You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/272494423

Hybrid Pits — Linking Conditional Simulation and Lerchs-Grossmann


Through Set Theory

Chapter · January 2007

CITATIONS READS

6 141

1 author:

David Whittle
University of Melbourne
21 PUBLICATIONS   28 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Underground Mine Plan Optimization View project

All content following this page was uploaded by David Whittle on 17 February 2015.

The user has requested enhancement of the downloaded file.


Hybrid Pits — Linking Conditional Simulation and
Lerchs-Grossmann Through Set Theory
D Whittle1 and A Bozorgebrahimi2

ABSTRACT Dimitrakopoulos (2003) outlined a technique similar to one


described above (Van Brunt and Rossi, 1999) but extended to
The authors have developed and tested a technique that leverages some of
the statistical properties of conditionally simulated models and the include the evaluation of each simulated model against each of
technical characteristics of Lerchs-Grossmann pits. The result is not one, the multiple LG pits. The objective of this approach was to find
but a nested set of pits, which are named Hybrid Pits in this paper, each the LG pit that delivered the highest average dollar value when
of which has a definable statistical characteristic, which ultimately evaluated against the full set of simulations.
reflects risk. Existing methods involve the generation of optimal pits, each
In terms of application of these Hybrid Pit designs, one further element for a separate model. The value of these methods revolves around
is introduced, that being the propensity for knowledge to increase over the way in which the multiple optimal pits are generated and
time. At the time of planning, a certain amount of orebody data is evaluated. In each case, the pit that is finally chosen will be an
available, leading to an estimable degree of uncertainty in the model. As LG pit that has been generated for a single model:
time passes and mining progresses, the amount of information increases
(due to additional drilling, etc) so the degree of model uncertainty should • a pit that is optimal for a representative model, such as a
decrease. This paper includes an explanation of how the hybrid set of pits kriged model or E-Type model, described by Van Brunt and
can be used as design guides to allow a degree of risk avoidance, Rossi (1999); or
associated with the higher uncertainty in early times.
The benefit of applying this methodology is a managed reduction in
• a best performing pit as described by Dimitrakopoulos
risk, contributing to higher project values. (2003).
In early 2000, one of the authors (Whittle) commenced work
INTRODUCTION on a methodology that would lead to the creation of pits that
were directly influenced by a set of conditionally simulated
In applying Lerchs-Grossmann (LG) pit optimisation (Lerchs models, and produced some preliminary software specifications
and Grossmann, 1965) to an orebody model, you are applying a to enable the technique to be developed. The expectation at the
process that will guarantee to find the optimal pit outline that time was that methodology, called Hybrid Pits in this paper,
maximises the dollar value, for a given input orebody model and would provide a useful mechanism for relating the variance
a given set of economic and geotechnical conditions. The LG information inherent in conditionally simulated resource models,
method can only be applied to a single orebody model and into a Reserve context.
cannot directly take account of uncertainty associated with that In March 2004, Whittle undertook the completion of the Set
model. Theory model for hybrid pits, which provides mathematical
Conditional simulation has emerged as a methodology to rigour to the ideas that were hitherto based on intuition. Having
provide more meaningful models of orebodies, taking into then a sound theoretical basis for hybrid pits, the next step was to
account the uncertainty inherent in the sampling and trial the technique using a small database.
interpolation process, and providing multiple representative Dr Bozorgebrahimi joined Gemcom Software International Inc
models for any given set of data. in June 2004, as a Business Analyst – Mining Engineer, the same
The question that arose early in the development of office as Whittle. With Bozorgebrahimi’s training and experience
conditional simulation is, how does one use the additional in conditional simulation, the opportunity to collaborate on this
information that the process provides, to better design mines? next phase of the development of the hybrid pits concept
Van Brunt and Rossi (1997) describe the general nature of emerged. Whittle and Bozorgebrahimi immediately commenced
conditionally simulated models and their application in mine work on the project. The trial was successful, leading to
design, and describe a construct and an analysis method that are refinement of, and support for the mathematical models.
both relied upon in this paper. These are:
• the probabilistic framework within which simulated models HYBRID PITS
exist; and Conditional simulation produces multiple orebody models, each
• the evaluation of a mine design against multiple simulated being an equally probable estimate of the real resource. It is
models. possible to generate optimal pit outlines for each of these
orebody models using the Lerchs-Grossmann method (Lerchs
Van Brunt and Rossi (1999) expand on their earlier work and and Grossmann, 1965), where each pit is optimal for its
describe the generation of optimal pit shells for each of a set of corresponding orebody model, meaning:
simulated models. Dimitrakopoulos, Farrelly and Godoy (2001)
extend the application of the Van Brunt and Rossi (1999) method • the pit obeys the pit slope constraints as modelled by the
including analysis techniques described in the context of a case structure arcs in the graph model; and
involving 50 simulations of a typical disseminated low-grade • the $ value of the pit is maximised.
epithermal quartz breccia-type gold deposit. The value of the pit can then be estimated by applying the
whole family of models to the pit and recalculating the $ value
(Dimitrakopoulos, 2003). However, the optimality of the
1. MAusIMM, Whittle Product Manager, Gemcom Software Lerchs-Grossmann (LG) pit relates to the individual orebody
International Inc.
model that was used in its generation, rather than to the family of
2. Business Analyst – Mine Engineering, Gemcom Software pits. In the creation of the shape of the pit, there was no account
International Inc. taken of the family of models.

