You are on page 1of 7

IEEE Transactions on Powcr Systems, Vol. 12, No.

2, May 1997 889


Dynamic Reduction of Large Power Systems for Stability Studies

Lei Wangt Meir Klein$ Solomon Yirgat Prabha Kundurt


Member, IEEE Senior Member, IEEE Member, IEEE Fellow, IEEE

Abstract - This paper documents experience with applications of This paper describes the authors’ experience with the application
dynamic reductions to large power system models for stability of DYNRED to perform dynamic reductions on three large power
studies. The main factors that affect the quality of the reduced systems for the purpose of studying transient and small-signal
models are discussed. The quality of reduced models and the stability. The study addresses the following issues related to
benefits of dynamic reductions are demonstrated for three large dynamic reductions and their applications:
interconnected power systems. reduction process algorithms
* accuracy of the reduced order models
Keywords - Dynamic reduction, coherency, aggregation, power benefits of using dynamic reductions
system stability. reduction procedures for different types of applications
1. INTRODUCTION 2. THE DYNAMIC REDUCTION PROCESS
Modern interconnected electric power systems cover very large The process to reduce the dynamic model of a power system can
geographic areas, served by many utilities. To study the stability be divided into three stages: coherency identification, generator
of such systems, it i s neither practical nor necessary to model in aggregation, and network reduction. In the following, we provide
detail the entire interconnected system. It is a common practice to a brief description of the techniques that DYNRED uses in each
represent parts of the system by some form of a reduced order of the stages of the reduction process.
equivalent model. In more specific applications, such as dynamic
security assessment and system control design, reduced order Coherency Identification
models of the entire system, or part of it, are needed to satisfy
computational or software constraints. The desired characteristics In this stage, coherent generators are identified and grouped
of the reduced model will depend on its application and use. together. This identification procedure may be greatly simplified
by using the following assumptions:
For most applications, a static network reduction as well as a non-generator dynamics may be ignored
dynamic reduction of generators is needed. Although research in classical generator models may be used
this area dates back to the 1970s [l], few mature production grade the linearized system model preserves well the trends of
analysis tools have been available, mainly because of the rigorous coherency
requirements to handle the complexity of modern interconnected
Under these assumptions, the system model can be represented in
power systems. As a result, industry experience in the area of
a linear state space form:
dynamic equivalencing is limited [2,3,4], and often reductions are
done using heuristic methods. x = Ax (1)
where the dimension of the state matrix A corresponds to the
Recently, a dynamic reduction program, DYNRED, was developed number of generators in the system, and the state vector x contains
under the EPRI project RP2447 [5].DYNRED uses the advanced generator speeds only.
techniques developed in the past decade and provides the
necessary interfaces for conducting dynamic reductions in a Three coherency identification methods are available in DYNRED:
production mode. There have been other advances in the past few Weak Links (WL) [SI. In this method, the coherency is
years for dynamic equivalencing of power systems. An improved determined by analyzing the coupling of generators in the state
method to construct an aggregated classical generator model is matrix A. A group of generators are identified as coherent if the
presented in [6]. A new framework called Synchronic Modal coupling coefficients among them are high.
Equivalencing, which generalizes the slow-coherency concept and Two-time Scale (TS) 191. This method is based on the concept
uses modal equivalencing for generator aggregation, is introduced that a slow oscillation is caused by two groups of strongly
in [7]. However, there has been no comprehensive evaluation of coherent generators interconnected through weak ties.
the performance of the reduction techniques and well established Computationally, the two oscillating generator groups can be
procedures for model reduction do not exist. easily identified using the eigenvector associated with the mode
of oscillation. With this method, the system can be partitioned
into an arbitrary number of coherent generator groups by
96 SM 537-1 PWRS A paper recommended and approved by the analyzing the same number of the slowest modes of oscillations.
IEEE Power System Engineering Committee of the IEEE Power Linear Time Simulation (LS) [ I O ] . This is the classical method
Engineering Society for presentation at the 1996 IEEE/PES Summer to identify coherent generators. The time domain response of
Meeting, July 28 - August 1, 1996, in Denver, Colorado. Manuscript
submitted December 28, 1995; made available for printing June 27,
?Powertech Labs Inc., Surrey, B.C., Canada
1996.
$Ontario Hydro, Toronto, Ontario, Canada

