Professional Documents
Culture Documents
or a total of 56,901.53
with interest, and in not awarding to the plaintiff as damages in this case the sum of P319,253.40, with legal
interest thereon from the date of filing the complaint in this case, in the manner and form computed but it,
and in awarding damages to the plaintiff for the sum of only P2,219.60. with costs.
xxx xxx xxx
JOHNS, J.:
In this action plaintiff seeks to recover damages from the defendant which it claims to have sustained after
September, 1923, arising from, and growing out of, its original contract of September 10, 1918, as modified on
January 1, 1919, to continue for a period of ten years from that date.
In paragraph VIII of its complaint, plaintiff alleges that about the last part of July, 1920, the defendant "willfully and
deliberately breached its said contract," and that it "flatly refused to make any deliveries under said contract, and
finally on November 23, 1923," it was forced to commence action in the Court of First Instance against the defendant
known as case No. 25352, to recover the damages which it had then sustained by reason of such flagrant violation of
said contract on the part of the defendant, in which judgment was rendered in favor of the plaintiff and against the
defendant for P26,1119.08, as damages suffered by this plaintiff by the defendant's breach of said contract from July
1920, up to and including September, 1923, with legal interest thereon from November 23, 1923, and for the costs,"
in which the court refused to order the defendant to resume the delivery of the coal and water gas tar to the plaintiff,
in accord with said contract, but left it with its remedy for damages against the defendant for any subsequent
breaches of the contract. A copy of that judgment, which was later affirmed by this court, is attached to, marked
Exhibit G, and made a part of, the complaint in this action.
In their respective briefs, opposing counsel have much to say about the purpose and intent of the judgment, and it is
vigorously asserted that it was never intended that it should be or become a bar to another action by the plaintiff to
recover any damages it may have sustained after September, 1923, during the remainder of the ten-year period of
that contract. Be that as it may, it must be conceded that the question as to what would be the legal force and effect
of that judgment in that case was never presented to, or decided by, the lower court or this court. In the very nature
of things, neither court in that case would have the power to pass upon or decided the legal force and effect of its
own judgment, for the simple reason that it would be premature and outside of the issues of any pleading, and could
not be raised or presented until after the judgment became final and then only by an appropriate plea, as in this
case.
Plaintiff specifically alleges that the defendant willfully and deliverately breached the contract and "flatly refused to
make any deliveries under said contract," by reason of. which it was forced to and commenced its former action in
which it was awarded P26,119.08 damages against the defendant by reason of its breach of the contract from July,
1920, to September, 1923.
In the final analysis, plaintiff in this action seeks to recover damages growing out of, and arising from, other and
different breaches of that same contract after November, 1923, for the remainder of the ten-year period, and the
question is thus squarely presented as to whether the rendition of the former judgment is a bar to the right of the
plaintiff to recover damages from and after September, 1923, arising from, and growing out of, breaches of the
original contract of September 10, 1918, as modified on January 1, 1919. That is to say, whether the plaintiff, in a
former action, having recovered judgment for the damages which it sustained by reason of a breach of its contract by
the defendant up to September, 1923, can now in this action recover damages it may have sustained after
September, 1923, arising from, and growing out of, a breach of the same contract, upon and for which it recovered its
judgment in the former action.
In the former action in which the judgment was rendered, it is alleged in the compliant:
"7. That about the last part of July or the first part of August, 1920, the Manila Gas Corporation, the
defendant herein, without any cause ceased delivering coal and water gas tar to the plaintiff herein; and that
from that time up to the present date, the plaintiff corporation, Blossom & Company, has frequently and
urgently demanded of the defendant, the Manila Gas Corporation, that it comply with its aforesaid contract
Exhibit A by continuing to deliver coal and water gas tar to this plaintiff — but that the said defendant has
refused and still refuses, to deliver to the plaintiff any coal and water gas tar whatsoever under the said
contract Exhibit A, since the said month of July 1920.
"9. That owing to the bad faith of the said Manila Gas Corporation, defendant herein, in not living up to its
said contract Exhibit A, made with this plaintiff, and refusing now to carry out the terms of the same, be
delivering to this plaintiff the coal and water gas tar mentioned in the said Exhibit A, has caused to this
plaintiff great and irreparable damages amounting to the sum total of one hundred twenty- four thousand
eight hundred forty eight pesos and seventy centavos (P124,848,70);and that the said defendant corporation
has refused, and still refuses, to pay to this plaintiff the whole or any part of the aforesaid sum.
"10. That the said contract Exhibit A, was to be in force until January 1, 1929, that is to say ten (10) years
counted from January 1, 1929; and that unless the defendant again commence to furnish and supply this
plaintiff with coal and water gas tar, as provided for in the said contract Exhibit A, the damages already
suffered by this plaintiff will continually increase and become larger and larger in the course of years
preceding the termination of the said contract on January 1, 1929."
In that action plaintiff prays for judgment against the defendant:
"(a) That upon trial of this this cause judgment be rendered in favor of the plaintiff and against the defendant
for the sum of P124,8484.70), with legal interest thereon from November 23, 1923;
"(b) That the court specifically order the defendant to resume the delivery of the coal and water gas tar to
the plaintiff under the terms of the said contract Exhibit A of this complaint."
In the final analysis, plaintiff must stand or fall on its own pleadings, and tested by that rule it must be admitted that
the plaintiff's original cause of action, in which it recovered judgment for damages, was founded on the ten-year
contract, and that the damages which it then recovered were recovered for a breach of that contract.
Both actions are founded on one and the same contract. By the terms of the original contract of September 10, 1018,
the defendant was to sell and the plaintiff was to purchase three tons of water gas tar per month form September to
January 1, 1919, and twenty tons of water gas tar per month after January 1, 1919, one-half ton of coal gas tar per
month from September to January 1, 1919, and six tons of coal gas tar per month after January 1, 1919. That from
and after January 1, 1919, plaintiff would take at least the quantities specified in the contract of September 10, 1918,
and that at its option, it would have the right to take the total output of water gas tar of defendant's plant and 50 per
cent of the gross output of its coal gas tar, and upon giving ninety days' notice, it would have the right to the entire
output of coal gas tar, except such as the defendant might need for its own use. That is to say, the contract provided
for the delivery to the plaintiff from month to month of the specified amounts of the different tars as ordered and
requested by the plaintiff. In other words, under plaintiff's own theory, the defendant was to make deliveries from
month to month of the tars during the period of ten years, and it is alleged in both complaints that the defendant
broke its contract, and in bad faith refused to make any more deliveries.
In 34 Corpus Juris, p. 839, it is said:
As a general rule a contract to do several things at several times in its nature, so as to authorize successive
actions; and a judgment recovered for a single breach of a continuing contract or covenant is no bar to a suit
for a subsequent breach thereof. But where the covenant or contract is entire, and the breach total, there
can be only one action, and plaintiff must therein recover all his damages.
In the case of Rhoelm vs, Horst, 178 U. U., 1; 44 Law. ed., 953, that court said:
An unqualified and positive refusal to perform a contract, though the performance thereof is not yet due,
may, if the renunciation goes to the whole contract, be treated as a complete breach which will entitle the
injured party to bring his action at once.
15 Ruling Case Law, 966, 967, sec. 441 says:
Similarly if there is a breach by the vendor of a contract for the sale of goods to be delivered and paid for in
installments, and the vendee maintains an action therefor and recovers damages, he cannot maintain a
subsequent action to recover for the failure to deliver later installments.
In Pakas vs. Hollingshead, 184 N. Y., 211; 77 N. E., 40; 3 L. R. A. (N. S.), 1024, the syllabus says:
Upon refusal, by the seller, after partial performance, longer to comply with his contract to sell and deliver a
quantity of articles in installments the buyer cannot keep the contract in force and maintain actions for
breaches as they occur but must recover all his damages in one suit.
And on page 1044 of its opinion, the court say:
The learned counsel for the plaintiff contends that the former judgment did not constitute a bar to the
present action but that the plaintiff had the right to elect to waive or disregard the breach, keep the contract
in force, and maintain successive actions for time to time as the installments of goods were to be delivered,
however numerous these actions might be. It is said that this contention is supported in reason and justice,
and has the sanction of authority at least in other jurisdictions. We do not think that the contention can be
maintained. There is not as it seems to us any judicial authority in this state that gives it any substantial
support. On the contrary, we think that the cases, so far as we have been able to examine them, are all the
other way, and are to the effect that, inasmuch as there was a total breach of the contract by the defendant's
refusal to deliver, the plaintiff cannot split up his demand and maintain successive actions, but must either
recover all his damages in the first suit or wait until the contract matured or the time for the delivery of all
the goods had arrived. In other words, there can be but one action for damages for a total breach of an
entire contract to deliver goods, and the fact that they were to be delivered in installment from time to time
does not change the general rule.
The case of L. Bucki & Son Lumber Co. vs. Atlantic Lumber Co. (109 Federal, 411), of the United States Circuit Court of
Appeals for the Fifth Circuit, is very similar.
The syllabus says:
1. CONTRACTS — CONSTRUCTION —ENTIRE CONTRACT. —A contract was made for the sale of a large
quantity of logs to be delivered in monthly installments during a period of eight years, payments to be made
also in installments at times having relation tot he deliveries. It contained stipulations as to such payments,
and guaranties as to the average size of the logs to be delivered in each installment. Held, that it was an
entire contract, and not a number of separate and independent agreements for the sale of the quantity to be
delivered and paid for each month, although there might be breaches of the minor stipulations and
warranties with reference thereto which would warrant suits without a termination of the contract.
2. JUDGMENTS — MATTERS CONCLUDED —ACTION FOR BREACH OF INDIVISIBLE CONTRACT. — The seller
declared the contract terminated for alleged breaches by the purchaser, and brought suit for general and
special damages the latter covering payments due for installments of logs delivered. By way of set-off and
recoupment against this demand, the purchaser pleaded breaches of the warranty as to the size of the logs
delivered during the months for which payment had not been made. Held, that the judgment in such action
was conclusive as to all claims or demands or either party against the other growing out of the entire
contract, and was a bar to a subsequent suit brought by the purchaser to recover for other breaches of the
same warranty in relation to deliveries made in previous months.
On page 415 of the opinion, the court says:
When the contract was ended, the claims of each party for alleged breaches and damages therefor
constituted an indivisible demand; and when the same, or any part of the same, was pleaded, litigation had,
and final judgment rendered, such suit and judgment constitute a bar to subsequent demands which were or
might have been litigated (Baird vs. U. S., 96 U. S., 430; 24 L. ed., 703.)
In Watts vs. Weston (238 Federal, 149), Circuit Court of Appeals, Second Circuit, the syllabus says:
1. JUDGMENTS — 593 — JUDGMENT AS BAR — MATTERS CONCLUDED. — Where a continuing contract was
terminated by the absolute refusal of the party whose action was necessary to further perform, a claim for
damages on account of the breach constituted as indivisible demand, and when the same or any part of the
same was pleaded, litigated, and final judgment rendered, such suit and judgment constitute a bar to
subsequent demands which were or might have been litigated therein.
And on page 150 of the opinion, the court says:
It is enough to show the lack of merit in the present contention to point out as an inexorable rule of law that,
when Kneval's contract was discharged by his total repudiation thereof, Watt's claims for breaches and
damages therefor constituted an indivisible demand, and when the same, or any part of the same, was
pleaded, litigation had and final judgment rendered, such suit and judgment constitute a bar to subsequent
demands which were or might have been litigated." (Bucki, etc., Co. vs. Atlantic, etc., Co., 109 Fed. at page
415; 48 C. C. A., 459; Cf. Landon vs. Bulkley, 95 Fed., 344; 337 C. C. A., 96.)
The rule is usually applied in cases of alleged or supposed successive breaches, and consequently severable
demands for damages; but if the contract has been discharged by breach, if suit for damages is all that is left,
the rule is applicable, and every demand arising form that contract and possessed by any given plaintiff must
be presented (at least as against any given defendant) in one action; what the plaintiff does not advance he
foregoes by conclusive presumption.
Inn Abbott vs. 76 Land and Water Co. (118 Pac., 425; 161 Cal., 42), at page 428, the court said:
In Fish vs. Folley, 6 Hill (N. Y.), 54, it was held, in accord with the rule we have discussed, that, where the
defendant had covenanted that plaintiff should have a continual supply of water for his mill from a dam, and
subsequently totally failed to perform for nine years, and plaintiff brought an action for the breach and
recovered damages sustained by him to that time, the judgment was a bar to a second action arising from
subsequent failure to perform, on the theory that, although he covenant was a continuing one in one sense,
it was an entire contract, and a total breach put an end to it, and gave plaintiff the right to sue for an
equivalent in damages.
In such a case it is no warrant for a second action that the party may not be able to actually prove in the first
action all the items of the demand, or that all the damage may not then have been actually suffered. He is
bound to prove in the first action not only such damages as has been actually suffered, but also such
prospective damage by reason of the breach as he may be legally entitled to, for the judgment he recovers in
such action will be a conclusive adjudication as to the total damage on account of the breach.
It will thus be seen that, where there is a complete and total breach of a continuous contract for a term of years, the
recovery of a judgment for damages by reason of the breach is a bar to another action on the same contract for and
on account of the continuous breach.
In the final analysis is, there is no real dispute about any material fact, and the important and decisive question is the
legal construction of the pleadings in the former case and in this case, and of the contract between the plaintiff and
the defendant of January 1, 1920.
The complaint on the former case specifically alleges that the defendant "has refused and still refuses, to deliver to
the plaintiff any coal and water gas tar whatsoever under the said contract Exhibit A, since the said month of July,
1920." " That owing to the bad faith of the said Manila Gas Corporation, defendant herein, in not living up to its said
contract Exhibit A, made with this plaintiff, and refusing now to carry out the terms of the same." That is a specific
allegation not only a breach of the contract since the month of July, 1920, but of the faith of the defendant in its
continuous refusal to make deliveries of any coal and water gas tar. That amended complaint was filed on July 11,
1924, or four years after the alleged bad faith in breaking the contract.
Having recovered damages against it, covering a period of four years, upon the theory that the defendant broke the
contract, and in bad faith refused to make deliveries of either of the tars, how can the plaintiff now claim and assert
that the contract is still in fierce and effect? In the instant case the plaintiff alleges and relies upon the ten year
contract on January 11, 1920, which in bad faith was broken by the defendant. If the contract was then broken, how
can it be enforced in this action?
It is admitted that the defendant never made any deliveries of any tar from July, 1920, to April, 1936. Also that it
made nine deliveries to plaintiff of the minimum quantities of coal and water gas tar from April 7, 1926, to January 5,
1927.
Plaintiff contends that such deliveries were made under and in continuation of the old contract.
March 26, 1926, after the decision of this court affirming the judgment in the original action, plaintiff wrote the
defendant:
. . . It is our desire to take deliveries of at least the minimum quantities set forth therein and shall appreciate
to have you advise us how soon you will be in a position to make deliveries; . . .
. . . In view of the fact that you have only effected settlement up to November 23, 1923, please inform us
what adjustment you are willing to make for the period of time that has since elapsed without your
complying with the contract.
In response to which on March 31, 1926, the defendant wrote this letter to the plaintiff:
In reply to your letter of March 26th, 1926, in regard to tar, we beg to advise you that we are prepared to
furnish the minimum quantities of coal and water gas tars as per your letter, viz: twenty tons of water gas tar
and six tons of coal gas tar. The price figured on present costs of raw materials is P39.01 ) Thirty-nine and
01/100 Pesos) per ton of water gas and P33.59 (Thirty-three and 59/100 Pesos) per ton of coal tar.
We shall expect you to take delivery and pay for the above amount of tars at our factory on or before April
7th prox.
Thereafter we shall be ready to furnish equal amounts on the first of each month. Kindly make your
arrangements accordingly.
On January 29, 1927, the plaintiff wrote the defendant that:
On July 31st last, we made demand upon you, under the terms of our tar contract for 50 per cent of your
total coal tar production for that month and also served notice on you that beginning 90 days from August
1st we would require you total output of coal tar monthly; this in addition to the 20 tons of water gas tar
provided for in the contract to be taken monthly.
xxx xxx xxx
We are here again on your for your total output of coal tar immediately and the regular minimum monthly
quantity of water gas tar. In this connection we desire to advise you that within 90 days of your initial delivery
to us of your total coal tar output we will require 50 per cent of your total water gas tar output, and, further,
that two months thereafter we will require your total output of both tars.
February 2, 1927, the defendant wrote the plaintiff:
Replying to your letter of Jan. 29, we would sat that we have already returned to you the check enclosed
there with. As we have repeatedly informed you we disagree with you as to the construction of your contract
and insist that you take the whole output of both tars if you wish to secure the whole of the coal tar.
With regard to your threat of further suits we presume that you will act as advised. If you make it necessary
we shall do the same.lawphil.net
From an analysis of these letters it clearly appears that the plaintiff then sought to reply upon and enforce the
contract of January 1, 1920, and that defendant denied plaintiff's construction of the contract, and insisted "that you
take the whole output of both tars if you wish to secure the whole of the coal tar."
February 28, 1927, the plaintiff wrote the defendant:
In view of your numerous violations of and repeated refusal and failure to comply with the terms and
provisions of our contract dated January 30-31, 1919, for the delivery to us of water and coal gas tars, etc.,
we will commence action," which it did.
The record tends to show that tars which the defendant delivered after April 7, 1926, were not delivered under the
old contract of January 1, 1920, and that at all times since July 1920, the defendant has consistently refused to make
any deliveries of any tars under that contract.
The referee found as a fact that plaintiff was entitled to P2,219.60 for and on account of overcharges which the
defendant made for the deliveries of fifty-four tons of coal gas tar, and one hundred eighty tons of water gas tar after
April, 1926, and upon that point the lower says:
The fourth charge that plaintiff makes is meritorious. The price was to be fixed on the basis of raw materials.
The charge for deliveries during 1926 were too high. In this I agree with entirely with the referee and adopt
his findings of fact and calculations. (See Referee's report, p. 83) The referee awarded for overcharge during
the period aforesaid, the sum of P2,219.60. The defendant was trying to discharge plaintiff from buying tars
and made the price of raw material appear as high as possible.
That finding is sustained upon the theory that the defendant broke its contract which it made with the plaintiff for
the sale and delivery of the tars on and after April, 1926.
After careful study of the many important questions presented on this appeal in the exhaustive brief of the appellant,
we are clearly of the opinion that, as found by the lower court, the plea of res judicata must be sustained. The
judgment of the lower court is affirmed. It is so ordered, with costs against the appellant.
SWAGMAN HOTELS AND TRAVEL, INC., Petitioners vs. COURT OF APPEALS, and NEAL CHRISTIAN, Respondents. G.R.
No. 161135. April 8, 2005
May a complaint that lacks a cause of action at the time it was filed be cured by the accrual of a cause of action
during the pendency of the case? This is the basic issue raised in this petition for the Court’s consideration.
Sometime in 1996 and 1997, petitioner Swagman Hotels and Travel, Inc., through Atty. Leonor L. Infante and Rodney
David Hegerty, its president and vice-president, respectively, obtained from private respondent Neal B. Christian
loans evidenced by three promissory notes dated 7 August 1996, 14 March 1997, and 14 July 1997. Each of the
promissory notes is in the amount of US$50,000 payable after three years from its date with an interest of 15% per
annum payable every three months.1 In a letter dated 16 December 1998, Christian informed the petitioner
corporation that he was terminating the loans and demanded from the latter payment in the total amount of
US$150,000 plus unpaid interests in the total amount of US$13,500. 2
On 2 February 1999, private respondent Christian filed with the Regional Trial Court of Baguio City, Branch 59, a
complaint for a sum of money and damages against the petitioner corporation, Hegerty, and Atty. Infante. The
complaint alleged as follows: On 7 August 1996, 14 March 1997, and 14 July 1997, the petitioner, as well as its
president and vice-president obtained loans from him in the total amount of US$150,000 payable after three years,
with an interest of 15% per annum payable quarterly or every three months. For a while, they paid an interest of 15%
per annum every three months in accordance with the three promissory notes. However, starting January 1998 until
December 1998, they paid him only an interest of 6% per annum, instead of 15% per annum, in violation of the terms
of the three promissory notes. Thus, Christian prayed that the trial court order them to pay him jointly and solidarily
the amount of US$150,000 representing the total amount of the loans; US$13,500 representing unpaid interests
from January 1998 until December 1998; ₱100,000 for moral damages; ₱50,000 for attorney’s fees; and the cost of
the suit.3
The petitioner corporation, together with its president and vice-president, filed an Answer raising as defenses lack of
cause of action and novation of the principal obligations. According to them, Christian had no cause of action
because the three promissory notes were not yet due and demandable. In December 1997, since the petitioner
corporation was experiencing huge losses due to the Asian financial crisis, Christian agreed (a) to waive the interest
of 15% per annum, and (b) accept payments of the principal loans in installment basis, the amount and period of
which would depend on the state of business of the petitioner corporation. Thus, the petitioner paid Christian capital
repayment in the amount of US$750 per month from January 1998 until the time the complaint was filed in February
1999. The petitioner and its co-defendants then prayed that the complaint be dismissed and that Christian be
ordered to pay ₱1 million as moral damages; ₱500,000 as exemplary damages; and ₱100,000 as attorney’s fees. 4
In due course and after hearing, the trial court rendered a decision 5 on 5 May 2000 declaring the first two promissory
notes dated 7 August 1996 and 14 March 1997 as already due and demandable and that the interest on the loans
had been reduced by the parties from 15% to 6% per annum. It then ordered the petitioner corporation to pay
Christian the amount of $100,000 representing the principal obligation covered by the promissory notes dated 7
August 1996 and 14 March 1997, "plus interest of 6% per month thereon until fully paid, with all interest payments
already paid by the defendant to the plaintiff to be deducted therefrom."
The trial court ratiocinated in this wise:
(1) There was no novation of defendant’s obligation to the plaintiff. Under Article 1292 of the Civil Code, there is an
implied novation only if the old and the new obligation be on every point incompatible with one another.
The test of incompatibility between the two obligations or contracts, according to an imminent author, is whether
they can stand together, each one having an independent existence. If they cannot, they are incompatible, and the
subsequent obligation novates the first (Tolentino, Civil Code of the Philippines, Vol. IV, 1991 ed., p. 384). Otherwise,
the old obligation will continue to subsist subject to the modifications agreed upon by the parties. Thus, it has been
written that accidental modifications in an existing obligation do not extinguish it by novation. Mere modifications of
the debt agreed upon between the parties do not constitute novation. When the changes refer to secondary
agreement and not to the object or principal conditions of the contract, there is no novation; such changes will
produce modifications of incidental facts, but will not extinguish the original obligation. Thus, the acceptance of
partial payments or a partial remission does not involve novation (id., p. 387). Neither does the reduction of the
amount of an obligation amount to a novation because it only means a partial remission or condonation of the same
debt.
In the instant case, the Court is of the view that the parties merely intended to change the rate of interest from 15%
per annum to 6% per annum when the defendant started paying $750 per month which payments were all accepted
by the plaintiff from January 1998 onward. The payment of the principal obligation, however, remains unaffected
which means that the defendant should still pay the plaintiff $50,000 on August 9, 1999, March 14, 2000 and July 14,
2000.
(2) When the instant case was filed on February 2, 1999, none of the promissory notes was due and demandable. As
of this date however, the first and the second promissory notes have already matured. Hence, payment is already
due.
Under Section 5 of Rule 10 of the 1997 Rules of Civil Procedure, a complaint which states no cause of action may be
cured by evidence presented without objection. Thus, even if the plaintiff had no cause of action at the time he filed
the instant complaint, as defendants’ obligation are not yet due and demandable then, he may nevertheless recover
on the first two promissory notes in view of the introduction of evidence showing that the obligations covered by the
two promissory notes are now due and demandable.
(3) Individual defendants Rodney Hegerty and Atty. Leonor L. Infante can not be held personally liable for the
obligations contracted by the defendant corporation it being clear that they merely acted in representation of the
defendant corporation in their capacity as General Manager and President, respectively, when they signed the
promissory notes as evidenced by Board Resolution No. 1(94) passed by the Board of Directors of the defendant
corporation (Exhibit "4").6
In its decision7 of 5 September 2003, the Court of Appeals denied petitioner’s appeal and affirmed in toto the
decision of the trial court, holding as follows:
In the case at bench, there is no incompatibility because the changes referred to by appellant Swagman consist only
in the manner of payment. . . .