Orebody Modelling and Strategic Mine Planning Perth, WA, 22 - 24 November 2004 399
D WHITTLE and A BOZORGEBRAHIMI

The authors propose the use of hybrid pits, which are derived With the application of the Associative Law, the intersection of
from the family of pits that are generated from the family of any combination of o-sets will lead to a set that represents a
orebody models. The hybrid pits are derived from LG pits, feasible pit.
are technically feasible and have specific probabilistic
characteristics. In order to describe the derivation of the hybrid Principle 2 – unions of o-sets represent feasible pits
pits, it is necessary to establish certain principles, and Set Theory
provides a useful framework for doing this. An illustration of a union of three pits is shown in Figure 2. In
the Set Theory model, this is the union of three o-sets.
Set theory model for hybrid pits A union of o-sets will constitute a feasible pit. For any block x,
the o-set or o-sets to which it is a member must include X (all the
Let the Universal Set be the set of blocks in a block model blocks that must be mined if x is to be mined). The pit can only
framework. become unfeasible if blocks are removed from an o-set, and
determining the unions of sets will not lead to the removal of any
Universal Set U {x|x is a block in the model framework} blocks.
A {x|x is a block being a member of pit A, which is
optimal for simulation a}
B {x|x is a block being a member of pit B, which is
optimal for simulation b}
C {x|x is a block being a member of pit C, which is
optimal for simulation c}
D {x|x is a block being a member of pit D, which is
optimal for simulation d}, etc
The sets defined above will be referred to as the ‘o-sets’
(original sets representing LG pits for single simulations), to
make the distinction between this type of set and other types of
sets that will be discussed.
In o-set A, for any block x, it can be said that the set includes
all the blocks that must be mined if x is to be mined. This is true FIG 2 - A union of technically feasible pits will produce a
because the application of the Lerchs-Grossmann algorithm, technically feasible (hybrid) pit.
through which the set was defined, requires it to be true. The
same can be said for o-sets B, C, D, etc. Principle 3 – the set of all blocks which are members
Let us call the set of all blocks that must be mined if x is of more than or equal to m o-sets (A, B, C, D, etc)
mined, X. It is true to say that for any given x, X is unique. There represents a feasible pit
cannot be two sets of blocks that satisfy the condition of needing
to be mined if x is mined. Principle 3 is explained fully for the case in which there are four
(A, B, C and D) o-sets, but the logic is extendable to any number
Principle 1 – intersections of o-sets represent of o-sets. The explanation is included in Table 1.
feasible pits
Principle 4 – the set of blocks which is a member of
An illustration of an intersection of three pits is shown in m or more o-sets, is a subset of the set of blocks
Figure 1. In the Set Theory model, this is the intersection of three which are members of m-1 or more o-sets
o-sets.
If block x is an element of o-sets A and B, then both A and B Principle 4 is explained fully for the case in which there are four
must include X (all the blocks that must be mined if x is mined). o-sets (A, B, C and D), but the logic is extendable to any number
If X is a subset of both A and B, then it follows that that x must of o-sets. The explanation is included in Table 2.
include X. This is true for all X sets, for all incidents of x that are
members of both A and B. Accordingly A B (the intersection of GENERAL BEHAVIOUR OF HYBRID PITS AS
o-sets A and B) will constitute a pit that can be mined, as it APPLIED TO CONDITIONALLY SIMULATED
obeys the precedence rules of mining. The same can be said of
MODELS
B C, C D, etc.
The real resource is the actual mineralisation that exists in the
ground, but which cannot be absolutely known by the modeller,
as the modeller only has samples of it, rather than absolute
knowledge of it. Conditional simulation seeks to generate n
equally probable models of the real resource, where n is
sufficiently large that the full set of simulations is representative
of the whole population of possible models. The models are
equally probable representations of the real resource, which at
the time of modelling is not absolutely known, it is only know
through the samples of it. One of the conditionally simulated
models will be the most representative of the real resource, but it
is not known which model this is. If n is sufficiently large, then it
is highly probable that at least one of the models will be
sufficiently representative of the real resource, such that in the
process of mining, the real resource should behave for all
economic and operational purposes, exactly like that model. The
FIG 1 - An intersection of technically feasible pits will produce a chance of any of the models being the most representative of the
technically feasible (hybrid) pit. real resource is 1/n.

