You are on page 1of 7

Applying Technical Limit Methodology for

Step Change in Understanding and


Performance
D.F. Bond, SPE, P.W. Scott, SPE, P.E. Page, SPE, and T.M. Windham,* Woodside Offshore Petroleum Pty. Ltd.

Summary to every component of well construction resulted in aggregate


This paper presents an alternative planning approach to the drilling drilling and completion time, which was called the technical limit.
and completion process, technical limit, which has resulted in a step Technical limit was a term used to describe a level of perfor-
change in Woodside’s performance. Three new wells and six mance defined as the best possible for a given set of design
subsea completions were finished 20% under budget with this tool parameters. Such performance can be approached but requires a
and with a simple philosophy characterized by the following questions. perfect set of conditions, tools, and people. A close analogy of the
● What is current performance? technical limit is a world record in athletics.
● What is possible?
● What is needed to get there?
The target was to drill a directional well in 20 days when the The Philosophy of Targeting Technical Limit
previous best time was 42 days. A target of 12 days was set on The decision to target technical limit was a profoundly significant
subsea completions, although a conventional approach had previ- one. As with a decision to pursue a world record in athletics, pursuit
ously been 201 days. of technical limit required extraordinary effort and commitment and
The methodology was to ask what would be possible if every- would probably not be achieved. This is contrary to the commonly
thing went perfectly on every operation making up the well time. held belief that targets must be achievable. Implications included
This is not the usual trouble free time but a well time built up of a need for highly competent people, team work, and effective
individual components, with each component representing its the- leadership.
oretical best performance. In meeting the challenge, many deficiencies were exposed (and
Details of how the approach was used to plan, and operational dealt with) that had not been exposed in the past, thereby inviting
data that confirm that the technical limit can be approached are criticism and invoking the blame culture, not uncommon in the oil
presented. As a result, the well construction performance delivered industry. A key success factor was to stay committed to the
step change improvement when managed against the technical limit. technical limit strategy, not to image.

Introduction
Drilling performance offshore on the North West Shelf of Australia Determining the Technical Limit
from 1968 to 1992 was erratic. A simple plot of time vs. total depth The Theoretical Well. The first stage in the development of a
(Fig. 1) showed unacceptable scatter and a high average drilling technical limit well time was the construction of a theoretical well.
time, particularly when benchmarked against published data (No- The theoretical well assumed a flawless operation on the basis of
erager et al.1). The conclusion was the well construction process current knowledge and design technology. It was made up of
was not in control. The company developed a plan to remedy this activities and durations that were derived from collective experi-
when faced with an upcoming development project (Wanaea and ence. Assumptions included, for example, no midsection trips
Cossack subsea development). required to change bit or bottomhole assembly (BHA), no reaming
An aggressive target setting and planning methodology was (stable hole), no waiting on equipment, no wiper trips,2,3 and no
developed on the basis of question, “What is possible?” rather significant circulating time. This diverged from the assumptions
than the question, “What can be improved?” to get the desired made by Kadaster5 for a normal well. We concluded that to include
performance. such times would have included technical shortcomings in the plan.
The approach was greatly influenced by achievements in other The goal was to highlight technical shortcomings as the focus for
parts of the world. Some new drilling operations standards were set action and change, rather than accept, them.
in the North Sea during the late 1970’s and early 1980’s, as The well construction was broken into easily definable sections
documented by Shute et al.2. A major factor claimed in the success to calculate a theoretical well, such as drilling a 171⁄2-in. hole,
of this work came from time analysis, which rigorously pursued the running and cementing 133⁄8-in. casing, and drilling a 121⁄4-in. hole.
identification and removal of drilling problems. Work by Huber et This produced about 9 to 16 sections depending on the design detail
al.3 in the North Sea took a similar approach, which also produced of the particular well. The sections were then broken into subac-
excellent results. tivities as shown in the following example.
The high level objective for the Wanaea and Cossack projects Section: 171⁄2-in. Hole. Lay down 26-in. BHA; pick up 171⁄2-in.
was the requirement for highly productive wells and low construc- BHA; run in hole; drill shoe; perform leak-off test; drill 171⁄2-in.
tion cost. Work carried out to maximize well productivity had the hole; circulate bottoms up; and, pull out of hole.
highest priority because of the potential pay back and has been The aim of breaking each section down was to define sufficient
documented by Walters.4 The focus of this paper was the reduction design detail to enable estimating of actual durations; too much
of well costs. detail became cumbersome to work with. Durations were then
With time as the predominant cost driver for well cost (70% of estimated for each subgroup. Drilling time assumed a 10 minute
the well cost was time sensitive), time reduction took priority over connection time3 and rate of penetration (ROP) from the best bit
unit cost reduction. Application of the “ What is possible?” question runs in the area. A well time produced by this method often resulted
in disbelief of the short duration calculated (see Table 1).
By developing the theoretical well’s technical limit in a group
Copyright 1998 Society of Petroleum Engineers session, it was possible to bring about a shift in paradigms about
This paper (SPE 51181) was revised for publication from paper SPE 35077, first
what was, and is possible.
presented at the 1996 IADC/SPE Drilling Conference held in New Orleans, 12–15
March. Original manuscript received for review 12 July 1996. Revised manuscript
received 30 April 1997. Paper peer approved 17 April 1998. Removable Time. The difference between actual well time and
*Now with Chevron Overseas Petroleum Inc. theoretical well time was called removable time. It included con-

