Following completion of the Phase I Market Study, the design team members of
the Study Team began the second phase of this feasibility study - evaluation of
expansion and alternate sites. The analysis steps included an estimation of the
required gross enclosed area of the project, an evaluation of the existing facility,
an expansion site and an alternate site, the preparation of building organization DELAWARE SITE
diagrams to best respond to the building program on the expansion and alternate
sites, and finally, the preparation of preliminary order-of-magnitude cost estimates
for the two options identified. STATLER SITE
Several major planning goals governed the exploration of building organizational EXISTING BNCC FACILITY
concepts on the expansion and alternate sites. These goals included:
Construction of a new Convention Center on the HSBC site that includes all the
Recommended Function Spaces in a two-floor facility.