Appellant Swagman’s interpretation that the three (3) promissory notes have been novated by reason of appellee
Christian’s acceptance of the monthly payments of US$750.00 as capital repayments continuously even after the
filing of the instant case is a little bit strained considering the stiff requirements of the law on novation that the
intention to novate must appear by express agreement of the parties, or by their acts that are too clear and
unequivocal to be mistaken. Under the circumstances, the more reasonable interpretation of the act of the appellee
Christian in receiving the monthly payments of US$750.00 is that appellee Christian merely allowed appellant
Swagman to pay whatever amount the latter is capable of. This interpretation is supported by the letter of demand
dated December 16, 1998 wherein appellee Christian demanded from appellant Swagman to return the principal
loan in the amount of US$150,000 plus unpaid interest in the amount of US$13,500.00
...
Appellant Swagman, likewise, contends that, at the time of the filing of the complaint, appellee Christian ha[d] no
cause of action because none of the promissory notes was due and demandable.
Again, We are not persuaded.
...
In the case at bench, while it is true that appellant Swagman raised in its Answer the issue of prematurity in the filing
of the complaint, appellant Swagman nonetheless failed to object to appellee Christian’s presentation of evidence to
the effect that the promissory notes have become due and demandable.
The afore-quoted rule allows a complaint which states no cause of action to be cured either by evidence presented
without objection or, in the event of an objection sustained by the court, by an amendment of the complaint with
leave of court (Herrera, Remedial Law, Vol. VII, 1997 ed., p. 108). 8
Its motion for reconsideration having been denied by the Court of Appeals in its Resolution of 4 December 2003, 9the
petitioner came to this Court raising the following issues:
I. WHERE THE DECISION OF THE TRIAL COURT DROPPING TWO DEFENDANTS HAS BECOME FINAL AND EXECUTORY,
MAY THE RESPONDENT COURT OF APPEALS STILL STUBBORNLY CONSIDER THEM AS APPELLANTS WHEN THEY DID
NOT APPEAL?
ii. Where there is no cause of action, is the decision of the lower court valid?
III. MAY THE RESPONDENT COURT OF APPEALS VALIDLY AFFIRM A DECISION OF THE LOWER COURT WHICH IS
INVALID DUE TO LACK OF CAUSE OF ACTION?
IV. Where there is a valid novation, may the original terms of contract which has been novated still prevail? 10
The petitioner harps on the absence of a cause of action at the time the private respondent’s complaint was filed
with the trial court. In connection with this, the petitioner raises the issue of novation by arguing that its obligations
under the three promissory notes were novated by the renegotiation that happened in December 1997 wherein the
private respondent agreed to waive the interest in each of the three promissory notes and to accept US$750 per
month as installment payment for the principal loans in the total amount of US$150,000. Lastly, the petitioner
questions the act of the Court of Appeals in considering Hegerty and Infante as appellants when they no longer
appealed because the trial court had already absolved them of the liability of the petitioner corporation.
On the other hand, the private respondent asserts that this petition is "a mere ploy to continue delaying the payment
of a just obligation." Anent the fact that Hegerty and Atty. Infante were considered by the Court of Appeals as
appellants, the private respondent finds it immaterial because they are not affected by the assailed decision anyway.
Cause of action, as defined in Section 2, Rule 2 of the 1997 Rules of Civil Procedure, is the act or omission by which a
party violates the right of another. Its essential elements are as follows:
1. A right in favor of the plaintiff by whatever means and under whatever law it arises or is created;
2. An obligation on the part of the named defendant to respect or not to violate such right; and
3. Act or omission on the part of such defendant in violation of the right of the plaintiff or constituting a breach of
the obligation of the defendant to the plaintiff for which the latter may maintain an action for recovery of damages or
other appropriate relief.11
It is, thus, only upon the occurrence of the last element that a cause of action arises, giving the plaintiff the right to
maintain an action in court for recovery of damages or other appropriate relief.
It is undisputed that the three promissory notes were for the amount of P50,000 each and uniformly provided for (1)
a term of three years; (2) an interest of 15 % per annum, payable quarterly; and (3) the repayment of the principal
loans after three years from their respective dates. However, both the Court of Appeals and the trial court found that
a renegotiation of the three promissory notes indeed happened in December 1997 between the private respondent
and the petitioner resulting in the reduction – not waiver – of the interest from 15% to 6% per annum, which from
then on was payable monthly, instead of quarterly. The term of the principal loans remained unchanged in that they
were still due three years from the respective dates of the promissory notes. Thus, at the time the complaint was
filed with the trial court on 2 February 1999, none of the three promissory notes was due yet; although, two of the
promissory notes with the due dates of 7 August 1999 and 14 March 2000 matured during the pendency of the case
with the trial court. Both courts also found that the petitioner had been religiously paying the private respondent
US$750 per month from January 1998 and even during the pendency of the case before the trial court and that the
private respondent had accepted all these monthly payments.
With these findings of facts, it has become glaringly obvious that when the complaint for a sum of money and
damages was filed with the trial court on 2 February 1999, no cause of action has as yet existed because the
petitioner had not committed any act in violation of the terms of the three promissory notes as modified by the
renegotiation in December 1997. Without a cause of action, the private respondent had no right to maintain an
action in court, and the trial court should have therefore dismissed his complaint.
Despite its finding that the petitioner corporation did not violate the modified terms of the three promissory notes
and that the payment of the principal loans were not yet due when the complaint was filed, the trial court did not
dismiss the complaint, citing Section 5, Rule 10 of the 1997 Rules of Civil Procedure, which reads:
Section 5. Amendment to conform to or authorize presentation of evidence. — When issues not raised by the
pleadings are tried with the express or implied consent of the parties, they shall be treated in all respects as if they
had been raised in the pleadings. Such amendment of the pleadings as may be necessary to cause them to conform
to the evidence and to raise these issues may be made upon motion of any party at any time, even after judgment;
but failure to amend does not affect the result of the trial of these issues. If evidence is objected to at the trial on the
ground that it is not within the issues made by the pleadings, the court may allow the pleadings to be amended and
shall do so with liberality if the presentation of the merits of the action and the ends of substantial justice will be
subserved thereby. The court may grant a continuance to enable the amendment to be made.
According to the trial court, and sustained by the Court of Appeals, this Section allows a complaint that does not
state a cause of action to be cured by evidence presented without objection during the trial. Thus, it ruled that even
if the private respondent had no cause of action when he filed the complaint for a sum of money and damages
because none of the three promissory notes was due yet, he could nevertheless recover on the first two promissory
notes dated 7 August 1996 and 14 March 1997, which became due during the pendency of the case in view of the
introduction of evidence of their maturity during the trial.
Such interpretation of Section 5, Rule 10 of the 1997 Rules of Civil Procedure is erroneous.
Amendments of pleadings are allowed under Rule 10 of the 1997 Rules of Civil Procedure in order that the actual
merits of a case may be determined in the most expeditious and inexpensive manner without regard to
technicalities, and that all other matters included in the case may be determined in a single proceeding, thereby
avoiding multiplicity of suits.12 Section 5 thereof applies to situations wherein evidence not within the issues raised in
the pleadings is presented by the parties during the trial, and to conform to such evidence the pleadings are
subsequently amended on motion of a party. Thus, a complaint which fails to state a cause of action may be cured by
evidence presented during the trial.
However, the curing effect under Section 5 is applicable only if a cause of action in fact exists at the time the
complaint is filed, but the complaint is defective for failure to allege the essential facts. For example, if a complaint
failed to allege the fulfillment of a condition precedent upon which the cause of action depends, evidence showing
that such condition had already been fulfilled when the complaint was filed may be presented during the trial, and
the complaint may accordingly be amended thereafter. 13 Thus, in Roces v. Jalandoni,14 this Court upheld the trial court
in taking cognizance of an otherwise defective complaint which was later cured by the testimony of the plaintiff
during the trial. In that case, there was in fact a cause of action and the only problem was the insufficiency of the
allegations in the complaint. This ruling was reiterated in Pascua v. Court of Appeals.15
It thus follows that a complaint whose cause of action has not yet accrued cannot be cured or remedied by an
amended or supplemental pleading alleging the existence or accrual of a cause of action while the case is
pending.16 Such an action is prematurely brought and is, therefore, a groundless suit, which should be dismissed by
the court upon proper motion seasonably filed by the defendant. The underlying reason for this rule is that a person
should not be summoned before the public tribunals to answer for complaints which are immature. As this Court
eloquently said in Surigao Mine Exploration Co., Inc. v. Harris:17
It is a rule of law to which there is, perhaps, no exception, either at law or in equity, that to recover at all there must
be some cause of action at the commencement of the suit. As observed by counsel for appellees, there are reasons
of public policy why there should be no needless haste in bringing up litigation, and why people who are in no default
and against whom there is yet no cause of action should not be summoned before the public tribunals to answer
complaints which are groundless. We say groundless because if the action is immature, it should not be entertained,
and an action prematurely brought is a groundless suit.
It is true that an amended complaint and the answer thereto take the place of the originals which are thereby
regarded as abandoned (Reynes vs. Compañía General de Tabacos [1912], 21 Phil. 416; Ruyman and Farris vs.
Director of Lands [1916], 34 Phil., 428) and that "the complaint and answer having been superseded by the amended
complaint and answer thereto, and the answer to the original complaint not having been presented in evidence as an
exhibit, the trial court was not authorized to take it into account." (Bastida vs. Menzi & Co. [1933], 58 Phil., 188.) But
in none of these cases or in any other case have we held that if a right of action did not exist when the original
complaint was filed, one could be created by filing an amended complaint. In some jurisdictions in the United States
what was termed an "imperfect cause of action" could be perfected by suitable amendment (Brown vs. Galena
Mining & Smelting Co., 32 Kan., 528; Hooper vs. City of Atlanta, 26 Ga. App., 221) and this is virtually permitted in
Banzon and Rosauro vs. Sellner ([1933], 58 Phil., 453); Asiatic Potroleum [sic] Co. vs. Veloso ([1935], 62 Phil., 683);
and recently in Ramos vs. Gibbon (38 Off. Gaz., 241). That, however, which is no cause of action whatsoever cannot
by amendment or supplemental pleading be converted into a cause of action: Nihil de re accrescit ei qui nihil in re
quando jus accresceret habet.
We are therefore of the opinion, and so hold, that unless the plaintiff has a valid and subsisting cause of action at
the time his action is commenced, the defect cannot be cured or remedied by the acquisition or accrual of one
while the action is pending, and a supplemental complaint or an amendment setting up such after-accrued cause
of action is not permissible. (Emphasis ours).
Hence, contrary to the holding of the trial court and the Court of Appeals, the defect of lack of cause of action at the
commencement of this suit cannot be cured by the accrual of a cause of action during the pendency of this case
arising from the alleged maturity of two of the promissory notes on 7 August 1999 and 14 March 2000.
Anent the issue of novation, this Court observes that the petitioner corporation argues the existence of novation
based on its own version of what transpired during the renegotiation of the three promissory notes in December
1997. By using its own version of facts, the petitioner is, in a way, questioning the findings of facts of the trial court
and the Court of Appeals.
As a rule, the findings of fact of the trial court and the Court of Appeals are final and conclusive and cannot be
reviewed on appeal to the Supreme Court 18 as long as they are borne out by the record or are based on substantial
evidence.19 The Supreme Court is not a trier of facts, its jurisdiction being limited to reviewing only errors of law that
may have been committed by the lower courts. Among the exceptions is when the finding of fact of the trial court or
the Court of Appeals is not supported by the evidence on record or is based on a misapprehension of facts. Such
exception obtains in the present case.20
This Court finds to be contrary to the evidence on record the finding of both the trial court and the Court of Appeals
that the renegotiation in December 1997 resulted in the reduction of the interest from 15% to 6% per annum and
that the monthly payments of US$750 made by the petitioner were for the reduced interests.
It is worthy to note that the cash voucher dated January 1998 21 states that the payment of US$750 represents
"INVESTMENT PAYMENT." All the succeeding cash vouchers describe the payments from February 1998 to September
1999 as "CAPITAL REPAYMENT."22 All these cash vouchers served as receipts evidencing private respondent’s
acknowledgment of the payments made by the petitioner: two of which were signed by the private respondent
himself and all the others were signed by his representatives. The private respondent even identified and confirmed
the existence of these receipts during the hearing. 23 Significantly, cognizant of these receipts, the private respondent
applied these payments to the three consolidated principal loans in the summary of payments he submitted to the
court.24
Under Article 1253 of the Civil Code, if the debt produces interest, payment of the principal shall not be deemed to
have been made until the interest has been covered. In this case, the private respondent would not have signed the
receipts describing the payments made by the petitioner as "capital repayment" if the obligation to pay the interest
was still subsisting. The receipts, as well as private respondent’s summary of payments, lend credence to petitioner’s
claim that the payments were for the principal loans and that the interests on the three consolidated loans were
waived by the private respondent during the undisputed renegotiation of the loans on account of the business
reverses suffered by the petitioner at the time.
There was therefore a novation of the terms of the three promissory notes in that the interest was waived and the
principal was payable in monthly installments of US$750. Alterations of the terms and conditions of the obligation
would generally result only in modificatory novation unless such terms and conditions are considered to be the
essence of the obligation itself.25 The resulting novation in this case was, therefore, of the modificatory type, not the
extinctive type, since the obligation to pay a sum of money remains in force.
Thus, since the petitioner did not renege on its obligation to pay the monthly installments conformably with their
new agreement and even continued paying during the pendency of the case, the private respondent had no cause of
action to file the complaint. It is only upon petitioner’s default in the payment of the monthly amortizations that a
cause of action would arise and give the private respondent a right to maintain an action against the petitioner.
Lastly, the petitioner contends that the Court of Appeals obstinately included its President Infante and Vice-President
Hegerty as appellants even if they did not appeal the trial court’s decision since they were found to be not personally
liable for the obligation of the petitioner. Indeed, the Court of Appeals erred in referring to them as defendants-
appellants; nevertheless, that error is no cause for alarm because its ruling was clear that the petitioner corporation
was the one solely liable for its obligation. In fact, the Court of Appeals affirmed in toto the decision of the trial court,
which means that it also upheld the latter’s ruling that Hegerty and Infante were not personally liable for the
pecuniary obligations of the petitioner to the private respondent.
In sum, based on our disquisition on the lack of cause of action when the complaint for sum of money and damages
was filed by the private respondent, the petition in the case at bar is impressed with merit.
WHEREFORE, the petition is hereby GRANTED. The Decision of 5 September 2003 of the Court of Appeals in CA-G.R.
CV No. 68109, which affirmed the Decision of 5 May 2000 of the Regional Trial Court of Baguio, Branch 59, granting in
part private respondent’s complaint for sum of money and damages, and its Resolution of 4 December 2003, which
denied petitioner’s motion for reconsideration are hereby REVERSED and SET ASIDE. The complaint docketed as Civil
Case No. 4282-R is hereby DISMISSED for lack of cause of action.
No costs.
SO ORDERED.
LILIA ADA, LUZ B. ADANZA, FLORA BAYLON, REMO BAYLON, JOSE BAYLON, ERIC BAYLON, FLORENTINO BAYLON,
and MA. RUBY BAYLON, Petitioners vs. FLORANTE BAYLON, Respondent.
G.R. No. 182435 August 13, 2012
Before this Court is a petition for review on certiorari under Rule 45 of the Rules of Court seeking to annul and set
aside the Decision1 dated October 26, 2007 rendered by the Court of Appeals (CA) in CA-G.R. CV No. 01746. The
assailed decision partially reversed and set aside the Decision 2 dated October 20, 2005 issued ~y the Regional Trial
Court (RTC), Tan jay City, Negros Oriental, Branch 43 in Civil Case No. 11657.
The Antecedent Facts
This case involves the estate of spouses Florentino Baylon and Maximina Elnas Baylon (Spouses Baylon) who died on
November 7, 1961 and May 5, 1974, respectively. 3 At the time of their death, Spouses Baylon were survived by their
legitimate children, namely, Rita Baylon (Rita), Victoria Baylon (Victoria), Dolores Baylon (Dolores), Panfila Gomez
(Panfila), Ramon Baylon (Ramon) and herein petitioner Lilia B. Ada (Lilia).
Dolores died intestate and without issue on August 4, 1976. Victoria died on November 11, 1981 and was survived by
her daughter, herein petitioner Luz B. Adanza. Ramon died intestate on July 8, 1989 and was survived by herein
respondent Florante Baylon (Florante), his child from his first marriage, as well as by petitioner Flora Baylon, his
second wife, and their legitimate children, namely, Ramon, Jr. and herein petitioners Remo, Jose, Eric, Florentino and
Ma. Ruby, all surnamed Baylon.
On July 3, 1996, the petitioners filed with the RTC a Complaint 4 for partition, accounting and damages against
Florante, Rita and Panfila. They alleged therein that Spouses Baylon, during their lifetime, owned 43 parcels of
land5all situated in Negros Oriental. After the death of Spouses Baylon, they claimed that Rita took possession of the
said parcels of land and appropriated for herself the income from the same. Using the income produced by the said
parcels of land, Rita allegedly purchased two parcels of land, Lot No. 4709 6 and half of Lot No. 4706,7 situated in
Canda-uay, Dumaguete City. The petitioners averred that Rita refused to effect a partition of the said parcels of land.
In their Answer,8 Florante, Rita and Panfila asserted that they and the petitioners co-owned 22 9 out of the 43 parcels
of land mentioned in the latter’s complaint, whereas Rita actually owned 10 parcels of land 10 out of the 43 parcels
which the petitioners sought to partition, while the remaining 11 parcels of land are separately owned by Petra
Cafino Adanza,11 Florante,12 Meliton Adalia,13 Consorcia Adanza,14 Lilia15 and Santiago Mendez.16 Further, they claimed
that Lot No. 4709 and half of Lot No. 4706 were acquired by Rita using her own money. They denied that Rita
appropriated solely for herself the income of the estate of Spouses Baylon, and expressed no objection to the
partition of the estate of Spouses Baylon, but only with respect to the co-owned parcels of land.
During the pendency of the case, Rita, through a Deed of Donation dated July 6, 1997, conveyed Lot No. 4709 and
half of Lot No. 4706 to Florante. On July 16, 2000, Rita died intestate and without any issue. Thereafter, learning of
the said donation inter vivos in favor of Florante, the petitioners filed a Supplemental Pleading 17 dated February 6,
2002, praying that the said donation in favor of the respondent be rescinded in accordance with Article 1381(4) of
the Civil Code. They further alleged that Rita was already sick and very weak when the said Deed of Donation was
supposedly executed and, thus, could not have validly given her consent thereto.
Florante and Panfila opposed the rescission of the said donation, asserting that Article 1381(4) of the Civil Code
applies only when there is already a prior judicial decree on who between the contending parties actually owned the
properties under litigation.18
The RTC Decision
On October 20, 2005, the RTC rendered a Decision, 19 the decretal portion of which reads:
Wherefore judgment is hereby rendered:
(1) declaring the existence of co-ownership over parcels nos. 1, 2, 3, 5, 7, 10, 13, 14, 16, 17, 18, 26, 29, 30,
33, 34, 35, 36, 40 and 41 described in the complaint;
(2) directing that the above mentioned parcels of land be partitioned among the heirs of Florentino Baylon
and Maximina Baylon;
(3) declaring a co-ownership on the properties of Rita Baylon namely parcels no[s]. 6, 11, 12, 20, 24, 27, 31,
32, 39 and 42 and directing that it shall be partitioned among her heirs who are the plaintiffs and defendant
in this case;
(4) declaring the donation inter vivos rescinded without prejudice to the share of Florante Baylon to the
estate of Rita Baylon and directing that parcels nos. 1 and 2 paragraph V of the complaint be included in the
division of the property as of Rita Baylon among her heirs, the parties in this case;
(5) excluding from the co-ownership parcels nos. 20, 21, 22, 9, 43, 4, 8, 19 and 37.
Considering that the parties failed to settle this case amicably and could not agree on the partition, the parties are
directed to nominate a representative to act as commissioner to make the partition. He shall immediately take [his]
oath of office upon [his] appointment. The commissioner shall make a report of all the proceedings as to the
partition within fifteen (15) days from the completion of this partition. The parties are given ten (10) days within
which to object to the report after which the Court shall act on the commissioner report.
SO ORDERED.20 (Emphasis ours)
The RTC held that the death of Rita during the pendency of the case, having died intestate and without any issue, had
rendered the issue of ownership insofar as parcels of land which she claims as her own moot since the parties below
are the heirs to her estate. Thus, the RTC regarded Rita as the owner of the said 10 parcels of land and, accordingly,
directed that the same be partitioned among her heirs. Nevertheless, the RTC rescinded the donation inter vivos of
Lot No. 4709 and half of Lot No. 4706 in favor of Florante. In rescinding the said donation inter vivos, the RTC
explained that:
However, with respect to lot nos. 4709 and 4706 which [Rita] had conveyed to Florante Baylon by way of donation
inter vivos, the plaintiffs in their supplemental pleadings (sic) assailed the same to be rescissible on the ground that it
was entered into by the defendant Rita Baylon without the knowledge and approval of the litigants [or] of competent
judicial authority. The subject parcels of lands are involved in the case for which plaintiffs have asked the Court to
partition the same among the heirs of Florentino Baylon and Maximina Elnas.
Clearly, the donation inter vivos in favor of Florante Baylon was executed to prejudice the plaintiffs’ right to succeed
to the estate of Rita Baylon in case of death considering that as testified by Florante Baylon, Rita Baylon was very
weak and he tried to give her vitamins x x x. The donation inter vivos executed by Rita Baylon in favor of Florante
Baylon is rescissible for the reason that it refers to the parcels of land in litigation x x x without the knowledge and
approval of the plaintiffs or of this Court. However, the rescission shall not affect the share of Florante Baylon to the
estate of Rita Baylon.21
Florante sought reconsideration of the Decision dated October 20, 2005 of the RTC insofar as it rescinded the
donation of Lot No. 4709 and half of Lot No. 4706 in his favor. 22 He asserted that, at the time of Rita’s death on July
16, 2000, Lot No. 4709 and half of Lot No. 4706 were no longer part of her estate as the same had already been
conveyed to him through a donation inter vivos three years earlier. Thus, Florante maintained that Lot No. 4709 and
half of Lot No. 4706 should not be included in the properties that should be partitioned among the heirs of Rita.
On July 28, 2006, the RTC issued an Order 23 which denied the motion for reconsideration filed by Florante.
The CA Decision
24
On appeal, the CA rendered a Decision dated October 26, 2007, the dispositive portion of which reads:
WHEREFORE, the Decision dated October 20, 2005 and Order dated July 28, 2006 are REVERSEDand SET
ASIDE insofar as they decreed the rescission of the Deed of Donation dated July 6, 1997 and the inclusion of lot no.
4709 and half of lot no. 4706 in the estate of Rita Baylon. The case is REMANDED to the trial court for the
determination of ownership of lot no. 4709 and half of lot no. 4706.
SO ORDERED.25
The CA held that before the petitioners may file an action for rescission, they must first obtain a favorable judicial
ruling that Lot No. 4709 and half of Lot No. 4706 actually belonged to the estate of Spouses Baylon and not to Rita.
Until then, the CA asserted, an action for rescission is premature. Further, the CA ruled that the petitioners’ action for
rescission cannot be joined with their action for partition, accounting and damages through a mere supplemental
pleading. Thus:
If Lot No. 4709 and half of Lot No. 4706 belonged to the Spouses’ estate, then Rita Baylon’s donation thereof in favor
of Florante Baylon, in excess of her undivided share therein as co-heir, is void. Surely, she could not have validly
disposed of something she did not own. In such a case, an action for rescission of the donation may, therefore,
prosper.
