Professional Documents
Culture Documents
Abstract - This paper documents experience with applications of This paper describes the authors’ experience with the application
dynamic reductions to large power system models for stability of DYNRED to perform dynamic reductions on three large power
studies. The main factors that affect the quality of the reduced systems for the purpose of studying transient and small-signal
models are discussed. The quality of reduced models and the stability. The study addresses the following issues related to
benefits of dynamic reductions are demonstrated for three large dynamic reductions and their applications:
interconnected power systems. reduction process algorithms
* accuracy of the reduced order models
Keywords - Dynamic reduction, coherency, aggregation, power benefits of using dynamic reductions
system stability. reduction procedures for different types of applications
1. INTRODUCTION 2. THE DYNAMIC REDUCTION PROCESS
Modern interconnected electric power systems cover very large The process to reduce the dynamic model of a power system can
geographic areas, served by many utilities. To study the stability be divided into three stages: coherency identification, generator
of such systems, it i s neither practical nor necessary to model in aggregation, and network reduction. In the following, we provide
detail the entire interconnected system. It is a common practice to a brief description of the techniques that DYNRED uses in each
represent parts of the system by some form of a reduced order of the stages of the reduction process.
equivalent model. In more specific applications, such as dynamic
security assessment and system control design, reduced order Coherency Identification
models of the entire system, or part of it, are needed to satisfy
computational or software constraints. The desired characteristics In this stage, coherent generators are identified and grouped
of the reduced model will depend on its application and use. together. This identification procedure may be greatly simplified
by using the following assumptions:
For most applications, a static network reduction as well as a non-generator dynamics may be ignored
dynamic reduction of generators is needed. Although research in classical generator models may be used
this area dates back to the 1970s [l], few mature production grade the linearized system model preserves well the trends of
analysis tools have been available, mainly because of the rigorous coherency
requirements to handle the complexity of modern interconnected
Under these assumptions, the system model can be represented in
power systems. As a result, industry experience in the area of
a linear state space form:
dynamic equivalencing is limited [2,3,4], and often reductions are
done using heuristic methods. x = Ax (1)
where the dimension of the state matrix A corresponds to the
Recently, a dynamic reduction program, DYNRED, was developed number of generators in the system, and the state vector x contains
under the EPRI project RP2447 [5].DYNRED uses the advanced generator speeds only.
techniques developed in the past decade and provides the
necessary interfaces for conducting dynamic reductions in a Three coherency identification methods are available in DYNRED:
production mode. There have been other advances in the past few Weak Links (WL) [SI. In this method, the coherency is
years for dynamic equivalencing of power systems. An improved determined by analyzing the coupling of generators in the state
method to construct an aggregated classical generator model is matrix A. A group of generators are identified as coherent if the
presented in [6]. A new framework called Synchronic Modal coupling coefficients among them are high.
Equivalencing, which generalizes the slow-coherency concept and Two-time Scale (TS) 191. This method is based on the concept
uses modal equivalencing for generator aggregation, is introduced that a slow oscillation is caused by two groups of strongly
in [7]. However, there has been no comprehensive evaluation of coherent generators interconnected through weak ties.
the performance of the reduction techniques and well established Computationally, the two oscillating generator groups can be
procedures for model reduction do not exist. easily identified using the eigenvector associated with the mode
of oscillation. With this method, the system can be partitioned
into an arbitrary number of coherent generator groups by
96 SM 537-1 PWRS A paper recommended and approved by the analyzing the same number of the slowest modes of oscillations.
IEEE Power System Engineering Committee of the IEEE Power Linear Time Simulation (LS) [ I O ] . This is the classical method
Engineering Society for presentation at the 1996 IEEE/PES Summer to identify coherent generators. The time domain response of
Meeting, July 28 - August 1, 1996, in Denver, Colorado. Manuscript
submitted December 28, 1995; made available for printing June 27,
?Powertech Labs Inc., Surrey, B.C., Canada
1996.
