LAYOUT DETAIL FOR LCOT FENCING UPGRADE PARAMETER AS AT 02.09.

2017
TASK / ACTIVITY (SECTION 8)
Install temporary fencing (100%)
Remove & cart away wire mesh & post (100%)
Demolish fence foundation (100%)
Clearance of vegetation & small tree (100%)
Excavate top soil (100%)
Construct formwork - footing (100%)
TASK / ACTIVITY (SECTION 2)
Install new fence post (100%)
Install temporary fencing (100%)
Concreting work - footing (100%)
Remove & cart away wire mesh & post (100%)
Construct formwork - kerb (100%)
Demolish fence foundation (100%)
Concreting work - kerb (100%)
Clearance of vegetation & small tree (100%)
Remove formwork- kerb (100%)
Excavate top soil (100%)
Install new fence panel (100%)
TASK / ACTIVITY (SECTION 1)
Construct formwork - footing (100%)
Install barbed wire & concertina (0%)
Install temporary fencing (100%)
Install new fence post (100%)
Remove & cart away wire mesh & post (100%) Overall Progress for Section 8 - 92.31%
Se Concreting work - footing (100%)
ct io
Demolish fence foundation (100%) n8
( 12 Construct formwork - kerb (100%)
9m
Clearance of vegetation & small tree (100%) -PB
JV
) Concreting work - kerb (100%)
Excavate top soil (100%)
S ec Remove formwork- kerb (100%) SUMMARY OF WORK PROGRESS
t io
Construct formwork - footing (100%) n8
(10 Install new fence panel (100%)
0m DATE: 02.09.2017
Install new fence post (100%) )
Install barbed wire & concertina (0%)
)
5m

Concreting work - footing (100%) FENCE REPLACEMENT:


(40

Overall Progress for Section 2 - 92.31%


Install new fence panel (100%)
n1

TASK / ACTIVITY (SECTION 3)


a). Section 1 - 71.43%
c t io

Install barbed wire & concertina (100%) Install temporary fencing (100%)
Se
Se

c t io
Excavate top soil - kerb (0%)
n2 b). Section 2 - 92.31%
(52 Remove & cart away wire mesh & post (59.33%)
2m
)
Construct formwork - kerb (0%) Clearance of vegetation & small tree (100%) c). Section 3 - 65.58%
Concreting work - kerb (0%) Excavate top soil (100%)
d). Section 4 - 47.2%
Remove formwork- kerb (0%) Construct formwork - footing & kerb (92.96%)
Overall Progress for Section 1 - 71.43%
e). Section 5 - 33.87%
Install new fence post (92.96%)
TANK 1
Concreting work - footing & kerb (67.84%) f). Section 6 - 60%
TANK 2
TANK 3 Remove formwork- kerb (67.84%)
g). Section 7 - 48.28%
Install new fence panel (67.84%)
Se
h). Section 8 - 92.31%
ct io Install barbed wire & concertina (0%)

Se
n7

ct
(31

io
4m TANK 4 Overall Progress for Section 3 - 65.58%

n
)
PATHWAY & STAIR:

3
(4
26
TASK / ACTIVITY (SECTION 7)

m
)
a) Section 4/5 - 34.33%

BALU
KINA ER
Install temporary fencing (100%)

TOW
Sludge Pump Drain (Proposed 1200mm Dia. Spiral HDPE)
Remove & cart away wire mesh & post (100%)
Proposed 2 Units of 600mm
b). Section 6/7 - 35.24%
Dia. Spiral HDPE SLUDGE
S ec FARM Existing Drain (Proposed 1200mm Dia. Spiral HDPE)
Clearance of vegetation & small tree (100%) t ion

O
6 (4

FWK
86m Large Stone (New fence to construct on the top)
OVERALL PROGRESS: 63.48%
Excavate top soil (100%) )
Proposed Pipeline Extension
(Distance/Length = 400m)
Construct formwork - footing & kerb (41.40%) SCHEDULE COMPLETE: 65.11%
Proposed 600mm Valley Area
Install new fence post (41.40%) Dia. Spiral HDPE
Secti
LGAST VARIANCE: -1.63
Newly Installed on 5 (4 Fencing
Concreting work - footing & kerb (0%) Workershed
26m
TASK / ACTIVITY (SECTION 6) ) m)
n 4 (417
Remove formwork- kerb (0%) Sect io
Install temporary fencing (100%)
Install new fence panel (0%) Hilly area to cut and fill
Remove & cart away wire mesh & post (100%)
Install barbed wire & concertina (0%)
to construct access way
Clearance of vegetation & small tree (100%)
Overall Progress for Section 7 - 48.28%
Excavate top soil (100%) TASK / ACTIVITY (SECTION 5)
TASK / ACTIVITY (SECTION 4)
Construct formwork - footing & kerb (100%) Install temporary fencing (100%)
Install temporary fencing (100%) LEGEND / MARK
Install new fence post (100%) Remove & cart away wire mesh & post (23.47%)
Remove & cart away wire mesh & post (100%)
Concreting work - footing & kerb (0%) Clearance of vegetation & small tree (100%) Work Completed
Clearance of vegetation & small tree (100%)
Remove formwork- kerb (0%) Excavate top soil (100%)
Excavate top soil (100%) Work On-Going (In-Progress)
Install new fence panel (0%) Construct formwork - footing & kerb (11.10%)
Construct formwork - footing & kerb (45.7%) Work Not Yet Started
Install barbed wire & concertina (0%) Install new fence post (4.13%)
Install new fence post (26.34%)
Overall Progress for Section 6 - 60% Concreting work - footing & kerb (0%) New Fencing Parameter
Concreting work - footing & kerb (0%)
Remove formwork- kerb (0%)
Remove formwork- kerb (0%) Proposed Pathway & Stair
Install new fence panel (0%)
Install new fence panel (0%) Proposed Access Way
Install barbed wire & concertina (0%)
Install barbed wire & concertina (0%)
Proposed Parking Area for Mobile
Overall Progress for Section 5 - 33.87%
Overall Progress for Section 4 - 47.2% Concrete Pump