SPE Drilling & Completion, September 1998 197


Fig. 1—Days to total depth (TD) for wells drilled on the North West Shelf between 1968
and 1992.

edge. The study provided quantification of the missing invisible lost


TABLE 1—ACTUAL VS. THEORETICAL DURATIONS
time and a list of all the problems and technical limitations that
prevented best performance on those wells.
Theoretical Time Actual Time
Offset Directional Wells (Days) (Days) The result was significantly greater after subtracting removable
time from actual time than the time predicted by the theoretical
Cossack 2 22.0 42.3 well. This indicated that either the theoretical well was overly
optimistic or that further removable time was hidden in the reports.
Cossack 3 22.0 51.5
To deal with this discrepancy, another term was introduced, effec-
tive time (shown in Table 2).
It was concluded that there must be a component of invisible lost
ventional lost time and down time and also another component time associated with such things as efficiency improvements in rig
termed invisible lost time. Invisible lost time was the name given crew activities and drilling optimization (e.g., bit type and bit
to the time taken to perform those activities included in a normal weight). It would require cross comparison of inefficiencies on
well but excluded in the theoretical well. It was called invisible different wells to identify the best.
because, before development of this method, it had not been recog- The data set of the eight immediate offset wells was checked for
nized or reported as lost time. Fig. 2 shows the relationship between effective time for each section to investigate these inefficiencies
theoretical well, invisible lost time, and conventional lost time.5 further. Table 3 shows the effective time for each section of the
The times being generated by the theoretical well were indicating wells. The highlighted times represented the best sections, and,
that reductions of 40 to 60% were possible, so quantifying the when combined, they added up to 19 days. This compared very
amount of removable time was important. closely with, in fact a little lower than, the theoretical well times
Identification of the removable time (invisible lost time and estimated, although design parameters had changed somewhat for
normal lost time3) was achieved manually by use of daily reports the new wells. The conclusion was that the theoretical well times
from offset wells and application of the assumptions made for the were valid as the starting point for the technical limit.
theoretical well. The exercise of extracting removable time analysis The theoretical well time developed for the completions (as with
was very time consuming (up to 2 man months for the eight wells drilling) also appeared too low. A similar exercise of removable
reviewed) and required a high level of drilling/completion knowl- time analysis was performed on a comparable North Sea subsea
completion campaign. The results from the study confirmed the
theoretical durations.
An opportunity to reduce well times by up to 60% was revealed
by objectively assessing the removable time with this method.

Use of the Technical Limit Method


Planning. The planning process used the technical limit concept to
identify the problems that prevented the technical limit being

TABLE 2—AN EXAMPLE OF EFFECTIVE TIME WITH


COSSACK 2 AND 3 DURATIONS

Theoretical Actual Removable Effective


Offset Wells Well Times Time Time

Fig. 2—Diagrammatic representation of the relationship be- Cossack 2 22.0 42.3 13.6 28.7
tween the theoretical well, invisible lost time, technical limit, and Cossack 3 22.0 51.5 22.3 29.2
conventional lost time.

