Problems in Facility Planning & Design 2014
11. The Inah Burger restaurant chain uses a distribution center to prepare the food ingredients it provides
its individual restaurants. The company is attempting to determine the location for new distribution
center that will service five restaurants. The grid-map coordinates of the five restaurants and the annual
numbers of 40-foot trailer trucks transported to each restaurant are as follows:
X = 25200/108
X = 233.33 = 233
12. The Inah Burger restaurant chain in the previous problem is considering three potential sites. With the
following grid-map coordinates for its new distribution center: A(350, 300). B. (150, 250), and C (250,
300). Determine the best location using the load-distance formula.
76 | P a g e
Solved Problems in Facility Planning & Design 2014
2 2
Site B: d1 = (X1 – Xa) + (Y1 – Yb)
2 2
= (100 – 150) + (300 - 250) = 70.71
2 2
d2 = (X2 – Xb) + (Y2 – Yb)
2 2
= (210 – 150) + (180 – 250) = 92.20
2 2
d3 = (X3 – Xb) + (Y3 – Yb)
77 | P a g e
Solved Problems in Facility Planning & Design 2014
13. Marla Homes, a home improvement/ building supply chain, is going to build a new warehouse facility
to serve its stores in six Metro Manila Cities - Taguig, Pasig, Mandaluyong, Makati, Pasay, and
Quezon City. The coordinates of this cities (in miles), using Manila, as the origin (0,0) of a set of
coordinates, and the annual truck loads that supply each city as shown as follows. Determine the best
site using the center- gravity technique.
14. Refer to problem no. 13, Marla Homes base has two parcel of land, Site A & B in Metro Manila. Use
the load-distance technique to determine which would be the best site with its load-distance value.
Site X Y
A 88 80
B 13 127
For Site A:
2 2
d Pasig = (15 – 88) + (85 – 80) = 73.17
For Site B:
d Pasig = (15 – 13)2 + (85 – 127)2 = 42.05
2 2
d Taguig = (42 – 13) + (145 – 127) = 34.13
78 | P a g e
Solved Problems in Facility Planning & Design 2014
Load Distance:
For Site A:
For Site B:
LD = 160(42.05) + 90(34.13) + 105(77.13) + 35(112.75) + 60(122.00) + 75(199.42)
= 44,121.10 = 44,121
15. Roy Automobile Accessories, a manufacturer of automobile fan belts is considering three locations—
Subic, Clark, and Laguna for a new plant. Cost studies indicate that fixed costs per year at the sites
are P30,000.00, P60,000.00, and P110,000.00, respectively; and variable cost are P75.00 per unit,
P45.00 per unit, and P25.00 per unit, respectively. The expected selling price of the fan belt produced
is P120.00. The company wishes to find the most economical location for an expected volume of
2,000 units per year.
For Subic,
Total Cost = P30,000.00 + P75.00(2,000) = P180,000.00
For Clark,
Total Cost = P60,000.00 + P45.00(2,000) = P150,000.00
For Laguna,
Total Cost = P110,000.00 + P25.00(2000) = P160,000.00
With an expected volume of 2,000 units per year, Clark provides the lowest cost location.
16. A plastic firm has four work centers (A, B, C, and D) in series with individual capacities (units per day) and
actual output as shown.
A B C D
450 390 360 400 actual output = 306/ day
a. 306 b. 360
c. 450 d. 1,600
Answer: b. 360
Process Capacity = capacity of most limited component in the line = 360 units/ day
79 | P a g e
Solved Problems in Facility Planning & Design 2014
a. 19% b. 22.5%
c. 68% d. 85%
Answer: d. 85%
18. Dennis Furniture Company manufactures four-drawer oak cabinets in six stages. In the first stage, the
boards forming the walls of the cabinets are cut; in the second stage the front drawer panels are
woodworked; in the third stage the boards are sanded and finished; in the fourth stage the boards are
cleaned, stained, and painted with a clear finish; in the fifth stage the hardware for pulls, runners, and
fittings is installed; and in the final stage the cabinets are assembled. Inspection occurs at each stage
of the process, and the average percentages of good-quality units are as follows:
The cabinets are produced in weekly production runs with a product input for 300 units. Determine
the weekly product yield of good-quality cabinets.
a. 186 b. 288
c. 312 d. 486
Answer: a. 186
19. Refer to problem no. 18, what would weekly product input have to be in order to achieve a final
weekly product yield of 300 cabinets?
a. 186 b. 288
c. 312 d. 486
Answer: d. 486
I = 300 / (0.87)(0.91)(0.94)(0.93)(0.93)(0.96)
I = 485.5 = 486
80 | P a g e
Solved Problems in Facility Planning & Design 2014
20. The Jelo Motor Company, motors are produced in a three-stage process. Motors are inspected
following each stage with percentage yields of good quality in process units as follows:
3 0.95
The company wants to know the daily product yield for product input of 250 units per day.
a. 263 b. 238
c. 223 d. 280
Answer: c. 223
O = (250)(0.96)(0.98)(0.95)
O = 223.44 = 224
21. Refer to problem no. 20, how many input units it would have to start with each day to result in a final
daily yield of 250 good quality units?
a. 263 b. 238
c. 223 d. 280
Answer: d. 280
I = 250 / (0.96)(0.98)(0.95)
I = 279.72 motors = 280
22. Rafael Metals Company manufactures of wood burning stove. What is the product input for 15,000
stoves if the good quality of each stove is 88%?
a. 13,200 b. 1,800
c. 125,000 d. 17,045
Answer: d.