400 Perth, WA, 22 - 24 November 2004 Orebody Modelling and Strategic Mine Planning
HYBRID PITS — LINKING CONDITIONAL SIMULATION AND LERCHS-GROSSMANN THROUGH SET THEORY

TABLE 1
Explanation of Principle 3 as it relates to four sets (A, B, C and D).

Symbols
∩ ‘intersection’. The intersection of two sets, A and B (A B), is the set of all elements that are common to both A and B.
∪ ‘union’. The union of sets A and B (A B), is the set of all elements that are members of set A and/or set B.
The set of blocks that are members of one or more o-sets
All elements of A B C D (the union of sets A, B, C and D) must be a member or one or more o-sets.
The set of blocks that are members of one or more o-sets is equal to A B C D which, in accordance with Principle 2, is a feasible pit.
The set of blocks that are members of two or more o-sets
If x is a member of two or more o-sets, then it must be a member of one or more of the following:
A B A C A D B C B D C D
All members of one or more of the above sets are members of two or more o-sets. Accordingly, the set of all blocks that are members of two or more
o-sets is equal to:
(A B) (A C) (A D) (B C) (B D) (C D)
With the application of both Principle 1 and 2, it follows that the set of all blocks that are members of two or more o-sets represents a feasible pit.
The set of blocks that are members of three or more o-sets
If x is a member of three or more o-sets, then it must be a member of one or more of the following:
A B C A B D A C D B C D
All members of one or more of the above sets are members of three or more o-sets. Accordingly, the set of all blocks that are members of three or more
sets is equal to:
(A B C) B D) (A C D) (B C D)
With the application of both Principle 1 and 2, it follows that the set of all blocks that are members of three or more o-sets represents a feasible pit.
The set of blocks that are members of four sets (all sets)
If x is a member of four o-sets, then it must be a member of A B C D. With the application of Principle 1, this represents a feasible pit.

TABLE 2
Explanation of Principle 4 as it relates to four sets (A, B, C and D).
Additional Symbol
(Also refer also to Table 1 for the explanation of symbols)
⊂ ‘is a subset to’. Indicates that the set on the right of the symbol contains (at least) all the elements that are members of the set on the left of the
symbol. For example G H means that all elements in set G can also be found in set H.
U ‘The Universal Set’. This is the set of all elements that could be members of any of the sets under consideration. In the context of this discussion,
the Universal Set is the set of all blocks in the block model.
The set of blocks that is a member of one or more o-sets, is a subset of the set of blocks that are members of zero or more o-sets.
(A B C D) U

The set of blocks that is a member of two or more o-sets, is a subset of the set of blocks that are members of one or more o-sets.
(A B) (A C) (A D) (B C) (B D) (C D) (A B C D)

The set of blocks that is a member of three or more o-sets, is a subset of the set of blocks that are members of two or more o-sets.
(A B C) (A B D) (A C D) (B C D) (A B) (A C) (A D) (B C) (B D) (C D)

The set of blocks that is a member of four (all) o-sets, is a subset of the set of blocks that are members of three or more o-sets.
(A B C D) (A B C) (A B D) (A C D) (B C D)

