Professional Documents
Culture Documents
December 6, 2017
Contents of lecture
• Introduction
▫ Classification of admixture technology
• Comparison of concrete and stabilized soil
• Cement Deep Mixing Method
▫ laboratory test
▫ DM machine
▫ Execution
▫ Quality control
▫ Case history
• Concluding remarks
3
machine
development
projects
1968, field trial 1971, first work 1994, Kansai Airport 2010, Haneda Airport
Design standard
& manual
1979, lab. test 1990, design, lab. test 2002 2007, design 2013
6
Deep mixing
7
applications
slip failure prevention quay wall
settlement reduction revetment
Detailed design
10
OBJECTIVES:
To obtain the mixing condition to achieve
the design strength at field.
molding measuring
capping testing
15
Mixing blades
Japan Nordic countries USA
20
execution procedure
penetration injection withdrawal injection
where
T: blade rotation number (N/m)
Nd: number of rotation of mixing blades
during penetration (N/min)
Nu: number of rotation of mixing blades
during withdrawal (N/min)
Vd: penetration speed of mixing blades
(m/min)
Vu: withdrawal speed of mixing blades
(m/min)
M: total number of mixing blades
25
penetration speed of shaft 1.0 m/min 1.0 m/min 1.0 - 2.0 m/min
withdrawal speed of shaft 1.0 m/min 0.7 - 1.0 m/min 0.7 - 0.9 m/min
rotation speed of blade 20 - 60 rpm 20 - 40 rpm 24 - 64 rpm
amount of stabilizing agent 70 - 300 kg/m3 70 - 300 kg/m3 100 - 300 kg/m3
penetration penetration
injection phase withdrawal
withdrawal withdrawal
26
Execution
cement
How to control amount of cement to
be mixed ?
Plant:
supply cement slurry constant at rate
DM machine:
keep constant penetration and
withdrawal speeds.
QC/QA
blade rotation number
N d Nu
T M
Vd Vu
where
T : blade rotation number (n/m)
M : total number of mixing blades
Nd : rotation speed of the blades during
penetration (rpm)
Vd : mixing blade penetration velocity
(m/min)
Nu : rotational speed of the blades during
withdrawal (rpm)
Vu : mixing blade withdrawal velocity
(m/min)
29
Quality assurance
Core boring
On land works:
3 cores < 500 columns
+ 1 core for every 250 columns
Marine works:
3 cores < 500 columns
+ 1 core for every 500 columns
UC test
The JGS standard of UC test for cohesive
soil is applied.
30
Mixing condition
- Tokyo/Haneda Airport -
field strength
field strength, quf28 binder factor
no. of
depth ave. max. min. CV CW rev. CN rev.
specimen
(kN/m2) (kN/m2) (kN/m2) (%) (kg/m3) (kg/m3)
surface
-19 to -21 m 20 3,409 5,608 2,391 27.1 165 160 165 160
layer
clay 1-C1 -21 to -30 m 36 4,009 7,981 2,568 28.9 140 120 145 125
clay 2-C2 -30 to -34 m 16 3,929 6,116 2,257 21.3 130 110 135 120
sand 2-C -34 to -45 m 44 4,534 7,595 2,617 26.4 110 80 120 85
total 116 4,094 7,981 2,257 28.3
clay 1-C1 -21 to -30 m 72 4,410 7,313 2,013 29.8 120 125
clay 1-C2 -30 to -34 m 32 4,561 7,726 2,092 33.9 110 120
Concluding remarks
Japanese techniques and experiences on DMM is briefly
introduced to show a similar to but quite different technology
from concrete technology.