I = O/(1 - P)
I = 15,000/(1 - 0.12)
I = 17,045.45 = 17,045
23. Lara Company operates a small telephone order system for a catalog of its clothing products. The
catalog orders are processed in four stages. Errors can be made in orders at any of these stages,
and the average percentages of errors that occur at each stage are as follows.
Stage %Error
1 19%
2 16%
3 10%
4 8%
81 | P a g e
Solved Problems in Facility Planning & Design 2014
If an average of 460 telephone orders is processed each day, how many errorless orders will result?
a. 112 b. 259
c. 244 d. 129
Answer: b. 259
24. Liam Manufacturing Company has a weekly product input of 2,800 units. The average percentage of
good-quality product is 87 percent. Of the poor quality products 60 percent can be reworked and sold
as good-quality products. Determine the weekly product output?
a. 2,654 b. 5,364
c. 1,462 d. 3,218
Answer: 2,654
O = 2,800(0.87) + 2,800(0.13)(0.60)
O = 2,436 + 218.4
O = 2,654.4 = 2,654
25. Assume that production volume is 1,600 pieces per day, the standard time is 0.004 hour per piece, 8
working hours per day, setup time at 0.2 hr per day, and scrap rate of 0.10. Find the fractional
machine number.
a. 1.12 b. 0.85
c. 0.91 d. 1.21
Answer: c. 0.91
26. A product requires two sequential machine operations. The first takes 3.5 minutes and the defect
percentage is 12. The second takes 6.0 minutes and the defect percentage is 7. In another similar
plant belonging to the same company, past annual data on identical operations and working
conditions indicate that a total of 2,198 hours due to set up of machines and 2,052 hours due to
machine unavailability due to maintenance per year. Assuming 250 work days per year and a daily
shift of 10 hours, it is desired to determine the minimum fractional number of machines to
manufacture 50,000 units per year.
a. 4 b. 5
c. 6 d. 7
Answer: b. 5
P2 = 50,000/0.93 = 53,763.44
P1 = 53,763.44/0.88 = 61,094.82
F = ((53,763.44)(6) + (61094.82)(3.5))/(60*250*10)(2,198/2,500)(2,052/2,500)) = 5
82 | P a g e
Solved Problems in Facility Planning & Design 2014
27. Eric Explosives Company is considering the expansion of a solid-propellant manufacturing process by
adding more 1-ton capacity curing furnaces. Each batch (1 ton) of propellant must undergo 30 minutes of
furnace time, including load and unload operations. However, the furnace is used only 80 percent of the
time due to power restrictions in the other parts of the system. The required output for the new layout is to
be 16 tons per shift (8 hours). Plant (system) efficiency is estimated at 50 percent of system capacity.
Determine the number of furnaces required.
a. 3 b. 4
c. 1 d. 5
Answer: a. 3
F = 30 mins per ton x 16 tons per shift/ 8 x 60 x 0.50 x 0.80 = 480/ 192 = 2.5 = 3
28. Refer to problem no. 27, estimate the percentage of time the furnaces will be idled.
a. 20% b. 25%
c. 33% d. 67%
Answer: d. 67%
29. Charmz Developing Agency must determine how many photo-enlarger cubicles are required to maintain
an output of 200 good prints per hour. The set-up and exposure time can theoretically be done in 2
minutes per print, but operators are on the average only 90 percent efficient and, in addition, 5 percent of
the prints must be scrapped and redone. Also, the cubicles can be utilized for enlarging only 70 percent of
the time. What is the required process capacity in prints per hour?
a. 212 b. 250
c. 211 d. 200
Answer: c. 211
Required process capacity = good output/ process efficiency = 200/ 0.95 = 211 prints/ hr
30. Refer to problem no. 29, what average output per hour can be expected from each cubicle, taking its use
factor and efficiency into account?
a. 211 b. 30
c. 19 d. 200
Answer: c. 19
31. Refer to problem no. 29, how many enlarger cubicles are required?
a. 14 b. 10
c. 16 d. 12
83 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: d. 12
Number of cubicles = 210.5 prints/ hr required/ 18.9 prints/ hr-cubicle = 11.4 or 12 cubicles
32. Dason Plastics manufacturer must acquire some molding machines capable of producing 160,000 good
parts per year. They will be installed in a production line that normally produces 20 percent rejects
because of the tight aerospace specifications. Assume that it takes 90 seconds to mold each part and the
plant operates 2,000 hours per year. If the molding machines are used only 50 percent of the time and
are 90 percent efficient, what actual (usable) molding machine output per hour would be achieved?