0885-8950/97/$10.00 0 1996 IEEE


890
the system (1) is solved for a specified fault in the power 4. TRANSIENT STABILITY ANALYSIS
system, and the rotor angles of generators are compared. Those
generators with rotor angles swinging together are identified as Scope of the Studies
coherent.
These studies compared the stability performances of the reduced
Generator Aggregation order models to those of the base model by considering:
different operating conditions
After a group of coherent generators is identified, the generators powerflow limits on critical interfaces
in it are aggregated and reduced to one or a few equivalent sensitivity to fault location
generators. Generally, the generator aggregation can take one of
two forms: WEST System
0 Classical aggregation (CA). The generators in a coherent group
are represented by an equivalent classical generator model. In The focus of the WEST system study was the transient stability
its simplest form, the equivalent inertia is the sum of the inertia performance of the BC Hydro system. Thus the reduction
of all generators in the group, and the equivalent transient specifications were to retain the entire BC Hydro system and a
reactance is obtained by paralleling the transient reactances of small part of the neighbouring Bonneville Power Administration
all generators in the group. (BPA) system. The rest of the system in the WEST base model
e Detailed aggregation (DA) [ l l ] .If some or all generators in a
was reduced, except for high tension buses in the BPA system.
coherent group have similar control systems, they can be
aggregated to a detailed generator model with an equivalent Six reduced order models were created using a combination of
exciter, stabilizer, and governor. The parameters of the coherency identification and generator aggregation methods
equivalent models are obtained using a combination of two available in the program. The resulting reduced order models and
approaches: a least square fit of the frequency responses to the associated number of buses, branches, generators are
determine the linear characteristics, and an evaluation of the summarized in Table 2.
time-domain constraints to set the nonlinear characteristics.
Table 2 - Reduced Models of the WEST System
Network Reduction
Once equivalent generators are determined for the coherent
groups, a network reduction is performed. This reduction is
I I Buses
(% of base) I Branches
(% of base) I Generators
(% of base) I
achieved in two steps:
The equivalent generators are inserted into the system and the
generators in the associated coherent groups are removed. The
network is modified to maintain the balanced steady state
powerflow conditions.
The network is reduced by using an adaptive reduction
technique similar to the one in [12], which automatically
determines the buses to be eliminated such that maximum * The model designation denotes the coherency identification and
advantage is taken of network sparsity. generator aggregation methods, e.g., WL-CA is the weak links -
classical aggregation model.
3. DESCRIPTIONS OF THE STUDY SYSTEMS
The reduced order models were validated against the base model
Three large models of North American power systems were used using time-domain simulations. The contingency simulated was a
in this study: three-phase fault at a 500 kV bus on the BC Hydro - BPA
0 West Coast interconnected US-Canada system (WEST) interface, followed by the tripping of one of the two 500 kV lines
e East Coast interconnected US-Canada system (EAST) which make up the interface. Figures 1 and 2 show the faulted bus
Mid-continent interconnected US-Canada system (CENTRE) voltage and the active power flow on the remaining 500 kV line
of the interface.
Table 1 gives the sizes of the three base models. In addition to
gcnerators, thcsc models also include other dynamic devices such T h e results in Figures 1 and 2 exhibit good agreement between the
as HVDC links and SVCs. base model and all the reduced models. However, the ones created
by detailed aggregation (DA) are clearly better than those created
Table 1 - Sizes of the Base Models by classical aggregation (CA). On the other hand, the coherency
I System I
I
Buses 1
I
Branches I
I
Generators I identification method does not significantly influence the
performance of the reduced order models. Consequently, the weak
WEST I 5,326 I 9,708 I 468 links method would be the preferred choice for coherency
I EAST I 11,666 I 23,300 I 1,740 I identification, since it is the fastest among the three methods and
CENTRE I 2,287 I 4,942 I 510 I the easiest to apply.
891
F a u l t e d bus v o l t a g e (pu) Faulted bus voltage (pu)
1.1 I

1
I' " I
0 2 4 6 a 10
Time (seconds) T i m e (seconds)

Line active power (MW) Line active power (MW)

600
: ; O ; ; k k
400

200
2,000
n
"0 2 4 6 a 10 0 2 4 6 a io
T h e (seconds) Time (seconds)

- Basemodel WL-CA model - Basemodel WL-DA model


____.
TS-CA model LS-CA model
Figure 3 - Simulations at Very Stressed Conditions
Figure 1 - Performance of CA Reduced Order Models
Error (%)

Faulted bus v o l t a g e (pu) 4/

A
1.05

Time (seconds) WL-CA TS-CA LS-CA WL-DA TS-DA LS-DA


Reduced order models
Line active power (MW)
I Figure 4 - Errors in Power Transfer Limit

transfer limit for various reduced models. The errors are between
2% and 3% of the power transfer limit of 3835 MW determined
from the base model.