$Ontario Hydro, Toronto, Ontario, Canada
1
I' " I
0 2 4 6 a 10
Time (seconds) T i m e (seconds)
600
: ; O ; ; k k
400
200
2,000
n
"0 2 4 6 a 10 0 2 4 6 a io
T h e (seconds) Time (seconds)
A
1.05
transfer limit for various reduced models. The errors are between
2% and 3% of the power transfer limit of 3835 MW determined
from the base model.
, w I
Figure 5 gives the CPU times for a 10-second simulation using the
0 ' "
0 2 4 6 8 10 reduced models as a percentage of the CPU time needed by the
Time (seconds) base model. These savings range from 40% to 60%
- Basemodel WL-DA model
____.
TS-DA model LS-DA model
The LS method is inherently fault-dependent. To see how good a The five dynamic reductions, which are summarized in Table 3,
model derived from this method is for other contingencies, we were performed to study transfer limits on the two interfaces. In
performed simulations of faults in other locations using the LS- the first, second, and fifth reductions, the entire Ontario Hydro
DA reduced model. Location 1 is well within the retained area, system was retained, while in the third and fourth reductions, only
while location 2 is outside of the retained area. Figure 6 shows the part of the Ontario Hydro system was retained and the rest
faulted bus voltages from the two simulations. It is clear that, for reduced. In the reduced areas, buses of 120 kV and higher were
fault location 1, the results of the LS-DA reduced model and the retained as were all HVDC links and SVCs.
base model are almost identical, while for fault location 2, a
significant phase shift can be observed. Table 4 provides transfer limits (accurate to the last 20 MW)
computed for the full and reduced system models on the FABC
Faulted bus voltage (pu) within retained area and FS interfaces.
I I I I
1.05 Buses Branches Generators
(% of base) (% of base) (% of base)
WL-CA 7106 (61%) 18739 (80%) 655 (38%)
0.95 ' '
0 2 4 6 8
I
I O
LS-CA 6879 (60%) 18624 (79%) 433 (25%)
Time (seconds)
FS Limit
Model Limit Error Limit Error
(MW) (MWI%) (MW) (MWI%)
2 4 6 8 10 Full 6300 320
Time (seconds)
WL-CA 6260 4 0 1 0.62 340 20 16.25
___ B a s e m o d e l LS-DA model
LS-CA 6280 2010.31 305 15 I 4.68
Figure 6 - Simulations for Faults Inside LS-CA 6220 80 11.24 300 20 16.25
and Outside of the Retained Area LS-DA 6240 6010.93 290 30 19.37
I 4010.62
I
I 370
I
I 5 0 1 15.62 I
The limits derived from each of the reduced systems are
The stability analysis of the EAST system focused on power
reasonably accurate. The methods used to identify coherent
transfer limits across two transmission interfaces in the Ontario
Hydro system. To overcome the power transfer restrictions, generators and their aggregation do not appear to be critical. The
percent errors associated with the FS interface are relatively higher
generation rejection schemes are currently in place; however, these
since the limit on this interface is much lower than on the FABC
were not modelled in these simulations.
interface.
The first interface, known as flow away from Bruce (FABC),
consists of four 500 kV and six 230 kV circuits. It is a radial CENTRE System
interface which joins the two nuclear plants, Bruce A and B, to Manitoba's power system is connected to the systems of the two
the Ontario Hydro system. At high outputs, a nearby fault states to the south, Minnesota and North Dakota, through one 500
resulting in the removal of two 500 kV circuits may cause both kV and two 230 kV circuits. One of the main contingencies that
plants to lose synchronism in the first swing. limits the power transfer south from Manitoba to the US is a fault
with breaker failure in the Twin Cities area in Minnesota. The
The second interface, known as flow south (FS), connects delayed clearing causes a transient voltage dip on the 500 kV tie,
Northwestern Ontario to the rest of the system. Two 500 kV about 1.5 s after the fault has been cleared, as seen in Figure 7.
circuits and one 230 kV circuit make up this interface. Unlike
FABC, it has a parallel high impedance path through Manitoba Table 5 summarizes the four dynamic reductions developed for
and the US. The power transfer across this interface is limited by this system. The power systems of Manitoba and Minnesota were
contingencies on the 500 kV circuits which cause a group of retained in their entirety. In addition, buses of 120 kV or higher,
hydraulic plants to lose synchronism. HVDC links, and SVC buses were retained throughout the system.