If the lots, however, are found to have belonged exclusively to Rita Baylon, during her lifetime, her donation thereof
in favor of Florante Baylon is valid. For then, she merely exercised her ownership right to dispose of what legally
belonged to her. Upon her death, the lots no longer form part of her estate as their ownership now pertains to
Florante Baylon. On this score, an action for rescission against such donation will not prosper. x x x.
Verily, before plaintiffs-appellees may file an action for rescission, they must first obtain a favorable judicial ruling
that lot no. 4709 and half of lot no. 4706 actually belonged to the estate of Spouses Florentino and Maximina Baylon,
and not to Rita Baylon during her lifetime. Until then, an action for rescission is premature. For this matter, the
applicability of Article 1381, paragraph 4, of the New Civil Code must likewise await the trial court’s resolution of the
issue of ownership.
Be that as it may, an action for rescission should be filed by the parties concerned independent of the proceedings
below. The first cannot simply be lumped up with the second through a mere supplemental pleading. 26 (Citation
omitted)
The petitioners sought reconsideration27 of the Decision dated October 26, 2007 but it was denied by the CA in its
Resolution28 dated March 6, 2008.
Hence, this petition.
Issue
The lone issue to be resolved by this Court is whether the CA erred in ruling that the donation inter vivos of Lot No.
4709 and half of Lot No. 4706 in favor of Florante may only be rescinded if there is already a judicial determination
that the same actually belonged to the estate of Spouses Baylon.
The Court’s Ruling
The petition is partly meritorious.
Procedural Matters
Before resolving the lone substantive issue in the instant case, this Court deems it proper to address certain
procedural matters that need to be threshed out which, by laxity or otherwise, were not raised by the parties herein.
Misjoinder of Causes of Action
The complaint filed by the petitioners with the RTC involves two separate, distinct and independent actions –
partition and rescission. First, the petitioners raised the refusal of their co-heirs, Florante, Rita and Panfila, to
partition the properties which they inherited from Spouses Baylon. Second, in their supplemental pleading, the
petitioners assailed the donation inter vivos of Lot No. 4709 and half of Lot No. 4706 made by Rita in favor of
Florante pendente lite.
The actions of partition and
rescission cannot be joined in a
single action.
By a joinder of actions, or more properly, a joinder of causes of action is meant the uniting of two or more demands
or rights of action in one action, the statement of more than one cause of action in a declaration. It is the union of
two or more civil causes of action, each of which could be made the basis of a separate suit, in the same complaint,
declaration or petition. A plaintiff may under certain circumstances join several distinct demands, controversies or
rights of action in one declaration, complaint or petition. 29
The objectives of the rule or provision are to avoid a multiplicity of suits where the same parties and subject matter
are to be dealt with by effecting in one action a complete determination of all matters in controversy and litigation
between the parties involving one subject matter, and to expedite the disposition of litigation at minimum cost. The
provision should be construed so as to avoid such multiplicity, where possible, without prejudice to the rights of the
litigants.30
Nevertheless, while parties to an action may assert in one pleading, in the alternative or otherwise, as many causes
of action as they may have against an opposing party, such joinder of causes of action is subject to the condition,
inter alia, that the joinder shall not include special civil actions governed by special rules. 31
Here, there was a misjoinder of causes of action. The action for partition filed by the petitioners could not be joined
with the action for the rescission of the said donation inter vivos in favor of Florante. Lest it be overlooked, an action
for partition is a special civil action governed by Rule 69 of the Rules of Court while an action for rescission is an
ordinary civil action governed by the ordinary rules of civil procedure. The variance in the procedure in the special
civil action of partition and in the ordinary civil action of rescission precludes their joinder in one complaint or their
being tried in a single proceeding to avoid confusion in determining what rules shall govern the conduct of the
proceedings as well as in the determination of the presence of requisite elements of each particular cause of action. 32
A misjoined cause of action, if not
severed upon motion of a party or
by the court sua sponte, may be
adjudicated by the court together
with the other causes of action.
Nevertheless, misjoinder of causes of action is not a ground for dismissal. Indeed, the courts have the power, acting
upon the motion of a party to the case or sua sponte, to order the severance of the misjoined cause of action to be
proceeded with separately.33 However, if there is no objection to the improper joinder or the court did not motu
proprio direct a severance, then there exists no bar in the simultaneous adjudication of all the erroneously joined
causes of action. On this score, our disquisition in Republic of the Philippines v. Herbieto34 is instructive, viz:
This Court, however, disagrees with petitioner Republic in this regard. This procedural lapse committed by the
respondents should not affect the jurisdiction of the MTC to proceed with and hear their application for registration
of the Subject Lots.
xxxx
Considering every application for land registration filed in strict accordance with the Property Registration Decree as
a single cause of action, then the defect in the joint application for registration filed by the respondents with the MTC
constitutes a misjoinder of causes of action and parties. Instead of a single or joint application for registration,
respondents Jeremias and David, more appropriately, should have filed separate applications for registration of Lots
No. 8422 and 8423, respectively.
Misjoinder of causes of action and parties do not involve a question of jurisdiction of the court to hear and proceed
with the case. They are not even accepted grounds for dismissal thereof. Instead, under the Rules of Court, the
misjoinder of causes of action and parties involve an implied admission of the court’s jurisdiction. It acknowledges
the power of the court, acting upon the motion of a party to the case or on its own initiative, to order the severance
of the misjoined cause of action, to be proceeded with separately (in case of misjoinder of causes of action); and/or
the dropping of a party and the severance of any claim against said misjoined party, also to be proceeded with
separately (in case of misjoinder of parties).35 (Citations omitted)
It should be emphasized that the foregoing rule only applies if the court trying the case has jurisdiction over all of the
causes of action therein notwithstanding the misjoinder of the same. If the court trying the case has no jurisdiction
over a misjoined cause of action, then such misjoined cause of action has to be severed from the other causes of
action, and if not so severed, any adjudication rendered by the court with respect to the same would be a nullity.
Here, Florante posed no objection, and neither did the RTC direct the severance of the petitioners’ action for
rescission from their action for partition. While this may be a patent omission on the part of the RTC, this does not
constitute a ground to assail the validity and correctness of its decision. The RTC validly adjudicated the issues raised
in the actions for partition and rescission filed by the petitioners.
Asserting a New Cause of Action in a Supplemental Pleading
In its Decision dated October 26, 2007, the CA pointed out that the said action for rescission should have been filed
by the petitioners independently of the proceedings in the action for partition. It opined that the action for rescission
could not be lumped up with the action for partition through a mere supplemental pleading.
We do not agree.
A supplemental pleading may raise
a new cause of action as long as it
has some relation to the original
cause of action set forth in the
original complaint.
Section 6, Rule 10 of the Rules of Court reads:
Sec. 6. Supplemental Pleadings. – Upon motion of a party the court may, upon reasonable notice and upon such
terms as are just, permit him to serve a supplemental pleading setting forth transactions, occurrences or events
which have happened since the date of the pleading sought to be supplemented. The adverse party may plead
thereto within ten (10) days from notice of the order admitting the supplemental pleading.
In Young v. Spouses Sy,36 this Court had the opportunity to elucidate on the purpose of a supplemental pleading.
Thus:
As its very name denotes, a supplemental pleading only serves to bolster or add something to the primary pleading.
A supplement exists side by side with the original. It does not replace that which it supplements. Moreover, a
supplemental pleading assumes that the original pleading is to stand and that the issues joined with the original
pleading remained an issue to be tried in the action. It is but a continuation of the complaint. Its usual office is to set
up new facts which justify, enlarge or change the kind of relief with respect to the same subject matter as the
controversy referred to in the original complaint.
The purpose of the supplemental pleading is to bring into the records new facts which will enlarge or change the kind
of relief to which the plaintiff is entitled; hence, any supplemental facts which further develop the original right of
action, or extend to vary the relief, are available by way of supplemental complaint even though they themselves
constitute a right of action.37 (Citations omitted and emphasis ours)
Thus, a supplemental pleading may properly allege transactions, occurrences or events which had transpired after
the filing of the pleading sought to be supplemented, even if the said supplemental facts constitute another cause of
action.
Admittedly, in Leobrera v. Court of Appeals,38 we held that a supplemental pleading must be based on matters arising
subsequent to the original pleading related to the claim or defense presented therein, and founded on the same
cause of action. We further stressed therein that a supplemental pleading may not be used to try a new cause of
action.
However, in Planters Development Bank v. LZK Holdings and Development Corp., 39 we clarified that, while a matter
stated in a supplemental complaint should have some relation to the cause of action set forth in the original
pleading, the fact that the supplemental pleading technically states a new cause of action should not be a bar to its
allowance but only a matter that may be considered by the court in the exercise of its discretion. In such cases, we
stressed that a broad definition of "cause of action" should be applied.
Here, the issue as to the validity of the donation inter vivos of Lot No. 4709 and half of Lot No. 4706 made by Rita in
favor of Florante is a new cause of action that occurred after the filing of the original complaint. However, the
petitioners’ prayer for the rescission of the said donation inter vivos in their supplemental pleading is germane to,
and is in fact, intertwined with the cause of action in the partition case. Lot No. 4709 and half of Lot No. 4706 are
included among the properties that were sought to be partitioned.
The petitioners’ supplemental pleading merely amplified the original cause of action, on account of the gratuitous
conveyance of Lot No. 4709 and half of Lot No. 4706 after the filing of the original complaint and prayed for
additional reliefs, i.e., rescission. Indeed, the petitioners claim that the said lots form part of the estate of Spouses
Baylon, but cannot be partitioned unless the gratuitous conveyance of the same is rescinded. Thus, the principal
issue raised by the petitioners in their original complaint remained the same.
Main Issue: Propriety of Rescission
After having threshed out the procedural matters, we now proceed to adjudicate the substantial issue presented by
the instant petition.
The petitioners assert that the CA erred in remanding the case to the RTC for the determination of ownership of Lot
No. 4709 and half of Lot No. 4706. They maintain that the RTC aptly rescinded the said donation inter vivos of Lot No.
4709 and half of Lot No. 4706 pursuant to Article 1381(4) of the Civil Code.
In his Comment,40 Florante asserts that before the petitioners may file an action for rescission, they must first obtain a
favorable judicial ruling that Lot No. 4709 and half of Lot No. 4706 actually belonged to the estate of Spouses Baylon.
Until then, Florante avers that an action for rescission would be premature.
The petitioners’ contentions are well-taken.
The resolution of the instant dispute is fundamentally contingent upon a determination of whether the donation
inter vivos of Lot No. 4709 and half of Lot No. 4706 in favor of Florante may be rescinded pursuant to Article 1381(4)
of the Civil Code on the ground that the same was made during the pendency of the action for partition with the
RTC.
Rescission is a remedy to address
the damage or injury caused to the
contracting parties or third
persons.
Rescission is a remedy granted by law to the contracting parties and even to third persons, to secure the reparation
of damages caused to them by a contract, even if it should be valid, by means of the restoration of things to their
condition at the moment prior to the celebration of said contract. 41 It is a remedy to make ineffective a contract,
validly entered into and therefore obligatory under normal conditions, by reason of external causes resulting in a
pecuniary prejudice to one of the contracting parties or their creditors. 42
Contracts which are rescissible are valid contracts having all the essential requisites of a contract, but by reason of
injury or damage caused to either of the parties therein or to third persons are considered defective and, thus, may
be rescinded.
The kinds of rescissible contracts, according to the reason for their susceptibility to rescission, are the following: first,
those which are rescissible because of lesion or prejudice; 43 second, those which are rescissible on account of fraud
or bad faith;44 and third, those which, by special provisions of law, 45 are susceptible to rescission.46
Contracts which refer to things
subject of litigation is rescissible
pursuant to Article 1381(4) of the
Civil Code.
Contracts which are rescissible due to fraud or bad faith include those which involve things under litigation, if they
have been entered into by the defendant without the knowledge and approval of the litigants or of competent
judicial authority. Thus, Article 1381(4) of the Civil Code provides:
Art. 1381. The following contracts are rescissible:
xxxx
(4) Those which refer to things under litigation if they have been entered into by the defendant without the
knowledge and approval of the litigants or of competent judicial authority.
The rescission of a contract under Article 1381(4) of the Civil Code only requires the concurrence of the following:
first, the defendant, during the pendency of the case, enters into a contract which refers to the thing subject of
litigation; and second, the said contract was entered into without the knowledge and approval of the litigants or of a
competent judicial authority. As long as the foregoing requisites concur, it becomes the duty of the court to order the
rescission of the said contract.
The reason for this is simple. Article 1381(4) seeks to remedy the presence of bad faith among the parties to a case
and/or any fraudulent act which they may commit with respect to the thing subject of litigation.
When a thing is the subject of a judicial controversy, it should ultimately be bound by whatever disposition the court
shall render. The parties to the case are therefore expected, in deference to the court’s exercise of jurisdiction over
the case, to refrain from doing acts which would dissipate or debase the thing subject of the litigation or otherwise
render the impending decision therein ineffectual.
There is, then, a restriction on the disposition by the parties of the thing that is the subject of the litigation. Article
1381(4) of the Civil Code requires that any contract entered into by a defendant in a case which refers to things under
litigation should be with the knowledge and approval of the litigants or of a competent judicial authority.
Further, any disposition of the thing subject of litigation or any act which tends to render inutile the court’s
impending disposition in such case, sans the knowledge and approval of the litigants or of the court, is unmistakably
and irrefutably indicative of bad faith. Such acts undermine the authority of the court to lay down the respective
rights of the parties in a case relative to the thing subject of litigation and bind them to such determination.
It should be stressed, though, that the defendant in such a case is not absolutely proscribed from entering into a
contract which refer to things under litigation. If, for instance, a defendant enters into a contract which conveys the
thing under litigation during the pendency of the case, the conveyance would be valid, there being no definite
disposition yet coming from the court with respect to the thing subject of litigation. After all, notwithstanding that
the subject thereof is a thing under litigation, such conveyance is but merely an exercise of ownership.
This is true even if the defendant effected the conveyance without the knowledge and approval of the litigants or of a
competent judicial authority. The absence of such knowledge or approval would not precipitate the invalidity of an
otherwise valid contract. Nevertheless, such contract, though considered valid, may be rescinded at the instance of
the other litigants pursuant to Article 1381(4) of the Civil Code.
Here, contrary to the CA’s disposition, the RTC aptly ordered the rescission of the donation inter vivos of Lot No. 4709
and half of Lot No. 4706 in favor of Florante. The petitioners had sufficiently established the presence of the
requisites for the rescission of a contract pursuant to Article 1381(4) of the Civil Code. It is undisputed that, at the
time they were gratuitously conveyed by Rita, Lot No. 4709 and half of Lot No. 4706 are among the properties that
were the subject of the partition case then pending with the RTC. It is also undisputed that Rita, then one of the
defendants in the partition case with the RTC, did not inform nor sought the approval from the petitioners or of the
RTC with regard to the donation inter vivos of the said parcels of land to Florante.
Although the gratuitous conveyance of the said parcels of land in favor of Florante was valid, the donation inter vivos
of the same being merely an exercise of ownership, Rita’s failure to inform and seek the approval of the petitioners or
the RTC regarding the conveyance gave the petitioners the right to have the said donation rescinded pursuant to
Article 1381(4) of the Civil Code.
Rescission under Article 1381(4) of
the Civil Code is not preconditioned
upon the judicial determination as
to the ownership of the thing
subject of litigation.
In this regard, we also find the assertion that rescission may only be had after the RTC had finally determined that the
parcels of land belonged to the estate of Spouses Baylon intrinsically amiss. The petitioners’ right to institute the
action for rescission pursuant to Article 1381(4) of the Civil Code is not preconditioned upon the RTC’s determination
as to the ownership of the said parcels of land.
It bears stressing that the right to ask for the rescission of a contract under Article 1381(4) of the Civil Code is not
contingent upon the final determination of the ownership of the thing subject of litigation. The primordial purpose of
Article 1381(4) of the Civil Code is to secure the possible effectivity of the impending judgment by a court with
respect to the thing subject of litigation. It seeks to protect the binding effect of a court’s impending adjudication vis-
à-vis the thing subject of litigation regardless of which among the contending claims therein would subsequently be
upheld. Accordingly, a definitive judicial determination with respect to the thing subject of litigation is not a condition
sine qua non before the rescissory action contemplated under Article 1381(4) of the Civil Code may be instituted.
Moreover, conceding that the right to bring the rescissory action pursuant to Article 1381(4) of the Civil Code is
preconditioned upon a judicial determination with regard to the thing subject litigation, this would only bring about
the very predicament that the said provision of law seeks to obviate. Assuming arguendo that a rescissory action
under Article 1381(4) of the Civil Code could only be instituted after the dispute with respect to the thing subject of
litigation is judicially determined, there is the possibility that the same may had already been conveyed to third
persons acting in good faith, rendering any judicial determination with regard to the thing subject of litigation
illusory. Surely, this paradoxical eventuality is not what the law had envisioned.
Even if the donation inter vivos is
validly rescinded, a determination
as to the ownership of the subject
parcels of land is still necessary.
Having established that the RTC had aptly ordered the rescission of the said donation inter vivos in favor of Florante,
the issue that has to be resolved by this Court is whether there is still a need to determine the ownership of Lot No.
4709 and half of Lot No. 4706.
In opting not to make a determination as to the ownership of Lot No. 4709 and half of Lot No. 4706, the RTC
reasoned that the parties in the proceedings before it constitute not only the surviving heirs of Spouses Baylon but
the surviving heirs of Rita as well. As intimated earlier, Rita died intestate during the pendency of the proceedings
with the RTC without any issue, leaving the parties in the proceedings before the RTC as her surviving heirs. Thus, the
RTC insinuated, a definitive determination as to the ownership of the said parcels of land is unnecessary since, in any
case, the said parcels of land would ultimately be adjudicated to the parties in the proceedings before it.
We do not agree.
Admittedly, whoever may be adjudicated as the owner of Lot No. 4709 and half of Lot No. 4706, be it Rita or Spouses
Baylon, the same would ultimately be transmitted to the parties in the proceedings before the RTC as they are the
only surviving heirs of both Spouses Baylon and Rita. However, the RTC failed to realize that a definitive adjudication
as to the ownership of Lot No. 4709 and half of Lot No. 4706 is essential in this case as it affects the authority of the
RTC to direct the partition of the said parcels of land. Simply put, the RTC cannot properly direct the partition of Lot
No. 4709 and half of Lot No. 4706 until and unless it determines that the said parcels of land indeed form part of the
estate of Spouses Baylon.
It should be stressed that the partition proceedings before the RTC only covers the properties co-owned by the
parties therein in their respective capacity as the surviving heirs of Spouses Baylon. Hence, the authority of the RTC
to issue an order of partition in the proceedings before it only affects those properties which actually belonged to the
estate of Spouses Baylon.
In this regard, if Lot No. 4709 and half of Lot No. 4706, as unwaveringly claimed by Florante, are indeed exclusively
owned by Rita, then the said parcels of land may not be partitioned simultaneously with the other properties subject
of the partition case before the RTC. In such case, although the parties in the case before the RTC are still co-owners
of the said parcels of land, the RTC would not have the authority to direct the partition of the said parcels of land as
the proceedings before it is only concerned with the estate of Spouses Baylon.
WHEREFORE, in consideration of the foregoing disquisitions, the petition is PARTIALLY GRANTED. The Decision dated
October 26, 2007 issued by the Court of Appeals in CA-G.R. CV No. 01746 is MODIFIED in that the Decision dated
October 20, 2005 issued by the Regional Trial Court, Tanjay City, Negros Oriental, Branch 43 in Civil Case No. 11657,
insofar as it decreed the rescission of the Deed of Donation dated July 6, 1997 is hereby REINSTATED. The case
is REMANDED to the trial court for the determination of the ownership of Lot No. 4709 and half of Lot No. 4706 in
accordance with this Decision.
SO ORDERED.
NORLINDA MARILAG, Petitioner vs. MARCELINO MARTINEZ, Respondent.
G.R. No. 201892 JULY 22, 2015
Assailed in this petition for review on certiorari 1 are the Decision2 dated November 4, 2011 and the Resolution 3dated
May 14, 2012 of the Court of Appeals (CA) in CA-G.R. CV No. 81258 which recalled and set aside the Orders dated
November 3, 2003 4 and January 14, 2004 5 of the Regional Trial Court (RTC) of Las Piñas City, Branch 202 (court a
quo) in Civil Case No. 980156, and reinstated the Decision 6 dated August 28, 2003 directing petitioner Norlinda S.
Marilag (petitioner) to return to respondent Marcelino B. Martinez (respondent) the latter's excess payment, plus
interest, and to pay attorney's fees and the costs of suit.
The Facts
On July 30, 1992, Rafael Martinez (Rafael), respondent's father, obtained- from petitioner a loan in the amount of
₱160,000.00, with a stipulated monthly interest of five percent ( 5% ), payable within a period of (6) months. The
loan was secured by a real estate mortgage over a parcel of land covered by Transfer Certificate of Title (TCT) No. T-
208400. Rafael failed'. to settle his obligation upon maturity and despite repeated demands, prompting petitioner to
file a Complaint for Judicial Foreclosure of Real Estate Mortgage before the RTC of Imus, Cavite, Branch 90 7(RTC-
lmus) on November 10, 1995, 8 docketed as Civil Case No. 1208-95 (judicial foreclosure case).
Rafael failed to file his answer and, upon petitioner's motion, was declared in default. After an ex parte presentation
of petitioner's evidence, the RTC-lmus issued a Decision 9 dated January 30, 1998, (January 30, 1998 Decision) in the
foreclosure case, declaring the stipulated 5% monthly interest to be usurious and reducing the same to 12% per
annum (p.a.). Accordingly, it ordered Rafael to pay petitioner the amount of ₱229,200.00, consisting of the principal
of ₱160,000.00 and accrued interest of ₱59,200.00 from July 30, 1992 to September 30, 1995. 10 Records do not
show that this Decision had already attained finality.
Meanwhile, prior to Rafael's notice of the above decision, respondent agreed to pay Rafael's obligation to petitioner
which was pegged at ₱689,000.00. After making a total payment of ₱400,000.00, 11 he executed a promissory
note 12 dated February 20, 1998 (subject PN), binding himself to pay on or before March 31, 1998 the amount of
₱289,000.00, "representing the balance of the agreed financial obligation of [his] father to [petitioner]." 13 After
learning of the January 30, 1998 Decision, respondent refused to pay the amount covered by the subject PN despite
demands, prompting petitioner to file a complaint 14 for sum of money and damages before the court a quo on July 2,
1998, docketed as Civil Case No. 98-0156 (collection case).
Respondent filed his answer, 15 contending that petitioner has no cause of action against him. He averred that he has
fully settled Rafael's obligation and that he committed a mistake in paying more than the amount due under the loan,
i.e., the amount of ₱229,200.00 as adjudged by the RTC-Imus in the judicial foreclosure case which, thus, warranted
the return of the excess payment. He therefore prayed for the dismissal of the complaint, and interposed a
compulsory counterclaim for the release of the mortgage, the return of the excess payment, and the payment of
moral and exemplary damages, attorney's fees and litigation expenses. 16
The Court A Quo's Ruling
17
In a Decision dated August 28, 2003 (August 28, 2003 Decision), the court a quo denied recovery on the subject PN.