198 SPE Drilling & Completion, September 1998


TABLE 3—EFFECTIVE TIME IN HOURS FROM WANAEA AND COSSACK REMOVAL TIME STUDY

Wanaea Cossack
Technical
Section No. 1 No. 2 No. 3 No. 4 No. 5 No. 1 No. 2 No. 3 Limit

Run TGB 2.25 2.00 3.00 2.50 1.50 6.50 2.50 2.50 1.50
Drill 36-in. hole 9.50 8.50 11.00 19.50 7.50 18.00 9.00 15.50 7.50
Run 30-in. casing 10.50 7.00 6.00 6.75 4.60 9.50 10.25 8.50 4.60
Drill 26-in. hole 28.25 33.00 23.00 27.25 27.75 28.50 30.50 25.75 23.00
Run 20-in. casing 10.25* 11.50 13.50 13.50 13.50 11.50 13.50 15.00 10.25
Run Bop 13.25 13.50 13.00 10.00 16.25 17.00 9.00 10.75 9.00
Drill 17 1⁄2-in. hole 133.25 110.00 118.00 117.50 114.75 155.50 172.75 174.00 110.00
Run 13 3⁄8-in. casing 32.50 23.50 36.25 21.75 25.00 22.50 22.75 23.00 21.76
Drill 12 1⁄4-in. hole 270.25 201.50 119.50 105.50 106.50 319.00 122.75 193.75 106.60
Run 9 5⁄8-in. casing 44.00 25.00 27.50 24.25 44.75 24.50 42.25 23.75 23.76
Drill 8 1⁄2-in. hole 130.25 53.00 72.00 90.75 71.25 61.00 98.50 111.25 53.00
Log 49.00 71.00 54.00 36.50 43.00 22.75 62.0m 36.50
Run liner 59.50 25.00 37.50 41.25 23.50 42.50 42.50 23.50
Clean out 44.00 37.50 26.50 45.00 69.50 26.60

Total hours 684.5 640.00 576.25 227.25 511.00 785.00 668.50 715.25 466.26
Total days 28.5 26.70 24.00 23.20 21.30 32.70 27.90 29.80 19.00

* The highlighted cells identify previous best (Technical Limit) times.

reached and then planned their removal. The time taken to drill and waiting on weather (WOW), 13%; and other, 15%. Clearly, if the
complete wells would be the indication of the ability to understand bit/BHA and mud problems were addressed, then 72% of the
and manage the variables. removable time would be eliminated. Drilling and completing
Approximately 9 months were spent planning the startup of outside cyclone season would potentially remove another 13%
operations. The planning process used the theoretical well and because of WOW.
offset well analysis to develop an engineering workscope and The development of the theoretical well activities and times
determine the resources needed. Execution of the engineering provided a baseline for further analysis of the sequences required.
workscope involved getting engineers and contractors to under- Program evaluation review technique charts were constructed,
stand potential obstacles to achieving the technical limit and then typically listing 300 tasks/well, and used to undertake critical path
manage them. analysis. A number of activities were removed from the critical path
Approximately 175 days were identified as removable time from by introducing new tools and/or techniques.
a total of 435 days on the eight offset wells. The problems identified The engineering planning work had a big impact on the speci-
by analysis are shown in Fig. 3 as a Pareto chart. Significantly, the fication of the drilling rig needed for the project. The cost of the
invisible lost time was categorized as bit/BHA, 47%; mud, 23%; higher rig specification was easily justified against the potential

Fig. 3—Results of the removable time study performed on eight offset wells. Categorized by bit/BHA, mud, WOW,
and other.

SPE Drilling & Completion, September 1998 199


Fig. 4 —Diagrammatic representation of the management model developed to
support the technical limit approach.

efficiencies indicated by the theoretical well time. The result allowed technical limit time had been underestimated), a new time was
fit for purpose rig selection and, ultimately, sole source negotiation of defined for the next well. If it was removable, solutions were
the selected rig rather than a low bid tendering process. developed that would prevent reoccurrence of the event.
A number of other factors were addressed during the planning Similar to the approach taken by Kadaster,5 the use of a total
stage and were influential in the overall success of the project. quality management (TQM) approach was found to be very effec-
These included identification and management of risk; communi- tive (see the TQM feedback loop in Fig. 4). The feedback system
cation of the plan to all involved, to gain ownership and shared was very broad in it’s application and became very efficient with
goals; and, preoffshore review of procedures, sequence of events, proper resourcing from either company or contractor.
and equipment. Initially, offshore personnel were uncomfortable reporting
against the technical limit because every nonconformance, large or
Operations. Invisible lost time was made very visible in the small, was exposed. It was important that management encouraged
operational phase of the project. Any activity time deviation from and supported the offshore team in pursuit of the ideal standards
the technical limit schedule was reported on the daily report. If the that had been set. A no-blame environment was essential and
deviation was negative (i.e., time reduced), the time expected on practiced with vigor.
future wells was adjusted downward and a new technical limit was The measurement of operations against the technical limit sched-
defined. If the deviation was positive (i.e., extra time taken), it was ule was extremely powerful. No better way was found to highlight
analyzed for cause. If the extra time taken was unavoidable (i.e., the and pursue maximum opportunity for improvement.