The three point-to-point HVDC links, one running north-south and
893
This section discusses these issues with examples from the WEST
and the EAST systems.
WEST System
Figure 7 - Tie Bus Voltages in the Full and Reduced Models Base model WL-DA model
Mode
two east-west, made it difficult to achieve higher reductions since I
f* I 4** f* I 4** I
II II II II
response from the reduced transfer function follows very closely
1I WL-CA
Buses
(% of base)
7407 (63%)
Branches
(% of base)
17945 (77%)
Generators
(% of base)
829 (48%)
that from the full model.
Magnitude (pu)
LS-CA
LS-DA
7551 (65%)
7619 (65%)
17658 (76%)
17638 (76%)
958 (55%)
1183 (68%)
54
TS-CA 7387 (63%) 17850 (77%) 829 (48%)
results show that the 0.6 Hz mode is well preserved in all the Phase angle (degrees)
reduced cases. This is mainly due to retaining the generating units 200
which are significant participants in the oscillation, as well as the
\ 1
\?---.\__i.--
1501
network which interconnects them.
100 ,---_
Transfer Function Reduction f o r System Control Design
50
'-.-
Most control design methods to damp power system oscillations
require that the mathematical model of the physical system be Frequency (Hz)
expressed either by a transfer function or in the state space form
[ 141. The transfer-function is normally between the input of the - Full model ____ Reduced transfer function
device selected for supplementary control and an output signal Figure 9 - Frequency Response Comparisons
selected for feedback to modulate the chosen device.
895
6. CONCLUSIONS “Synchronic Modal Equivalencing (SME) for Structure-
Preserving Dynamic Equivalents”, Paper 95-WM113-1-
This paper has illustrated the practical requirements of and PWRS, Presented at IEEE PES Winter Meeting, New York,
experience with model reduction of large interconnected power January, 1995.
systems for stability analysis. The results of investigations on three [8] R. Nath, S.S. Lamba, K.S. Prakasa Rao, “Coherency Based
power systems with significantly different characteristics lead to System Decomposition into Study and External Areas Using
the following main conclusions: Weak Coupling”, IEEE Trans., Vol. PAS-104, pp. 1443-
For most planning or operating stability studies, large power 1449, June, 1985.
system models can be reduced by up to 50% without excessive [9] J.R. Winkelman, J.H. Chow, B.C. Bowler, B. Avramovic,
loss of accuracy. and P.V. Kokotovic, “An Analysis of Interarea Dynamics of
The three coherency identification methods studied in this paper Multi-Machine Systems”, IEEE Trans., Vol. PAS- 100, pp.
all produce good generator grouping. No significant difference 754-763, February, 1981.
in the quality of the reduced models was observed by using 101 R. Podmore, “Identification of Coherent Generators for
these three different methods. Dynamic Equivalents”, IEEE Trans., Vol. PAS-97, pp. 1344-
Classical aggregation of coherent generating units results in 1354, July/August, 1978.
simpler and lower order reduced models than detailed 111 A.J. Germond and R. Podmore, “Dynamic Aggregation of
aggregation and is adequate in many cases. In some cases, a Generating Unit Models”, IEEE Trans. Vol. PAS-97, pp.
detailed aggregation is required to achieve better accuracy. 1060-1069, July/August, 1978.
The accuracy of a reduced order model, with respect to a 121 W.F. Tinney and J.M. Bright, “Adaptive Reductions for
specific phenomenon, depends to a great extent on retaining the Power Flow Equivalents”, IEEE Trans. Vol. PWRS-2, pp.
system elements which are most relevant to that phenomenon. 351-360, May 1987.
