You are on page 1of 6

SA SAFETY

Safety Engineering,
Risk Analysis
and Asset Integrity
Safe design from concept to operation

INERCO is currently developing major worldwide projects in the matter of industrial safety for large engineering
companies and operators in industries such as Oil & Gas (upstream and downstream), petrochemical, chemical,
mining and energy.

Keywords
Safety, Tools in the field of risk analysis, Risk management

Juan Santos Remesal Gabriela Reyes Delgado


Manager Industrial Safety Division INERCO Process Safety Area Manager INERCO
Alfredo Ramos Rodriguez Pastora Fernández Zamora
Head of Industrial Safety Department INERCO Risk Assessments Area Manager INERCO

62 Industria Química Special Achema 2015


SAFETY ENGINEERING, RISK ANALYSIS AND ASSET INTEGRITY

IN EACH SECTOR advanced safety to establish adequate mitigation or hazards in all these areas are known
criteria as well as applicable protection measures to have in all sooner, before taking decisions that
international standards and cases an acceptable risk associated lead us to take significant risks or
regulations are used. The set of tools with the facilities. incur into significant costs due to
applied in the projects goes from, • Defining the strategic action plan the need to implement mitigation
among others, HAZID/HAZOP Studies, in emergencies and development of measures; to have a hazard register of
SIL Analysis (SIL Index Determination, emergency and contingency plans. the identified hazards and a corrective
Safety Requirement Specification action plan in which the strategy of
or SRS and SIL Verification), LOPA Among others, the most widely used risk management is indicated and
Analysis, Fire & Gas system design, tools in the field of risk analysis are: measures to avoid, reduce or control
Quantitative Risk Analysis and them during design phase are in
ALARP, to studies as RAMS Analysis, • HAZID Analysis place; the measures taken can be
Risk-Based Inspection (RBI) and • HAZOP Analysis planned, implemented and audited
Risk Centered Maintenance (RCM), • Bow-Tie Analysis or controlled in time by the project
BOW-TIE, Safety Critical Elements • SIL analysis (SIL Index Determination, management; and delays in the
Determination and design standards Safety Requirement Specification or design or construction and budgetary
for these elements. SRS and SIL Verification) slippages by unidentified hazards are
Thus, both the promoters of • QRA or HAZAN Analysis avoided.
these projects, as the engineering • FHA/FEHA
companies that developed them, • FMEA Analysis HAZOP (HAZARD AND
implement, at the different stages of • RAMS Analysis OPERABILITY) ANALYSIS
the project, risk analysis tools focused • Risk-Based Studies Inspection HAZOP studies are conducted in order
on increasing safety levels and achieve (RBI) and Risk Centered Maintenance to identify all those deviations from
goals such as: (RCM) the design conditions that can lead
• Safety Critical Elements (SCEs) and to accidents, or constitute serious
• Identification of hazards from Performance Standards (PSs) operability problems, with special
external sources that can potentially • EERA attention to deviations that can cause
affect on plant inside. • SVA accidents with major consequences.
• Identification of hazards from The team working on a HAZOP
internal sources that may lead to HAZID (HAZARD follows an analytical structure through
an accident scenario, due to the IDENTIFICATION) ANALYSIS a set of guidewords (no, more, less,
hazardous characteristics associated HAZID analysis is a tool to identify etc.) to examine deviations from the
with the substances present and to hazards and make an initial assessment normal process conditions at key
operations during construction and of the risks. It aims to identify at an points (called NODES) of the unit.
operation phases of the plant. early stage all the hazards that the These guidewords are applied to
• Estimation of the consequences. project can be exposed to, from an the most relevant parameters (flow,
According to the hazardous internal and external point of view. pressure, temperature, level, etc.)
characteristics of the substances The areas where hazards are identified in order to identify potential causes
capable of causing any risk situation and risks are assessed include that can lead to this situation, the
quantifying the effects and geographic location, environmental consequences of the deviation of
consequences. conditions, requirements in matter of these parameters from the expected
• Estimation of the probability of environmental, engineering, safety, values and safeguards installed to
occurrence for the identified hazards, security or prevention of occupational avoid them.
so that the overall risk of the facilities hazards. As a result of the development and
can be known, once its consequences The timing of a HAZID study is application of HAZOP methodology to
are assessed. critical to maximize profit. Inevitably a industrial facilities, recommendations
• Identification of those points in HAZID will lead to changes in design would be obtained, for example,
the facilities where improvements or operational changes of the plant. concerning the design conditions of
might be needed in the design, It takes time to implement these the facilities (lines, equipment, need
inspection and maintenance to reach changes, the optimal time for a HAZID for additional instrumentation, valves,
a safer operation. is in basic engineering and before instrumentation and equipment
• Identification of areas, facilities, starting the detailed design. accessibility, etc.), alarm configuration
equipment and processes that The expected results of this type in controllers and indicators, status
contribute the most to risk, in order of study are, that in an early stage, indication of motors, verification of