a. 40 b. 18
c. 45 d. 20
Answer: b. 18
33. Refer to problem no. 32, how many molding machines would be required?
a. 4 b. 8
c. 6 d. 12
Answer: c. 6
34. Given:
Year Demand (units)
1 220,000
2 275,000
3 380,000
4 420,000
5 565,000
% Scrap: 3%
Standard Time: 2 minutes per unit
Target Machine Efficiency: 90%
Machine Breakdown: 30 minutes per day
Operation Schedule: 8am – 4pm daily schedule/ 20 working days per month
a. 5 b. 7
c. 2 d. 9
Answer: a. 5
84 | P a g e
Solved Problems in Facility Planning & Design 2014
Given: H = 480
E = 0.85
R = 480-30 = 450/480 = 0.9375
T = 2 mins per unit
O1 = 220,000 per year
O2 = 275,000 per year
O3 = 380,000 per year
O4 = 420,000 per year
O5 = 565,000 per year
P = 3%
Solution:
Q1 = 220,000/ (1 – 0.03) = /12 = /20 = 945.017 per day
Q2 = 275,000/ (1 – 0.03) = /12 = /20 = 1,181.271 per day
Q3 = 380,000/ (1 – 0.03) = /12 = /20 = 1,632.302 per day
Q4 = 420,000/ (1 – 0.03) = /12 = /20 = 1,804.124 per day
Q5 = 565,000/ (1 – 0.03) = /12 = /20 = 2,426.976 per day
35. Refer to problem 34, how many machines you will acquire/ buy on Year 2?
a. 5 b. 7
c. 1 d. 9
Answer: c. 1
36. Refer to problem no. 34, how many machines you will acquire/ buy on Year 3?
a. 5 b. 7
c. 3 d. 9
Answer: c. 3
37. Refer to problem no. 34, how many machines you will acquire/ buy on Year 4?
a. 1 b. 10
c. 2 d. 9
Answer: a. 1
85 | P a g e
Solved Problems in Facility Planning & Design 2014
38. Refer to problem no. 34, how many machines you will acquire/ buy on Year 5?
a. 1 b. 10
c. 3 d. 13
Answer: c. 3
39. A team of Industrial Engineers conducted a work sampling of identical machines being used for a
manufacturing company and they have observed the following:
% Idleness
Machine 1 20%
Machine 2 35%
Machine 3 15%
Machine 4 55%
The machines are running based on the schedule of operation per shift.
Shift Schedule: 6am – 2pm/ 2pm – 10pm/ 10pm – 6am
Break Time: 1-hr meal break and 15 minutes coffee or short break per shift.
a. 1 b. 2
c. 3 d. 4
Answer: c. 3
40. Mandy Garments produces T-shirts for road races. They need to acquire some new stamping
machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but
the new machines will be used for T-shirts only 60 percent of the time and the output usually includes
5 percent that are ―seconds‖ and unusable. The stamping operation takes 1 minute per T-shirt, and
the stamping machines are expected to have 90 percent efficiency when considering adjustments,
changeover of patterns, and unavoidable downtime. How many machines are required?
a. 5 b. 6
c. 7 d. 8
Answer: a. 5
86 | P a g e
Solved Problems in Facility Planning & Design 2014
41. During one-8-hour shift, 770 non-defective parts are desired from a fabrication operation. The
standard time for the operation is 12 minutes. Because the machine operators are unskilled, the
actual time it takes to perform the operation is 25 minutes and, on the average, one-sixth of the parts
that begin fabrication are scrapped. Assuming that each of the machines used for this operation will
not be available for 45 minutes each shift and there is a probability of 0.05 that each machine will
breakdown, determine the number of machines required.
a. 50 b. 52
c. 54 d. 56
Answer: d. 56
S = 12 mins.
E = 12/25 = 0.48
R = 1 – 0.05 = 0.95
H = 480 – 45 = 453 mins.
P = 1/6 = 0.167
Q= 770 = 924 Parts
1 – 0.167
Solution:
42. Nestor Briefcases is an exclusive producer of handcrafted, stylish cases. Priding itself on its earlier
reputation, the company assembles each case with care and attention to detail. This laborious
process requires the completion of six primary work elements, which are listed here.
If the demand is 50 cases per 40-hour week, compute the cycle time for the process.
a. 30 b. 40
c. 46 d. 48
Answer: d. 48
87 | P a g e
Solved Problems in Facility Planning & Design 2014
30 15 10
A B C
D E F
5 10 10
43. Refer to problem no. 42, compute the lead time required for assembling one briefcase.
a. 30 b. 48
c. 80 d. 45
Answer: c. 80
44. Refer to problem no. 42, calculate the theoretical minimum number of workstations.
a. 3 b. 2
c. 4 d. 1
Answer: b. 2
45. Refer to problem no. 42, balance the line based on the most number of followers.
a.