It is therefore important to have a good understanding of the [13] P. Kundur, Power System Stability and Control, McGraw-
phenomenon before starting the reductions. Hill, 1994.
A reduced model of a power system that is suitable for the [14] P. Kundur, Investigation of Low Frequency Interarea
study of one phenomenon in that system is not necessarily Oscillation problems in Large Interconnected Power Systems,
suitable for the study of another phenomenon. CEA Report 294T622, May, 1993.
[15] M. Klein, L.X. Le, G.J. Rogers, S. Farrokhpuy, N.J. Balu,
7. ACKNOWLEDGEMENT “H, Damping Controller Design in Large Power Systems”,
IEEE Trans. Vol. PWRS-IO, pp. 158-166, February 1995.
The authors wish to thank Mr. Kip Morison of Powertech Labs
Inc. for his valuable advice. This work has been supported by the Lei Wang received the B.A.Sc and M.A.Sc degrees from
Canadian Electrical Association under project 347T961. Shanghai Jiao Tong University, China in 1982 and 1984,
respectively, and the Ph.D degree from the University of Toronto,
8. REFERENCES Canada in 1991. He worked for Ontario Hydro from 1989 to 1993
as a system studies engineer. In 1993, he joined Powertech Labs
R. Podmore, Development of Dynamic Equivalents for Inc. as a research engineer.
Transient Stability Studies, EPRI Report EL-456, 1977. Meir Klein received his B.A.Sc. and M. Eng. degrees from the
R.J. Newell, M.D. Risan, L. Allen, K.S. Rao, D.L. Stuehm, University of Toronto in 1978 and 1983, respectively. He joined
“Utility Experience with Coherency-based Dynamic Ontario Hydro in 1978, and is currently a Senior Engineer in the
Equivalents of Very Large Systems”, IEEE Trans. Vol. PAS- Integrated Transmission Planning and Operations Department.
104, pp. 3056-3063, November, 1985.
G. Troullinos, J. Dorsey, H. Wong, and J. Myers, “Reducing Solomon Yirga received his B.Sc degree from Addis Ababa
the Order of Very Large Power System Models”, IEEE University and his M.A.Sc degree from the University of Toronto
Trans. Vol. PWRS-3, pp. 127-133, February, 1988. in 1984 and 1994, respectively. From 1984 to 1991 he worked for
Y. Mansour, E. Vaahedi, A.Y. Chang, B.R. Coms, B.W. the Ethiopian Electric Light & Power Authority. From 1992 to
Garrett, K. Demaree, T. Athay, K. Cheung, “B.C. Hydro’s 1993 he worked for Ontario Hydro in the Analytical Methods and
On-line Transient Stability Assessment (TSA) Model Specialized Studies Department. In 1994, he joined Powertech
Development, Analysis, and Post-processing”, IEEE Trans. Labs Inc. as a research engineer.
Vol. PWRS-10, pp. 241-253, February, 1995.
Prabhashankar Kundur received the M.A.Sc and Ph.D degrees
P. Kundur, G.J. Rogers, D.Y. Wong, J. Ottevangers, and L.
from the University of Toronto, Canada in 1965 and 1967
Wang, Dynamic Reduction, EPRI TR- 102234 Project 2447-
respectiveIy. He taught at Mysore and Bangalore Universities
01, Final Report, April, 1993.
during 1967-1969. In 1969 he joined Ontario Hydro where he
J.H. Chow, R. Galarza, P. Accari, and, W.W. Price, “Inertial
became Manager of the Analytical Methods & Specialized Studies
and Slow Coherency Aggregation Algorithms for Power
Department. In 1993 he moved to Powertech Labs Inc. where he
System Dynamic Model Reduction”, IEEE Trans. Vol.
is currently the President and CEO. He also holds the positions of
PWRS-IO, pp. 680-685, May, 1995.
Adjunct Professor at the University of Bntish Columbia and
G.N. Ramaswamy, L. Rouco, 0. Fillatre, and G.C. Verghese,
Western Ontario.