You are on page 1of 1

Project Co-

Proj No. Z089 Summary Report ordinator:


Vignesh
Project In-
Date 3-Oct-18 BWTS SEAVOYAGER charge:
Sankar/Neeraj
Delivery Percentage
S.No Drawing No. Rev No. Drawing Name Status
Date STATUS
1 0 Site Scan (ER and Pump Room) 100.0% Completed
2 0 Data collection from Ship 100.0% Completed
3 0 Data receiving by Design Team 100.0% Completed
4 0 Point cloud creation 100.0% Completed
5 0 Vendor Data Collection 100.0% Completed
6 0 Input review 100.0% Completed
7 Z089-M-01 0 Ballast system P&ID 100.0% Completed
8 Z089-M-02 0 Bilge/Drain System P&ID 90.0% Ontime
9 Z089-M-03 0 Fresh water P&ID 90.0% Ontime
10 Z089-M-04 0 Instrument air system P &ID 90.0% Ontime
11 Z089-M-05 0 Steam system 0.7Mpa P&ID 90.0% Ontime
12 Z089-M-06 0 Vendor P&ID 100.0% Completed
13 Z089-G-03 0 Equipment Placing in 2D plan (GA Plan) 100.0% Completed
14 Z089-G-04 0 3D Equipment Modeling 100.0% Completed
15 Z089-G-05 0 Placing of 3D Equipment model 100.0% Completed
16 Z089-G-06 0 Equipment arrangement drawing 0.0% Ontime
17 Z089-G-07 0 Equipment loading plan 0.0% Ontime
18 0 Pipe routing 80.0% Ontime
19 Z089-P-07 0 Illegical bypass 100.0% Completed
20 0 Pipe routing verification 0.0% Lagging
21 Z089-R-01 0 Feasibility report 100.0% Completed
22 Z089-P-01 0 Pipe spool drawing 0.0% Lagging
23 0 spool drawing verification 0.0% Ontime
24 Z089-P-02 0 Pipe Spool arrangement drawing 0.0% Ontime
25 Z089-P-03 0 Pipe Tie in point plan. 0.0% Ontime
26 Z089-P-04 0 3D Pipe Spool drawing 0.0% Ontime
27 Z089-P-05 0 Pipe Support drawing 0.0% Ontime
28 0 Support drawing verification 20.0% Ontime
29 Z089-P-06 0 Pipe support arrangement 0.0% Ontime
30 Z089-P-07 0 Location of ballast water sampling facilities 0.0% Ontime
31 Z089-R-02 0 Pressure drop calculation 0.0% Ontime
32 Z089-G-01 0 Engine room Arragement drawing 0.0% Ontime
33 Z089-G-02 0 New BWTS Arragement drawing 0.0% Lagging
34 Z089-S-01 0 Equipment foundation drawing 0.0% Lagging
35 Z089-S-02 0 EDU foundation detail drawing 60.0% Ontime
36 Z089-S-03 0 ANU foundation detail drawing 60.0% Ontime
37 Z089-S-04 0 AFU 01/02 foundation detail drawing 60.0% Ontime
38 Z089-S-05 0 EQ13 foundation detail drawing 60.0% Ontime
39 Z089-S-06 0 ODU foundation detail drawing 60.0% Ontime
40 Z089-S-07 0 TSU foundation detail drawing 60.0% Ontime
41 Z089-S-08 0 TDU foundation detail drawing 60.0% Ontime
42 Z089-S-09 0 EQ37 Heat Exchanger foundation detail drawing 60.0% Ontime
43 Z089-S-10 0 EQ 02 Taiko 214 pump foundation detail drawing 60.0% Ontime
44 Z089-S-11 0 EQ 02 Taiko 85 pump foundation detail drawing 60.0% Ontime
45 Z089-S-12 0 EQ 02 Taiko 14 pump foundation detail drawing 60.0% Ontime
46 Z089-S-13 0 EQ 04 Taiko 21 pump foundation detail drawing 60.0% Ontime
47 Z089-S-14 0 TRO 1 Analyzer non EX foundation detail drawing 60.0% Ontime
48 Z089-S-15 0 TRO 2 Analyzer EX foundation detail drawing 60.0% Ontime
49 0 Equipment foundation verification 60.0% Ontime
50 Z089-R-03 0 BOM of steel work 0.0% Ontime
51 Z089-R-04 0 BOM of Pipe 0.0% Ontime
52 Z089-R-05 0 Electrical load analysis 0.0% Ontime
53 Z089-E-01 0 Cable routing in ER and Pump Room 0.0% Ontime
54 Z089-R-06 0 Electrical BWTS Single Line Diagram 0.0% Ontime
55 Z089-E-02 0 Cable penetration drawing ER & Pump Room 0.0% Ontime
56 Z089-E-03 0 Hydraulic Remote control valve wiring , schematic , manual etc. 0.0% Ontime
57 Z089-E-04 0 Ballast water console layout and termination drawings 0.0% Ontime
58 Z089-E-05 0 Automation integration document for alarm integration 0.0% Ontime
59 Z089-E-06 0 Main switchboard wiring drawing 0.0% Ontime
60 Z089-E-07 0 GPS single line diagram, manual and termination drawing 0.0% Ontime
61 Z089-E-08 0 Main switchboard layout drawing 0.0% Ontime
62 Z089-E-09 0 Distribution board circuit diagram 0.0% Ontime
63 Z089-E-10 0 Electrical lighting layout drawings in ER & Pump room 0.0% Ontime
64 Z089-E-11 0 Ballast water pump starter / control panel drawing 0.0% Ontime
Electrical load condition during ballasting and deballasting operation (
Z089-E-12 0 0.0% Ontime
65 individual loads of the all the generators )
66 Z089-R-07 0 BOM of Cable 0.0% Ontime
67 Z089-R-08 0 BWTS Equipment Site lifting & Installtion Plan 0.0% Ontime
68 Z089-R-09 0 Ballast water management plan 0.0% Ontime

Page 1 of 1