It found that the consideration for its execution was Rafael's indebtedness to petitioner, the extinguishment of which
necessarily results in the consequent extinguishment of the cause therefore. Considering that the RTC-Imus had
adjudged Rafael liable to petitioner only for the amount of ₱229,200.00, for which a total of ₱400,000.00 had already
been paid, the court a quo found no valid or compelling reason to allow petitioner to recover further on the subject
PN. There being an excess payment of Pl 71,000.00, it declared that a quasi-contract (in the concept of solution
indebiti) exists between the parties and, accordingly, directed petitioner to return the said amount to respondent,
plus 6% interest p.a.18 reckoned from the date of judicial demand 19 on August 6, 1998 until fully paid, and to pay
attorney's fees and the costs of suit. 20
In an Order 21 dated November 3, 2003 (November 3, 2003 Order), however, the court a quo granted petitioner's
motion for reconsideration, and recalled and set aside its August 28, 2003 Decision. It declared that the causes of
action in the collection and foreclosure cases are distinct, and respondent's failure to comply with his obligation
under the subject PN justifies petitioner to seek judicial relief. It further opined that the stipulated 5% monthly
interest is no longer usurious and is binding on respondent considering the suspension of the Usury Law pursuant to
Central Bank Circular 905, series of 1982. Accordingly, it directed respondent to pay the amount of ₱289,000.00 due
under the subject PN, plus interest at the legal rate reckoned from the last extra judicial demand on May 15, 1998,
until fully paid, as well as attorney's fees and the costs of suit. 22
Aggrieved, respondent filed a motion for reconsideration 23 which was denied in an Order 24 dated January 14, 2004,
prompting him to elevate the matter to the CA. 25
The CA Ruling
In a Decision 26 dated November 4, 2011, the CA recalled and set aside the court a quo 's November 3, 2003 and
January 14, 2004 Orders, and reinstated the August 28, 2003 Decision. It held that the doctrine of res judicata finds
application in the instant case, 27 considering that both the judicial foreclosure and collection cases were filed as a
consequence of the non-payment of Rafael's loan, which was the principal obligation secured by the real estate
mortgage and the primary consideration for the execution of the subject PN. Since res judicata only requires
substantial, not actual, identity of causes of action and/or identity of issue, 28 it ruled that the judgment in the judicial
foreclosure case relating to Rafael's obligation to petitioner is final and conclusive on the collection case.
Petitioner's motion for reconsideration was denied in a Resolution 29 dated May 14, 2012; hence, this petition.
The Issue before the Court
The essential issue for the Court's resolution is whether or not the CA committed reversible error in upholding the
dismissal of the collection case.
The Court's Ruling
The petition lacks merit.
A case is barred by prior judgment or res judicata when the following elements concur: (a) the judgment sought to
bar the new action must be final; ( b) the decision must have been rendered by a court having jurisdiction over the
subject matter and the parties; (c) the disposition of the case must be a judgment on the merits; and ( d) there must
be as between the first and second action, identity of parties, subject matter, and causes of action. 30
After a punctilious review of the records, the Court finds the principle of res judicata to be inapplicable to the present
case. This is because the records are bereft of any indication that the August 28, 2003 Decision in the judicial
foreclosure case had already attained finality, evidenced, for instance, by a copy of the entry of judgment in the said
case. Accordingly, with the very first element of res judicata missing, said principle cannot be made to obtain.
This notwithstanding, the Court holds that petitioner's prosecution of the collection case was barred, instead, by the
principle of litis pendentia in view of the substantial identity of parties and singularity of the causes of action in the
foreclosure and collection cases, such that the prior foreclosure case barred petitioner's recourse to the subsequent
collection case.
To lay down the basics, litis pendentia, as a ground for the dismissal of a civil action, refers to that situation where
in another action is pending; between the same parties for the same cause of action, such that the second action
becomes unnecessary and vexatious. For the bar of litis pendentia to be invoked, the following requisites must
concur: (a) identity of parties, or at least such parties as represent the same interests in both actions; ( b) identity of
rights asserted and relief prayed for, the relief being founded on the same facts; and ( c) the identity of the two
preceding particulars is such that any judgment rendered in the pending case, regardless of which party is successful
would amount to res judicata in the other. 31 The underlying principle of litis pendentia is the theory that a party is
not allowed to vex another more than once regarding the same subject matter and for the same cause of action. This
theory is founded on the public policy that the same subject matter should not be the subject of controversy in
courts more than once, in order that possible conflicting judgments may be avoided for the sake of the stability of
the rights and status of persons, and also to avoid the costs and expenses incident to numerous
suits. 32 Consequently, a party will not be permitted to split up a single cause of action and make it a basis for several
suits as the whole cause must be determined in one action. 33 To be sure, splitting a cause of action is a mode of
forum shopping by filing multiple cases based on the same cause of action, but with different prayers, where the
~round of dismissal is litis pendentia (or res judicata, as the case may be). 34
In this relation, it must be noted that the question of whether a cause of action is single and entire or separate is not
always easy to determine and the same must often be resolved, not by the general rules, but by reference to the
facts and circumstances of the particular case. The true rule, therefore, is whether the entire amount arises from one
and the same act or contract which must, thus, be sued for in one action, or the several parts arise from distinct and
different acts or contracts, for which a party may maintain separate suits. 35
In loan contracts secured by a real estate mortgage, the rule is that the creditor-mortgagee has a single cause of
action against the debtor-mortgagor, i.e., to recover the debt, through the filing of a personal action for collection of
sum of money or the institution of a real action to foreclose on the mortgage security. The two remedies are
alternative,36 not cumulative or successive, 37 and each remedy is complete by itself. Thus, if the creditor-mortgagee
opts to foreclose the real estate mortgage, he waives the action for the collection of the unpaid debt, 38 except only
for the recovery of whatever deficiency may remain in the outstanding obligation of the debtor-mortgagor after
deducting the bid price in the public auction sale of the mortgaged properties. 39 Accordingly, a deficiency judgment
shall only issue after it is established that the mortgaged property was sold at public auction for an amount less than
the outstanding obligation.
In the present case, records show that petitioner, as creditor-mortgagee, instituted an action for judicial foreclosure
pursuant to the provisions of Rule 68 of the Rules of Court in order to recover on Rafael's debt. In light of the
foregoing discussion, the availment of such remedy thus bars recourse to the subsequent filing of a personal action
for collection of the same debt, in this case, under the principle of litis pendentia, considering that the foreclosure
case only remains pending as it was not shown to have attained finality.
While the ensuing collection case was anchored on the promissory note executed by respondent who was not the
original debtor, the same does not constitute a separate and distinct contract of loan which would have given rise to
a separate cause of action upon breach. Notably, records are bereft of any indication that respondent's agreement to
pay Rafael's loan obligation and the execution of the subject PN extinguished by novation 40 the contract of loan
between Rafael and petitioner, in the absence of express agreement or any act of equal import. Well-settled is the
rule that novation is never presumed, but must be clearly and unequivocally shown. Thus, in order for a new
agreement to supersede the old one, the parties to a contract must expressly agree that they are abrogating their old
contract in favor of a new one, 41 which was not shown here.
On the contrary, it is significant to point out that: (a) the consideration for the subject PN was the same consideration
that supported the original loan obligation of Rafael; (b) respondent merely assumed to pay Rafael's remaining
unpaid balance in the latter's behalf, i.e., as Rafael's agent or representative; 42 and (c) the subject PN was executed
after respondent had assumed to pay Rafael's obligation and made several payments thereon. Case law states that
the fact that the creditor accepts payments from a third person, who has assumed the obligation, will result merely
in the addition of debtors, not novation, and the creditor may enforce the obligation against both debtors. 43 for
ready reference, the subject PN reads in full:
February 20, 1998
PROMISSORY NOTE
₱289, 000.00
===========
I, MARCELINO B. MARTINEZ son of Mr. RAFAEL MARTINEZ, of legal age, Filipino, married and a resident of No. 091 Anabu I-A, Imus, Cavite, by
these presents do hereby specifically and categorically PROMISE, UNDERTAKE and bind myself in behalf of my father, to pay to Miss NORLINDA
S. MARILAG, Mortgagee-Creditor of my said father, the sum of TWO HUNDRED EIGHTY NINE THOUSAND PESOS (₱289,000.00), Philippine
Currency, on or before MARCH 31, 1998, representing the balance of the agreed financial obligation of my said father to her.
Executed at Pamplona I, Las Piñas City, Metro Manila, this 20th day of February, 1998.
Sgd. MARCELINO B. MARTINEZ (Promissory )
Petitioner's contention that the judicial foreclosure and collection cases enforce independent rights 45 must,
therefore, fail because the Deed of Real Estate Mortgage 46 and the subject PN both refer to one and the same
obligation, i.e., Rafael's loan obligation. As such, there exists only one cause of action for a single breach of that
obligation. Petitioner cannot split her cause of action on Rafael's unpaid loan obligation by filing a petition for the
judicial foreclosure of the real estate mortgage covering the said loan, and, thereafter, a personal action for the
collection of the unpaid balance of said obligation not comprising a deficiency arising from foreclosure, without
violating the proscription against splitting a single cause of action, where the ground for dismissal is either res
judicata or litis pendentia, as in this case.
47
As elucidated by this Court in the landmark case of Bachrach Motor Co., Inc. v. lcaranga!.
For non-payment of a note secured by mortgage, the creditor has a single cause of action against the debtor. This
single cause of action consists in the recovery of the credit with execution of the security. In other words, the creditor
in his action may make two demands, the payment of the debt and the foreclosure · of his mortgage. But both
demands arise from the same cause, the nonpayment of the debt, and, for that reason, they constitute a single cause
of action. Though the debt and the mortgage constitute separate agreements, the latter is subsidiary to the former,
and both refer to one and the same obligation. Consequently, there exists only one cause of action for a single breach
of that obligation. Plaintiff. then, by applying the rule above stated, cannot split up his single cause of action by filing
a complaint (or payment of the debt, and thereafter another complaint (or foreclosure of the mortgage. If he does
so, the filing of the first complaint will bar the subsequent complaint. By allowing the creditor to file two separate
complaints simultaneously or successively, one to recover his credit and another to foreclose his mortgage, we will, in
effect, be authorizing him plural redress for a single breach of contract at so much cost to the courts and with so
much vexation and oppression to the debtor. (Emphases and underscoring supplied)
Further on the point, the fact that no foreclosure sale appears to have been conducted is of no moment because the
remedy of foreclosure of mortgage is deemed chosen upon the filing of the complaint there for. 48 In Suico Rattan &
Buri Interiors, Inc. v. CA, 49 it was explained:
x x x x In sustaining the rule that prohibits mortgage creditors from pursuing both the remedies of a personal action
for debt or a real action to foreclose the mortgage, the Court held in the case of Bachrach Motor Co., Inc. v. Esteban
Icarangal, et al. that a rule which would authorize the plaintiff to bring a personal action against the debtor and
simultaneously or successively another action against the mortgaged property, would result not only in multiplicity of
suits so offensive to justice and obnoxious to law and equity, but also in subjecting the defendant to the vexation of
being sued in the place of his residence or of the residence of the plaintiff, and then again in the place where the
property lies. Hence, a remedy is deemed chosen upon the filing of the suit for collection or upon the filing of the
complaint in an action for foreclosure of mortgage, pursuant to the provisions of Rule 68 of the Rules of Court. As to
extrajudicial foreclosure, such remedy is deemed elected by the mortgage creditor upon filing of the petition not
with any court of justice but with the office of the sheriff of the province where the sale is to be made, in accordance
with the provisions of Act No. 3135, as amended by Act No. 4118. (Emphases supplied)
As petitioner had already instituted judicial foreclosure proceedings over the mortgaged property, she is now
barred from availing herself of an ordinary action for collection, regardless of whether or not the decision in the
foreclosure case had attained finality. In fine, the dismissal of the collection case is in order. Considering, however,
that respondent's claim for return of excess payment partakes of the nature of a compulsory counterclaim and, thus,
survives the dismissal of petitioner's collection suit, the same should be resolved based on its own merits and
evidentiary support. 50
Records show that other than the matter of interest, the principal loan obligation and the payments made were not
disputed by the parties.1âwphi1 Nonetheless, the Court finds the stipulated 5% monthly interest to be excessive and
unconscionable. In a plethora of cases, the Court has affirmed that stipulated interest rates of three percent (3°/o)
per month and higher are excessive, iniquitous, unconscionable, and exorbitant, 51 hence, illegal 52 and void for being
contrary to morals.53 In Agner v. BPI Family Savings Bank, Inc., 54 the Court had the occasion to rule:
Settled is the principle which this Court has affirmed in a number of cases that stipulated interest rates of three
percent (3%) per month and higher are excessive, iniquitous, unconscionable, and exorbitant. While Central Bank
Circular No. 905-82, which took effect on January 1, 1983, effectively removed the ceiling on interest rates for both
secured and unsecured loans, regardless of maturity, nothing in the said circular could possibly be read as granting
carte blanche authority to lenders to raise interest rates to levels which would either enslave their borrowers or lead
to a hemorrhaging of their assets. Since the stipulation on the interest rate is void for being contrary to morals, if not
against the law, it is as if there was no express contract on said interest rate; thus, the interest rate may be reduced as
reason and equity demand. (Emphases supplied)
As such, the stipulated 5% monthly interest should be equitably reduced to l % per month or 12% p.a. reckoned from
the execution of the real estate mortgage on July 30, 1992. In order to determine whether there was any
overpayment as claimed by respondent, we first compute the interest until January 30, 1998 55 when he made a
payment in the amount of ₱300,000.00 on Rafael's loan obligation. Accordingly, the amount due on the loan as of the
latter date is hereby computed as follows:
a) As to petitioner’s name :
Middle Name : SY
b) As to petitioner’s nationality/citizenship :
: FILIPINO
SO ORDERED.15
The RTC concluded that respondent’s petition would neither prejudice the government nor any third party. It also
held that the names "Norma Sy Lugsanay" and "Anita Sy" refer to one and the same person, especially since the Local
Civil Registrar of Gingoog City has effected the correction. Considering that respondent has continuously used and
has been known since childhood as "Norma Sy Lugsanay" and as a Filipino citizen, the RTC granted the petition to
avoid confusion.16
On February 18, 2011, the CA affirmed in toto the RTC Order. The CA held that respondent’s failure to implead other
indispensable parties was cured upon the publication of the Order setting the case for hearing in a newspaper of
general circulation for three (3) consecutive weeks and by serving a copy of the notice to the Local Civil Registrar, the
OSG and the City Prosecutor’s Office.17 As to whether the petition is a collateral attack on respondent’s filiation, the
CA ruled in favor of respondent, considering that her parents were not legally married and that her siblings’ birth
certificates uniformly state that their surname is Lugsanay and their citizenship is Filipino. 18 Petitioner’s motion for
reconsideration was denied in a Resolution dated July 27, 2011.
Hence, the present petition on the sole ground that the petition is dismissible for failure to implead indispensable
parties.
Cancellation or correction of entries in the civil registry is governed by Rule 108 of the Rules of Court, to wit:
SEC. 1. Who may file petition. – Any person interested in any act, event, order or decree concerning the civil status of
persons which has been recorded in the civil register, may file a verified petition for the cancellation or correction of
any entry relating thereto, with the Regional Trial Court of the province where the corresponding civil registry is
located.
SEC. 2. Entries subject to cancellation or correction. – Upon good and valid grounds, the following entries in the civil
register may be cancelled or corrected: (a) births; (b) marriages; (c) deaths; (d) legal separations; (e) judgments of
annulments of marriage; (f) judgments declaring marriages void from the beginning; (g) legitimations; (h) adoptions;
(i) acknowledgments of natural children; (j) naturalization; (k) election, loss or recovery of citizenship; (l) civil
interdiction; (m) judicial determination of filiation; (n) voluntary emancipation of a minor; and (o) changes of name.
SEC. 3. Parties. – When cancellation or correction of an entry in the civil register is sought, the civil registrar and all
persons who have or claim any interest which would be affected thereby shall be made parties to the proceeding.
SEC. 4. Notice and Publication. – Upon the filing of the petition, the court shall, by an order, fix the time and place for
the hearing of the same, and cause reasonable notice thereof to be given to the persons named in the petition. The
court shall also cause the order to be published once a week for three (3) consecutive weeks in a newspaper of
general circulation in the province.
SEC. 5. Opposition. – The civil registrar and any person having or claiming any interest under the entry whose
cancellation or correction is sought may, within fifteen (15) days from notice of the petition, or from the last date of
publication of such notice, file his opposition thereto.
SEC. 6. Expediting proceedings. – The court in which the proceeding is brought may make orders expediting the
proceedings, and may also grant preliminary injunction for the preservation of the rights of the parties pending such
proceedings.
SEC. 7. Order. – After hearing, the court may either dismiss the petition or issue an order granting the cancellation or
correction prayed for. In either case, a certified copy of the judgment shall be served upon the civil registrar
concerned who shall annotate the same in his record. 19
In this case, respondent sought the correction of entries in her birth certificate, particularly those pertaining to her
first name, surname and citizenship. She sought the correction allegedly to reflect the name which she has been
known for since childhood, including her legal documents such as passport and school and professional records. She
likewise relied on the birth certificates of her full blood siblings who bear the surname "Lugsanay" instead of "Sy" and
citizenship of "Filipino" instead of "Chinese." The changes, however, are obviously not mere clerical as they touch on
respondent’s filiation and citizenship. In changing her surname from "Sy" (which is the surname of her father) to
"Lugsanay" (which is the surname of her mother), she, in effect, changes her status from legitimate to illegitimate;
and in changing her citizenship from Chinese to Filipino, the same affects her rights and obligations in this country.
Clearly, the changes are substantial.
It has been settled in a number of cases starting with Republic v. Valencia 20 that even substantial errors in a civil
registry may be corrected and the true facts established provided the parties aggrieved by the error avail themselves
of the appropriate adversary proceeding.21 The pronouncement of the Court in that case is illuminating:
It is undoubtedly true that if the subject matter of a petition is not for the correction of clerical errors of a harmless
and innocuous nature, but one involving nationality or citizenship, which is indisputably substantial as well as
controverted, affirmative relief cannot be granted in a proceeding summary in nature. However, it is also true that a
right in law may be enforced and a wrong may be remedied as long as the appropriate remedy is used. This Court
adheres to the principle that even substantial errors in a civil registry may be corrected and the true facts established
provided the parties aggrieved by the error avail themselves of the appropriate adversary proceeding. x x x
What is meant by "appropriate adversary proceeding?" Black’s Law Dictionary defines "adversary proceeding" as
follows:
One having opposing parties; contested, as distinguished from an ex parte application, one of which the party
seeking relief has given legal warning to the other party, and afforded the latter an opportunity to contest it. Excludes
an adoption proceeding.22
In sustaining the RTC decision, the CA relied on the Court’s conclusion in Republic v. Kho, 23 Alba v. Court of
Appeals,24 and Barco v. Court of Appeals,25 that the failure to implead indispensable parties was cured by the
publication of the notice of hearing pursuant to the provisions of Rule 108 of the Rules of Court. In Republic v.
Kho,26 petitioner therein appealed the RTC decision granting the petition for correction of entries despite
respondents’ failure to implead the minor’s mother as an indispensable party. The Court, however, did not strictly
apply the provisions of Rule 108, because it opined that it was highly improbable that the mother was unaware of
the proceedings to correct the entries in her children’s birth certificates especially since the notices, orders and
decision of the trial court were all sent to the residence she shared with them. 27
In Alba v. Court of Appeals,28 the Court found nothing wrong with the trial court’s decision granting the petition for
correction of entries filed by respondent although the proceedings was not actually known by petitioner. In that case,
petitioner’s mother and guardian was impleaded in the petition for correction of entries, and notices were sent to
her address appearing in the subject birth certificate. However, the notice was returned unserved, because
apparently she no longer lived there. Thus, when she allegedly learned of the granting of the petition, she sought the
annulment of judgment which the Court denied. Considering that the petition for correction of entries is a
proceeding in rem, the Court held that acquisition of jurisdiction over the person of the petitioner is, therefore, not
required and the absence of personal service was cured by the trial court’s compliance with Rule 108 which requires
notice by publication.29
In Barco v. Court of Appeals,30 the Court addressed the question of whether the court acquired jurisdiction over
petitioner and all other indispensable parties to the petition for correction of entries despite the failure to implead
them in said case. While recognizing that petitioner was indeed an indispensable party, the failure to implead her
was cured by compliance with Section 4 of Rule 108 which requires notice by publication. In so ruling, the Court
pointed out that the petitioner in a petition for correction cannot be presumed to be aware of all the parties whose
interests may be affected by the granting of a petition. It emphasized that the petitioner therein exerted earnest
effort to comply with the provisions of Rule 108. Thus, the publication of the notice of hearing was considered to
have cured the failure to implead indispensable parties.
In this case, it was only the Local Civil Registrar of Gingoog City who was impleaded as respondent in the petition
below. This, notwithstanding, the RTC granted her petition and allowed the correction sought by respondent, which
decision was affirmed in toto by the CA.
We do not agree with the RTC and the CA.
This is not the first time that the Court is confronted with the issue involved in this case. Aside from Kho, Alba and
Barco, the Court has addressed the same in Republic v. Coseteng-Magpayo, 31 Ceruila v. Delantar,32 and Labayo-Rowe
v. Republic.33
In Republic v. Coseteng-Magpayo, 34 claiming that his parents were never legally married, respondent therein filed a
petition to change his name from "Julian Edward Emerson Coseteng Magpayo," the name appearing in his birth
certificate to "Julian Edward Emerson Marquez Lim Coseteng." The notice setting the petition for hearing was
published and there being no opposition thereto, the trial court issued an order of general default and eventually
granted respondent’s petition deleting the entry on the date and place of marriage of parties; correcting his surname
from "Magpayo" to "Coseteng"; deleting the entry "Coseteng" for middle name; and deleting the entry "Fulvio
Miranda Magpayo, Jr." in the space for his father. The Republic of the Philippines, through the OSG, assailed the RTC
decision on the grounds that the corrections made on respondent’s birth certificate had the effect of changing the
civil status from legitimate to illegitimate and must only be effected through an appropriate adversary proceeding.
The Court nullified the RTC decision for respondent’s failure to comply strictly with the procedure laid down in Rule
108 of the Rules of Court. Aside from the wrong remedy availed of by respondent as he filed a petition for Change of
Name under Rule 103 of the Rules of Court, assuming that he filed a petition under Rule 108 which is the appropriate
remedy, the petition still failed because of improper venue and failure to implead the Civil Registrar of Makati City
and all affected parties as respondents in the case.
In Ceruila v. Delantar,35 the Ceruilas filed a petition for the cancellation and annulment of the birth certificate of
respondent on the ground that the same was made as an instrument of the crime of simulation of birth and,
therefore, invalid and spurious, and it falsified all material entries therein. The RTC issued an order setting the case
for hearing with a directive that the same be published and that any person who is interested in the petition may
interpose his comment or opposition on or before the scheduled hearing. Summons was likewise sent to the Civil
Register of Manila. After which, the trial court granted the petition and nullified respondent’s birth certificate. Few
months after, respondent filed a petition for the annulment of judgment claiming that she and her guardian were not
notified of the petition and the trial court’s decision, hence, the latter was issued without jurisdiction and in violation
of her right to due process. The Court annulled the trial court’s decision for failure to comply with the requirements
of Rule 108, especially the non-impleading of respondent herself whose birth certificate was nullified.1âwphi1
In Labayo-Rowe v. Republic,36 petitioner filed a petition for the correction of entries in the birth certificates of her
children, specifically to change her name from Beatriz V. Labayu/Beatriz Labayo to Emperatriz Labayo, her civil status
from "married" to "single," and the date and place of marriage from "1953-Bulan" to "No marriage." The Court
modified the trial court’s decision by nullifying the portion thereof which directs the change of petitioner’s civil status
as well as the filiation of her child, because it was the OSG only that was made respondent and the proceedings taken
was summary in nature which is short of what is required in cases where substantial alterations are sought.
Respondent’s birth certificate shows that her full name is Anita Sy, that she is a Chinese citizen and a legitimate child
of Sy Ton and Sotera Lugsanay. In filing the petition, however, she seeks the correction of her first name and
surname, her status from "legitimate" to "illegitimate" and her citizenship from "Chinese" to "Filipino." Thus,
respondent should have impleaded and notified not only the Local Civil Registrar but also her parents and siblings as
the persons who have interest and are affected by the changes or corrections respondent wanted to make.
