DSLNG Project Job No.

: 0-5151-20
Doc. No. : S-900-1670-561 <Rev.0>
TEST AND INSPECTION PLAN FOR HOT OIL HEATER ERECTION SHEET 6 OF 38

6. SCOPE OF TEST & INSPECTION

WITNESS BY

CONTRACTOR
SUBCONT’R
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS

OWNER
1.1 Material Receiving Packing List, NA Before Install 5000-502 NA FI/P NA
Vendor Drawing

1.2 Equipment Drawing As per V-2156-001-A-802 After setting 5000-701 FI/P FW SW


Installation Erection Manual (for erection
(1) Foundation Check tolerance) 5000-703
(2) Plumbness 5000-705
(3) Elevation 5000-708
5000-506

1.3 Anchor Bolts ANSI A10.13 Snug tight, fully tightened by After setting 5000-701 FI/P FW SW
Section 9.6 using ordinary spud wrench
5000-703

5000-704

5000-506

1.4 Grouting of base plate No Voids 5000-701 FI/P FW FW

5000-703
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-561 <Rev.0>
TEST AND INSPECTION PLAN FOR HOT OIL HEATER ERECTION SHEET 7 OF 38

WITNESS BY

CONTRACTOR
SUBCONT’R
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS

OWNER
1.5 Platform and Ladders As per drawing 5000-999 FI/P FW FW

5000-705

1.6 Final Connection 5000-001B


between Equipment 5000-510 FI H FW
and Piping.
5000-511
(1) Flange Face
(2) Gasket 5000-704
(3) Bolt and Nut 5000-709
(4) Bolt Tightening

1.7 Name Plate As required 5000-320 FI H FW

1.8 Process Coils Related Vendor As per V-2156-001-A-802 5000-702 FI/P FW SW


Installation Documents, V- Erection Manual para 5.10,6.0
2156-001-A- 5000-001B
207/247 5000-510

1.9 Burner Installation Related Vendor As per V-2156-001-A-802 5000-710 FI/P FW SW


Documents, V- Erection Manual para 6.2
2156-001-A- 5000-711
208/209
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-561 <Rev.0>
TEST AND INSPECTION PLAN FOR HOT OIL HEATER ERECTION SHEET 8 OF 38

WITNESS BY REMARKS

CONTRACTOR
SUBCONT’R
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM

OWNER
1.10 Refractory Related Vendor As per V-2156-001-A-802 5000-603 FI/P FW SW
Documents, V- Erection Manual para 6.3
2156-001-A-
305/625

1.11 Fire Proofing Related Vendor As per Doc.D-900-1330-012 8000-001 FI/P FW SW


Documents, V- Standard Drawing for Steel
2156-001-A-273 Structure Fire Proofing.

1.12 Commissioning As per V-2156-001-A-801 5000-715 FI/P FW SW


Installation, Operation and
Maintenance Manual (IOM)

1.13 Functional Test After As per V-2156-001-A-801 5000-716 FI/P FW SW


Installation Installation, Operation and
Maintenance Manual (IOM)

1.14 Painting at Field As per S-900-13A0-001 A000-003 FI/P FW SW


Specification for Painting
9000-003F

1.15 Preservation As per V-2156-001-A-624 5000-501 FI/P FW SW


Long Term Storage Procedure
at Site
DSLNG Project Job No. : 0-5151-20
Doc. No. : S-900-1670-561 <Rev.0>
TEST AND INSPECTION PLAN FOR HOT OIL HEATER ERECTION SHEET 9 OF 38

WITNESS BY

CONTRACTOR
SUBCONT’R

OWNER
SITE INSPECTION ITEM REFERENCE REQUIREMENT FREQUENCY FORM REMARKS

2. Box Up
2.1 Internal cleaning 5000-312 FI/P H FW

2.2 Final closure inspection Manhole bolt, nut and gasket 5000-312
equipment nozzle face/ check (use ceramic fiber)
MH face gasket, Bolt 5000- FI/P H FW
and Nut 001B

2.3 Bolt Tightening Final Manhole bolt, nut and gasket 5000-312
closure inspection after check (Bolt tensioning work, if
final manway closure applicable) 5000-511 FI/P H H