35 45
AD BCEF
b.
45 35
AB CDEF
88 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
30 30 20
A BCD EF
d.
30 25 25
A BC DEF
Answer: b
45 35
AB CDEF
Station 1 Station 2
A (48 – 30 = 18) C (48 – 10 = 38)
B (18 – 15 = 3) D (38 – 5 = 33)
E (33 – 10 = 23)
F (23 – 10 = 13)
ST1 = 45 mins ST2 = 35 mins
a. 89% b. 83%
c. 81% d. 93%
Answer: b. 83%
47. Refer to problem no. 42, suppose the demand for briefcases increases to 80 cases per week.
Calculate a new cycle time.
a. 30 b. 35
c. 50 d. 45
Answer: a. 30
89 | P a g e
Solved Problems in Facility Planning & Design 2014
48. Refer to problem no. 47, balance the line based on the longest task time
a.
35 45
AD BCEF
b.
45 35
AB CDEF
c.
30 30 20
A BCD EF
d.
30 25 25
A BC DEF
Answer: c
30 30 20
A BCD EF
90 | P a g e
Solved Problems in Facility Planning & Design 2014
49. Refer to problem no. 47, calculate the new efficiency of the manufacturing process.
a. 89% b. 83%
c. 81% d. 93%
Answer: a. 89%
50. Refer to problem no. 47, calculate the theoretical minimum number of workstations.
a. 3 b. 2
c. 4 d. 1
Answer: a. 3
51. Pepper & Mys Bakeshop has set a production quota of 600 party cakes per 40-hour workweek. Use
the following information to compute for the cycle time.
a. 3 b. 16
c. 4 d. 13
Answer: c. 4
1 2 2
A B C
F 4
E D
3 4
91 | P a g e
Solved Problems in Facility Planning & Design 2014
52. Refer to problem no. 51, compute the theoretical minimum number of workstations.
a. 5 b. 3
c. 2 d. 4
Answer: d. 4
lead time (1 + 2 + 2 + 4 + 3 + 4)
N= = = 4 workstations
cycle time 4
53. Refer to problem no. 51, balance the line using incremental utilization method
a.
b.
c.
3 3.25 3.25 3.25
3.25
d.
3.0 3.0 3.25 3.25 3.25
Answer: c
3.25
3 3.25 3.25 3.25
92 | P a g e
Solved Problems in Facility Planning & Design 2014
54. Refer to problem no. 51, calculate the efficiency of the assembly line.
a. 95% b. 90%
c. 80% d. 83%
Answer: c. 80%
lead time (1 + 2 + 2 + 4 + 3 + 4)
Efficiency = = = 80%
no. of workstations x cycle time 5(4)
55. The Hanzel Pizza is revamping its order processing and pizza-making procedures. In order to deliver
fresh pizza fast, six elements must be completed.
If the demand is 120 pizzas per night (5:00 p.m. to 1:00 a.m.), compute the cycle time for the process.
a. 4 b. 3
c. 14 d. 13
Answer: a. 4
2 1 3 3 3
A B D E F
C
2
93 | P a g e
Solved Problems in Facility Planning & Design 2014
56. Refer to problem no. 55, compute the lead time for the process.
a. 4 b. 3
c. 14 d. 13
Answer: c. 14
57. Refer to problem no. 55, Calculate the theoretical minimum number of workstations.
a. 2 b. 3
c. 4 d. 5
Answer: c. 4
lead time (2 + 1 + 2 + 3 + 3 + 3)
N= = = 3.5 ≈ 4 workstations
cycle time 4
58. Refer to problem no. 55, balance the line using the most number of followers method.
a.
3 5 3 3
AB CD E F
b.
3 2 3 3 3
AB C D E F
c.
4 1 3 3 3
AC B D E F
d.
4 4 3 3
AC BD E F
94 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: d
4 4 3 3
AC BD E F
59. Refer to problem no. 55, compute the efficiency of the line.
a. 88% b. 91%
c. 89% d. 93%
Answer: a. 88%
lead time (2 + 1 + 2 + 3 + 3 + 3)
Efficiency = = = 87.5%
no. of workstations x cycle time 4(4)
60. Refer to problem no. 55, suppose demand increases to 160 pizzas per night. What is the new cycle
time?
a. 4 b. 3
c. 14 d. 13
Answer: b. 3
1
B
2 3 3 3
A D E F
C
2
95 | P a g e
Solved Problems in Facility Planning & Design 2014
61. Refer to problem no. 60, balance the line based on the longest task time method.
a.
3 5 3 3
AB CD E F
b.
3 2 3 3 3
AB C D E F
c.
4 1 3 3 3
AC B D E F
d.