Fig. 5—Days to total depth (TD) for wells drilled on the North West Shelf between 1968 and
1992. Results from Wanaea and Cossack have been included to show the improvement made.

200 SPE Drilling & Completion, September 1998


TABLE 4—POST-WELL ANALYSIS FROM WELL 1

Starting New
Technical Actual Removable Effective Technical
Section Limit Time Time Time Limit

Drill 36-in. 9.0 11.0 0 11.0 10.0


Run 30-in. 11.0 9.0 2.0 7.0 7.0
Drill 26-in. 21.0 27.0 0 27.0 21.0
Run 20-in. 25.0 67.0 42.0 25.0 25.0
Run BOP 20.0 30.0 0 30.0 20.0
Drill 17 1⁄2-in. 107.0 380.0 249.0 131.0 107.0
Run 13 3⁄8-in. 36.0 43.0 2.0 41.0 36.0
Drill 12 1⁄4-in. 77.0 142.0 48.0 94.0 77.0
Run 9 5⁄8-in. 44.0 42.0 0 42.0 42.0
Drill 6 1⁄2-in. 65.0 104.0 39.0 65.0 65.0
TD logging 6.0 14.0 5.0 8.0 6.0
4 1⁄2-in. liner 57.0 292.0 241.0 51.0 51.0

Total hours 476.0 1158.0 626.75 531.0 467.0


Total days 19.8 48.2 26.1 22.1 19.5

Results A comparison between the technical limit, actual, and effective


Drilling Performance. Typical historical drilling times for direc- times on Well 1 is presented in Table 4. The fifth column shows
tional appraisal wells on these fields were 42 to 52 days. Antici- where a new technical limit had been set.
pating some improvement in performance, 50/50 budget estimates Furthermore, Well 1 took 22.1 effective days. This was an
(a budget estimate based on time, considered as equally likely to be improvement of 6.6 days compared with effective times of 28.7 and
exceeded than beaten) had been prepared with 34 days for a typical 29.2 days of the previous offset wells; however, Well 1 had 26.2
moderately deviated well and 46 days for a horizontal section well. days of removable time. Table 5 shows the causes of the removable
Technical limit determination was carried out with the methodol- time and the actions taken to prevent recurrence. Most of the
ogy described, arriving at durations of 19.8 days and 27.5 days, removable times were new problems not seen on the offset wells,
respectively. an indication that the drilling process was still not in control.

TABLE 5—POST WELL REMOVABLE TIME ANALYSIS FOR WELL 1

Removable
Time
Number Problem (hours) Cause Action and Solution

1 Back-off in 17 1⁄2-in. hole 187.25 High drilling torque as a Reduce drilling parameters. Eliminate
result of formation and string weak-points, review drilling
aggressive drilling. procedures.
2 Twist off 2 3⁄8-in. drillpipe in liner 97.00 Excess weight on pipe. Procedures. Source stronger pipe.
Minimize use.
3 Cleanout of cement in liner 71.00 Plug not bumped, no shear Reviewed procedures. Developed inner
indication. string method.
4 Dropped junk basket and nut 64.00 Nut backed off downhole. Weld nut to shank. Review tool
procedures.
5 Correction run in 12 1⁄4-in. hole 44.00 Right hand bit walk and drop Review bit and BHA selection. Allow left
too high. hand lead.
6 No cement in 9 5⁄8-in. shoe 29.00 Mud syphoning through top Reviewed cement head design. Increased
drive when changing over to shoe track to 3 joints. Plan to bump plug
release dart. and pressure test casing.
7 Dropped 20-in. casing 24.00 Backup tong slipped. Review top drive and casing procedures.
8 Rig downtime (total) 22.00 Various equipment problems, Review maintenance planning.
critical path maintenance.
9 Problem landing CGB 18.00 Incorrect bolts-quality Use correct bolts. Review procedures.
control. Cuttings build up at
wellhead.
10 Washout in Monel DC 14.00 Stress corrosion cracking. Inspect all monels internal (boroscope).
Review quality assurance/quality control
procedures.
11 Trip in 17 1⁄2-in. slow ROP 11.00 Bit balling. Use PDC bit. Review mud system.
12 Logging failure 4.00 Intermittent short in tool Tool returned for repair. Calibrate backup
connection. before use.
13 Miscellaneous 42.50 Small events. As available resources allow.