Pit optimisation generates sets of blocks that represent the n is sufficiently large, the set of all blocks that are members of m
reserve and necessary stripping, such that the $ value of the pit is or more o-sets, represents a feasible pit, which has m/n
maximised. If you generate an optimal pit for each of n models probability of being a subset of the optimal pit for the real
and if n is sufficiently large, then any one of these pit resource.
optimisations has a 1/n chance of being optimal for the real With the application of Principle 2 (established above), and if
resource. n is sufficiently large, the union of all o-sets is a feasible pit,
If a pit is suboptimal for the real resource, then it must include which is a superset to the optimal pit for the real resource.
material that should not be mined and/or it must not include With the application of Principle 4 (established above), the set
material that should be mined. In other words, if the real resource of blocks for m≥1, m 2, m 3, …, m n, are progressively more
was absolutely known, and the pit optimisation proceeded on the likely to be subsets of the optimal outline of the real resource.
basis of a precise model of it, the pit would be different to, and Principle 4 also establishes that the pits represented by the set of
have a higher value than any of the suboptimal pits. blocks for m≥1, m 2, m 3, …, m n progressively nest (they are
With the application of Principle 3 (established above), and if each supersets to the next).

Orebody Modelling and Strategic Mine Planning Perth, WA, 22 - 24 November 2004 401
D WHITTLE and A BOZORGEBRAHIMI

PROJECTED APPLICATION OF HYBRID PITS uncertainty associated with any hybrid pit H-Pit(m). As m
increases:
With reference to the above discussion, a Hybrid Pit will now be
defined: 1. the size of the pit decreases, and
H-Pit(m) is the set of all blocks that are members of m or more 2. the probability that it does not over-mine the optimal pit for
o-sets. The set represents a feasible pit, which has m/n the real resource increases.
probability of being a subset of the optimal pit for the real The authors envisage that this model will be applied in future
resource. to determine pit shapes that exhibit a known and acceptable
Where: compromise between certainty (risk reduction) and size (reserve
n is number of o-pits maximisation).

Outer-bound pit – H-Pit(1) INITIAL TRIAL OF HYBRID PITS TO A


CONDITIONALLY SIMULATED MODEL
You can produce a pit outline that is feasible, by finding all
blocks that are members of any of the original pits. This is
referred to as H-Pit(1), meaning that it includes all blocks that
Methodology of the trial
are members of one or more o-pits. If n is sufficiently large, this In order to check the theory of Hybrid Pits, a block model related
pit will almost certainly include the pit outline, which would be to a gold deposit was selected. Based on this original model, five
optimal for the real resource. Such a pit provides an outer bound separate block models were created using a simulation program.
for the optimal outline. For normal modelling purposes, five simulations are not
adequate, but five are adequate for the purposes of testing the
Inner-bound pit – H-Pit(n) mathematical propositions put forward in this paper.
Each of these simulated models has a chance to represent a
You can produce a pit outline that is feasible, by finding all possible real resource. In the next step, Whittle software was
blocks that are members of all of the original pits. This is utilised to perform optimisation analysis on simulated models. In
referred to as H-Pit(n), meaning that it includes all blocks that order to be consistent in optimisation, the same parameters were
are members of all o-pits. If n is sufficiently large, the resulting applied in analysis. The optimised pit shells were then exported
outline will almost certainly be a subset of the optimal outline for to GEMS software where they were used to modify new
the real resource, and you can be highly confident that H-Pit(n) attributes within block models. The values of these attributes
will not exceed the boundaries of the optimal outline for the real were then exported into spreadsheets with their block numbers.
resource. Such a pit provides an inner bound for the optimal Using the theory explained above, a pit-list file for Hybrid Pits
outline for the real resource. was created. This pit list then was imported into Whittle and
there a cash flow analysis was performed for each simulated
High confidence reserve pit model and Hybrid-Pits.
The inner-bound pit H-Pit(n) may be used as a type of High Figure 3 shows the procedures of this experiment.
Confidence Reserve pit. You can be highly confident that this pit
will not over-mine the real resource. By the time you have mined
the High Confidence Reserve pit, you will have better geological Simulation
data available for the remaining resource, and will be in a much
better position to determine the direction in which to expand the
pit. This is an example of the mechanism by which the Hybrid
Pits technique can be used as design guides to allow a degree of Optimisation
risk avoidance, associated with the higher uncertainty in early analysis
times.