4 4 3 3
AC BD E F
Answer: b
3 2 3 3 3
AB C D E F
62. Refer to problem no. 60, calculate the new theoretical minimum number of workstations.
a. 2 b. 3
c. 4 d. 5
96 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: d. 5
lead time (2 + 1 + 2 + 3 + 3 + 3)
N= = = 4.6 ≈ 5 workstations
cycle time 3
63. Neren’s Eye Care, Inc., is a full-service optical supplier that sells eyeglasses, contact lenses,
protective eye apparel to opticians. Bogs’ job is to assemble custom-ordered lenses into eyeglasses
for customers. Sales have been good lately, and Bogs has been assembling 100 glasses a day. The
manager of Neren’s asked Bogs to write down the precedence requirements and approximate
assembly times for each step in the assembly process. The data are shown here.
Assuming an 8-hour workday, how long does it take Bogs to assemble one pair of glasses?
a. 2 b. 2.4
c. 4 d. 4.8
Answer: d. 4.8
0.4
C
1 1
A B E
2
D
0.4
64. Refer to problem no. 63, Neren’s anticipates a surge in demand with the opening of its own retail
outlets. If the assembly process is set up as an assembly line, what is the maximum number of
eyeglasses that can be assembled in one day, regardless of the number of workers hired?
a. 200 b. 240
c. 100 d. 480
Answer: b. 240
97 | P a g e
Solved Problems in Facility Planning & Design 2014
1 1.8 2
A BCD E
With maximum time in a workstation of 2 minutes it can produce 240 eyeglasses with 3 workers
65. Refer to problem no. 64, what is the efficiency of the line?
a. 80% b. 91%
c. 100% d. 95%
Answer: a. 80%
66. Prof. Jone has assigned 15 cases in his Seminar class to be completed in a 15 week semester. The
students, of course, are moaning and groaning that the caseload cannot possibly be completed in the
time allotted. Prof. Jone sympathetically suggests that the students work in groups and learn to
organize their work efficiently. Knowing when a situation is hopeless, the students make a list of the
tasks that have to be completed in preparing a case. These tasks are listed here, along with
precedence requirements and estimated time in days. Assuming students will work 5 days a week on
this assignment, how many students should be assigned to each group?
a. 3 b. 4
c. 5 d. 6
Answer: b. 4
4 1 4
B D E
1
C F
3 4
98 | P a g e
Solved Problems in Facility Planning & Design 2014
lead time (1 + 4 + 3 + 1 + 4 + 4)
N= = = 3.4 ≈ 4 workstations or students
cycle time 5
67. The precedence diagram and task times (in minutes) for assembling Reyson’s Stamp Pad are shown
here. Set up an assembly line to produce 125 stamp pads in a 40-hour week. What is the cycle time?
8 5
A B F 4 J 9
C D E H 7 K 3
6 10 2
G I
a. 10 5 b. 19.2
c. 61 d. 2
Answer: b. 19.2
68. Refer to problem no. 67, balance the line based on the most number of followers.
a.
19 19 11 12
b.
19 19 18 5
c.
19 17 13 12
99 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
19 16 14 12
Answer: b.
19 19 18 5
A 8 7 1
B 5 6 3
C 6 6 2
D 10 5 4
E 2 4 7
F 4 4 6
G 5 4 5
H 7 3 8
I 2 1 10
J 9 1 9
K 3 0 11
69. The work elements, precedence requirements, and time requirements to assemble a picture frame
are shown here. What is the cycle time capable of producing 1,600 frames per 40-hour week?
a. 1.5 b. 0.70
c. 0.10 d. 3.4
Answer: a. 1.5
100 | P a g e
Solved Problems in Facility Planning & Design 2014
.10
I
.35 .50
A D
.20
C F H .50
.70
B E
.35 .50
G
.20
70. Refer to problem no. 69, balance the assembly line based on the computed cycle time using
incremental utilization method
a.
1.4 1.2 .80
b.
1.30 1.40 0.70
DABI CEF GH
c.
1.40 1.40 0.60
ABC DEFG HI
d.
1.45 1.45 0.50
DEAI BCFG H
Answer: c
101 | P a g e
Solved Problems in Facility Planning & Design 2014
ABC DEFG HI
Effective CT = 1.40
71. Refer to Problem No. 70, what is the maximum output per week?
a. 1,600 b. 1,715
c. 1,750 d. 1,656
Answer: b. 1,715
Maximum Output per Week = 2,400 mins per week = 1,715 units/ week
------------------------------
1.40
72. Refer to problem no. 69, balance the assembly line based on the computed cycle time using most
number of followers method.
a.
1.4 1.2 .80
b.
1.30 1.40 0.70
DABI CEF GH
102 | P a g e
Solved Problems in Facility Planning & Design 2014
c.
1.40 1.40 0.60
ABC DEFG HI
d.
1.45 1.45 0.50
DEAI BCFG H
Answer: b
Effective CT = 1.40
DABI CEF GH
73. Refer to Problem No. 72, what is the maximum output per week?
a. 1,600 b. 1,715
c. 1,750 d. 1,656
Answer: b. 1,715
Maximum Output per Week = 2,400 mins per week = 1,715 units/ week
------------------------------
1.40
103 | P a g e
Solved Problems in Facility Planning & Design 2014
74. Refer to problem no. 69, balance the assembly line based on the computed cycle time using longest
task time method.
a.