SPE Drilling & Completion, September 1998 201


TABLE 6—POST WELL ANALYSIS FOR WELL 3

Starting Technical Actual Removable Effective New Technical


Section Limit Time Time Time Limit

Drill 36-in. 10.0 7.5 0 7.5 7.5


Run 30-in. 7.5 6.5 0 6.5 6.5
Drill 26-in. 21.0 24.5 1.5 23.0 21.0
Run 20-in. 25.0 24.0 4.0 20.0 20.0
Run BOP 16.5 19.8 0 19.8 16.5
Drill 17 1⁄2-in. 111.0 117.0 1.8 115.3 111.0
Run 13 3⁄8-in. 36.0 40.0 7.5 32.5 32.5
Drill 12 1⁄4-in. 77.0 103.8 16.3 87.5 77.0
Run 9 5⁄8-in. 42.0 41.3 3.0 38.3 38.3
Drill 6 1⁄2-in. 63.0 59.8 4.8 55.0 55.0
TD logging 6.0 9.3 1.8 7.5 6.0
4 1⁄2-in. liner 51.0 205.3 155.0 50.3 50.3

Total hours 466.0 658.5 195.5 463.0 441.5


Total days 19.4 27.4 8.1 19.3 18.4

Fig. 6 —Comparison of the effective time and removable time wells drilled
before the start of the project and Wells 1 and 3. The inefficiency shown is
a result of advancing the technical limit and taking a backward view.

Fig. 7—Comparison of the effective time and removable time for the
comparable portions of the completions. Again inefficiency can be shown
by taking a backward view from the final technical limit.

