Professional Documents
Culture Documents
2002 Extra over item 2001(a) for quantities of works, executed in or under 1,857 Cum 47
water and/or liquid mud/under foul position including pumping out
water as required.
2003 Providing and laying M 10 cement concrete in foundation and floor 2,463 Cum 2,017
using well graded stone aggregate of 40 MM nominal size.
2004 Providing and laying design mix control concrete M20/M25 in piers, 7,775 Cum 3,052
retaining walls, wing walls, return walls, bottom/top plug of wells and
protection work etc. using well graded stone aggregate of 40 MM/20
MM nominal size.
S.No Description of item Qty Unit Rate in Rs
2005 Providing and laying Design mix control concrete M25/M30/M40 in 23,568 Cum 4,020
cast-in-situ RCC works of raft, pile cap, pier, abutment, well steining,
RCC well kerb, well cap, pier cap, Jacketing, dirt wall, return wall,
wing wall, fly wing wall, retaining wall, approach slab, foot path slab,
wearing course, ballast retainers, RCC railing, inspection platform,
pedestal, boxes and other miscellaneous works using well graded
stone aggregate of 20 MM nominal size.
2006 Providing precast/cast-in-situ post tensioned PSC griders including 545 Cum 11,478
diaphragms and deck slab with design mix control concrete M45/M50
including sheathing, anchorages, bearing plates, permanent wedges,
positioning of strands in sheathing as per profile, stressing and
distressing, grouting, launching, precast griders in position, etc.
S.No Description of item Qty Unit Rate in Rs
2007 Extra for laying concrete in or under water and/or liquid mud/under 1,438 Cum Per 209
foul position including cost of pumping or bailing out water and Meter
removing slush etc complete. Depth
Note: The quantity will be calculated by multiplying the depth
measured from the sub-soil water level up to center of concrete under
sub-soil water level with quantity of concrete in cum executed under
sub-soil water. The depth of centre of gravity shall be reckoned
correct to 0.1m, 0.05m or more shall be taken as 0.1m and less than
0.05m ignored.
2008 Providing and fixing elastomeric bearings as per specification provided 1,890,000 Cm3 1
as per drawing.
2009 Providing and laying 40MM expansion joint as per RDSO drawing No.B- 140 M 12,532
1757R.
2010 Deflection test
2010b Above 10 to 13 3 Each 327,000
2010c Above 13 to 22 2 Each 420,500
2010e More than 26 3 Each 531,400
2015 Providing and laying dry stone backing behind abutments, wing walls, 6,079 Cum 737
return walls, RCC boxes
2016 Providing and laying backfill material behind abutments, wing walls, 19,318 Cum 397
return walls consisting of granular materials of GW, GP, SW
S.No Description of item Qty Unit Rate in Rs
2017 Providing and laying 300mm thick dry stone pitching in flooring, 13,254 Cum 831
exposed slopes, etc.
2018 Providing IPN coating (developed by CBRI) 5,960 Sqm 405
2019 Providing two coats of coal tar epoxy of 150 to 200 microns on R.C.C 22,769 Sqm 166
substructures of bridges
2020 Providing and fixing bridge plaque 58 Each 224
2021 Providing and fixing river name boards 32 Each 4,370
2022 Boring in all soils except hard rock and big big boulder and providing &
installing reinforced Piles
2022a 1200 MM dia pile 4,788 Meter 6,991
2022b 1000 MM dia pile 4,428 Meter 6,149
2023 Extra for chiselling over item no. 2022
2023a 1200 MM dia pile 321 Meter 3,203
2023b 1000 MM dia pile 297 Meter 2,448
2024 Conducting load testing on single pile or on separate test pile
2024a initial vertical load test 20 Each 470,000
2024b Routine test 20 Each 105,032
2029 Supplying and filling sand in well/box etc 3,501 Cum 198
2031 Providing and fixing of 100 mm dia PVC pipe for weep holes 7,424 Meter 211
2033 Providing and placing sand/earth filled bags in layers 7,300 Each 7
2037 Rail piling upto 5m depth to protect the existing embankment with 1,242 Meter 624
rails of any section supplied by the employer
S.No Description of item Qty Unit Rate in Rs
2037a Rail piling beyond 5m depth to protect the existing embankment with 180 Meter 935
rails of any section supplied by the employer
2039 Random rubble masonry 780 Cum. 1,328
2042e 1000 mm dia Pipe 140 Meter 5,419
Total For Bill No. - 02A -BRIDGE WORK (OTHER THAN STEEL WORKS)
Bill No. - 02B -BRIDGE WORK (STEEL ITEMS INVOLVING - FABRICATION AND ERECTION)
2055 Supply and installing casting pipe of MS sheet for bored piles as
directed by the engineer.