, w I
Figure 5 gives the CPU times for a 10-second simulation using the
0 ' "
0 2 4 6 8 10 reduced models as a percentage of the CPU time needed by the
Time (seconds) base model. These savings range from 40% to 60%
- Basemodel WL-DA model
____.
TS-DA model LS-DA model

Figure 2 - Performance of DA Reduced Order Models

To examine the validity of reduced order models over a wide


range of system operating conditions, the loading and generation
in the base case and the reduced order models were adjusted to
increase the power transfer on the interface from 285 MW to 3725
MW (close to transfer limit). Figure 3 compares the results of the
base model and the WL-DA model at this high power transfer
level. Other reduced models exhibit similar results. It is evident
that the reduced models perform satisfactorily, even at very
stressed conditions. Figure 4 shows the errors on the power Figure 5 - Comparisons of Computation Times
892

The LS method is inherently fault-dependent. To see how good a The five dynamic reductions, which are summarized in Table 3,
model derived from this method is for other contingencies, we were performed to study transfer limits on the two interfaces. In
performed simulations of faults in other locations using the LS- the first, second, and fifth reductions, the entire Ontario Hydro
DA reduced model. Location 1 is well within the retained area, system was retained, while in the third and fourth reductions, only
while location 2 is outside of the retained area. Figure 6 shows the part of the Ontario Hydro system was retained and the rest
faulted bus voltages from the two simulations. It is clear that, for reduced. In the reduced areas, buses of 120 kV and higher were
fault location 1, the results of the LS-DA reduced model and the retained as were all HVDC links and SVCs.
base model are almost identical, while for fault location 2, a
significant phase shift can be observed. Table 4 provides transfer limits (accurate to the last 20 MW)
computed for the full and reduced system models on the FABC
Faulted bus voltage (pu) within retained area and FS interfaces.

Table 3 - Sizes of the Reduced Systems

I I I I
1.05 Buses Branches Generators
(% of base) (% of base) (% of base)
WL-CA 7106 (61%) 18739 (80%) 655 (38%)
0.95 ' '
0 2 4 6 8
I
I O
LS-CA 6879 (60%) 18624 (79%) 433 (25%)

Time (seconds)

Faulted bus voltage (pu) outside o f retained area


1.15 I I

FS Limit
Model Limit Error Limit Error
(MW) (MWI%) (MW) (MWI%)
2 4 6 8 10 Full 6300 320
Time (seconds)
WL-CA 6260 4 0 1 0.62 340 20 16.25
___ B a s e m o d e l LS-DA model
LS-CA 6280 2010.31 305 15 I 4.68
Figure 6 - Simulations for Faults Inside LS-CA 6220 80 11.24 300 20 16.25
and Outside of the Retained Area LS-DA 6240 6010.93 290 30 19.37

EAST System I TS-DA I 6260


I

I 4010.62
I

I 370
I

I 5 0 1 15.62 I
The limits derived from each of the reduced systems are
The stability analysis of the EAST system focused on power
reasonably accurate. The methods used to identify coherent
transfer limits across two transmission interfaces in the Ontario
Hydro system. To overcome the power transfer restrictions, generators and their aggregation do not appear to be critical. The
percent errors associated with the FS interface are relatively higher
generation rejection schemes are currently in place; however, these
since the limit on this interface is much lower than on the FABC
were not modelled in these simulations.
interface.
The first interface, known as flow away from Bruce (FABC),
consists of four 500 kV and six 230 kV circuits. It is a radial CENTRE System
interface which joins the two nuclear plants, Bruce A and B, to Manitoba's power system is connected to the systems of the two
the Ontario Hydro system. At high outputs, a nearby fault states to the south, Minnesota and North Dakota, through one 500
resulting in the removal of two 500 kV circuits may cause both kV and two 230 kV circuits. One of the main contingencies that
plants to lose synchronism in the first swing. limits the power transfer south from Manitoba to the US is a fault
with breaker failure in the Twin Cities area in Minnesota. The
The second interface, known as flow south (FS), connects delayed clearing causes a transient voltage dip on the 500 kV tie,
Northwestern Ontario to the rest of the system. Two 500 kV about 1.5 s after the fault has been cleared, as seen in Figure 7.
circuits and one 230 kV circuit make up this interface. Unlike
FABC, it has a parallel high impedance path through Manitoba Table 5 summarizes the four dynamic reductions developed for
and the US. The power transfer across this interface is limited by this system. The power systems of Manitoba and Minnesota were
contingencies on the 500 kV circuits which cause a group of retained in their entirety. In addition, buses of 120 kV or higher,
hydraulic plants to lose synchronism. HVDC links, and SVC buses were retained throughout the system.
The three point-to-point HVDC links, one running north-south and
893
This section discusses these issues with examples from the WEST
and the EAST systems.