202 SPE Drilling & Completion, September 1998


Well 3 was almost identical to the first well (Well 2 had the and a technical limit. These concepts were quantified and used in
horizontal section) and makes a good comparison. The drilling an aggressive method to target the “What is possible?” question.
performance for Well 3 is presented in Table 6. Overall perfor- Technical limit was applied to planning and operations. The fol-
mance had improved by 2.8 days, as indicated by the effective time; lowing points have been concluded from this approach.
also, the offshore team was more efficient in many areas, including 1. Drilling and completion performances can be usefully mod-
running blowout preventer and casing. Again, new events happened eled with the technical limit.
that had not been anticipated. Only 8.2 days were identified as 2. The invisible lost time component of this model offers insight
removable time, 85% of which was accounted for by just two into operational inefficiencies that conventional industry lost time
events. An indication that process control was quickly improving. systems ignore.
The analysis for Well 2 (with 808 m of horizontal section) was 3. Technical limit was used to set the highest performance
drilled in 40.4 days with 9.4 days of removable time. Adding all standards possible.
wells together, the drilling part of the project took 116.1 days 4. Quantifying and addressing removable lost time provided the
compared to the budget base time of 114 days. Although drilling maximum opportunity to improve.
performance still contained significant removable time, it was a 5. The technical limit model led to a step change in understanding
marked improvement on the past (see Fig. 5). and performance when applied to three new directional wells and
A learning curve is evident by comparing effective time and six subsea completions.
removable time for each of the three wells (Fig. 6). Indeed, it would 6. Adoption of this technique requires courage because it reveals
appear that the operational efficiency had approached the technical every deviation from the ideal. A no-blame culture was essential to
limit in just three wells. Such a performance has been described by its acceptance.
Brett et al.6 and termed as excellent. Good is the adjective used for
approaching the learning curve asymptote in five wells. Acknowledgments
We thank Woodside Offshore Petroleum and its joint venture
Completion Performance. Subsea completions technical limits of participants [BHP Petroleum, BP Developments Australia, Chev-
10.5 days (new well) and 14.0 days (predrilled well) had been ron Asiatic, Japan Australia LNG (MIMI), and Shell Development
established based on the planning phase described. These compared Australia] for support throughout this project. Additional thanks to
with 50/50 budget estimates of 16.5 days and 21.5 days, respec- Sedco Forex, Baker I.S., and all personnel that contributed to the
tively. All these times included production testing. development and application of the technical limit method. Per-
The actual durations achieved averaged 11.3 days for new wells sonal thanks to Phillis Harley for tireless support from the begin-
and 15.9 days for existing wells on the six well campaign. ning of the project and through the preparation of this paper.
The process of refining the technical limit continued as wells
References
were completed. The six completion times are shown in Table 7.
The technical limit for a new well had changed from 10.5 days to 1. Noerager, J.A., White, J.P., and Floetia, A.: “Drilling Time Predictions
8.5 days at the end of the six well campaign. The best new well From Statistical Analysis” paper SPE/IADC 16164 presented at the 1987
completion was 9.1 days, which includes all forms of removable SPE/IADC Drilling Conference, New Orleans, Louisiana, 15–18 March.
time. The subsea completions were finished 33 days ahead of the 2. Shute, J. and Alldredge, G.: “Conoco Cuts North Sea Drilling Time by
50/50 budget times. 40%.” World Oil (July 1982).
The completions, by their more mechanically controllable na- 3. Huber, D.D. and Walton, H.: “A Realistic Goal From a Semi: Drill to
ture, started further along the learning curve than drilling did. The 10,000 ft in 10 Days,” World Oil (September 1983).
first completion took 25% less time than the 50/50 budget time. Fig. 4. Walters, N.S.: “Maximizing Well Potential: An Integrated Approach,”
7 shows the technical limit after the final completion compared with paper SPE 36997 presented at the 1996 SPE Asia Pacific Oil and Gas
effective time and removable time for each core completion ac- Conference, Adelaide, Australia, 28–31 October.
tivity. The completions learning curve is still evident in Fig. 7, 5. Kadaster, A.G., Townsend, C.W., and Albaugh, E.K.: “Drilling Time
although less pronounced than with drilling. Analysis: A Total Quality Management Tool for Drilling in the 1990’s,”
The drilling and completion campaign not only delivered sig- paper SPE 24559 presented at the 1992 SPE Annual Technical Confer-
nificant cost savings against the budget, but also delivered subsea ence and Exhibition, Washington, D.C., 4–7 October.
wells with productivity 30% greater than expected. 6. Brett, J.F. and Millhiem, K.K.: “The Drilling Performance Curve: A
Yardstick for Judging Drilling Performance,” paper SPE 15362 presented
at the 1996 SPE Annual Technical Conference and Exhibition, New
Conclusions Orleans, Louisiana, 5–8 October.
The results presented here could be considered lucky with such a
small data set; this is not disputed. The important conclusion with SI Metric Conversion Factors
the methodology outlined lies with a focus on the theoretical well ft 3 3.048* E201 5 m
in. 3 2.54 E100 5 cm
*Conversion factors are exact. SPEDC
TABLE 7—FULL COMPLETION TIMES
David F. Bond is a principal drilling engineer for Woodside
Technical Actual Removable Effective Energy Ltd. in Perth, Australia, responsible for technical integrity
Limit Time Time Time and performance of all Woodside drilling activities. He holds a
Completion (days) (days) (days) (days) BS degree in mechanical engineering from the U. of Leeds, U.K.
Phil W. Scott is an implementation manager for new systems
1 11.4 12.5 1.4 11.1 being developed by Woodside Energy Ltd. in Perth, Australia.
His recent focus has been on human elements in well construc-
2 10.7 12.8 2.3 10.5
tion. He holds a BS degree in civil engineering from the U. of
3 10.9 10.8 1.2 9.6 Western Australia. Peter E. Page is a senior completions engi-
4 8.9 9.1 1.2 7.9 neer for Woodside Energy Ltd. in Perth, Australia. Previously,
Peter worked for Shell Intl. He has worked for Shell in the U.K. and
5 14.9* 19.3 4.7 14.6
in Norway before moving to Australia in 1992. Tom M. Windham
6 13.2* 14.2 2.0 12.4 is a drilling superintendent with Chevron Overseas Petroleum
Inc., in Escravos, Nigeria. He was seconded to Woodside from
* Include running additional equipment. November 1993 to December 1996. He holds a BS degree in
petroleum engineering from West Virginia U.

SPE Drilling & Completion, September 1998 203

You might also like