The fact that the notice of hearing was published in a newspaper of general circulation and notice thereof was served
upon the State will not change the nature of the proceedings taken. 37 A reading of Sections 4 and 5, Rule 108 of the
Rules of Court shows that the Rules mandate two sets of notices to different potential oppositors: one given to the
persons named in the petition and another given to other persons who are not named in the petition but
nonetheless may be considered interested or affected parties. 38 Summons must, therefore, be served not for the
purpose of vesting the courts with jurisdiction but to comply with the requirements of fair play and due process to
afford the person concerned the opportunity to protect his interest if he so chooses. 39
While there may be cases where the Court held that the failure to implead and notify the affected or interested
parties may be cured by the publication of the notice of hearing, earnest efforts were made by petitioners in bringing
to court all possible interested parties.40 Such failure was likewise excused where the interested parties themselves
initiated the corrections proceedings;41 when there is no actual or presumptive awareness of the existence of the
interested parties;42 or when a party is inadvertently left out. 43
It is clear from the foregoing discussion that when a petition for cancellation or correction of an entry in the civil
register involves substantial and controversial alterations, including those on citizenship, legitimacy of paternity or
filiation, or legitimacy of marriage, a strict compliance with the requirements of Rule 108 ofthe Rules of Court is
mandated.44 If the entries in the civil register could be corrected or changed through mere summary proceedings and
not through appropriate action wherein all parties who may be affected by the entries are notified or represented,
the door to fraud or other mischief would be set open, the consequence of which might be detrimental and far
reaching.45
WHEREFORE, premises considered, the petition is hereby GRANTED. The Court of Appeals Decision dated February
18, 2011 and Resolution dated July 27, 20011 in CA-G.R. CV No. 00238-MIN, are SET ASIDE. Consequently, the June
28, 2004 Order of the Regional Trial Court, Branch 27, Gingoog City, in Spl. Proc. No. 230-2004 granting the Petition
for Correction of Entry of Certificate of Live Birth filed by respondent Dr. Norma S. Lugsanay Uy, is NULLIFIED.
SO ORDERED.
This Resolution was personally served to the above parties, at the above addresses on February 23, 2012. On March
20, 2012, JAPEX Philippines, Ltd. (JAPEX PH), by way of special appearance, filed a Motion to Admit 23 its Motion for
Clarification,24 wherein JAPEX PH requested to be clarified as to whether or not it should deem the February 7, 2012
Resolution as this Court's Order of its inclusion in the case, as it has not been impleaded. It also alleged that JAPEX
PH had already stopped exploration activities in the Taft. on Strait way back in 2008, rendering this case moot.
On March 22, 2012, JAPEX PH, also by special appearance, filed a Motion for Extension of Time 25 to file its
Memorandum. It stated that since it received the February 7, 2012 Resolution on February 23, 2012, it had until
March 22, 2012 to file its Memorandum. JAPEX PH then asked for an additional thirty days, supposedly to give this
Court some time to consider its Motion for Clarification.
On April 24, 2012, this Court issued a Resolution 26 granting JAPEX PH's Motion to Admit its Motion for Clarification.
This Court, addressing JAPEX PH's Motion for Clarification, held:
With regard to its Motion for Clarification (By Special Appearance) dated March 19, 2012, this Court considers JAPEX
Philippines, Ltd. as a real party-in-interest in these cases. Under Section 2, Rule 3 of the 1997 Rules of Court, a real
party-in-interest is the party who stands to be benefited or injured by the judgment in the suit, or the party entitled
to the avails of the suit. Contrary to JAPEX Philippines, Ltd. 's allegation that it is a completely distinct corporation,
which should not be confused with JAPEX Company, Ltd., JAPEX Philippines, Ltd. is a mere branch office, established
by JAPEX Company, Ltd. for the purpose of carrying out the latter's business transactions here in the Philippines.
Thus, JAPEX Philippines, Ltd., has no separate personality from its mother foreign corporation, the party impleaded in
this case.
Moreover, Section 128 of the Corporation Code provides for the responsibilities and duties of a resident agent of a
foreign corporation:
SECTION 128. Resident agent; service of process. - The Securities and Exchange Commission shall require as a
condition precedent to the issuance of the license to transact business in the Philippines by any foreign corporation
that such corporation file with the Securities and Exchange Commission a written power of attorney designating
some person who must be a resident of the Philippines, on whom any summons and other legal processes may be
served in all actions or other legal proceedings against such corporation, and consenting that service upon such
resident agent shall be admitted and held as valid as if served upon the duly authorized officers of the foreign
corporation at its home office. Any such foreign corporation shall likewise execute and file with the Securities and
Exchange Commission an agreement or stipulation, executed by the proper authorities of said corporation, in form
and substance as follows:
"The (name of foreign corporation) does hereby stipulate and agree, in consideration of its being granted by the
Securities and Exchange Commission a license to transact business in the Philippines, that if at any time said
corporation shall cease to transact business in the Philippines, or shall be without any resident agent in the
Philippines on whom any summons or other legal processes may be served, then in any action or proceeding arising
out of any business or transaction which occurred in the Philippines, service of any summons or other legal process
may be made upon the Securities and Exchange Commission and that such service shall have the same force and
effect as if made upon the duly-authorized officers of the corporation at its home office."
Whenever such service of summons or other process shall be made upon the Securities and Exchange Commission,
the Commission shall, within ten (10) days thereafter, transmit by mail a copy of such summons or other legal
process to the corporation at its home or principal office. The sending of such copy by the Commission shall be a
necessary part of and shall complete such service. All expenses incurred by the Commission for such service shall be
paid in advance by the party at whose instance the service is made.
In case of a change of address of the resident agent, it shall be his or its duty to immediately notify in writing the
Securities and Exchange Commission of the new address.
It is clear from the foregoing provision that the function of a resident agent is to receive summons or legal processes
that may be served in all actions or other legal proceedings against the foreign corporation. These cases have been
prosecuted in the name of JAPEX Company, Ltd., and JAPEX Philippines Ltd., as its branch office and resident agent,
had been receiving the various resolutions from this Court, as evidenced by Registry Return Cards signed by its
representatives.
And in the interest of justice, this Court resolved to grant JAPEX PH's motion for extension of time to file its
memorandum, and was given until April 21, 2012, as prayed for, within which to comply with the submission. 27
Without filing its Memorandum, JAPEX PH, on May 14, 2012, filed a motion, asking this Court for an additional thirty
days to file its Memorandum, to be counted from May 8, 2012. It justified its request by claiming that this Court's
April 24, 2012 Resolution was issued past its requested deadline for filing, which was on April 21, 2012. 28
On June 19, 2012, this Court denied JAPEX PH's second request for additional time to file its Memorandum and
dispensed with such filing.
Since petitioners had already filed their respective memoranda, 29 and public respondents had earlier filed a
Manifestation30 that they were adopting their Comment dated March 31, 2008 as their memorandum, this Court
submitted the case for decision.
Petitioners.' Allegations
Protesting the adverse ecological impact of JAPEX's oil exploration activities in the Tañon Strait, petitioners Resident
Marine Mammals and Stewards aver that a study made after the seismic survey showed that the fish catch was
reduced drastically by 50 to 70 percent. They claim that before the seismic survey, the average harvest per day would
be from 15 to 20 kilos; but after the activity, the fisherfolk could only catch an average of 1 to 2 kilos a day. They
attribute this "reduced fish catch" to the destruction of the ''payao," also known as the "fish aggregating device" or
"artificial reef."31 Petitioners Resident Marine Mammals and Stewards also impute the incidences of "fish
kill"32observed by some of the local fisherfolk to the seismic survey. And they further allege that the ECC obtained by
private respondent JAPEX is invalid because public consultations and discussions with the affected stakeholders, a
pre-requisite to the issuance of the ECC, were not held prior to the ECC's issuance.
In its separate petition, petitioner FIDEC confirms petitioners Resident Marine Mammals and Stewards' allegations of
reduced fish catch and lack of public consultations or discussions with the fisherfolk and other stakeholders prior to
the issuance of the ECC. Moreover, it alleges that during the seismic surveys and drilling, it was barred from entering
and fishing within a 7-kilometer radius from the point where the oilrig was located, an area greater than the 1.5-
kilometer radius "exclusion zone" stated in the IEE. 33 It also agrees in the allegation that public respondents DENR
and EMB abused their discretion when they issued an ECC to public respondent DOE and private respondent JAPEX
without ensuring the strict compliance with the procedural and substantive requirements under the Environmental
Impact Assessment system, the Fisheries Code, and their implementing rules and regulations. 34It further claims that
despite several requests for copies of all the documents pertaining to the project in Tañon Strait, only copies of the P
AMB-Tañon Strait Resolution and the ECC were given to the fisherfolk. 35
Public Respondents' Counter-Allegations
Public respondents, through the Solicitor General, contend that petitioners Resident Marine Mammals and Stewards
have no legal standing to file the present petition; that SC-46 does not violate the 1987 Constitution and the various
laws cited in the petitions; that the ECC was issued in accordance with existing laws and regulations; that public
respondents may not be compelled by mandamus to furnish petitioners copies of all documents relating to SC-46;
and that all the petitioners failed to show that they are entitled to injunctive relief. They further contend that the
issues raised in these petitions have been rendered moot and academic by the fact that SC-46 had been mutually
terminated by the parties thereto effective June 21, 2008. 36
ISSUES
The following are the issues posited by petitioners Resident Marine Mammals and Stewards in G.R. No. 180771:
I. WHETHER OR NOT PETITIONERS HAVE LOCUS STAND! TO FILE THE INSTANT PETITION;
II. WHETHER OR NOT SERVICE CONTRACT NO. 46 IS VIOLA T[IVE] OF THE 1987 PHILIPPINE CONSTITUTION
AND STATUTES;
III. WHETHER OR NOT THE ON-GOING EXPLORATION AND PROPOSED EXPLOITATION FOR OIL AND NATURAL
GAS AT, AROUND, AND UNDERNEATH THE MARINE WATERS OF THE TAÑON STRAIT PROTECTED SEASCAPE IS
INCONSISTENT WITH THE PHILIPPINE COMMITMENTS TO INTERNATIONAL ENVIRONMENTAL LAWS AND
INSTRUMENTS; AND
IV. WHETHER OR NOT THE ISSUANCE OF THE ENVIRONMENTAL COMPLIANCE CERTIFICATE (ECC) IN
ENVIRONMENTALLY CRITICAL AREAS AND HABITATS OF MARINE WILDLIFE AND ENDANGERED SPECIES IS
LEGAL AND PROPER.37
Meanwhile, in G.R. No. 181527, petitioner FIDEC presented the following issues for our consideration:
I. WHETHER OR NOT SERVICE CONTRACT NO. 46 EXECUTED BETWEEN RESPONDENTS DOE AND JAPEX
SHOULD BE NULLIFIED AND SET ASIDE FOR BEING IN DIRECT VIOLATION OF SPECIFIC PROVISIONS OF THE
1987 PHILIPPINE CONSTITUTION AND APPLICABLE LAWS;
II. WHETHER OR NOT THE OFF-SHORE OIL EXPLORAT[I]ON CONTEMPLATED UNDER SERVICE CONTRACT NO.
46 ·IS LEGALLY PERMISSIBLE WITHOUT A LAW BEING DULY PASSED EXPRESSLY FOR THE PURPOSE;
III. WHETHER OR NOT THE OIL EXPLORATION BEING CONDUCTED WITHIN THE TAÑON STRAIT PROTECTED
SEASCAPE VIOLATES THE RIGHTS AND LEGAL PROTECTION GRANTED TO PETITIONERS UNDER THE
CONSTITUTION AND APPLICABLE LAWS.
IV. WHETHER OR NOT THE ISSUANCE OF THE ENVIRONMENTAL COMPLIANCE CERTIFICATE (ECC) FOR SUCH
AN ENVIRONMENTALLY CRITICAL PROJECT INSIDE AN ENVIRONMENTALLY CRITICAL AREA SUCH AS THE
TAÑON STRAIT PROTECTED SEASCAPE CONFORMED TO LAW AND EXISTING RULES AND REGULATIONS ON
THE MATTER.
V. WHETHER OR NOT THE RESPONDENTS MAY BE COMPELLED BY MANDAMUS TO FURNISH PETITIONERS
WITH COPIES OF THE DOCUMENTS PERTAINING TO THE TAÑON STRAIT OIL EXPLORATION PROJECT. 38
In these consolidated petitions, this Court has determined that the various issues raised by the petitioners may be
condensed into two primary issues:
I. Procedural Issue: Locus Standi of the Resident Marine Mammals and Stewards, petitioners in G.R. No. 180771; and
II. Main Issue: Legality of Service Contract No. 46.
DISCUSSION
At the outset, this Court makes clear that the "'moot and academic principle' is not a magical formula that can
automatically dissuade the courts in resolving a case." Courts have decided cases otherwise moot and academic
under the following exceptions:
1) There is a grave violation of the Constitution;
2) The exceptional character of the situation and the paramount public interest is involved;
3) The constitutional issue raised requires formulation of controlling principles to guide the bench, the bar,
and the public; and
4) The case is capable of repetition yet evading review. 39
In this case, despite the termination of SC-46, this Court deems it necessary to resolve these consolidated petitions
as almost all of the foregoing exceptions are present in this case. Both petitioners allege that SC-46 is violative of the
Constitution, the environmental and livelihood issues raised undoubtedly affect the public's interest, and the
respondents' contested actions are capable of repetition.
Procedural Issues
Locus Standi of Petitioners Resident Marine Mammals and Stewards
The Resident Marine Mammals, through the Stewards, "claim" that they have the legal standing to file this action
since they stand to be benefited or injured by the judgment in this suit. 40 Citing Oposa v. Factoran, Jr.,41 they also
assert their right to sue for the faithful performance of international and municipal environmental laws created in
their favor and for their benefit. In this regard, they propound that they have the right to demand that they be
accorded the benefits granted to them in multilateral international instruments that the Philippine Government had
signed, under the concept of stipulation pour autrui. 42
For their part, the Stewards contend that there should be no question of their right to represent the Resident Marine
Mammals as they have stakes in the case as forerunners of a campaign to build awareness among the affected
residents of Tañon Strait and as stewards of the environment since the primary steward, the Government, had failed
in its duty to protect the environment pursuant to the public trust doctrine. 43
Petitioners Resident Marine Mammals and Stewards also aver that this Court may lower the benchmark in locus
standi as an exercise of epistolary jurisdiction. 44
In opposition, public respondents argue that the Resident Marine Mammals have no standing because Section 1,
Rule 3 of the Rules of Court requires parties to an action to be either natural or juridical persons, viz.:
Section 1. Who may be parties, plaintiff and defendant. - Only natural or juridical persons, or entities authorized by
law may be parties in a civil action. The term "plaintiff' may refer to the claiming party, the counter-claimant, the
cross-claimant, or the third (fourth, etc.)-party plaintiff. The term "defendant" may refer to the original defending
party, the defendant in a counterclaim, the cross-defendant, or the third (fourth, etc.)-party defendant.
The public respondents also contest the applicability of Oposa, pointing out that the petitioners therein were all
natural persons, albeit some of them were still unborn. 45
As regards the Stewards, the public respondents likewise challenge their claim of legal standing on the ground that
they are representing animals, which cannot be parties to an action. Moreover, the public respondents argue that the
Stewards are not the real parties-in-interest for their failure to show how they stand to be benefited or injured by the
decision in this case.46 Invoking the alter ego principle in political law, the public respondents claim that absent any
proof that former President Arroyo had disapproved of their acts in entering into and implementing SC-46, such acts
remain to be her own.47
The public respondents contend that since petitioners Resident Marine Mammals and Stewards' petition was not
brought in the name of a real party-in-interest, it should be dismissed for failure to state a cause of action. 48
The issue of whether or not animals or even inanimate objects should be given legal standing in actions before courts
of law is not new in the field o f animal rights and environmental law. Petitioners Resident Marine Mammals and
Stewards cited the 1972 United States case Sierra Club v. Rogers C.B. Morton, 49 wherein Justice William 0. Douglas,
dissenting to the conventional thought on legal standing, opined:
The critical question of "standing" would be simplified and also put neatly in focus if we fashioned a federal rule that
allowed environmental issues to be litigated before federal agencies or federal courts in the name of the inanimate
object about to be despoiled, defaced, or invaded by roads and bulldozers and where injury is the subject of public
outrage. x x x. Inanimate objects are sometimes parties in litigation. A ship has a legal personality, a fiction found
useful for maritime purposes. The corporation sole - a creature of ecclesiastical law - is an acceptable adversary and
large fortunes ride on its cases. The ordinary corporation is a "person" for purposes of the adjudicatory processes,
whether it represents proprietary, spiritual, aesthetic, or charitable causes.
So it should be as respects valleys, alpine meadows, rivers, lakes, estuaries, beaches, ridges, groves of trees,
swampland, or even air that feels the destructive pressures of modem technology and modem life. The river, for
example, is the living symbol of all the life it sustains or nourishes-fish, aquatic insects, water ouzels, otter, fisher,
deer, elk, bear, and all other animals, including man, who are dependent on it or who enjoy it for its sight, its sound,
or its life. The river as plaintiff speaks for the ecological unit of life that is part of it. Those people who have a
meaningful relation to that body of water-whether it be a fisherman, a canoeist, a zoologist, or a logger-must be able
to speak for the values which the river represents and which are threatened with destruction. 50 (Citations omitted.)
The primary reason animal rights advocates and environmentalists seek to give animals and inanimate objects
standing is due to the need to comply with the strict requirements in bringing a suit to court. Our own 1997 Rules of
Court demand that parties to a suit be either natural or juridical persons, or entities authorized by law. It further
necessitates the action to be brought in the name of the real party-in-interest, even if filed by a representative, viz.:
Rule 3
Parties to Civil Actions
Section 1. Who may be parties; plaintiff and defendant. - Only natural or juridical persons, or entities authorized by
law may be parties in a civil action. The term "plaintiff' may refer to the claiming party, the counter-claimant, the
cross-claimant, or the third (fourth, etc.)-party plaintiff. The term "defendant" may refer to the original defending
party, the defendant in a counterclaim, the cross-defendant, or the third (fourth, etc.)-party defendant.
Sec. 2. Parties in interest. - A real party in interest is the party who stands to be benefited or injured by the judgment
in the suit, or the party entitled to the avails of the suit. Unless otherwise authorized by law or these Rules, every
action must be prosecuted or defended in the name of the real party in interest.
Sec. 3. Representatives as parties. - Where the action is allowed to be prosecuted or defended by a representative or
someone acting in a fiduciary capacity, the beneficiary shall be included in the title of the case and shall be deemed
to be the real party in interest. A representative may be a trustee of an express trust, a guardian, an executor or
administrator, or a party authorized by law or these Rules. An agent acting in his own name and for the benefit of an
undisclosed principal may sue or be sued without joining the principal except when the contract involves things
belonging to the principal.
It had been suggested by animal rights advocates and environmentalists that not only natural and juridical persons
should be given legal standing because of the difficulty for persons, who cannot show that they by themselves are
real parties-in-interests, to bring actions in representation of these animals or inanimate objects. For this reason,
many environmental cases have been dismissed for failure of the petitioner to show that he/she would be directly
injured or affected by the outcome of the case. However, in our jurisdiction, locus standi in environmental cases has
been given a more liberalized approach. While developments in Philippine legal theory and jurisprudence have not
progressed as far as Justice Douglas's paradigm of legal standing for inanimate objects, the current trend moves
towards simplification of procedures and facilitating court access in environmental cases.
Recently, the Court passed the landmark Rules of Procedure for Environmental Cases, 51 which allow for a "citizen
suit," and permit any Filipino citizen to file an action before our courts for violations of our environmental laws:
SEC. 5. Citizen suit. - Any Filipino citizen in representation of others, including minors or generations yet unborn, may
file an action to enforce rights or obligations under environmental laws. Upon the filing of a citizen suit, the court
shall issue an order which shall contain a brief description of the cause of action and the reliefs prayed for, requiring
all interested parties to manifest their interest to intervene in the case within fifteen (15) days from notice thereof.
The plaintiff may publish the order once in a newspaper of a general circulation in the Philippines or furnish all
affected barangays copies of said order.
Citizen suits filed under R.A. No. 8749 and R.A. No. 9003 shall be governed by their respective provisions. 52(Emphasis
ours.)
Explaining the rationale for this rule, the Court, in the Annotations to the Rules of Procedure for Environmental
Cases, commented:
Citizen suit. To further encourage the protection of the environment, the Rules enable litigants enforcing
environmental rights to file their cases as citizen suits. This provision liberalizes standing for all cases filed enforcing
environmental laws and collapses the traditional rule on personal and direct interest, on the principle that humans
are stewards of nature. The terminology of the text reflects the doctrine first enunciated in Oposa v. Factoran, insofar
as it refers to minors and generations yet unborn. 53 (Emphasis supplied, citation omitted.) Although this petition was
filed in 2007, years before the effectivity of the Rules of Procedure for Environmental Cases, it has been consistently
held that rules of procedure "may be retroactively applied to actions pending and undetermined at the time of their
passage and will not violate any right of a person who may feel that he is adversely affected, inasmuch as there is no
vested rights in rules of procedure."54
Elucidating on this doctrine, the Court, in Systems Factors Corporation v. National Labor Relations Commission 55held
that:
Remedial statutes or statutes relating to remedies or modes of procedure, which do not create new or take away
vested rights, but only operate in furtherance of the remedy or confirmation of rights already existing, do not come
within the legal conception of a retroactive law, or the general rule against retroactive operation of statutes. Statutes
regulating the procedure of the courts will be construed as applicable to actions pending and undetermined at the
time of their passage. Procedural laws are retroactive in that sense and to that extent. x x x.
Moreover, even before the Rules of Procedure for Environmental · Cases became effective, this Court had already
taken a permissive position on the issue of locus standi in environmental cases. In Oposa, we allowed the suit to be
brought in the name of generations yet unborn "based on the concept of intergenerational responsibility insofar as
the right to a balanced and healthful ecology is concerned." 56 Furthermore, we said that the right to a balanced and
healthful ecology, a right that does not even need to be stated in our Constitution as it is assumed to exist from the
inception of humankind, carries with it the correlative duty to refrain from impairing the environment. 57
In light of the foregoing, the need to give the Resident Marine Mammals legal standing has been eliminated by our
Rules, which allow any Filipino citizen, as a steward of nature, to bring a suit to enforce our environmental laws. It is
worth noting here that the Stewards are joined as real parties in the Petition and not just in representation of the
named cetacean species. The Stewards, Ramos and Eisma-Osorio, having shown in their petition that there may be
possible violations of laws concerning the habitat of the Resident Marine Mammals, are therefore declared to
possess the legal standing to file this petition.
Impleading Former President Gloria Macapagal-Arroyo
as an Unwilling Co-Petitioner
Petitioners Stewards in G.R. No. 180771 impleaded as an unwilling co-petitioner former President Gloria Macapagal-
Arroyo for the following reasons, which we quote:
Her Excellency Gloria Macapagal-Arroyo, also of legal age, Filipino and resident of Malacailang Palace, Manila
Philippines. Steward Gloria Macapagal-Arroyo happens to be the incumbent President of the Philippine Islands. She
is personally impleaded in this suit as an unwilling co-petitioner by reason of her express declaration and undertaking
under the recently signed ASEAN Charter to protect Your Petitioners' habitat, among others. She is meantime
dominated as an unwilling co-petitioner due to lack of material time in seeking her signature and imprimatur hereof
and due to possible legal complications that may hereafter arise by reason of her official relations with public
respondents under the alter ego principle in political law. 58 This is incorrect.
Section 10, Rule 3 of the Rules of Court provides:
Sec. 10. Unwilling co-plaintiff. - If the consent of any party who should be joined as plaintiff can not be obtained, he
may be made a defendant and the reason therefor shall be stated in the complaint.
Under the foregoing rule, when the consent of a party who should be joined as a plaintiff cannot be obtained, he or
she may be made a party defendant to the case. This will put the unwilling party under the jurisdiction of the Court,
which can properly implead him or her through its processes. The unwilling party's name cannot be simply included
in a petition, without his or her knowledge and consent, as such would be a denial of due process.
Moreover, the reason cited by the petitioners Stewards for including former President Macapagal-Arroyo in their
petition, is not sufficient to implead her as an unwilling co-petitioner. Impleading the former President as an
unwilling co-petitioner, for an act she made in the performance of the functions of her office, is contrary to the public
policy against embroiling the President in suits, "to assure the exercise of Presidential duties and functions free from
any hindrance or distraction, considering that being the Chief Executive of the Government is a job that, aside from
requiring all of the office holder's time, also demands undivided attention." 59
Therefore, former President Macapagal-Arroyo cannot be impleaded as one of the petitioners in this suit. Thus, her
name is stricken off the title of this case.