www.industriaquimica.es Industria Química 63


SAFETY

Table 1.

PROJECT PHASE RISK ANALYSIS METHODOLOGY EXPECTED RESULTS

- Guidance for the selection process


HAZID - Detect unacceptable process hazards
CONCEPTUAL ENGINEERING CHECKLIST - Help for process design
WHAT IF - Identify key process modifications that reduce the risk level.
- Assist in the geographical location of the project

PHA
HAZID - Identify hazards in a more detailed way in the selected
CHECKLIST process and in the proposed design
BASIC ENGINEERING
WHAT IF - Risks associated with the geographic location
FMEA - Risks on special or critical equipment in the process
HAZOP

CHECKLIST
WHAT IF
FMEA
PHA
HAZOP
BOW-TIE - Identify all the hazards in the process, assessing the
Critical Elements studies, Safety associated risks
DETAILED ENGINEERING Barriers and performance standards - Identify aspects of the operation not initially contemplated
SIL/VERIFICATION AND SRS - Help to establish operating, commissioning and start-up
QRA procedures
FHA
RAMS
RBI/RCM
EERA
SVA

CHECKLIST
HAZOP
- Ensure the operation and that the information regarding
SIL/VERIFICATION AND SRS
quality, legal requirements, process safety and operating
FHA
procedures are complete and up to date
FACILITIES IN OPERATION QRA
- Incorporate lessons learned from recent accidents or
RAMS
incidents and consider the addition of new equipment,
RBI/RCM
systems and technologies that will improve safety levels
EERA
SVA

the design conditions of safety valves Element (hardware) or Critical activity to prevent a specific Threat from
or the need to install or configure (procedures, processes, operator action). releasing the Hazard, Verifiable – how
an interlock system or Safety • A clear visual representation shall the effectiveness of the barrier be
Instrumented System in the facilities. to enable ALARP review to be confirmed? And Independent of other
undertaken. barriers in the same Threat line, e.g.
BOW-TIE ANALYSIS • An aid in the incident review no ‘common mode failure’.
The bow-tie analysis is a model that process if occurrence of such a major
represents how a hazard can be incident has occurred. SIL ANALYSIS (SAFETY
released, escalate and how it is INTEGRITY LEVEL)
controlled. This methodology is The role of a barrier on the bow-tie SIL analysis is a risk study applied
usually applied to Major Accidents diagrams is to prevent (Left hand side to interlock systems or Safety
Hazards (MAH). For each MAH, the of BT) or limit (Right hand side of BT) Instrumented Systems (SIS), in which
bow-tie methodology allows: the consequence of a major accident. the safety level or SIL index (Safety
The barriers are divided into the Integrity Level) is analyzed. In this
• Identification of the hazard following different types: Structural sense, the SIL index has a direct
release, escalation and consequence Integrity (SI), Process Containment relation with the average Probability
scenarios. (PC), Ignition Control (IC), Detection of Failure on Demand and the Risk
• Identification of controls, e.g. Systems (DS), Shutdown Systems (SD), Reduction Factor.
barrier and escalation factor controls Protection Systems (PS), Emergency Functional Safety regulations and
required to manage hazards. Response (ER), Life Saving (LS). standards, ANSI-ISA-S84 and IEC-
• C a t e g o r i s a t i o n o f c o n t ro l s Barriers shall be effective in preventing 61511/61508 establish the different
into Inherent Safety, Safety Critical the Top Event or Consequence, able stages to cover in the Safety Life Cycle