WEST System

We first examined the interarea modes in the WEST system


computed from the base model and the reduced order models
created for transient stability studies, as described in Table 2. The
results again showed that the coherency identification method is
not critical and that the detailed generator aggregation gives better
results than the classical aggregation. As an example, in Table 6
TIMEINSECONDS
we provide the interarea modes in the base model and in the WL-
-
FULL
........ .. . .. .., ~ .. .. . .. DA reduced model.
WL-CA LS-CA LS-DA TS-CA

Figure 7 - Tie Bus Voltages in the Full and Reduced Models Base model WL-DA model
Mode
two east-west, made it difficult to achieve higher reductions since I
f* I 4** f* I 4** I

the areas surrounding the converters had to be retained to preserve I


I
1 I 0.29 I 0.160 I 0.30 I 0.180 I
I
the correct response of the dc links. I 2 I 0.47 I 0.100 I 0.49 I 0.094 I
Table 5 - Sizes of the Reduced Svstems 3 0.62 0.056 0.61 0.055
4 0.78 0.041 0.76 0.085
Buses Branches Generators
5 0.80 0.092 0.81 0.083

The accuracy of the modal characteristics computed from the


reduced order models varied from very good (e.g., Mode 3) to
I
I
TS-CA I 1703 (74%) I 4283 (87%) I 313 (61%)
I
very poor (e.g., Mode 4 for which the damping ratio has more
than doubled). This can be explained by the mode shapes obtained
Figure 7 contains voltage plots from the full and reduced systems. from the base model and shown in Figure 8. The two oscillating
The voltage responses from reductions WL-CA, LS-CA, and TS- sides of a mode are denoted by + and -.
CA are very similar, differing only in the coherency identification
method. The response from model LS-DA is the closest to the
original system. Two factors contribute to the improved response:
the detailed modelling of equivalent generators and the larger size
of this model compared to the other three.

5. SMALL-SIGNAL STABILITY ANALYSIS

Scope of the Studies

In a power system, there are two types of swing modes: local


plant modes and interarea modes [13]. The local plant modes
involve only a small number of generators, and therefore the ones
that exist in a retained area are usually well preserved in a reduced Mode 3 Mode 4
order model. The interarea modes, on the other hand, may spread
over a very large area in the system, and their characteristics are Figure 8 - Shapes of Modes 3 and 4
sometimes critical to the overall stability of the system.
Figure 8 shows that Mode 3 involves mostly the BC Hydro system
When evaluating reduced models for small-signal stability and some surrounding areas. A fair amount of the dynamics in
analysis, the following are the main issues: these areas were kept in the reduced models. For Mode 4,
the characteristics of the interarea modes however, the swing is basically the northwest and southwest
preservation of the characteristics of the interarea modes of against the centre. Most of the dynamics in the southwest and
interest centre were equivalenced in the WL-DA reduced model. This
the suitability of the models for system control design simply means that the reduced order models are not adequate to
study Mode 4.
894
Given the shape of Mode 4, it would be logical to create the Table 8 - Characteristics of the 0.6 Hz Mode
reduced models for studying this mode by retaining some
dominant generators in the southwest and centre areas. This basis
was used to create a model which better preserves Mode 4. An
Model I Frequency
1 Damping
Ratio
1 Mode Shape
I
additional requirement for this model was that it should be small
enough to allow a full eigenvalue analysis, so that a transfer
function can be computed for control design, as explained below.
Using these criteria, a reduced order model, RED-4, was obtained,
which consists of 191 generators of which 15 have detailed
models and the rest classical models, with a total of 530 states.
I LS-DA I 0.632 I -0.006 I I
In the RED-4 model, Mode 4 has a frequency of 0.76 Hz and a I TS-CA I 0.628 I 0.005 I I
damping ratio of 0.043, which are very close to those of Mode 4
of the base model. This model also fits into the capabilities of Two factors limit the size of the design model: the capability of
MASS, a small-signal analysis program that computes all the the control design software and the order of the controller, which
eigenvalues of the system [13]. I
in some advanced control methods equals the order of the design
model [ 151.
EAST System
To construct a low-order transfer function between the exciter
One of the dominant interarea modes in the EAST system is an reference point and the rotor speed of a dominant generator in
oscillation of about 0.6 Mz involving generating units in the states Mode 4 of the WEST system, the base model was first reduced,
of New York and Pennsylvania. The study was performed on a as described earlier, to the RED-4 model. Using MASS, the
system with the four Niagara ties between Ontario and New York complete transfer function of the order of 530 from the RED-4
out of service. Under these conditions, the damping of the mode model was obtained. Close poles and zeros of this transfer
decreases markedly to practically zero. function were cancelled, resulting in a transfer function of 16'h
order. The poles and zeros of this low-order transfer function were
To study the effect of reductions on interarea oscillations, the finally refined by using the corresponding eigenvalues and zeros
four reduced models described in Table 7 were created. In all four computed from the base model by PEALS, a program capable of
reductions, the power systems of New York and Pennsylvania computing a subset of the system eigenvalues in large systems
were retained. In the reduced areas, buses of 120 kV and higher C131.
were retained.
Figure 9 shows frequency responses from the full model and the
Table 7 - Sizes of the Reduced Systems reduced transfer function. It can be seen that the frequency