Main Issue:
Legality of Service Contract No. 46
Service Contract No. 46 vis-a-vis
Section 2, Article XII of the
1987 Constitution
Petitioners maintain that SC-46 transgresses the Jura Regalia Provision or paragraph 1, Section 2, Article XII of the
1987 Constitution because JAPEX is 100% Japanese-owned. 60 Furthermore, the FIDEC asserts that SC-46 cannot be
considered as a technical and financial assistance agreement validly executed under paragraph 4 of the same
provision.61 The petitioners claim that La Bugal-B'laan Tribal Association, Inc. v. Ramos 62 laid down the guidelines for a
valid service contract, one of which is that there must exist a general law for oil exploration before a service contract
may be entered into by the Government. The petitioners posit that the service contract in La Bugal is presumed to
have complied with the requisites of (a) legislative enactment of a general law after the effectivity of the 1987
Constitution (such as Republic Act No. 7942, or the Philippine Mining Law of 1995, governing mining contracts) and
(b) presidential notification. The petitioners thus allege that the ruling in La Bugal, which involved mining contracts
under Republic Act No. 7942, does not apply in this case. 63 The petitioners also argue that Presidential Decree No. 87
or the Oil Exploration and Development Act of 1972 cannot legally justify SC-46 as it is deemed to have been
repealed by the 1987 Constitution and subsequent laws, which enunciate new policies concerning the
environment.64 In addition, petitioners in G.R. No. 180771 claim that paragraphs 2 and 3 of Section 2, Article XII of
the 1987 Constitution mandate the exclusive use and enjoyment by the Filipinos of our natural resources, 65 and
paragraph 4 does not speak of service contracts but of FTAAs or Financial Technical Assistance Agreements. 66
The public respondents again controvert the petitioners' claims and asseverate that SC-46 does not violate Section 2,
Article XII of the 1987 Constitution. They hold that SC-46 does not fall under the coverage of paragraph 1 but instead,
under paragraph 4 of Section 2, Article XII of the 1987 Constitution on FTAAs. They also insist that paragraphs 2 and
3, which refer to the grant of exclusive fishing right to Filipinos, are not applicable to SC-46 as the contract does not
grant exclusive fishing rights to JAPEX nor does it otherwise impinge on the FIDEC's right to preferential use of
communal marine and fishing resources.67
Ruling of the Court
On the legality of Service Contract No. 46
vis-a-vis Section 2, Article XII of the 1987 Constitution
The petitioners insist that SC-46 is null and void for having violated Section 2, Article XII of the 1987 Constitution,
which reads as follows:
Section 2. All lands of the public domain, waters, minerals, coal, petroleum, and other mineral oils, all forces of
potential energy, fisheries, forests or timber, wildlife, flora and fauna, and other natural resources are owned by the
State. With the exception of agricultural lands, all other natural resources shall not be alienated. The exploration,
development, and utilization of natural resources shall be under the full control and supervision of the State. The
State may directly undertake such activities, or it may enter into co-production, joint venture, or production-sharing
agreements with Filipino citizens, or corporations or associations at least sixty per centum of whose capital is owned
by such citizens. Such agreements may be for a period not exceeding twenty-five years, renewable for not more than
twenty-five years, and under such terms and conditions as may be provided by law. In cases of water rights for
irrigation, water supply, fisheries, or industrial uses other than the development of water power, beneficial use may
be the measure and limit of the grant.
The State shall protect the nation's marine wealth in its archipelagic waters, territorial sea, and exclusive economic
zone, and reserve its use and enjoyment exclusively to Filipino citizens. The Congress may, by law, allow small-scale
utilization of natural resources by Filipino citizens, as well as cooperative fish farming, with priority to subsistence
fishermen and fishworkers in rivers, lakes, bays, and lagoons.
The President may enter into agreements with foreign-owned corporations involving either technical or financial
assistance for large-scale exploration, development, and utilization of minerals, petroleum, and other mineral oils
according to the general terms and conditions provided by law, based on real contributions to the economic growth
and general welfare of the country. In such agreements, the State shall promote the development and use of local
scientific and technical resources.
The President shall notify the Congress of every contract entered into in accordance with this provision, within thirty
days from its execution. (Emphases ours.)
This Court has previously settled the issue of whether service contracts are still allowed under the 1987 Constitution.
In La Bugal, we held that the deletion of the words "service contracts" in the 1987 Constitution did not amount to a
ban on them per se. In fact, in that decision, we quoted in length, portions of the deliberations of the members of
the Constitutional Commission (ConCom) to show that in deliberating on paragraph 4, Section 2, Article XII, they
were actually referring to service contracts as understood in the 1973 Constitution, albeit with safety measures to
eliminate or minimize the abuses prevalent during the martial law regime, to wit: Summation of the
ConCom Deliberations
At this point, we sum up the matters established, based on a careful reading of the Con Com deliberations, as follows:
In their deliberations on what was to become paragraph 4, the framers used the term service contracts in referring to
agreements x x x involving either technical or financial assistance.
They spoke of service contracts as the concept was understood in the 1973 Constitution.
It was obvious from their discussions that they were not about to ban or eradicate service contracts.
Instead, they were plainly crafting provisions to put in place safeguards that would eliminate or minimize the abuses
prevalent during the marital law regime. In brief, they were going to permit service contracts with foreign
corporations as contractors, but with safety measures to prevent abuses, as an exception to the general norm
established in the first paragraph of Section 2 of Article XII. This provision reserves or limits to Filipino citizens -- and
corporations at least 60 percent of which is owned by such citizens -- the exploration, development and utilization of
natural resources.
This provision was prompted by the perceived insufficiency of Filipino capital and the felt need for foreign
investments in the EDU of minerals and petroleum resources.
The framers for the most part debated about the sort of safeguards that would be considered adequate and
reasonable. But some of them, having more "radical" leanings, wanted to ban service contracts altogether; for them,
the provision would permit aliens to exploit and benefit from the nation's natural resources, which they felt should
be reserved only for Filipinos.
In the explanation of their votes, the individual commissioners were heard by the entire body. They sounded off their
individual opinions, openly enunciated their philosophies, and supported or attacked the provisions with fervor.
Everyone's viewpoint was heard.
In the final voting, the Article on the National Economy and Patrimony -- including paragraph 4 allowing service
contracts with foreign corporations as an exception to the general norm in paragraph 1 of Section 2 of the same
article --was resoundingly approved by a vote of 32 to 7, with 2 abstentions.
Agreements Involving Technical
Or Financial Assistance Are
Service Contracts with Safeguards
From the foregoing, we are impelled to conclude that the phrase agreements involving either technical or financial
assistance, referred to in paragraph 4, are in fact service contracts. But unlike those of the 1973 variety, the new ones
are between foreign corporations acting as contractors on the one hand; and on the other, the government as
principal or "owner" of the works. In the new service contracts, the foreign contractors provide capital, technology
and technical know-how, and managerial expertise in the creation and operation of large-scale mining/extractive
enterprises; and the government, through its agencies (DENR, MGB), actively exercises control and supervision over
the entire operation.68
In summarizing the matters discussed in the ConCom, we established that paragraph 4, with the safeguards in place,
is the exception to paragraph 1, Section 2 of Article XII. The following are the safeguards this Court enumerated in La
Bugal:
Such service contracts may be entered into only with respect to minerals, petroleum and other mineral oils. The
grant thereof is subject to several safeguards, among which are these requirements:
(1) The service contract shall be crafted in accordance with a general law that will set standard or uniform
terms, conditions and requirements, presumably to attain a certain uniformity in provisions and avoid the
possible insertion of terms disadvantageous to the country.
(2) The President shall be the signatory for the government because, supposedly before an agreement is
presented to the President for signature, it will have been vetted several times over at different levels to
ensure that it conforms to law and can withstand public scrutiny.
(3) Within thirty days of the executed agreement, the President shall report it to Congress to give that branch
of government an opportunity to look over the agreement and interpose timely objections, if any. 69
Adhering to the aforementioned guidelines, this Court finds that SC-46 is indeed null and void for noncompliance
with the requirements of the 1987 Constitution.
1. The General Law on Oil Exploration
The disposition, exploration, development, exploitation, and utilization of indigenous petroleum in the Philippines
are governed by Presidential Decree No. 87 or the Oil Exploration and Development Act of 1972. This was enacted by
then President Ferdinand Marcos to promote the discovery and production of indigenous petroleum through the
utilization of government and/or local or foreign private resources to yield the maximum benefit to the Filipino
people and the revenues to the Philippine Government. 70
Contrary to the petitioners' argument, Presidential Decree No. 87, although enacted in 1972, before the adoption of
the 1987 Constitution, remains to be a valid law unless otherwise repealed, to wit:
ARTICLE XVIII - TRANSITORY PROVISIONS
Section 3. All existing laws, decrees, executive orders, proclamations, letters of instructions, and other executive
issuances not inconsistent with this Constitution shall remain operative until amended, repealed, or revoked.
If there were any intention to repeal Presidential Decree No. 87, it would have been done expressly by Congress. For
instance, Republic Act No. 7160, more popularly known as the Local Government Code of 1991, expressly repealed a
number of laws, including a specific provision in Presidential Decree No. 87, viz.:
SECTION 534. Repealing Clause. - (a) Batas Pambansa Blg. 337, otherwise known as the "Local Government Code,"
Executive Order No. 112 (1987), and Executive Order No. 319 (1988) are hereby repealed.
(b) Presidential Decree Nos. 684, 1191, 1508 and such other decrees, orders, instructions, memoranda and
issuances related to or concerning the barangay are hereby repealed.
(c) The provisions of Sections 2, 3, and 4 of Republic Act No. 1939 regarding hospital fund; Section 3, a (3)
and b (2) of Republic Act No. 5447 regarding the Special Education Fund; Presidential Decree No. 144 as
amended by Presidential Decree Nos. 559 and 1741; Presidential Decree No. 231 as amended; Presidential
Decree No. 436 as amended by Presidential Decree No. 558; and Presidential Decree Nos. 381, 436, 464, 477,
526, 632, 752, and 1136 are hereby repealed and rendered of no force and effect.
(d) Presidential Decree No. 1594 is hereby repealed insofar as it governs locally-funded projects.
(e) The following provisions are hereby repealed or amended insofar as they are inconsistent with the
provisions of this Code: Sections 2, 16 and 29 of Presidential Decree No. 704; Section 12 of Presidential
Decree No. 87, as amended; Sections 52, 53, 66, 67, 68, 69, 70, 71, 72, 73, and 74 of Presidential Decree No.
463, as amended; and Section 16 of Presidential Decree No. 972, as amended, and
(f) All general and special laws, acts, city charters, decrees, executive orders, proclamations and
administrative regulations, or part or parts thereof which are inconsistent with any of the provisions of this
Code are hereby repealed or modified accordingly. (Emphasis supplied.)
This Court could not simply assume that while Presidential Decree No. 87 had not yet been expressly repealed, it had
been impliedly repealed. As we held in Villareña v. The Commission on Audit, 71 "[i]mplied repeals are not lightly
presumed." It is a settled rule that when laws are in conflict with one another, every effort must be exerted to
reconcile them. In Republic of the Philippines v. Marcopper Mining Corporation, 72 we said:
The two laws must be absolutely incompatible, and a clear finding thereof must surface, before the inference of
implied repeal may be drawn. The rule is expressed in the maxim, interpretare et concordare leqibus est optimus
interpretendi, i.e., every statute must be so interpreted and brought into accord with other laws as to form a uniform
system of jurisprudence. The fundament is that the legislature should be presumed to have known the existing laws
on the subject and not have enacted conflicting statutes. Hence, all doubts must be resolved against any implied
repeal, and all efforts should be exerted in order to harmonize and give effect to all laws on the subject. (Citation
omitted.)
Moreover, in cases where the statute seems to be in conflict with the Constitution, but a construction that it is in
harmony with the Constitution is also possible, that construction should be preferred. 73 This Court, in Pangandaman
v. Commission on Elections74 expounding on this point, pronounced:
It is a basic precept in statutory construction that a statute should be interpreted in harmony with the Constitution
and that the spirit, rather than the letter of the law determines its construction; for that reason, a statute must be
read according to its spirit and intent. x x x. (Citation omitted.)
Consequently, we find no merit in petitioners' contention that SC-46 is prohibited on the ground that there is no
general law prescribing the standard or uniform terms, conditions, and requirements for service contracts involving
oil exploration and extraction.
But note must be made at this point that while Presidential Decree No. 87 may serve as the general law upon which a
service contract for petroleum exploration and extraction may be authorized, as will be discussed below, the
exploitation and utilization of this energy resource in the present case may be allowed only through a law passed by
Congress, since the Tañon Strait is a NIPAS 75 area.
2. President was not the signatory to SC-46 and the same was not submitted to Congress
While the Court finds that Presidential Decree No. 87 is sufficient to satisfy the requirement of a general law, the
absence of the two other conditions, that the President be a signatory to SC-46, and that Congress be notified of
such contract, renders it null and void.
As SC-46 was executed in 2004, its terms should have conformed not only to the provisions of Presidential Decree
No. 87, but also to those of the 1987 Constitution. The Civil Code provides: ARTICLE 1306. The contracting parties
may establish such stipulations, clauses, terms and conditions as they may deem convenient, provided they are not
contrary to law, morals, good customs, public order, or public policy. (Italics ours.)
In Heirs of San Miguel v. Court of Appeals, 76 this Court held that:
It is basic that the law is deemed written into every contract. Although a contract is the law between the parties, the
provisions of positive law which regulate contracts are deemed written therein and shall limit and govern the
relations between the parties. x x x. (Citations omitted.) Paragraph 4, Section 2, Article XII of the 1987 Constitution
requires that the President himself enter into any service contract for the exploration of petroleum. SC-46 appeared
to have been entered into and signed only by the DOE through its then Secretary, Vicente S. Perez, Jr., contrary to the
said constitutional requirement. Moreover, public respondents have neither shown nor alleged that Congress was
subsequently notified of the execution of such contract.
Public respondents' implied argument that based on the "alter ego principle," their acts are also that of then
President Macapagal-Arroyo's, cannot apply in this case. In Joson v. Torres, 77 we explained the concept of the alter
ego principle or the doctrine of qualified political agency and its limit in this wise:
Under this doctrine, which recognizes the establishment of a single executive, all executive and administrative
organizations are adjuncts of the Executive Department, the heads of the various executive departments are
assistants and agents of the Chief Executive, and, except in cases where the Chief Executive is required by the
Constitution or law to act in person or the exigencies of the situation demand that he act personally, the multifarious
executive and administrative functions of the Chief Executive are performed by and through the executive
departments, and the acts of the Secretaries of such departments, performed and promulgated in the regular course
of business, are, unless disapproved or reprobated by the Chief Executive presumptively the acts of the Chief
Executive. (Emphasis ours, citation omitted.)
While the requirements in executing service contracts in paragraph 4, Section 2 of Article XII of the 1987 Constitution
seem like mere formalities, they, in reality, take on a much bigger role. As we have explained in La Bugal, they are the
safeguards put in place by the framers of the Constitution to "eliminate or minimize the abuses prevalent during the
martial law regime."78 Thus, they are not just mere formalities, which will only render a contract unenforceable but
not void, if not complied with. They are requirements placed, not just in an ordinary statute, but in the fundamental
law, the non-observance of which will nullify the contract. Elucidating on the concept of a "constitution," this Court,
in Manila Prince Hotel v. Government Service Insurance System, 79 held:
A constitution is a system of fundamental laws for the governance and administration of a nation. It is supreme,
imperious, absolute and unalterable except by the authority from which it emanates. It has been defined as the
fundamental and paramount law of the nation. It prescribes the permanent framework of a system of government,
assigns to the different departments their respective powers and duties, and establishes certain fixed principles on
which government is founded. The fundamental conception in other words is that it is a supreme law to which all
other laws must conform and in accordance with which all private rights must be determined and all public authority
administered. Under the doctrine of constitutional supremacy, if a law or contract violates any norm of the
constitution that law or contract whether promulgated by the legislative or by the executive branch or entered into
by private persons for private purposes is null and void and without any force and effect. Thus, since the Constitution
is the fundamental, paramount and supreme law of the nation, it is deemed written in every statute and contract.
(Emphasis ours.)
As this Court has held in La Bugal, our Constitution requires that the President himself be the signatory of service
agreements with foreign-owned corporations involving the exploration, development, and utilization of our minerals,
petroleum, and other mineral oils. This power cannot be taken lightly.
In this case, the public respondents have failed to show that the President had any participation in SC-46. Their
argument that their acts are actually the acts of then President Macapagal-Arroyo, absent proof of her disapproval,
must fail as the requirement that the President herself enter into these kinds of contracts is embodied not just in any
ordinary statute, but in the Constitution itself. These service contracts involving the exploitation, development, and
utilization of our natural resources are of paramount interest to the present and future generations. Hence,
safeguards were put in place to insure that the guidelines set by law are meticulously observed and likewise to
eradicate the corruption that may easily penetrate departments and agencies by ensuring that the President has
authorized or approved of these service contracts herself.
Even under the provisions of Presidential Decree No. 87, it is required that the Petroleum Board, now the DOE,
obtain the President's approval for the execution of any contract under said statute, as shown in the following
provision:
SECTION 5. Execution of contract authorized in this Act. -Every contract herein authorized shall, subject to the
approval of the President, be executed by the Petroleum Board created in this Act, after due public notice pre-
qualification and public bidding or concluded through negotiations. In case bids are requested or if requested no bid
is submitted or the bids submitted are rejected by the Petroleum Board for being disadvantageous to the
Government, the contract may be concluded through negotiation.
In opening contract areas and in selecting the best offer for petroleum operations, any of the following alternative
procedures may be resorted to by the Petroleum Board, subject to prior approval of the President[.]
Even if we were inclined to relax the requirement in La Bugal to harmonize the 1987 Constitution with the
aforementioned provision of Presidential Decree No. 87, it must be shown that the government agency or
subordinate official has been authorized by the President to enter into such service contract for the government.
Otherwise, it should be at least shown that the President subsequently approved of such contract explicitly. None of
these circumstances is evident in the case at bar.
Service Contract No. 46 vis-a-vis Other Laws
Petitioners in G.R. No. 180771 claim that SC-46 violates Section 27 of Republic Act. No. 9147 or the Wildlife
Resources Conservation and Protection Act, which bans all marine exploration and exploitation of oil and gas
deposits. They also aver that Section 14 of Republic Act No. 7586 or the National Integrated Protected Areas System
Act of 1992 (NIPAS Act), which allows the exploration of protected areas for the purpose of information-gathering,
has been repealed by Section 27 of Republic Act No. 914 7. The said petitioners further claim that SC-46 is anathema
to Republic Act No. 8550 or the Philippine Fisheries Code of 1998, which protects the rights of the fisherfolk in the
preferential use of municipal waters, with the exception being limited only to research and survey activities. 80
The FIDEC, for its part, argues that to avail of the exceptions under Section 14 of the NIP AS Act, the gathering of
information must be in accordance with a DENR-approved program, and the exploitation and utilization of energy
resources must be pursuant to a general law passed by Congress expressly for that purpose. Since there is neither a
DENR approved program nor a general law passed by Congress, the seismic surveys and oil drilling operations were
all done illegally.81 The FIDEC likewise contends that SC-46 infringes on its right to the preferential use of the
communal fishing waters as it is denied free access within the prohibited zone, in violation not only of the Fisheries
Code but also of the 1987 Constitutional provisions on subsistence fisherfolk and social justice. 82 Furthermore, the
FIDEC believes that the provisions in Presidential Decree No. 87, which allow offshore drilling even in municipal
waters, should be deemed to have been rendered inoperative by the provisions of Republic Act No. 8550 and
Republic Act No. 7160, which reiterate the social justice provisions of the Constitution. 83
The public respondents invoke the rules on statutory construction and argue that Section 14 of the NIP AS Act is a
more particular provision and cannot be deemed to have been repealed by the more general prohibition in Section
27 of Republic Act No. 9147. They aver that Section 14, under which SC-46 falls, should instead be regarded as an
exemption to Section 27.84 Addressing the claim of petitioners in G.R. No. 180771 that there was a violation of
Section 27 of Republic Act No. 9147, the public respondents assert that what the section prohibits is the exploration
of minerals, which as defined in the Philippine Mining Act of 1995, exclude energy materials such as coal, petroleum,
natural gas, radioactive materials and geothennal energy. Thus, since SC-46 involves oil and gas exploration, Section
27 does not apply.85
The public respondents defend the validity of SC-46 and insist that it does not grant exclusive fishing rights to JAPEX;
hence, it does not violate the rule on preferential use of municipal waters. Moreover, they allege that JAPEX has not
banned fishing in the project area, contrary to the FIDEC's claim. The public respondents also contest the attribution
of the declining fish catch to the seismic surveys and aver that the allegation is unfounded. They claim that according
to the Bureau of Fisheries and Aquatic Resources' fish catch data, the reduced fish catch started in the 1970s due to
destructive fishing practices.86
Ruling of the Court
On the legality of Service Contract No. 46
vis-a-vis Other Laws
Although we have already established above that SC-46 is null and void for being violative of the 1987 Constitution, it
is our duty to still rule on the legality of SC-46 vis-a-vis other pertinent laws, to serve as a guide for the Government
when executing service contracts involving not only the Tafion Strait, but also other similar areas. While the
petitioners allege that SC-46 is in violation of several laws, including international ones, their arguments focus
primarily on the protected status of the Tañon Strait, thus this Court will concentrate on those laws that pertain
particularly to the Tañon Strait as a protected seascape.
The Tañon Strait is a narrow passage of water bounded by the islands of Cebu in the East and Negros in the West. It
harbors a rich biodiversity of marine life, including endangered species of dolphins and whales. For this reason,
former President Fidel V. Ramos declared the Tañon Strait as a protected seascape in 1998 by virtue of Proclamation
No. 1234 -Declaring the Tañon Strait situated in the Provinces of Cebu, Negros Occidental and Negros Oriental as a
Protected Area pursuant to the NIP AS Act and shall be known as Tañon Strait Protected Seascape. During former
President Joseph E. Estrada's time, he also constituted the Tañon Strait Commission via Executive Order No. 76 to
ensure the optimum and sustained use of the resources in that area without threatening its marine life. He followed
this with Executive Order No. 177,87 wherein he included the mayor of Negros Occidental Municipality/City as a
member of the Tañon Strait Commission, to represent the LGUs concerned. This Commission, however, was
subsequently abolished in 2002 by then President Gloria Macapagal-Arroyo, via Executive Order No. 72. 88
True to the constitutional policy that the "State shall protect and advance the right of the people to a balanced and
healthful ecology in accord with the rhythm and harmony of nature," 89 Congress enacted the NIP AS Act to secure the
perpetual existence of all native plants and animals through the establishment of a comprehensive system of
integrated protected areas. These areas possess common ecological values that were incorporated into a holistic plan
representative of our natural heritage. The system encompasses outstandingly remarkable areas and biologically
important public lands that are habitats of rare and endangered species of plants and animals, biogeographic zones
and related ecosystems, whether terrestrial, wetland, or marine. 90 It classifies and administers all the designated
protected areas to maintain essential ecological processes and life-support systems, to preserve genetic diversity, to
ensure sustainable use of resources found therein, and to maintain their natural conditions to the greatest extent
possible.91 The following categories of protected areas were established under the NIPAS Act:
a. Strict nature reserve;
b. Natural park;
c. Natural monument;
d. Wildlife sanctuary;
e. Protected landscapes and seascapes;
f. Resource reserve;
g. Natural biotic areas; and
h. Other categories established by law, conventions or international agreements which the Philippine
Government is a signatory. 92
Under Section 4 of the NIP AS Act, a protected area refers to portions of land and water, set aside due to their unique
physical and biological significance, managed to enhance biological diversity and protected against human
exploitation.