1.4 1.2 .80
b.
1.30 1.40 0.70
DABI CEF GH
c.
1.40 1.40 0.60
ABC DEFG HI
d.
1.45 1.45 0.50
DEAI BCFG H
Answer: d
Effective CT = 1.45
104 | P a g e
Solved Problems in Facility Planning & Design 2014
DEAI BCFG H
75. Refer to Problem No. 74, what is the maximum output per week?
a. 1,600 b. 1,715
c. 1,750 d. 1,656
Answer: d. 1,656
Maximum Output per Week = 2,400 mins per week = 1,656 units/ week
------------------------------
1.45
76. Refer to problem no. 69, calculate the maximum number of frames that can be assembles each week.
a. 2,557 b. 2,452
c. 3,567 d. 3,429
Answer: d. 3,429
5 days 8 hours 60 minutes 1 frame
Number of frames(in a week) = x x x = 3428.57 ≈ 3429
week day hour 0.70min
77. Refer to problem no. 76, rebalance the line for maximum production. Assuming one worker per
workstation. How many workers would be required?
a. 5 b. 4
c. 6 d. 3
Answer: a. 5
Lead time = (0.35 + 0.35 + 0.70 + 0.50 + 0.50 + 0.20 + 0.20 + 0.50 + 0.10) = 3.4 minutes
78. Refer to problem no. 76, assume the company can sell as many frames as can be produced. If
workers are paid P60.00 an hour. What is the total cost per frame?
a. 1.67 b. 1.47
c. 6.17 d. 7.14
Answer: d. 7.14
105 | P a g e
Solved Problems in Facility Planning & Design 2014
79. The Racela Finance Corporation has set a processing quota of 80 insurance claims per 8-hour day.
The claims process consists of five elements, which are detailed in the following table. Racela has
decided to use an assembly line arrangement to process the forms and would like to make sure they
have set up the line in the most efficient fashion. Calculate the cycle time required to meet the
processing quota.
a. 5 b. 6
c. 15 d. 16
Answer: b. 6
4 5 2
A B C
3
D
1
80. Refer to problem no. 79, determine how many claims can actually be processed on your line.
106 | P a g e
Solved Problems in Facility Planning & Design 2014
81. A firm must produce 40 units/day during an 8-hour workday. Tasks, times, and predecessor activities
are given below.
a. 10 b. 38
c. 12 d. 20
Answer: c. 12
82. Thomas Santos, manager of a metropolitan branch office of the state department of motor vehicles,
attempted to perform an analysis of the driver’s license renewal operations. He identified the steps
and associated times required to perform each step as follows:
Santos found that each step was assigned to a different person. Santos also found that jobs A, B, C,
and D were handled by general clerks who were each paid P270.00 per hour. Job E was by a
photographer paid P360.00 per hour. Job F, the issuing of temporary licenses, was required by state
policy to be handled by a uniformed motor vehicle officer. Officers were paid P405.00 per hour, but
they could be assigned to any job except photography.
A review of the jobs indicated that job A, reviewing the application for correctness, had to be
performed before any other step could be taken. Similarly, job F, issuing the temporary license, could
not be performed until all the other steps were completed. The checking of file violations and
restrictions could be performed while the applicant is having his eye test. The branch offices were
charged P450.00 per hour for each camera to perform photography.
Determine the maximum number of applications per hour that can be handled by the present
configuration of the process?
a. 60 b. 90
c. 120 d. 180
Answer: a. 60
107 | P a g e
Solved Problems in Facility Planning & Design 2014
60
15 C
30 20 30
A B E F
40
CT = 60 seconds
83. Refer to problem no. 82, how many applications can be processed per hour if a second clerk is added
to check for violations?
a. 60 b. 90
c. 120 d. 180
Answer: b. 90
30
15 C
30 20 30
A B E F
40
CT = 40 seconds
Max. no. of applications per hour = 3,600 = 90 applications per hour
40
84. In addition to problem no. 83, assuming one more clerk is added to job D, what is the maximum
number of applications the process can handle?
a. 60 b. 90
c. 120 d. 180
Answer: c. 120
108 | P a g e
Solved Problems in Facility Planning & Design 2014
30
15 C
30 20 30
A B E F
20
CT = 30 seconds
Max. no. of applications per hour = 3,600 = 120 applications per hour
30
85. Refer to problem no. 82, what is the required cycle time of the process to accommodate 180
applications per hour?
a. 15 b. 20
c. 40 d. 60
Answer: b. 20
CT = 3,600 = 20 seconds
180
15
15 C
15 20 15
A B E F
20
86. Refer to problem no. 82, compute for the costs per application per hour involved in the current
process.