2055a For 1200 MM dia pipe (MS sheet 6mm thick) 2,135 Meter 11,813
2055b For 1000 MM dia pipe (MS sheet 6mm thick) 1,771 Meter 9,811
2056 Providing trolley/men refuges, inspection ladder, hand railing, other 1 MT 85,094
misc.
2065 Supply of Pre-stressing cables 45 MT 136,150
NS-1 Supplying, fitting and fixing in position true to line and level cast steel 1,500 MT 485
rocker bearing complete as per IS : 7666, IS:9565, IS:1030, IS:919, Bearing
IS:3073 and as per Bridge Code including all accessories as per drawing Capacity
and Technical Specifications
NS-2 Supplying, fitting and fixing in position true to line and level forged 1,500 MT 509
steel roller bearing complete as per IS : 7666, IS:9565, IS:1030, IS:919, Bearing
IS:3073 and as per Bridge Code including all accessories as per drawing Capacity
and Technical Specifications
S.No Description of item Qty Unit Rate in Rs
Total For Bill No. - 02B -BRIDGE WORK (STEEL ITEMS INVOLVING -
FABRICATION AND ERECTION)
Bill No. - 07A-PLATFORM, PASSENGER AMENTITIES AND MISCELLANEOUS WORKS (OTHER THAN STEEL ITEMS)
7004 Earth work in filling with contractor’s earth of approved quantity in 1,091,493 Cum 158
platform, circulating area, level crossing and other areas including all
lead and lift in layers not exceeding 30 CM in depth including
mechanical compaction and watering to achieve the desired
compaction as per specifications.
7008 Providing and laying water bound macadam with specified stone
aggregate, stone screening and binding material (good earth or
moorum) including screening, sorting, spreading to template and
compacting with power road roller of 8 to 10 tonne capacity etc.
complete
S.No Description of item Qty Unit Rate in Rs
7008a Sub-base with stone aggregate 90mm to 45mm size including stone 2,081 Cum 1,654
chips/screening 12.5/13.2mm size@ 0.1 cum per cum of WBM and
binding material @ 0.08 cum per cum of WBM
7008c Base course with stone aggregate 53mm to 22.4mm size including 1,561 Cum 1,410
stone chips/screening 10/11.2mm size @ 0.1 cum per cum of WBM and
binding material @ 0.08 cum per cum of WBM.
7009 Providing 40 MM premix carpet surfacing with 10-12.5 MM nominal size 14,564 Sqm 236
stone aggregate @ 5.4 cum per 100 Sqm and 54 kg hot bitumen per
cum of stone aggregate complete with paving asphalt 80/100 heated
and then mixed with solvent @ 70 Gms per KG of asphalt. The rate
also includes tack coat using hot straight rum bitumen of grade
80/100 @ 0.75 KG per SQM and preparation of the existing road
surface as per specifications.
7010 Providing seal coat of premixed fine aggregate (passing 2.36 MM and 14,564 Sqm 46
retained on 180 micron sieve) with bitumen using 128 KG of bitumen
of grade 8500 per cum of fine aggregate and 0.60 Cum of fine
aggregate per 100 Sqm of road surface including rolling and finishing
with road roller complete.
7011a For 50 MM completed thickness using coarse aggregate of size 40-20 14,564 Sqm 277
MM graded and key aggregate of size 12.5 MM graded.
7011b For 75 MM completed thickness in two layers using stone aggregate of 14,564 Sqm 392
size 63-41 MM graded and key aggregate of size 20 MM graded.
Bill No. - 07B-PLATFORM, PASSENGER AMENTITIES AND MISCELLANEOUS WORKS (STEEL ITEMS)
S.No Description of item Qty Unit Rate in Rs
7061 Providing FOB, platform shelters, height gauge, columns, beams, trusses and other 32 MT 85,128.00
steel components of miscellaneous works duly launched in position with or without
traffic block as directed by Engineer with contractors steel conforming to IS:2062-
1999 including fabrication, assembly, erection, launching, riveting/welding, bolting,
initial coats of zinc chromate priming conforming to relevant IS specification and
three subsequent coats of aluminum paint of approved quality conforming to IS:2339
after final erection on all surfaces complete. Rate is inclusive of supply and fixing of
MS holding down bolts for IRS type platform shelters and FOBs with required angles.
8002 Supply of 53 grade cement OPC conforming to IS: 12269 with latest amendments and 20,773 Bag of 50kg. 310.000
using the same in the work as per RVNl's approved mix design as per RVNl's
prescribed rates of consumption including all lead lift, labour, loading unloading,
ascent, descent, crossing of Railway lines(s), royalty, taxes, transport (contractor's
own), tools and plant complete.