The Tañon Strait, pursuant to Proclamation No. 1234, was set aside and declared a protected area under the category
of Protected Seascape. The NIP AS Act defines a Protected Seascape to be an area of national significance
characterized by the harmonious interaction of man and land while providing opportunities for public enjoyment
through recreation and tourism within the normal lifestyle and economic activity of this areas; 93 thus a management
plan for each area must be designed to protect and enhance the permanent preservation of its natural
conditions.94 Consistent with this endeavor is the requirement that an Environmental Impact Assessment (EIA) be
made prior to undertaking any activity outside the scope of the management plan. Unless an ECC under the EIA
system is obtained, no activity inconsistent with the goals of the NIP AS Act shall be implemented. 95
The Environmental Impact Statement System (EISS) was established in 1978 under Presidential Decree No. 1586. It
prohibits any person, partnership or corporation from undertaking or operating any declared environmentally critical
project or areas without first securing an ECC issued by the President or his duly authorized representative. 96Pursuant
to the EISS, which called for the proper management of environmentally critical areas, 97 Proclamation No. 214698 was
enacted, identifying the areas and types of projects to be considered as environmentally critical and within the scope
of the EISS, while DENR Administrative Order No. 2003-30 provided for its Implementing Rules and Regulations (IRR).
DENR Administrative Order No. 2003-30 defines an environmentally critical area as "an area delineated as
environmentally sensitive such that significant environmental impacts are expected if certain types of proposed
projects or programs are located, developed, or implemented in it"; 99 thus, before a project, which is "any activity,
regardless of scale or magnitude, which may have significant impact on the environment," 100 is undertaken in it, such
project must undergo an EIA to evaluate and predict the likely impacts of all its stages on the environment. 101An EIA is
described in detail as follows:
h. Environmental Impact Assessment (EIA) - process that involves evaluating and predicting the likely impacts of a
project (including cumulative impacts) on the environment during construction, commissioning, operation and
abandonment. It also includes designing appropriate preventive, mitigating and enhancement measures addressing
these consequences to protect the environment and the community's welfare. The process is undertaken by, among
others, the project proponent and/or EIA Consultant, EMB, a Review Committee, affected communities and other
stakeholders.102
Under Proclamation No. 2146, the Tañon Strait is an environmentally critical area, having been declared as a
protected area in 1998; therefore, any activity outside the scope of its management plan may only be implemented
pursuant to an ECC secured after undergoing an EIA to determine the effects of such activity on its ecological system.
The public respondents argue that they had complied with the procedures in obtaining an ECC 103 and that SC-46 falls
under the exceptions in Section 14 of the NIP AS Act, due to the following reasons:
1) The Tañon Strait is not a strict nature reserve or natural park;
2) Exploration is only for the purpose of gathering information on possible energy resources; and 3)
Measures are undertaken to ensure that the exploration is being done with the least damage to surrounding
areas.104
We do not agree with the arguments raised by the public respondents.
Sections 12 and 14 of the NIPAS Act read:
SECTION 12. Environmental Impact Assessment. - Proposals for activities which are outside the scope of the
management plan for protected areas shall be subject to an environmental impact assessment as required by law
before they are adopted, and the results thereof shall be taken into consideration in the decision-making process.
No actual implementation of such activities shall be allowed without the required Environmental Compliance
Certificate (ECC) under the Philippine Environmental Impact Assessment (EIA) system. In instances where such
activities are allowed to be undertaken, the proponent shall plan and carry them out in such manner as will minimize
any adverse effects and the preventive and remedial action when appropriate. The proponent shall be liable for any
damage due to lack of caution or indiscretion.
SECTION 14. Survey for Energy Resources. - Consistent with the policies declared in Section 2 hereof, protected areas,
except strict nature reserves and natural parks, may be subjected to exploration only for the purpose of gathering
information on energy resources and only if such activity is carried out with the least damage to surrounding areas.
Surveys shall be conducted only in accordance with a program approved by the DENR, and the result of such surveys
shall be made available to the public and submitted to the President for recommendation to Congress. Any
exploitation and utilization of energy resources found within NIP AS areas shall be allowed only through a law passed
by Congress.
It is true that the restrictions found under the NIP AS Act are not without exceptions. However, while an exploration
done for the purpose of surveying for energy resources is allowed under Section 14 of the NIP AS Act, this does not
mean that it is exempt from the requirement to undergo an EIA under Section 12. In Sotto v. Sotto, 105 this Court
explained why a statute should be construed as a whole:
A statute is passed as a whole and not in parts or sections and is animated by one general purpose and intent.
Consequently each part or section should be construed in connection with every other part or section and so as to
produce a harmonious whole. It is not proper to confine the attention to the one section to be construed. It is always
an unsafe way of construing a statute or contract to divide it by a process of etymological dissection, into separate
words, and then apply to each, thus separated from its context, some particular definition given by lexicographers,
and then reconstruct the instrument upon the basis of these definitions. An instrument must always be construed as
a whole, and the particular meaning to be attached to any word or phrase is usually to be ascertained from the
context, the nature of the subject treated of and the purpose or intention of the parties who executed the contract,
or of the body which enacted or framed the statute or constitution. x x x.
Surveying for energy resources under Section 14 is not an exemption from complying with the EIA requirement in
Section 12; instead, Section 14 provides for additional requisites before any exploration for energy resources may be
done in protected areas.
The rationale for such additional requirements are incorporated m Section 2 of the NIP AS Act, to wit:
SECTION 2. Declaration of Policy - Cognizant of the profound impact of man's activities on all components of the
natural environment particularly the effect of increasing population, resource exploitation and industrial
advancement and recognizing the critical importance of protecting and maintaining the natural biological and
physical diversities of the environment notably on areas with biologically unique features to sustain human life and
development, as well as plant and animal life, it is hereby declared the policy of the State to secure for the Filipino
people of present and future generations the perpetual existence of all native plants and animals through the
establishment of a comprehensive system of integrated protected areas within the classification of national park as
provided for in the Constitution.
It is hereby recognized that these areas, although distinct in features, possess common ecological values that may be
incorporated into a holistic plan representative of our natural heritage; that effective administration of this area is
possible only through cooperation among national government, local government and concerned private
organizations; that the use and enjoyment of these protected areas must be consistent with the principles of
biological diversity and sustainable development.
To this end, there is hereby established a National Integrated Protected Areas System (NIPAS), which shall encompass
outstandingly remarkable areas and biologically important public lands that are habitats of rare and endangered
species of plants and animals, biogeographic zones and related ecosystems, whether terrestrial, wetland or marine,
all of which shall be designated as "protected areas."
The public respondents themselves admitted that JAPEX only started to secure an ECC prior to the second sub-phase
of SC-46, which required the drilling of an oil exploration well. This means that when the seismic surveys were done
in the Tañon Strait, no such environmental impact evaluation was done. Unless seismic surveys are part of the
management plan of the Tañon Strait, such surveys were done in violation of Section 12 of the NIPAS Act and Section
4 of Presidential Decree No. 1586, which provides:
Section 4. Presidential Proclamation of Environmentally Critical Areas and Projects. - The President of the Philippines
may, on his own initiative or upon recommendation of the National Environmental Protection Council, by
proclamation declare certain projects, undertakings or areas in the country as environmentally critical. No person,
partnership or corporation shall undertake or operate any such declared environmentally critical project or area
without first securing an Environmental Compliance Certificate issued by the President or his duly authorized
representative. For the proper management of said critical project or area, the President may by his proclamation
reorganize such government offices, agencies, institutions, corporations or instrumentalities including the re-
alignment of government personnel, and their specific functions and responsibilities.
For the same purpose as above, the Ministry of Human Settlements shall: (a) prepare the proper land or water use
pattern for said critical project(s) or area(s); (b) establish ambient environmental quality standards; (c) develop a
program of environmental enhancement or protective measures against calamitous factors such as earthquakes,
floods, water erosion and others, and (d) perform such other functions as may be directed by the President from
time to time.
The respondents' subsequent compliance with the EISS for the second sub-phase of SC-46 cannot and will not cure
this violation. The following penalties are provided for under Presidential Decree No. 1586 and the NIPAS Act.
Section 9 of Presidential Decree No. 1586 provides for the penalty involving violations of the ECC requirement:
Section 9. Penalty for Violation. - Any person, corporation or partnership found violating Section 4 of this Decree, or
the terms and conditions in the issuance of the Environmental Compliance Certificate, or of the standards, rules and
regulations issued by the National Environmental Protection Council pursuant to this Decree shall be punished by the
suspension or cancellation of his/its certificates and/or a fine in an amount not to exceed Fifty Thousand Pesos
(₱50,000.00) for every violation thereof, at the discretion of the National Environmental Protection Council.
(Emphasis supplied.)
Violations of the NIP AS Act entails the following fines and/or imprisonment under Section 21:
SECTION 21. Penalties. - Whoever violates this Act or any rules and regulations issued by the Department pursuant to
this Act or whoever is found guilty by a competent court of justice of any of the offenses in the preceding section
shall be fined in the amount of not less than Five thousand pesos (₱5,000) nor more than Five hundred thousand
pesos (₱500,000), exclusive of the value of the thing damaged or imprisonment for not less than one (1) year but not
more than six (6) years, or both, as determined by the court: Provided, that, if the area requires rehabilitation or
restoration as determined by the court, the offender shall be required to restore or compensate for the restoration to
the damages: Provided, further, that court shall order the eviction of the offender from the land and the forfeiture in
favor of the Government of all minerals, timber or any species collected or removed including all equipment, devices
and firearms used in connection therewith, and any construction or improvement made thereon by the offender. If
the offender is an association or corporation, the president or manager shall be directly responsible for the act of his
employees and laborers: Provided, finally, that the DENR may impose administrative fines and penalties consistent
with this Act. (Emphases supplied.) Moreover, SC-46 was not executed for the mere purpose of gathering information
on the possible energy resources in the Tañon Strait as it also provides for the parties' rights and obligations relating
to extraction and petroleum production should oil in commercial quantities be found to exist in the area. While
Presidential Decree No. 87 may serve as the general law upon which a service contract for petroleum exploration and
extraction may be authorized, the exploitation and utilization of this energy resource in the present case may be
allowed only through a law passed by Congress, since the Tañon Strait is a NIPAS area. 106Since there is no such law
specifically allowing oil exploration and/or extraction in the Tañon Strait, no energy resource exploitation and
utilization may be done in said protected seascape.
In view of the foregoing premises and conclusions, it is no longer necessary to discuss the other issues raised in these
consolidated petitions.
WHEREFORE, the Petitions in G.R. Nos. 180771 and 181527 are GRANTED, Service Contract No. 46 is hereby declared
NULL AND VOID for violating the 1987 Constitution, Republic Act No. 7586, and Presidential Decree No. 1586.
SO ORDERED.
CONCURRING OPINION
"Until one has loved an animal,
a part of one 's soul remains unawakened."
Anatole France
LEONEN, J.:
I concur in the result, with the following additional reasons.
I
In G.R. No. 180771, petitioners Resident Marine Mammals allegedly bring their case in their personal capacity,
alleging that they stand to benefit or be injured from the judgment on the issues. The human petitioners implead
themselves in a representative capacity "as legal guardians of the lesser life-forms and as responsible stewards of
God's Creations."1 They use Oposa v. Factoran, Jr.2 as basis for their claim, asserting their right to enforce
international and domestic environmental laws enacted for their benefit under the concept of stipulation pour
autrui.3As the representatives of Resident Marine Mammals, the human petitioners assert that they have the
obligation to build awareness among the affected residents of Tañon Strait as well as to protect the environment,
especially in light of the government's failure, as primary steward, to do its duty under the doctrine of public trust. 4
Resident Marine Mammals and the human petitioners also assert that through this case, this court will have the
opportunity to lower the threshold for locus standi as an exercise of "epistolary jurisdiction." 5
The zeal of the human petitioners to pursue their desire to protect the environment and to continue to define
environmental rights in the context of actual cases is commendable. However, the space for legal creativity usually
required for advocacy of issues of the public interest is not so unlimited that it should be allowed to undermine the
other values protected by current substantive and procedural laws. Even rules of procedure as currently formulated
set the balance between competing interests. We cannot abandon these rules when the necessity is not clearly and
convincingly presented.
The human petitioners, in G.R. No. 180771, want us to create substantive and procedural rights for animals through
their allegation that they can speak for them. Obviously, we are asked to accept the premises that (a) they were
chosen by the Resident Marine Mammals of Tañon Strait; (b) they were chosen by a representative group of all the
species of the Resident Marine Mammals; (c) they were able to communicate with them; and (d) they received clear
consent from their animal principals that they would wish to use human legal institutions to pursue their interests.
Alternatively, they ask us to acknowledge through judicial notice that the interests that they, the human petitioners,
assert are identical to what the Resident Marine Mammals would assert had they been humans and the legal
strategies that they invoked are the strategies that they agree with.
In the alternative, they want us to accept through judicial notice that there is a relationship of guardianship between
them and all the resident mammals in the affected ecology.
Fundamental judicial doctrines that may significantly change substantive and procedural law cannot be founded on
feigned representation.
Instead, I agree that the human petitioners should only speak for themselves and already have legal standing to sue
with respect to the issue raised in their pleading. The rules on standing have already been liberalized to take into
consideration the difficulties in the assertion of environmental rights. When standing becomes too liberal, this can be
the occasion for abuse.
II
Rule 3, Section 1 of the 1997 Rules of Civil Procedure, in part, provides:
SECTION 1. Who may be parties; plaintiff and defendant. - Only natural or juridical persons, or entities authorized by
law may be parties in a civil action.
The Rules provide that parties may only be natural or juridical persons or entities that may be authorized by statute
to be parties in a civil action.
Basic is the concept of natural and juridical persons in our Civil Code:
ARTICLE 37. Juridical capacity, which is the fitness to be the subject of legal relations, is inherent in every natural
person and is lost only through death. Capacity to act, which is the power to do acts with legal effect, is acquired and
may be lost.
Article 40 further defines natural persons in the following manner:
ARTICLE 40. Birth determines personality; but the conceived child shall be considered born for all purposes that are
favorable to it, provided it be born later with the conditions specified 'in the following article.
Article 44, on the other hand, enumerates the concept of a juridical person:
ARTICLE 44. The following are juridical persons:
(1) The State and its political subdivisions;
(2) Other corporations, institutions and entities for public interest or purpose, created by law; their
personality begins as soon as they have been constituted according to law;
(3) Corporations, partnerships and associations for private interest or purpose to which the law grants a
juridical personality, separate and distinct from that of each shareholder, partner or member.
Petitioners in G.R. No. 180771 implicitly suggest that we amend, rather than simply construe, the provisions of the
Rules of Court as well as substantive law to accommodate Resident Marine Mammals or animals. This we cannot do.
Rule 3, Section 2 of the 1997 Rules of Civil Procedure further defines real party in interest:
SEC. 2. Parties in interest.-A real party in interest is the party who stands to be benefited or injured by the judgment
in the suit, or the party entitled to the avails of the suit. Unless otherwise authorized by law or these Rules, every
action must be prosecuted or defended in the name of the real party in interest. (2a) 6
A litigant who stands to benefit or sustain an injury from the judgment of a case is a real party in interest. 7 When a
case is brought to the courts, the real party in interest must show that another party's act or omission has caused a
direct injury, making his or her interest both material and based on an enforceable legal right. 8
Representatives as parties, on the other hand, are parties acting in representation of the real party in interest, as
defined in Rule 3, Section 3 of the 1997 Rules of Civil Procedure:
SEC. 3. Representatives as parties. - Where the action is allowed to be prosecuted or defended by a representative or
someone acting in a fiduciary capacity, the beneficiary shall be included in the title of the case and shall be deemed
to be the real party in interest. A representative may be a trustee of an express rust, a guardian, an executor or
administrator, or a party authorized by law or these Rules. An agent acting in his own name and for the benefit of an
undisclosed principal may sue or be sued without joining the principal except when the contract involves things
belonging to the principal.(3a)9
The rule is two-pronged. First, it defines .a representative as a party who is not bound to directly or actually benefit
or suffer from the judgment, but instead brings a case in favor of an identified real party in interest. 10 The
representative is an outsider to the cause of action. Second, the rule provides a list of who may be considered as
"representatives." It is not an exhaustive list, but the rule limits the coverage only to those authorized by law or the
Rules of Court.11
These requirements should apply even in cases involving the environment, which means that for the Petition of the
human petitioners to prosper, they must show that (a) the Resident Marine Mammals are real parties in interest; and
(b) that the human petitioners are authorized by law or the Rules to act in a representative capacity.
The Resident Marine Mammals are comprised of "toothed whales, dolphins, porpoises, and other cetacean species
inhabiting Tañon Strait."12 While relatively new in Philippine jurisdiction, the issue of whether animals have legal
standing before courts has been the subject of academic discourse in light of the emergence of animal and
environmental rights.
In the United States, anim4l rights advocates have managed to establish a system which Hogan explains as the
"guardianship model for nonhuman animals": 13
Despite Animal Lovers, there exists a well-established system by which nonhuman animals may obtain judicial review
to enforce their statutory rights and protections: guardianships. With court approval, animal advocacy organizations
may bring suit on behalf of nonhuman animals in the same way court-appointed guardians bring suit on behalf of
mentally-challenged humans who possess an enforceable right but lack the ability to enforce it themselves.
In the controversial but pivotal Should Trees Have Standing?-Toward Legal Rights for Natural Objects, Christopher D.
Stone asserts that the environment should possess the right to seek judicial redress even though it is incapable of
representing itself. While asserting the rights of
speechless entities such as the environment or nonhuman animals certainly poses legitimate challenges - such as
identifying the proper spokesman -the American legal system is already well-equipped with a reliable mechanism by
which nonhumans may obtain standing via a judicially established guardianship. Stone notes that other speechless -
and nonhuman - entities such as corporations, states, estates, and municipalities have standing to bring suit on their
own behalf. There is little reason to fear abuses under this regime as procedures for removal and substitution,
avoiding conflicts of interest, and termination of a guardianship are well established.
In fact, the opinion in Animal Lovers suggests that such an arrangement is indeed possible. The court indicated that
AL VA might have obtained standing in its own right if it had an established history of dedication to the cause of the
humane treatment of animals. It noted that the Fund for Animals had standing and indicated that another more well-
known advocacy organization might have had standing as well. The court further concluded that an organization's
standing is more than a derivative of its history, but history is a relevant consideration where organizations are not
well-established prior to commencing legal action. ALVA was not the proper plaintiff because it could not identify
previous activities demonstrating its recognized activism for and commitment to the dispute independent of its
desire to pursue legal action. The court's analysis suggests that a qualified organization with a demonstrated
commitment to a cause could indeed bring suit on behalf of the speechless in the form of a court-sanctioned
guardianship.
This Comment advocates a shift in contemporary standing doctrine to empower non-profit organizations with an
established history of dedication to the cause and relevant expertise to serve as official guardians ad !item on behalf
of nonhuman animals interests. The American legal system has numerous mechanisms for representing the rights
and interests of nonhumans; any challenges inherent in extending these pre-existing mechanisms to nonhuman
animals are minimal compared to an interest in the proper administration of justice. To adequately protect the
statutory rights of nonhuman animals, the legal system must recognize those statutory rights independent of humans
and provide a viable means of enforcement. Moreover, the idea of a guardianship for speechless plaintiffs is not new
and has been urged on behalf of the natural environment. 'Such a model is even more compelling as applied to
nonhuman animals, because they are sentient beings with the ability to feel pain and exercise rational thought. Thus,
animals are qualitatively different from other legally protected nonhumans and therefore have interests deserving
direct legal protection.
Furthermore, the difficulty of enforcing the statutory rights of nonhuman animals threatens the integrity of the
federal statutes designed to protect them, essentially rendering them meaningless. Sensing that laws protecting
nonhuman animals would be difficult to enforce, Congress provided for citizen suit provisions: the most well-known
example is found in the Endangered Species Act (ESA). Such provisions are evidence of legislative intent to encourage
civic participation on behalf of nonhuman animals. Our law of standing should reflect this intent and its implication
that humans are suitable representatives of the natural environment, which includes nonhuman animals. 14 (Emphasis
supplied, citation omitted)
When a court allows guardianship as a basis of representation, animals are considered as similarly situated as
individuals who have enforceable rights but, for a legitimate reason (e.g., cognitive disability), are unable to bring suit
for themselves. They are also similar to entities that by their very nature are incapable of speaking for themselves
(e.g., corporations, states, and others).
In our jurisdiction, persons and entities are recognized both in law and the Rules of Court as having standing to sue
and, therefore, may be properly represented as real parties in interest. The same cannot be said about animals.
Animals play an important role in households, communities, and the environment. While we, as humans, may feel
the need to nurture and protect them, we cannot go as far as saying we represent their best interests and can,
therefore, speak for them before the courts. As humans, we cannot be so arrogant as to argue that we know the
suffering of animals and that we know what remedy they need in the face of an injury.
Even in Hogan's discussion, she points out that in a case before the United States District Court for the Central District
of California, Animal Lovers Volunteer Ass'n v. Weinberger, 15 the court held that an emotional response to what
humans perceive to be an injury inflicted on an animal is not within the "zone-of-interest" protected by law. 16Such
sympathy cannot stand independent of or as a substitute for an actual injury suffered by the claimant. 17 The ability to
represent animals was further limited in that case by the need to prove "genuine dedication" to asserting and
protecting animal rights:
What ultimately proved fatal to ALVA 's claim, however, was the court's assertion that standing doctrine further
required ALVA to differentiate its genuine dedication to the humane treatment of animals from the general disdain
for animal cruelty shared by the public at large. In doing so, the court found ALVA 's asserted organizational injury to
be abstract and thus relegated ALVA to the ranks of the "concerned bystander. "
....
In fact, the opinion in Animal Lovers suggests that such an arrangement is indeed possible. The court indicated that
ALVA might have obtained standing in its own right if it had an established history of dedication to the cause of the
humane treatment of animals. It noted that the Fund for Animals had standing and indicated that another more well-
known advocacy organization might have had standing as well. The court further concluded that an organization's
standing is more than a derivative of its history, but history is a relevant consideration where organizations are not
well-established prior to commencing legal action. ALVA was not the proper plaintiff because it could not identify
previous activities demonstrating its recognized activism for and commitment to the dispute independent of its
desire to pursue legal action. The court's analysis suggests that a qualified organization with a demonstrated
commitment to a cause could indeed bring suit on behalf of the speechless in the form of a court-sanctioned
guardianship.18(Emphasis supplied, citation omitted)
What may be argued as being parallel to this concept of guardianship is the principle of human stewardship over the
environment in a citizen suit under the Rules of Procedure for Environmental Cases. A citizen suit allows any Filipino
to act as a representative of a party who has enforceable rights under environmental laws before Philippine courts,
and is defined in Section 5: .
SEC. 5. Citizen suit. - Any Filipino citizen in representation of others, including minors or generations yet unborn, may
file an action to enforce rights or obligations under environmental laws. Upon the filing of a citizen suit, the court
shall issue an order which shall contain a brief description of the cause of action and the reliefs prayed for, requiring
all interested parties to manifest their interest to intervene in the case within fifteen (15) days from notice thereof.
The plaintiff may publish the order once in a newspaper of a general circulation in the Philippines or furnish all
affected barangays copies of said order.
There is no valid reason in law or the practical requirements of this case to implead and feign representation on
behalf of animals. To have done so betrays a very anthropocentric view of environmental advocacy. There is no way
that we, humans, can claim to speak for animals let alone present that they would wish to use our court system,
which is designed to ensure that humans seriously carry their responsibility including ensuring a viable ecology for
themselves, which of course includes compassion for all living things.
Our rules on standing are sufficient and need not be further relaxed.
In Arigo v. Swift,19 I posed the possibility of further reviewing the broad interpretation we have given to the rule on
standing. While representatives are not required to establish direct injury on their part, they should only be allowed
to represent after complying with the following: [I]t is imperative for them to indicate with certainty the injured
parties on whose behalf they bring the suit. Furthermore, the interest of those they represent must be based upon
concrete legal rights. It is not sufficient to draw out a perceived interest from a general, nebulous idea of a potential
"injury."20
I reiterate my position in Arigo v. Swift and in Paje v. Casiño 21 regarding this rule alongside the appreciation of legal
standing in Oposa v. Factoran22 for environmental cases. In Arigo, I opined that procedural liberality, especially in
cases brought by representatives, should be used with great caution:
Perhaps it is time to revisit the ruling in Oposa v. Factoran.