64 Industria Química Special Achema 2015


SAFETY ENGINEERING, RISK ANALYSIS AND ASSET INTEGRITY

of a Safety Instrumented System, from SIS requirements shall be expressed The general methodology of QRA
initial conception until its removal. and structured so that they are clear, development comprises: identifying
According to the above normative, accurate, verifiable, sustainable, accident initiating events, causes and
there are several methodologies for feasible and written so that they can frequencies, determining the evolution
the development of SIL analysis, that be understood and applied. The design of initiating events to end accidents,
may be qualitative (Risk Graphs), requirements specification for the SIS determining the probability of weather
semiqualitative (Calibrated Risk Graph shall include the system or system conditions, the lethal threshold values,
or Risk Matrices), semiquantitative component function, the actions the range of the lethal consequences
( L O PA A n a l y s i s a n d L a y e r s o f that the system or component shall and determination of the probability
Protection Analysis) or quantitative do under prescribed circumstances of people presence nearby and / or
(Markov Analysis or Quantitative (functional specification) and the distribution of workers at the facility
Risk Analysis). The methodology required integrity (reliability and and risk quantification through a
finally used must be selected by the availability) to operate in these combination of all the above factors,
engineering company according to circumstances (integrity specification). for all scenarios identified.
specifications, the critical nature of SIS conceptual design is specified in The results of the QRA will allow,
processes and resources allocated for SIL Verification, defining the acquisition among other applications, to compare
the development of the study and will of the elements of the SIS according to obtained risk levels with tolerable
be based on risk acceptability criteria safety and reliability criteria, as well as individual and social risk levels, or to
established by the Property. setting ranges of system maintenance, identify those accidental scenarios
to comply with safety specifications that contribute the most to risk,
SRS (SAFETY REQUIREMENT derived from the SIL index determined to make decisions on optimal risk
SPECIFICATION) AND in the previous step. reduction measures to implement in
SIL VERIFICATION FOR order to achieve acceptable risk levels
THE CONCEPTUAL QRA (QUANTITATIVE RISK in case that the risk obtained is not
DESIGN OF THE SIS ASSESSMENT) OR HAZAN acceptable. It is a dynamic tool to be
SRS or Safety Requirement Specification (HAZARD ANALYSIS) updated not only during engineering
is another step in the life cycle of Quantitative Risk Assessment but also during operation since
Safety Instrumented Systems in which or HAZard ANalysis is a tool by the enlargement and new projects
the safety requirement specification which a risk identification followed modify the risk and will be useful for
is developed, essentially the system by a numerical evaluation of its management and decision making
operation philosophy. Each safety consequences and frequencies of regarding the safety of the facilities.
function must have an associated occurrence is performed, to finally
SIL requirement and reliability combine both factors and obtain FHA (FIRE HAZARD
requirements for spurious trip. It should a risk measure associated to the ANALYSIS), FEHA (FIRE
include all operating conditions of the activity analyzed on people. This AND EXPLOSION HAZARD
process, from start-up to shutdown, risk measure can be performed for ANALYSIS) OR CONSEQUENCE
including maintenance for each both to employees as to the outside SCOPE ANALYSIS
operation mode of the process. population of the facilities. Fire Hazard Analysis or Fire and

