Professional Documents
Culture Documents
A research identification, risk assessment and risk control was conducted Toyota Bukit Raja. The company that I take work
at is Takenaka Malaysia Sdn Bhd the job scope of the company is main contractor building Rc work, erection of roof truss,
erection of roofing work, installation of piping, electrical.Therefore, the installation and use of Scaffolds has been selected for
the purpose of this study.Hazard identification was conducted through workplace inspections and observations, hazard analysis
and document review. Evaluation indicates that exposure to critical hazards of the activity. Their risk is assessed based on
qualitative and quantitative risk assessment techniques by assessing the consequences and possibilities of any harm
Page:1
2. INTRODUCTION
2.1 Company Background
Takenaka Malaysia Sdn Bhd firm has been established to design, supply and installation of structure,roof truss,roofing,piping,elertrical, for the construction
industry which requires high quality assurance and client satisfaction.
By playing a role in meeting the market demand and specific needs by providing professional staff and technical approaches to Quality Control and Total
Quality Management effectively implementing and completing projects towards achieving quality outcomes.
Takenaka Malaysia Sdn Bhd has extensive experience on building factory,extension building, installations for new construction as well as in retrofit plant and
equipment for prestigious offices, buildings, commercial complexes.
Our company Takenaka are serving this types of services offered:
Building factory
Extension of factory
Building shopping complex
Extension of shopping complex
Building airport
Extension of airport
Page:2
2.2 Organizational Chart Ougri
Project Manager
012-9081106
MR,LIEW
MR. MOHAN
SAFETY OFFICER Site Manager
017-268 6923
012-206-2922
OVERALL HSE
CONTROL
PAGE:4
2.4 Scope of Work
All of the following scope of work is high and involves the use of Frame Scaffolding:
Activities carried out during the installation of the Frame Scaffolding(light duty) are as follows:
PAGE:5
3. OBJECTIVE
• Identify 4 safety hazards and 2 health hazards that come from the selected work activity at the site.
• Assessing safety and health risks arising from the identified hazards
• List and compile safety and health hazards that have been identified according to the critical level of risk.
• Prepare control measures to eliminate or mitigate those two critical hazard risks.
• Recommending an appropriate revision program against the stated risk control measures and benefits to the organization.
4. METHODS
4.1 Identify Hazard
Record and documents
Observation and advice at work
Analysis of ”Hazard”
4.3 Severity of hazard Severity can be divided into five categories. Severity are based upon an increasing level of severity to an
individual’s health, the environment, or to property. The table use as below:
PAGE:7
Severity(S) Example Rating
4.3.1 Risk assessment Risk can be presented in variety of ways to communicate the results of analysis to make decision on risk control. For risk
analysis that uses likelihood and severity in qualitative method, presenting result in a risk matrix is a very effective way of communicating the
distribution of the risk throughout a plant and area in a workplace.
PAGE:8
An example of risk matrix (Table C) is shown below: Table C
Serverity(S)
Likehood(L) 1 2 3 4 5
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
PAGE:9
Risk Description action
A HIGH risk requires
immediate action to control
the hazard as detailed in the
15-25 high hierarchy of control. Actions
taken must be documented
on the risk assessment form
including date for
completion
A MEDIUM risk requires a
planned approach to
controlling the hazard and
5-12 medium applies temporary measure if
required. Actions taken must
be documented on the risk
assessment form including
date for completion.
A LOW risk may be
considered as acceptable and
further reduction may not be
1-4 low necessary. However, if the
risk can be resolved quickly
and efficiently, control
measures should be
implemented and recorded.
Hazards assessed, as “High Risk” must have immediate actions, to resolve risk to life safety and or the environment. Individuals responsible for
required action, including follow up must be clearly identified. A further detail risk assessment method may require such as quantitative risk
assessment as means of determine suitable controls measures.
PAGE:10
5. RESULTS AND DISCUSSION
PAGE:11
5.2 Safety Hazard for Erection and using scaffold
1 Erection scaffold at high Fall from height Lose the 4 5 20 1)Safety Harness
ability
elevation of a 2)Barricade the area
lifetime
or die 3)Training
4)supervison by competent
person
4)supervisionby
competent person
3 loading material at the Bad planking Lose the 2 5 10 1)inspection the material
ability
planking(scaffold platform) of a
or damage before use
lifetime
or die
planking 2)training
3)supervision by
supervisor
3)supervision by
supervisor
PAGE:13
5.3Health hazarrd for Erection and using scaffold
status
3)
PAGE:14
5.4 Risk Control Method
METHODS DESCRIPTION
1)Elimination Getting rid of a hazardous job, tool, process, machine or substance is
perhaps the best way of protecting workers
2)Substitution Sometimes doing the same work in a less hazardous way is possible.