II II II II
response from the reduced transfer function follows very closely
1I WL-CA
Buses
(% of base)
7407 (63%)
Branches
(% of base)
17945 (77%)
Generators
(% of base)
829 (48%)
that from the full model.
Magnitude (pu)

LS-CA
LS-DA
7551 (65%)
7619 (65%)
17658 (76%)
17638 (76%)
958 (55%)
1183 (68%)
54
TS-CA 7387 (63%) 17850 (77%) 829 (48%)

The modal characteristics ($e., frequency, damping and mode A


shape) of the 0.6 Hz mode in the reduced systems were compared 1.4
to those in the full system. A summary is given in Table 8. The Frequency (Hz)

results show that the 0.6 Hz mode is well preserved in all the Phase angle (degrees)
reduced cases. This is mainly due to retaining the generating units 200
which are significant participants in the oscillation, as well as the
\ 1
\?---.\__i.--
1501
network which interconnects them.
100 ,---_
Transfer Function Reduction f o r System Control Design
50
'-.-
Most control design methods to damp power system oscillations
require that the mathematical model of the physical system be Frequency (Hz)
expressed either by a transfer function or in the state space form
[ 141. The transfer-function is normally between the input of the - Full model ____ Reduced transfer function

device selected for supplementary control and an output signal Figure 9 - Frequency Response Comparisons
selected for feedback to modulate the chosen device.
895
6. CONCLUSIONS “Synchronic Modal Equivalencing (SME) for Structure-
Preserving Dynamic Equivalents”, Paper 95-WM113-1-
This paper has illustrated the practical requirements of and PWRS, Presented at IEEE PES Winter Meeting, New York,
experience with model reduction of large interconnected power January, 1995.
systems for stability analysis. The results of investigations on three [8] R. Nath, S.S. Lamba, K.S. Prakasa Rao, “Coherency Based
power systems with significantly different characteristics lead to System Decomposition into Study and External Areas Using
the following main conclusions: Weak Coupling”, IEEE Trans., Vol. PAS-104, pp. 1443-
For most planning or operating stability studies, large power 1449, June, 1985.
system models can be reduced by up to 50% without excessive [9] J.R. Winkelman, J.H. Chow, B.C. Bowler, B. Avramovic,
loss of accuracy. and P.V. Kokotovic, “An Analysis of Interarea Dynamics of
The three coherency identification methods studied in this paper Multi-Machine Systems”, IEEE Trans., Vol. PAS- 100, pp.
all produce good generator grouping. No significant difference 754-763, February, 1981.
in the quality of the reduced models was observed by using 101 R. Podmore, “Identification of Coherent Generators for
these three different methods. Dynamic Equivalents”, IEEE Trans., Vol. PAS-97, pp. 1344-
Classical aggregation of coherent generating units results in 1354, July/August, 1978.
simpler and lower order reduced models than detailed 111 A.J. Germond and R. Podmore, “Dynamic Aggregation of
aggregation and is adequate in many cases. In some cases, a Generating Unit Models”, IEEE Trans. Vol. PAS-97, pp.
detailed aggregation is required to achieve better accuracy. 1060-1069, July/August, 1978.
The accuracy of a reduced order model, with respect to a 121 W.F. Tinney and J.M. Bright, “Adaptive Reductions for
specific phenomenon, depends to a great extent on retaining the Power Flow Equivalents”, IEEE Trans. Vol. PWRS-2, pp.
system elements which are most relevant to that phenomenon. 351-360, May 1987.