a. 30.60 b. 18.90
c. 23.40 d. 38.25
Answer: d. 38.25
109 | P a g e
Solved Problems in Facility Planning & Design 2014
A 1 x 270 = 270.00
B 1 x 270 = 270.00
C 1 x 270 = 270.00
D 1 x 270 = 270.00
E 1 x 360 = 360.00
F 1 x 405 = 405.00
-------------
1845.00
camera +450.00
-------------
2295/ 60 applications
P38.25 per application
87. Refer to problem no. 84, for the costs per application per hour involved in the alternative process.
a. 30.60 b. 18.90
c. 23.62 d. 38.25
Answer: c. 23.62
A 1 x 270 = 270.00
B 1 x 270 = 270.00
C 2 x 270 = 540.00
D 2 x 270 = 540.00
E 1 x 360 = 360.00
F 1 x 405 = 405.00
-------------
2385.00
camera +450.00
-------------
2835/ 120 applications
P23.62 per application
88. Given:
From/To A B C D E F
A 15 50 125
B 20 75
C 50 120 120
D
E 50 100
F 110 100
110 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
A B C
D E F
b.
C B E
F A D
c.
B A F
E C D
d.
D B E
C F A
Answer: c.
35 235
B A F
125 220
100
E C D
220
Zero non-adjacent loads
111 | P a g e
Solved Problems in Facility Planning & Design 2014
Layout:
B A F
E C D
89. Given:
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
1 2 6
4 3 5
b.
5 2 1
4 3 6
c.
2 6 5
3 4 1
112 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
6 3 4
1 5 2
Answer: b.
10 50
5 2 1
50 100
50 30 20
4 3 6
20 100
Layout:
5 2 1
4 3 6
90. Given:
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
4 1 2
113 | P a g e
6 5 3
Solved Problems in Facility Planning & Design 2014
b.
3 6 4
2 5 1
c.
1 5 4
3 6 2
d.
6 3 2
5 1 4
Answer: d.
Diagram: 1
8 Non-adjacent loads
6 3 2 5-2 1
9 5-4 2
Total = 3
10 3
6 1
5 1 4
6 5
114 | P a g e
Solved Problems in Facility Planning & Design 2014
Layout:
6 3 2
5 1 4
91. Given:
Loads/day
From/To A B C D E
A 30 60 20
B 30 30
C 80
D 40
E
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
C A
D E
b.
C B
D A
c.
B D
E A
115 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
A E
C B
Answer: c.
Diagram:
30
C B D
30
80 40
80 60
E A
20
Layout:
B D
E A
92. Matthew Design Company has been asked to design the layout for a newly constructed office
building of one of its clients. The closeness matrix showing the daily trips between its six department
offices is given below.
116 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
3 1 5
6 4 2
b.
2 5 3
4 1 6
c.
5 1 4
3 6 2
d.
1 6 2
3 5 4
Answer: b.
4 1 6
165
117 | P a g e
Solved Problems in Facility Planning & Design 2014
Layout:
2 5 3
4 1 6
93. Given:
Flow between Departments (Number of Moves)
Departments 1 2 3 4 5 6 7 8
1. Shipping and receiving 175 150 80 20 75
2. Plastic molding stamping 90 100 125 120
3. Metal forming 350
4. Sewing department 25 25
5. Small toy assembly 180 187
6. Large toy assembly 374 103
7. Painting 7
8. Mechanism assembly
Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
5 1
2 6 4
3 7 8
118 | P a g e
Solved Problems in Facility Planning & Design 2014
b.
1 7
5 2 6
3 8 4
c.
4 5
6 1 3
2 8 7
d.
6 4
7 8 2
5 1 3
119 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: d.
25
6 4
Diagram:
25
125
374 100
103
7 120
7 8 2
187 175
2 350
180 75 90
5 1 3
80 150
Zero non-adjacent loads
Layout:
6 4
7 8 2
5 1 3
94. Given:
120 | P a g e
Solved Problems in Facility Planning & Design 2014
Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building?
a.
Press Warehouse
Stores Turning
b.
Turning Stores
Plate Assembly
c.
Assembly Warehouse
Assembly Stores
d.
Milling Assembly
Stores Press
121 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: c.
Diagram:
7
Assembly Warehous
e
1
2 4 1
8 3
Milling Plate Press
1 5 Non-adjacent load
3 1
9 5 Assembly-Stores 5
Total = 5
Turning Stores
6
Layout:
Assembly Warehouse
Turning Stores
122 | P a g e
Solved Problems in Facility Planning & Design 2014
a.
4 6
1 5
2 3
b.
6 4
1 5
3 2
c.
2 3 6
1 5
d.
6 3 2
5 1
Answer:
c.
2 3 6
1 5
2 3 6
1 5
4
123 | P a g e
Solved Problems in Facility Planning & Design 2014
96. Based on the relationship chart below, what is its recommended layout?
a.
5 3 1
2 4
6 7
b. 1 3
4 2
5 6 7
c.
3 1
6 2 4
7 5
d.
1 3
6 2 4
5 7
124 | P a g e
Solved Problems in Facility Planning & Design 2014
Answer: d.