3)isolation If a hazard cannot be eliminated or replaced, it can some times be
isolated, contained or otherwise kept away from workers.
4)Engineering control Engineering controls are methods that are built into the design of a
plant, equipment or process to minimize the hazard. Engineering
controls are a very reliable way to control worker exposures as long as
the controls are designed, used and maintained properly.
5)Administrative control Administrative controls are changes in work procedures such as
written safety policies, rules, supervision, schedules, and training with
the goal of reducing the duration, frequency, and severity of exposure
to hazardous chemicals or situations.
6)Personal protection equipment Personal protective equipment (PPE) and clothing is used when other
controls measures are not feasible and where additional protection is
needed. Workers must be trained to use and maintain equipment
properly. The employer and workers must understand the limitations
of the personal protective equipment. The employer is expected to
require workers to use their equipment whenever it is needed. Care
must be taken to ensure that equipment is working properly
Page 15
PAGE:15
6. RECOMMENDATIONS
6.1 Recommendations for Safety Hazard Control Measures
Activiy Erect of scaffolding
Safety hazard Dropped from the side of the scaffold without no barrier especially at 2m height
PAGE:16
6.2 Recommendations for Health Hazard Control Measures
PAGE:18
6.3 Revision
• Review the safety procedures at the workplace at the Safety & Health Committee Meeting.
• Obtain feedback from employees about hazards or hazards that may arise.
• Investigate any complaints from employees about the occurrence of hazardous conditions
• Conduct security checks & safety audits
• Review the results of medical supervision of engaged employees to ensure the level of exposure & effectiveness of existing
controls
• Check accident reports, near-incidents or dangerous situations
PAGE:19
6.5 Profit From Proposition - Workers
• Work injury and illness can be avoided or reduced.
• Increase awareness among employees about the importance of safeguarding and improving the health of the workplace.
• Can work in safe condition without interruption.
• Create a healthy and safe working culture in every employee.
7. REFERENCE
Scaffold design
1. https://www.google.com/search?biw=1536&bih=772&tbm=isch&sa=1&ei=hgwEWuf8F4rhvgSh2qzICA&q=frame+scaffold+towe
r+design&oq=frame+scaffold+tower+design&gs_l=psy-ab.4...5722.6397.0.6581.6.6.0.0.0.0.197.378.0j2.2.0....0...1.1.64.psy-
ab..5.0.0....0.7kCW-LknRXA#imgrc=qy1NZkzwZXPOyM:
2. http://www.canadascaffold.com/professional-consultations/safety/main-hazards-of-scaffolds/
3. http://www.dosh.gov.my/index.php/en/list-of-documents/guidelines/hirarc-2
4. OSHA 1994
5. FMA
Page20
SCAFFOLD DESIGN
Page21
TOOL BOX,with training
Page22
Scaffold inspection approve by jkkp with lvl 3 and inspector course
Page23
Drawing design for working platform
Page 24
PE design for loading platform
Page 25
Green tag
Page 26
THANK YOU,THANK FOR READING
Report of hazard safety and health
Erection of scaffolding
Toyota Bukit Raja
SL/17/03/106500
W030020161223001
Green tag 26
HIRARC
control
cat Loading material Contact with Lose the ability of a 4 5 20 Safety 1)Safety Harness
mechinery lifetime or die
before erection 2)Barricade the area
scaffold 3)Training
4)supervison by
competent person
2 Erection of brick laying Getting struck by Serious injury 5 4 20 Safety 1)safety helmet
at high level elevation falling tools or
2)barricade the area
deris
3)signal man
4)supervisionby
competent person
3 loading material at the Bad planking Lose the ability of a 2 5 10 Safety 1)inspection the
lifetime or die
planking(scaffold
or damage material before use
platform)
planking 2)training
3)supervision by
supervisor
4 loading material at the Bad/Damage Lose the ability of a 2 5 10 Safety 1)inspection the
lifetime or die
planking(scaffold
material before use
platform)
base plate
2)training
3)supervision by
supervisor
5 Erection scaffold Ergonomic Muscle pain, 4 2 8 Health 1)have some rest time
Musculoskeletal
if work to long
Disorders
2)training
3)
few hours
Page17
JOB SAFETY ANALYSIS
Sequence of basic job step Potential hazard Percatuions
Prework Unauthorized erection of scaffold Cold work permit
Erection or use scaffold Falling sharp object Provide guard rail and toe board
Hand tool been tie with permanent
structure or person
Barricade the area during erection work
Accidental fall of person Wear harness
provide training
Unstable scaffold Scaffold must been check by
competent person
Weak scaffold The scaffold tag must indicate
maximum load
Damage scaffold Scaffold must been inspect weekly
Modified scaffold Addition modified must be reinspect
Improper scaffold Ensure scaffold is securely supported
on a rigid ground
Incomplete scaffold Do not put green tag
page 16