It is therefore important to have a good understanding of the [13] P. Kundur, Power System Stability and Control, McGraw-
phenomenon before starting the reductions. Hill, 1994.
A reduced model of a power system that is suitable for the [14] P. Kundur, Investigation of Low Frequency Interarea
study of one phenomenon in that system is not necessarily Oscillation problems in Large Interconnected Power Systems,
suitable for the study of another phenomenon. CEA Report 294T622, May, 1993.
[15] M. Klein, L.X. Le, G.J. Rogers, S. Farrokhpuy, N.J. Balu,
7. ACKNOWLEDGEMENT “H, Damping Controller Design in Large Power Systems”,
IEEE Trans. Vol. PWRS-IO, pp. 158-166, February 1995.
The authors wish to thank Mr. Kip Morison of Powertech Labs
Inc. for his valuable advice. This work has been supported by the Lei Wang received the B.A.Sc and M.A.Sc degrees from
Canadian Electrical Association under project 347T961. Shanghai Jiao Tong University, China in 1982 and 1984,
respectively, and the Ph.D degree from the University of Toronto,
8. REFERENCES Canada in 1991. He worked for Ontario Hydro from 1989 to 1993
as a system studies engineer. In 1993, he joined Powertech Labs
R. Podmore, Development of Dynamic Equivalents for Inc. as a research engineer.
Transient Stability Studies, EPRI Report EL-456, 1977. Meir Klein received his B.A.Sc. and M. Eng. degrees from the
R.J. Newell, M.D. Risan, L. Allen, K.S. Rao, D.L. Stuehm, University of Toronto in 1978 and 1983, respectively. He joined
“Utility Experience with Coherency-based Dynamic Ontario Hydro in 1978, and is currently a Senior Engineer in the
Equivalents of Very Large Systems”, IEEE Trans. Vol. PAS- Integrated Transmission Planning and Operations Department.
104, pp. 3056-3063, November, 1985.
G. Troullinos, J. Dorsey, H. Wong, and J. Myers, “Reducing Solomon Yirga received his B.Sc degree from Addis Ababa
the Order of Very Large Power System Models”, IEEE University and his M.A.Sc degree from the University of Toronto
Trans. Vol. PWRS-3, pp. 127-133, February, 1988. in 1984 and 1994, respectively. From 1984 to 1991 he worked for
Y. Mansour, E. Vaahedi, A.Y. Chang, B.R. Coms, B.W. the Ethiopian Electric Light & Power Authority. From 1992 to
Garrett, K. Demaree, T. Athay, K. Cheung, “B.C. Hydro’s 1993 he worked for Ontario Hydro in the Analytical Methods and
On-line Transient Stability Assessment (TSA) Model Specialized Studies Department. In 1994, he joined Powertech
Development, Analysis, and Post-processing”, IEEE Trans. Labs Inc. as a research engineer.
Vol. PWRS-10, pp. 241-253, February, 1995.
Prabhashankar Kundur received the M.A.Sc and Ph.D degrees
P. Kundur, G.J. Rogers, D.Y. Wong, J. Ottevangers, and L.
from the University of Toronto, Canada in 1965 and 1967
Wang, Dynamic Reduction, EPRI TR- 102234 Project 2447-
respectiveIy. He taught at Mysore and Bangalore Universities
01, Final Report, April, 1993.
during 1967-1969. In 1969 he joined Ontario Hydro where he
J.H. Chow, R. Galarza, P. Accari, and, W.W. Price, “Inertial
became Manager of the Analytical Methods & Specialized Studies
and Slow Coherency Aggregation Algorithms for Power
Department. In 1993 he moved to Powertech Labs Inc. where he
System Dynamic Model Reduction”, IEEE Trans. Vol.
is currently the President and CEO. He also holds the positions of
PWRS-IO, pp. 680-685, May, 1995.
Adjunct Professor at the University of Bntish Columbia and
G.N. Ramaswamy, L. Rouco, 0. Fillatre, and G.C. Verghese,
Western Ontario.

You might also like