That case was significant in that, at that time, there was need to call attention to environmental concerns in light of
emerging international legal principles. While "intergenerational responsibility" is a noble principle, it should not be
used to obtain judgments that would preclude future generations from making their own assessment based on their
actual concerns. The present generation must restrain itself from assuming that it can speak best for those who will
exist at a different time, under a different set of circumstances. In essence, the unbridled resort to representative suit
will inevitably result in preventing future generations from protecting their own rights and pursuing their own
interests and decisions. It reduces the autonomy of our children and our children 's children. Even before they are
born, we again restricted their ability to make their own arguments.
It is my opinion that, at best, the use of the Oposa doctrine in environmental cases should be allowed only when a)
there is a clear legal basis for the representative suit; b) there are actual concerns based squarely upon an existing
legal right; c) there is no possibility of any countervailing interests existing within the population represented or
those that are yet to be born; and d) there is an absolute necessity for such standing because there is a threat of
catastrophe so imminent that an immediate protective measure is necessary. Better still, in the light of its costs and
risks, we abandon the precedent all together. 23 (Emphasis in the original)
Similarly, in Paje:
A person cannot invoke the court's jurisdiction if he or she has no right or interest to protect. He or she who invokes
the court's jurisdiction must be the "owner of the right sought to be enforced." In other words, he or she must have a
cause of action. An action may be dismissed on the ground of lack of cause of action if the person who instituted it is
not the real party in interest. 24 The term "interest" under the Rules of Court must refer to a material interest that is
not merely a curiosity about or an "interest in the question involved." The interest must be present and substantial. It
is not a mere expectancy or a future, contingent interest.
A person who is not a real party in interest may institute an action if he or she is suing as representative of a .real
party in interest. When an action is prosecuted or defended by a representative, that representative is not and does
not become the real party in interest. The person represented is deemed the real party in interest. The
representative remains to be a third party to the action instituted on behalf of another.
....
To sue under this rule, two elements must be present: "(a) the suit is brought on behalf of an identified party whose
right has been violated, resulting in some form of damage, and (b) the representative authorized by law or the Rules
of Court to represent the victim."
The Rules of Procedure for Environmental Cases allows filing of a citizen's suit. A citizen's suit under this rule allows
any Filipino citizen to file an action for the enforcement of environmental law on behalf of minors or generations yet
unborn. It is essentially a representative suit that allows persons who are not real parties in interest to institute
actions on behalf of the real party in interest.
The expansion of what constitutes "real party in interest" to include minors and generations yet unborn is a
recognition of this court's ruling in Oposa v. Factoran. This court recognized the capacity of minors (represented by
their parents) to file a class suit on behalf of succeeding generations based on the concept of intergenerational
responsibility to ensure the future generation's access to and enjoyment of [the] country's natural resources.
To allow citizen's suits to enforce environmental rights of others, including future generations, is dangerous for three
reasons:
First, they run the risk of foreclosing arguments of others who are unable to take part in the suit, putting into.
question its representativeness. Second, varying interests may potentially result in arguments that are bordering on
political issues, the resolutions of which do not fall upon this court. Third, automatically allowing a class or citizen's
suit on behalf of minors and generations yet unborn may result in the oversimplification of what may be a complex
issue, especially in light of the impossibility of determining future generation's true interests on the matter.
In citizen's suits, persons who may have no interest in the case may file suits for others. Uninterested persons will
argue for the persons they represent, and the court will decide based on their evidence and arguments. Any decision
by the court will be binding upon the beneficiaries, which in this case are the minors and the future generations. The
court's decision will be res judicata upon them and conclusive upon the issues presented. 25
The danger in invoking Oposa v. Factoran to justify all kinds of environmental claims lies in its potential to diminish
the value of legitimate environmental rights. Extending the application of "real party in interest" to the Resident
Marine Mammals, or animals in general, through a judicial pronouncement will potentially result in allowing
petitions based on mere concern rather than an actual enforcement of a right. It is impossible for animals to tell
humans what their concerns are. At best, humans can only surmise the extent of injury inflicted, if there be any.
Petitions invoking a right and seeking legal redress before this court cannot be a product of guesswork, and
representatives have the responsibility to ensure that they bring "reasonably cogent, rational, scientific, well-founded
arguments"26 on behalf of those they represent.
Creative approaches to fundamental problems should be welcome. However, they should be considered carefully so
that no unintended or unwarranted consequences should follow. I concur with the approach of Madame Justice
Teresita J. Leonardo-De Castro in her brilliant ponencia as it carefully narrows down the doctrine in terms of standing.
Resident Marine Mammals and the human petitioners have no legal standing to file any kind of petition.
However, I agree that petitioners in G.R. No. 181527, namely, Central Visayas Fisherfolk Development Center,.
Engarcial, Yanong, and Labid, have standing both as real parties in interest and as representatives of subsistence
fisherfolks of the Municipalities of Aloguinsan and Pinamungahan, Cebu, and their families, and the present and
future generations of Filipinos whose rights are similarly affected. The activities undertaken under Service Contract
46 (SC-46) directly affected their source of livelihood, primarily felt through the significant reduction of their fish
harvest.27 The actual, direct, and material damage they suffered, which has potential long-term effects transcending
generations, is a proper subject of a legal suit.
III
In our jurisdiction, there is neither reason nor any legal basis for the concept of implied petitioners, most especially
when the implied petitioner was a sitting President of the Republic of the Philippines. In G.R. No. 180771, apart from
adjudicating unto themselves the status of "legal guardians" of whales, dolphins, porpoises, and other cetacean
species, human petitioners also impleaded Former President Gloria Macapagal-Arroyo as "unwilling co-petitioner"
for "her express declaration and undertaking in the ASEAN Charter to protect Tañon Strait." 28
No person may implead any other person as a co-plaintiff or co-petitioner without his or her consent. In our
jurisdiction, only when there is a party that should have been a necessary party but was unwilling to join would there
be an allegation as to why that party has been omitted. In Rule 3, Section 9 of the 1997 Rules of Civil Procedure:
SEC. 9. Non-joinder of necessary parties to be pleaded. -Whenever in any pleading in which a claim is asserted a
necessary party is not joined, the pleader shall set forth his name, if known, and shall state why he is omitted. Should
the court find the reason for the omission unmeritorious, it may order the inclusion of the omitted necessary party if
jurisdiction over his person may be obtained.
The failure to comply with the order for his inclusion, without justifiable cause, shall be deemed a waiver of the claim
against such party.
The non-inclusion of a necessary party does not prevent the court from proceeding in the action, and the judgment
rendered therein shall be without prejudice to the rights of such necessary party. 29
A party who should have been a plaintiff or petitioner but whose consent cannot be obtained should be impleaded
as a defendant in the nature of an unwilling co-plaintiff under Rule 3, Section 10 of the 1997 Rules of Civil Procedure:
SEC. 10. Unwilling co-plaintiff. - If the consent of any party who should be joined as plaintiff can not be obtained, he
may be made a defendant and the reason therefor shall be stated in the complaint. 30
The reason for this rule is plain: Indispensable party plaintiffs who should be part of the action but who do not
consent should be put within the jurisdiction of the court through summons or other court processes. Petitioners.
should not take it upon themselves to simply imp lead any party who does not consent as a petitioner. This places the
unwilling co-petitioner at the risk of being denied due process.
Besides, Former President Gloria Macapagal-Arroyo cannot be a party to this suit. As a co-equal constitutional
department, we cannot assume that the President needs to enforce policy directions by suing his or her alter-egos.
The procedural situation caused by petitioners may have gained public attention, but its legal absurdity borders on
the contemptuous. The Former President's name should be stricken out of the title of this case.
IV
I also concur with the conclusion that SC-46 is both. illegal and unconstitutional.
SC-46 is illegal because it violates Republic Act No. ·7586 or the National Integrated Protected Areas System Act of
1992, and Presidential Decree No. 1234, 31 which declared Tañon Strait as a protected seascape. It is unconstitutional
because it violates the fourth paragraph of Article XII, Section 2 of the Constitution.
V
Petitioner Central Visayas Fisherfolk Development Center asserts that SC-46 violated Article XII, Section 2, paragraph
1 of the .1987 Constitution because Japan Petroleum Exploration Co., Ltd. (JAPEX) is 100% Japanese-owned. 32 It
further asserts that SC-46 cannot be validly classified as a technical and financial assistance agreement executed
under Article XII, Section 2, paragraph 4 of the 1987 Constitution. 33 Public respondents counter that SC-46 does not
fall under the coverage of paragraph 1, but is a validly executed contract under paragraph 4. 34· Public respondents
further aver that SC-46 neither granted exclusive fishing rights to JAPEX nor violated Central Visayas Fisherfolk
Development Center's right to preferential use of communal marine and fishing resources. 35
VI
Article XII, Section 2 of the 1987 Constitution states:
Section 2. All lands of the public domain, waters, minerals, coal, petroleum, and other mineral oils, all forces of
potential energy, fisheries, forests or timber, wildlife, flora and fauna, and other natural resources are owned by the
State. With the exception. of agricultural lands, all other natural resources shall not be alienated. The exploration,
development, and utilization of natural resources shall be under the full control and supervision of the State. The
State may directly undertake such activities, or it may enter into co-production, joint venture, or production-sharing
agreements with Filipino citizens, or corporations or associations at least sixty per centum of whose capital is owned
by such citizens. Such agreements may be for a period not exceeding twenty-five years, renewable for not more than
twenty-five years, and under such terms and conditions as may be provided by law. In cases of water rights for
irrigation, water supply fisheries, or industrial uses other than the development of water power, beneficial use may
be the measure and limit of the grant.
The State shall protect the nation's marine wealth in its archipelagic waters, territorial sea, and exclusive economic
zone, and reserve its use and enjoyment exclusively to Filipino citizens.
The Congress may, by law, allow small-scale utilization of natural resources by Filipino citizens, as well as cooperative
fish farming, with priority to subsistence fishermen and fish-workers in rivers, lakes, bays, and lagoons.
The President may enter into agreements with foreign-owned corporations involving either technical or financial
assistance for large-scale exploration, development, and utilization of minerals, petroleum, and other mineral oils
according to the general terms and conditions provided by law, based on real contributions to the economic growth
and general welfare of the country. In such agreements, the State shall promote the development and use of local
scientific and technical resources.
The President shall notify the Congress of every contract entered into in accordance with this provision, within thirty
days from its execution. (Emphasis supplied)
I agree that fully foreign-owned corporations may participate in the exploration, development, and use of natural
resources, but only through either financial agreements or technical ones. This is the clear import of the words
"either financial or technical assistance agreements." This is also
the clear result if we compare the 1987 constitutional provision with the versions in the 1973 and 1935 Constitution:
1973 CONSTITUTION
ARTICLE XIV
THE NATIONAL ECONOMY AND THE PATRIMONY OF THE NATION
SEC. 9. The disposition, exploration, development, of exploitation, or utilization of any of the natural resources of the
Philippines shall be limited to citizens of the Philippines, or to corporations or association at least sixty per centum of
the capital of which is owned by such citizens. The Batasang Pambansa, in the national interest, may allow such
citizens, corporations, or associations to enter into service contracts for financial, technical, management, or other
forms of assistance with any foreign person or entity for the exploitation, development, exploitation, or utilization of
any of the natural resources. Existing valid and binding service contracts for financial, the technical, management, or
other forms of assistance are hereby recognized as such. (Emphasis supplied)
1935 CONSTITUTION
ARTICLE XIII
CONSERVATION AND UTILIZATION OF NATURAL RESOURCES
SECTION 1. All agricultural timber, and mineral. lands of the public domain, waters, minerals, coal, petroleum, and
other mineral oils, all forces of potential energy, and other natural resources of the Philippines belong to the State,
and their disposition, exploitation, development, or utilization shall be limited to citizens of the Philippines, or to
corporations or associations at least sixty per centum of the capital of which is owned by such citizens, subject to any
existing right, grant, lease, or concession at the time of the inauguration of the Government established under this
Constitution. Natural resources, with the exception of public agricultural land, shall not be alienated, and no license,
concession, or lease for the exploitation, development, or utilization of any of the natural resources shall be granted
for a period exceeding twenty-five years, renewable for another twenty-five years, except as to water rights for
irrigation, water supply, fisheries, or industrial uses other than the development of water power, in which cases
beneficial use may be the measure and the limit of the grant.
The clear text of the Constitution in light of its history prevails over any attempt to infer interpretation from the
Constitutional Commission deliberations. The constitutional texts are the product of a full sovereign act:
deliberations in a constituent assembly and ratification. Reliance on recorded discussion of Constitutional
Commissions, on the other hand, may result in dependence on incomplete authorship; Besides, it opens judicial
review to further subjectivity from those who spoke during the Constitutional Commission deliberations who may
not have predicted how their words will be used. It is safer that we use the words already in the Constitution. The
Constitution was their product. Its words were read by those who ratified it. The Constitution is what society relies
upon even at present.
SC-46 is neither a financial assistance nor a technical assistance agreement.
Even supposing for the sake of argument that it is, it could not be declared valid in light of the standards set forth in
La Bugal-B'laan Tribal Association, Inc. v. Ramos:36
Such service contracts may be entered into only with respect to minerals, petroleum and other mineral oils. The
grant thereof is subject to several safeguards, among which are these requirements:
(1) The service contract shall be crafted m accordance with a general law that will set standard or uniform
terms, conditions and requirements, presumably to attain a certain uniformity in provisions and avoid the
possible insertion of terms disadvantageous to the country.
(2) The President shall be the signatory for the government because, supposedly before an agreement is
presented to the President for signature, it will have been vetted several times over at different levels to
ensure that it conforms to law and can withstand public scrutiny.
(3) Within thirty days of the executed agreement, the President shall report it to Congress to give that branch
of government an opportunity to look over the agreement and interpose timely objections, if
any.37 (Emphasis in the original, citation omitted)
Based on the standards pronounced in La Bugal, SC-46' S validity must be tested against three important points: (a)
whether SC-46 was crafted in accordance with a general law that provides standards, terms, and conditions; (b)
whether SC-46 was signed by the President for and on behalf of the government; and (c) whether it was reported by
the President to Congress within 30 days of execution.
VII
The general law referred to as a possible basis for SC-46's validity is Presidential Decree No. 87 or the Oil Exploration
and Development Act of 1972.1âwphi1 It is my opinion that this law is unconstitutional in that it allows service
contracts, contrary to Article XII, Section 2 of the 1987 Constitution:
The President may enter into agreements with foreign-owned corporations involving either technical or financial
assistance for large-scale exploration, development, and utilization of minerals, petroleum, and other mineral oils
according to the general terms and conditions provided by law, based on real contributions to the economic growth
and general welfare of the country. In such agreements, the State shall promote the development and use of local
scientific and technical resources. (Emphasis supplied)
The deletion of service contracts from the enumeration of the kind of agreements the President may enter into with
foreign-owned corporations for exploration and utilization of resources means that service contracts are no longer
allowed by the Constitution. Pursuant to Article XVIII, Section 3 of the 1987 Constitution, 38 this inconsistency renders
the law invalid and ineffective.
SC-46 suffers from the lack of a special law allowing its activities. The Main Opinion emphasizes an important point,
which is that SC-46 did not merely involve exploratory activities, but also provided the rights and obligations of the
parties should it be discovered that there is oil in commercial quantities in the area. The Tañon Strait being a
protected seascape under Presidential Decree No. 1234 39 requires that the exploitation and utilization of energy
resources from that area are explicitly covered by a law passed by Congress specifically for that purpose, pursuant to
Section 14 of Republic Act No. 7586 or the National Integrated Protected Areas System Act of 1992:
SEC. 14. Survey for Energy R6'sources. - Consistent with the policies declared in Section 2, hereof, protected areas,
except strict nature reserves and natural parks, may be subjected to exploration only for the purpose of gathering
information on energy resources and only if such activity is carried out with the least damage to surrounding areas.
Surveys shall be conducted only in accordance with a program approved by the DENR, and the result of such surveys
shall be made available to the public and submitted to the President for recommendation to Congress. Any
exploitation and utilization of energy resources found within NIP AS areas shall be allowed only through a law passed
by Congress.40 (Emphasis supplied)
No law was passed by Congress specifically providing the standards, terms, and conditions of an oil exploration,
extraction, and/or utilization for Tañon Strait and, therefore, no such activities could have been validly undertaken
under SC-46. The National Integrated Protected Areas System Act of 1992 is clear that exploitation and utilization of
energy resources in a protected seascape such as Tañon Strait shall only be allowed through a specific law.
VIII
Former President Gloria Macapagal-Arroyo was not the signatory to SC-46, contrary to the requirement set by
paragraph 4 of Article XII, Section 2 for service contracts involving the exploration of petroleum. SC-46 was entered
into by then Department of Energy Secretary Vicente S. Perez, Jr., on behalf of the government. I agree with the Main
Opinion that in cases where the Constitution or law requires the President to act personally on the matter, the duty
cannot be delegated to another public official. 41 La Bugal highlights the importance of the President's involvement,
being one of the constitutional safeguards against abuse and corruption, as not mere formality:
At this point, we sum up the matters established, based on a careful reading of the ConCom deliberations, as follows:
• In their deliberations on what was to become paragraph 4, the framers used the term service contracts in
referring to agreements x x x involving either technical or financial assistance. • They spoke of service
contracts as the concept was understood in the 1973 Constitution.
• It was obvious from their discussions that they were not about to ban or eradicate service contracts.
• Instead, they were plainly crafting provisions to. put in place safeguards that would eliminate or m
minimize the abuses prevalent during the marital law regime. 42 (Emphasis in the original)
Public respondents failed to show that. Former President Gloria Macapagal-Arroyo was involved in the signing or
execution of SC-46. The failure to comply with this constitutional requirement renders SC-46 null and void.
IX
Public respondents also failed to show that Congress was subsequently informed of the execution and existence of
SC-46. The reporting requirement is an equally important requisite to the validity of any service contract involving the
exploration, development, and utilization of Philippine petroleum. Public respondents' failure to report to Congress
about SC-46 effectively took away any opportunity for the legislative branch to scrutinize its terms and conditions.
In sum, SC-46 was executed and implemented absent all the requirements provided under paragraph 4 of Article XII,
Section 2. It is, therefore, null and void.
X
I am of the view that SC-46, aside from not having complied with the 1987 Constitution, is also null and void for being
violative of environmental laws protecting Tañon Strait. In particular, SC-46 was implemented despite falling short of
the requirements of the National Integrated Protected Areas System Act of 1992.
As a protected seascape under Presidential Decree No. 1234, 43 Tañon Strait is covered by the National Integrated
Protected Areas System Act of 1992. This law declares as a matter of policy:
SEC. 2. Declaration of Policy. Cognizant of the profound impact of man's activities on all components of the natural
environment particularly the effect of increasing population, resource exploitation and industrial advancement and
recognizing the critical importance of protecting and maintaining the natural biological and physical diversities of the
environment notably on areas with biologically unique features to sustain human life and development, as well as
plant and animal life, it is hereby declared the policy of the State to secure for the Filipino people of present and
future generations the perpetual existence of all native plants and animals through the establishment of a
comprehensive system of integrated protected areas within the classification of national park as provided for in the
Constitution.
It is hereby recognized that these areas, although distinct in features, possess common ecological values that may be
incorporated into a holistic plan representative of our natural heritage; that effective administration of these areas is
possible only through cooperation among national government, local and concerned private organizations; that the
use and enjoyment of these protected areas must be consistent with the principles of biological diversity and
sustainable development.
To this end, there is hereby established a National Integrated Protected Areas System (NIPAS), which shall encompass
outstanding remarkable areas and biologically important public lands that are habitats of rare and endangered
species of plants and animals, biogeographic zones and related ecosystems, whether terrestrial, wetland or marine,
all of which shall be designated as "protected areas." 44 (Emphasis supplied)
Pursuant to this law, any proposed activity in Tañon Strait must undergo an Environmental Impact Assessment:
SEC. 12. Environmental Impact Assessment. - Proposals for activities which are outside the scope of the management
plan for protected areas shall be subject to an environmental impact assessment as required by law before they are
adopted, and the results thereof shall be taken into consideration in the decision-making process. 45(Emphasis
supplied)
The same provision further requires that an Environmental Compliance Certificate be secured under the Philippine
Environmental Impact Assessment System before arty project is implemented:
No actual implementation of such activities shall be allowed without the required Environmental Compliance
Certificate (ECC) under the Philippine Environment Impact Assessment (EIA) system. In instances where such
activities are allowed to be undertaken, the proponent shall plan and carry them out in such manner as will minimize
any adverse effects and take preventive and remedial action when appropriate. The proponent shall be liable for any
damage due to lack of caution or indiscretion. 46 (Emphasis supplied)
In projects involving the exploration or utilization of energy resources, the National Integrated Protected Areas
System Act of 1992 additionally requires that a program be approved by the Department of Environment and Natural
Resources, which shall be publicly accessible. The program shall also be submitted to the President, who in turn will
recommend the program to Congress. Furthermore, Congress must enact a law specifically allowing the exploitation
of energy resources found within a protected area such as Tañon Strait:
SEC. 14. Survey for Energy Resources. - Consistent with the policies declared in Section 2, hereof, protected areas,
except strict nature reserves and natural parks, may be subjected to exploration only for the purpose of gathering
information on energy resources and only if such activity is carried out with the least damage to surrounding areas.
Surveys shall be conducted only in accordance with a program approved by the DENR, and the result of such surveys
shall be made available to the public and submitted to the President for recommendation to Congress. Any
exploitation and utilization of energy resources found within NIPAS areas shall be allowed only through a taw passed
by Congress.47 (Emphasis supplied)
Public respondents argue that SC-46 complied with the procedural requirements of obtaining an Environmental
Compliance Certificate.48 At any rate, they assert that the activities covered by SC-46 fell under Section 14 of the
National Integrated Protected Areas System Act of 1992, which they interpret to be an exception to Section 12. They
argue that the Environmental Compliance Certificate is not a strict requirement for the validity of SC-46 since (a) the
Tañon Strait is not a nature' reserve or natural park; (b) the exploration was merely for gathering information; and ( c)
measures were in place to ensure that the exploration caused the least possible damage to the area. 49
Section 14 is not an exception to Section 12, but instead provides additional requirements for cases involving
Philippine energy resources. The National Integrated Protected Areas System Act of 1992 was enacted to recognize
the importance of protecting the environment in light of resource exploitation, among others. 50 Systems are put in
place to secure for Filipinos local resources under the most favorable conditions. With the status of Tañon Strait as a
protected seascape, the institution of additional legal safeguards is even more significant.
Public respondents did not validly obtain an Environmental Compliance Certificate for SC-46. Based on the records,
JAPEX commissioned an environmental impact evaluation only in the second subphase of its project, with the
Environmental Management .Bureau of Region
VII granting the project an Environmental Compliance Certificate on March 6, 2007. 51
Despite its scale, the seismic surveys from May 9 to 18, 2005 were conducted without any environmental assessment
contrary to Section 12 of the National Integrated Protected Areas System Act of 1992.
XI
Finally, we honor every living creature when we take care of our environment. As sentient species, we do not lack in
the wisdom or sensitivity to realize that we only borrow the resources that we use to survive and to thrive. We are
not incapable of mitigating the greed that is slowly causing the demise of our planet. Thus, there is no need for us to
feign representation of any other species or some imagined unborn generation in filing any action in our courts of
law to claim any of our fundamental rights to a healthful ecology. In this way and with candor and courage, we fully
shoulder the responsibility deserving of the grace and power endowed on our species.
ACCORDINGLY, I vote:
(a) to DISMISS G.R. No. 180771 for lack of standing and STRIKE OUT the name of Former President Gloria
Macapagal-Arroyo from the title of this case;
(b) to GRANT G.R. No. 181527; and
(c) to DECLARE SERVICE CONTRACT 46 NULL AND VOID for violating the 1987 Constitution, Republic Act No.
7586, and Presidential Decree No. 1234.
MARVIC M.V.F. LEONEN
Associate Justice