1 3
6 2 4
5 7
1 3
6 2 4
5 7
97. Given:
a. 10,000 b. 11,000
c. 12,000 d. 14,000
Answer: c. 12,000
TCR – Department 1 = 10,000(1) + 1,000(1) + 100(0) + 10(0) + 0(6) + absolute - 1000 (1) = 12,000
125 | P a g e
Solved Problems in Facility Planning & Design 2014
98. In reference to problem no. 97, what activity is the first to be placed on the grid?
a. 7 b. 2
c. 5 d. 6
Answer: d. 6
TCR – Department 6 = 10,000(2) + 1,000(1) + 100(1) + 10(0) + 0(5) + absolute - 1000 (0) = 21,100
a.
10 5 6
1 3 7
2 8 4 9
b.
10 1 7
3 5 6
4 8 9 2
c.
10 1 4
8 9 2
7 3 5 6
126 | P a g e
Solved Problems in Facility Planning & Design 2014
d.
10 5 6
8 4 7
2 1 3 9
Answer:
a.
10 5 6
8 4 7
1
2 3 9
127 | P a g e
Solved Problems in Facility Planning & Design 2014
4-5 = E = 1,000
4-6 = I = 100 8-5 = U = 0
4-7 = I = 100 8-6 = U =0
8-4 = I = 100
8-7 = U = 0
0 0 0
500 1000 5 6 0 0 0 0 0
1000 8 4 7 10 0 10 5 6 0
500 1000 505 10 5 0 8 4 7 0
0 50 100 50 0
8-10 = E = 1,000
5-10 =U=0 3-10 = U =0 3-8 = U = 0
6-10 =U=0 3-5 = U = 0 3-4 =I =100
4-10 =U = 0 3-6 = U = 0 3-7 = U = 0
7-10 = O = 10
10 5 6
8 4 7
2 1 3 9
128 | P a g e
Solved Problems in Facility Planning & Design 2014
100. Given:
Parts-Machines Matrix
Parts
1 2 3 4 5 6 7 8
A x x x
B x x
C x x
D x x x x
E x
Machines F x x
G x x
H x x x
I x x
J x x
K x
L x x x
Using Digital Clustering Algorithm (DCA), prepare the final cell formation with additional machines, if
needed.
a. 5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L X X X
G X X
K X
C X X
F X X
I X X
E X
b. 5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L1 X X
G X X
K X
L2 X
C X X
F X X
I X X
E X
129 | P a g e
Solved Problems in Facility Planning & Design 2014
c. 5 6 1 4 7 3 2 8
D X X X X
A X X X
H X X X
B X X
J X X
C X X
F X X
I X X
E X X X
L X X
G X X
K X
d. 5 6 1 4 7 3 2 8
D X X X X
A X X X
H X X X
B X X
J X X
C X X
F X X
I X X
E1 X
E2 x x
L X X
G X X
K X
Answer:
b. 5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L1 X X
G X X
K X
L2 X
C X X
F X X
I X X
E X
130 | P a g e
Solved Problems in Facility Planning & Design 2014
Solutions:
PRESENT LAYOUT
1 A
B
2
C
3 5
D
4 E
F
5
G
6 6
H
7 3
I
1
8 J
4
K
7
L
2
8
5 2 3 6 8 7 1 4
D X X X X
A X X X
H X X X
L X X X
B X X
C X X
F X X
G X X
I X X
J X X
E X
K X
131 | P a g e
Solved Problems in Facility Planning & Design 2014
5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
L X X X
B X X
C X X
F X X
G X X
I X X
J X X
E X
K X
5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L X X X
G X X
K X
C X X
F X X
I X X
E X
5 6 1 4 2 8 7 3
D X X X X
A X X X
H X X X
B X X
J X X
L1 X X
G X X
K X
L2 X
C X X
F X X
I X X
E X
132 | P a g e
Solved Problems in Facility Planning & Design 2014
PROPOSED LAYOUT
5 D 5
6 A
1 H 6
B
4 1
J 4
2 L
G 2
8 K 8
7 L2
3 C
I 7
E 3
133 | P a g e
Solved Problems in Facility Planning & Design 2014
REFERENCES
[1] Clark, J. E., ―Facility Planning, Principles, Technology, Guidelines‖. Pearson Prentice Hall, 2008
[2] Francis, R.L., McGinnis, L.F., Jr., and White, J.A. ―Facility Layout and Location – An Analytical
Approach, Second Edition‖. Prentice Hall, Inc., 1992
[3] Garcia-Diaz, A., and Smith, J.M. ―Facilities Planning and Design‖. Pearson Prentice Hall, 2008
[4] James, R. W. and Alcorn, P.A. ―A Guide to Facilities Planning‖. Pearson Prentice Hall, 1991
[5] Russel, R.S. and Taylor, B.W., III ―Operations Management, Third Edition‖, Prentice Hall, Inc.,
2000
[6] Schonberger, R.J., and Knod, E.M., Jr., ―Operations Management – Customer-Focused
Principles, Sixth Edition‖. Times Mirror Education Group, 1997
134 | P a g e