8003 Supply of Portland Pozzolana Cement (PPC) conforming to IS:1489 with latest 5,000 Bag of 50kg. 296.250
amendments and using the same in the work as per RVNl's approved mix design as
per RVNl's prescribed rates of consumption including all lead lift, labour, loading
unloading, ascent, descent, crossing of Railway lines(s), royalty, taxes, transport
(contractor's own), tools and plant complete.
9001 Providing site offices for Employer with Contractor's material, labour, Tools and 184 Per Sq.m. of 10,657.000
Plant, Equipment etc. including provision of Water Supply, Drainage, Power Plinth area
arrangements, office maintenance as per the details mentioned in clauses 3.1 to
3.2.8 & 3.5 to 3.5.2 of Chapter 3 (Site Facilities for the Employer and the Engineer)
of Section 5 (Work's Requirement) of Tender Documents.
Note 1: This item is provided with the contention that new site offices will be
constructed for this purpose and 75% payment of the accepted rates will be made
after making available functional office, balance 15% payment shall be made at the
end of the completion period and the remaining 10% will be paid after clearance of
site by the contractor.
Note 3: In case stipulated period gets extended, payment on monthly basis under
this item, in such extended period, shall be made as under
(i)In case of new construction @[(54% of Quoted rate) / (stipulated completion
period in months + defect liability period in months)] per Sq.m. of plinth area.
(ii)In case of accommodation on hire @[(90% of Quoted rate) / (stipulated
completion period in months + defect liability period in months)] per Sq.m. of plinth
area.
S.No Description of item Qty Unit Rate in Rs
9002 Providing Furniture as given under clauses 3.3, 3.3.1 of Chapter 3 (Site Facilities for 1 L S Per Site 827,760.000
the Employer) of Section 5 (work's Requirement) of Tender Documents. Office
Note: Payment shall be made @ 75% of the accepted rate after making available the
furniture items in functional office, balance 15% payment shall be made at the end
of the completion period and the remaining 10% will be paid after clearance of site
by the contractor
9003 Providing Road Vehicle mentioned below for the use of Engineer/Employer as per
the Conditions mentioned in Clause 3.4.3, i.e 3.4.3.1 to 3.4.3.3 of Chapter 3 (Site
Facilities for the Employer and the Engineer) of Section 5 Work's Requirement) of
Tender Documents.
9003 b Providing Road Vehicle (Tata Sumo, Bolero or similar) 390 Vehicle 38,284.000
months
9003 c Extra for running and maintenance of every additional km over and above 4000 kms 3,000 Per Km 10.350
as specified in item 9003 (a)
9003 d Extra for running and maintenance of every additional km over and above 4000 kms 24,000 Per Km 8.280
as specified in item 9003 (b)
Total For Bill No. - 10-OTHER ITEMS OF WORK NOT COVERED IN BILL
NO. 1 TO 09.
Amount in Rs
2,535,040.00
1,616,712.00
255,500.00
1,592,604.00
20,800.00
86,536.20
4,967,082.84
23,728,056.00
Amount in Rs
94,754,672.64
6,255,450.05
Amount in Rs
300,542.00
1,398,600.00
1,754,480.00
-
981,000.00
841,000.00
1,594,200.00
4,477,548.24
7,672,723.24
Amount in Rs
11,015,797.02
2,413,800.00
3,779,654.00
12,992.00
139,840.00
-
33,471,902.52
27,226,532.16
-
1,028,163.00
727,056.00
-
9,400,000.00
2,100,640.00
691,587.54
1,566,464.00
54,239.00
775,008.00
Amount in Rs
168,300.00
1,035,840.00
758,660.00
251,199,022.45
25,220,755.00
17,375,281.00
85,094.00
6,126,750.00
727,170.00
763,755.00
Amount in Rs
50,298,805.00
258,479,544.00
ITEMS)
172,259,425.26
-
Amount in Rs
3,441,974.00
2,201,010.00
3,437,104.00
671,546.04
-
Amount in Rs
4,034,228.00
5,709,088.00
758,073.60
192,512,448.90
Amount in Rs
2,724,096.00
2,724,096.00
99,964,822.50
Amount in Rs
6,439,630.00
1,481,250.00
107,885,702.50
Amount in Rs
1,960,888.00
Amount in Rs
827,760.00
3,470,376.00
14,930,760.00
31,050.00
198,720.00
21,419,554.00
5,000,000.00
Amount in Rs
5,000,000.00