www.industriaquimica.es Industria Química 65


SAFETY

Explosion Hazard Analysis is a RAMS ANALYSIS developed by the American Petroleum


structured and systematic approach (RELIABILITY, AVAILABILITY, Institute, is described in a series of API
to identify and assess fires and MAINTAINABILITY standards, which include the API 580
explosions, to ensure, in the design AND SAFETY) standards: Risk Based Inspection and
of the facilities, adequate fire and RAMS can be defined as an intrinsic API 581: Risk Based Inspection. Base
overpressure protections for various feature of a facility that measures the Resource Document.
equipment and facilities, reducing long-term operation of the facility M o re o v e r, a s a c o m p l e m e n t
the possibility of accidental climbing and that helps in decision making to the maintenance strategy, the
and ensuring as far as possible the to reduce the costs derived from implementation of a methodology
integrity of the plant. needs of shutdown for maintenance as Reliability Centered Maintenance,
Consequence Scope Analysis include and reparation in both normal and widely used in industries such as
hazard identification, consequences scheduled operations as in those aerospace and automotive, to the
calculation and risk zones according conducted by failures / unexpected Oil&Gas industry has as immediate
to predefined threshold values and shutdowns. The facility design must effect an increase in equipment and
the calculation of vulnerability of take into account this concept since components reliability and thus an
people and property. its influence is direct in the life cycle increase in safety levels of the facility.
T h e re s u l t s a l l o w o b t a i n i n g and performance of the facility. The methodology aims to establish
information to ensure safe and reliable Specifically, the concepts used in the a maintenance strategy for each
operation of the facilities for all phases RMS study are Reliability, Availability, component or equipment according to
of the project. Maintainability and Safety. their critical nature in the system that
RAMS analysis aims to predict the will be marked by the influence that a
FMEA ANALYSIS performance, availability and safety fault in the equipment or component
(FAILURE MODE of the process systems, as well as to has on parameters such as safety,
EFFECTS ANALYSIS) provide a basis for optimization of environmental condition, production,
Failure Mode Effects Analysis (FMEA) such systems and ensure achievement repair costs, etc., in an effective way in
is a technique for identifying hazards of fixed targets for the facility. These the implementation cost.
associated with equipment of a studies are increasingly becoming a It has been proved that the
process plant. This tool aims in its standard requirement for engineering application of these maintenance
application, to establish possible design. It can be said that RAMS strategies have a direct effect on the
faults in each and every one of the analysis shall form an intrinsic part of availability of the facilities and so on
elements (process and control) in a the original design and that its four exploiting them and in the business.
plant, to analyze the consequences of branches are closely linked, so that Both methodologies, RBI and
the failures established in the previous each affects the other. RCM are complementary and can be
step, to detect those that may lead to implemented so that the synergies
accidents and to establish protection RISK-BASED INSPECTION between the two are used for a
measures to prevent equipment STUDIES (RBI) AND greater economic benefit and to
failures that are significant. RISK CENTERED improve safety levels of any facility.
The FMEA can be used to MAINTENANCE (RCM)
complement other hazard RBI methodology facilitates SAFETY CRITICAL ELEMENTS
identification techniques such as the definition of maintenance (SCES) AND PERFORMANCE
HAZOP analysis of special systems, m a n a g e m e n t p ro g r a m o f t h e STANDARDS (PSS)
as furnaces or electrical / electronic facilities based on the results of The Safety Critical Elements are
systems. a comprehensive study of the defined through a Bow-Tie Analysis
The FMEA comes from of a list of risks associated with each of its of the Major Accidents Hazards
equipment and components of the equipments. This allows to focus on (MAH). Barriers for high risk hazards
plant under study that are likely to the maintenance of equipment in shall be classified as High Risk Hazards
cause a failure, and for each one, those that suppose a greater risk to Critical Elements and will be selected
its failure modes are identified. the human environment (workers, in accordance with corporative
The analysis is complemented by nearby towns), natural (air quality, Standards and good engineering
determining a risk index using for water and soil) and socioeconomic practices. A Safety Critical Element
example a double-entry matrix (infrastructure, historical-landscape (SCE) is any item of hardware, system
(probability and consequences) that heritage, economic activity). or logic software the failure of which
help to prioritize the definition of The theoretical basis on which could cause a major Accident Hazard
corrective measures. the RBI methodology is based on, or whose purpose is to prevent

