You are on page 1of 2

Review of Compensation Clause for Delay in Handing over of

Site in Highway Contracts


I D Kalra, Fellow

INTRODUCTION NHAI, following the provisions of National Highway Laws


(Amendment Bill), 1997.Initially a notification is issued by the
National Highways Authority of India (NHAI) was constituted Central Government in the official Gazette authorizing a person
under an Act of Parliament, the National Highway Authority or authority to perform the functions of competent authority
Act, 1988, to develop the National Highways. The development for such areas, as envisaged in the acquisition. This notification
works, entrusted to NHAI envisaged strengthening and four/ inter-alia also gives a brief description of the land proposed to
six-laning of existing high-density corridors. As the works were be acquired.The acquisition of land sometimes takes over one
generally financed by the external agencies, the contract year or even more after the above notification has been
documents for the works are prepared based on Federation published. The delay sometimes extends to several years in case
Internationale Des Ingenieurs-Conseils (FIDIC) Conditions of the parties resort to litigation.
Contract. NHAI has so far completed work on over 12 000 km
length of the various corridors. REVIEW OF CONTRACT DOCUMENTS

BACKGROUND The standard contract documents being used by NHAI for


inviting tenders for highway projects need review to provide
The work on most of the corridors got setback because full suitable safeguards to avoid highly inflated/frivolous claims
length of the encumbrance free land, as stipulated, could not from contractors due to delay in handing over of unencumbered
be handed over to the contractors as planned/stipulated in their sites and consequent idling/ underutilization of resources and
contracts resulting not only in prolongation of contract periods, their other cost over-runs. Some of the safeguards recommended
but also added to the cost of work done due to escalation in are as follows:
cost of inputs, additional cost of construction supervision,
claims from the contractors for idling/underutilization of their The contract should provide initially for submission of programs
resources and other cost over-runs. for site/sections, which are immediately available for taking up
the work. The contractors can submit the supplementary/revised
According to Sub-Clause 42.2 of FIDIC General Conditions, program as soon as further unencumbered site becomes available
if the contractor suffers delay and or increase in cost on account in affected sections.
of failure on the part of the employer to give possession of
land for completion of the work in accordance with terms of In case of anticipated delay in handing over site, the work should
Sub-Clause 42.1 of FIDC General Conditions, the engineer shall be foreclosed and a separate agreement may be entered into
after due consultation with the employer and the contractor with the contractor for executing the balance work, at later stage,
determine the amount of such costs, which shall be added to at mutually agreed terms when the balance encumbrance free
the contract price. In practice, it has been observed that once site has been made available by the client.
the acquisition/handing over possession of the land is delayed,
the contractors start lodging highly inflated/frivolous claims A suitable clause may be inserted in the contracts to provide
on various counts leading to disputes, which is mere exploitation for extra payment on account of delay in handing over of the
of the situation by the contractors. site beyond the date stipulated for handing over the
encumbrance free site in the contract.
PROCEDURE OF LAND ACQUISITION
The BOQ should provide for items requiring contractors to
The land is generally acquired for the highway projects, by quote for additional payments for different periods of delay in
handing over of the sites.
I D Karle is with Span Consultants Pvt Ltd, 92-C, Gurndwara Road,
Madangiri, New Delhi 110 062. In case it is not possible to vary the contract provisions as stated
This paper (modified) was received November 9, 2005. Written discussion on this above, the present contract documents should be revised to
paper will be entertained till April 30, 2006. include guidelines for assessing the actual cost of

Vol 86, February 2006 195


underutilization/idling of contractor’s resources on account of contractors on account of delay in handing over of the site/
delay in handing over the possession of unencumbered site as encumbrance free land, as required for completion of the
stipulated in the contract. This should invariably include method project, are inadequate. Thus there is a need to upgrade this
statement for computing man and machine resources actually document by making suitable provisions/amending the existing
deployed vis-à-vis sources theoretically required/provided in provision to avoid highly inflated/frivolous claims by the
the contract. contractors in case of delays in handing over of sites/
encumbrance free land, which are sometimes inevitable.
CONCLUSION
ACKNOWLEDGEMENT
The tender documents are highly legal and technical documents,
thus due care is required in preparing these documents. The The author is highly grateful to Prof B S Dhiman, Managing
present standard NHAI tender documents for highway contracts Director, Span Consultants Pvt Ltd, for his guidance and
are highly comprehensive documents. The documents encouragement in compilation of the paper. The author is also
meticulously cover all the aspects of highway projects. However, thankful to Shri Jawahar Kaul, Sr Director, Span Consultants
the provisions reg arding payment of compensation to Pvt Ltd, for his assistance in preparation of this paper.

196 IE(I) Journal-CV

You might also like