66 Industria Química Special Achema 2015


SAFETY ENGINEERING, RISK ANALYSIS AND ASSET INTEGRITY

or mitigate the effects of a Major in a reasonable and feasible way. EERA SVA (SECURITY
Accident Hazard. is a widely used tool in the design of VULNERABILITY ANALYSIS)
For every SCE selected a offshore platforms in which, taking It is increasingly necessary to take
Performance Standard (PS) shall be into account the characteristics of into consideration during the design
developed. A PS is a statement, which them, an emergency situation requires of industrial facilities aspects of
can be expressed in qualitative or that the measures of evacuation and protection from the point of view of
quantitative terms, of the functional rescue are perfectly designed and intentional threats on facilities. This is
performance required of a SCE, and analyzed since it is critical to ensure not solely a matter of controlling the
which is used as the basis for managing that people who live in there do perimeter or to have a security service.
the risk from the Major Hazards. The not suffer major consequences. In In industrial facilities in which threats
Performance Standards for SCEs shall ground facilities such as refineries this can be addressed to equipment
be established according to Design type of analysis is used to define the and systems handling hazardous
Standards and the results of safety mobilization of emergency teams, the substances that may be released
and environmental studies performed initial positioning of them and how intentionally and affect workers and
on the project. Performance Standards shall be the procedure of each team, nearby population, additional safety
are used as the basis for design and specifying firefighting or refrigeration measures shall be applied.
technical (operational) integrity equipment to use. This analysis can be These measures shall be taken
verification and are expressed in terms completed with the determination and from design and engineering. To do
of functionality, availability, reliability, analysis of firefighting water needs for this, Security Vulnerability Analysis
survivability and dependencies/ each risk scenario, depending on the or SVA can be used as a tool. SVA is
interactions with other SCEs. flow demand of each equipment and a process that identifies and analyzes
Functionality is an expression the estimated running time. the operational physical vulnerabilities
used to define what the system or EERA is a technique for assessing of the facilities against external threats
equipment is required to achieve in the performance of emergency determined as credible depending on
order to ensure design integrity. facilities and emergency response the type of installation, geographic
Reliability and Availability: Reliability procedures designed for this purpose. location or environment among others.
is defined as the required probability It consists of a structured review of
that the system or equipment will the realization of escape, evacuation CONCLUSIONS
operate on demand, when required. and rescue facilities and the action There are countless different tools that
Availability is defined as the extent procedures in the representative risk can be used depending on the phase
to which the system or equipment scenarios and takes as input the results of activity, the project to develop,
is required in order to retain its of a Consequence Scope Analysis. the target objective and the risk
functional integrity. Performing this analysis in management policy that the company
Survivability defines the external engineering design phase generates has set to achieve its safety objectives.
loading events such as fires, explosions as the most relevant results and As a reference, in the appended table
or extreme weather, associated with with direct transfer to facility design, it is shown in an illustrative way for the
the various MAHs against which the aspects such as identifying needs of different phases of activity some of the
system or equipment is required to additional material resources, both most appropriate risk analysis tools
retain its functional integrity. fixed and mobile to equip the facility, depending on the expected results.
Dependencies and Interactions. identification of the location of Its application offers significant
This is used to identify other systems commanding points, routes of attack safety benefits throughout the lifecycle
or equipments that are critical to the of the firefighting brigades and the of an industrial plant and it is important
functionality of the primary system definition of the dimensions of the to have the necessary experience to
or equipment. By identifying these attack and evacuation routes and the choose those that fit the installation to
dependencies and interactions it is possible isolation or zoning of the risks evaluate and the target objectives.
ensured that all interfaces have been to prevent the expand of the accident In this sense INERCO has over
covered. or domino effect, confinement or 30 years of experience advising on
containment dike sizing, safety risk management and increasing
EERA (ESCAPE, EVACUATION distances, etc. All this will end up comprehensive safety levels in the
AND RESCUE ANALYSIS) being the basis of a pre-fire plan or industrial sector (Oil & gas, chemical,
The main objective of the Escape, specific action procedure for each of energy, mining, metallurgy, industrial
Evacuation and Rescue Analysis (EERA) the identified situations and constitute engineering, etc.) using the most
is to ensure that the facilities meet the the operational part of emergency effective media in terms of cost-
highest level of safety in an emergency planning of the facility. effectiveness in reducing risk.

www.industriaquimica.es Industria Química 67

You might also like