Estimator of the impact of geological uncertainty Pit shells exported


One of the impacts of geological uncertainty is that it leads to to GEMS
uncertainty as to the shape and size of the final pit. With the
application of the Hybrid Pit approach, as is discussed above:
• you can be highly confident that the optimal pit for the real Attribute
resource will be a superset to H-Pit(1); and modification
• you can be highly confident that the optimal pit for the real
resource will be a subset to H-Pit(n).
The area bounded by H-Pit(1) and H-Pit(n) represents the area Hybrid-Pit
in which the optimal outline for the real resource can exist. If the creation
area is large, it indicates that the orebody model variance, as
expressed in the simulations, leads to a high degree of
uncertainty as to the position of the optimal pit boundary. If the Cash Flow
area is small, it indicates that there is a low degree of uncertainty
as to the position of the optimal pit boundary.
analysis
The above principles can be generalised as follows:
The probability of the optimal pit for the real resource
being a superset to H-Pit(m) is m/n. Conclusion
This is the manner in which specific probability estimates can
be applied. It means that there is a quantifiable degree of FIG 3 - Procedure of the experiment.

402 Perth, WA, 22 - 24 November 2004 Orebody Modelling and Strategic Mine Planning
HYBRID PITS — LINKING CONDITIONAL SIMULATION AND LERCHS-GROSSMANN THROUGH SET THEORY

Simulation The test for nesting, was performed by a visual inspection of


the pits bench by bench, and section by section. It was possible
Due to the lack of a real variance distribution model within the to verify that there was no violation of the nesting rule by this
block model that we had, we applied the following methodology method.
to create simulated block model. Using a random generator, a
normal distribution was applied to the original block model with The test to determine whether any pit slope constraints were
the following parameters: violated by the hybrid pits was performed with a modified
version of the Whittle Mining Width module. The module
µ = Original _ Grade re-applies the pit slope constraint to each shell and changes block
allocation in the event that a pit slope constraint is violated. By
σ = 0.3 × Original _ Grade
running the hybrid pits through this module it was possible to
Using this method five different simulated block models were verify that no pit slope constraints were violated.
created. The grades were controlled in order to avoid entering
into the negative territory. All simulated models have the same Results of the trial
origin and block size.
The five original optimal pits and the five Hybrid Pits were all
evaluated against the five simulated models, giving a total of fifty
Optimisation analysis
evaluations. The results are summarised in Table 4. In the table,
Optimisation analysis was performed on models using Whittle Pit 1 is the pit which is optimal for Simulation 1; Pit 2 is the pit
3.2. The same parameters were applied on each analysis. Table 3 which is optimal for Simulation 2, etc.
shows the parameters that were used for this analysis. As is to be expected, for each of the simulations, the pit which
Based on this analysis, five optimal pit were extracted into performs best is the corresponding original optimal pit.
GEMS. Using GEMS, some new attributes were defined and then H-Pit(5) is the inner bound pit. This can be used as a high
modified by these optimal pits. These attributes actually confidence reserve pit, in that you can be highly confident that
contained a value of 1 or 0 that defined whether the related cell is the optimal pit for the real resource will be a superset to H-Pit(5).
part of the pit or not. H-Pit(1) is the outer bound pit. You can be highly confident
that the optimal pit for the real reserve does not extend beyond
Hybrid pit creation the perimeter of H-Pit(1).
The calculation has been done on the attribute explained above to Refer to the section Projected Application of Hybrid Pits for a
create hybrid pits. discussion of the intended interpretation and application of these
results.
Hybrid pits were found to be technically feasible Figure 4 shows the spatial relationship between H-Pit(1) and
H-Pit(5) in an elevation view. As can be seen the effect of the
The mathematics indicated that the hybrid pits would be variance in the model, as expressed in the five simulations, leads
technically feasible – they would nest and they would not violate to uncertainty as to the position of the pit wall on the right hand
pit slope constraints. The authors found that the trial supported side of the diagram, as well as some minor uncertainty as to the
this. pit wall position on the left hand side.
Table 4 also provides:
TABLE 3 • The average value of each o-pit (Pits one through five) as
Parameters used in optimisation analysis. evaluated against the five simulated models. With the
application of the Dimitrakopoulos (2003) technique pit
Parameter Value number two could be chosen as a design pit, as it provides
Block size 10*10*8 the highest mean value (meaning that it is the most likely to
return the highest value) of all the o-pits.
Number of blocks in each model 63 296
Gold price 380 $/oz
• The average value of each of the hybrid pit as evaluated
against the five simulated models. In this trial H-Pit(2)
Mining cost 1 $/tonne produced the highest average value. It is interesting that,
Processing cost 22 $/tonne evaluated in this way, an H-Pit outperforms all of the o-pits
Mining recovery 95% in this trial. However, it is not a central aspect of this paper,
and the authors have not attempted to determine theoretically
Processing recovery 95%
whether this may always be the case.

TABLE 4
Summary results of the Hybrid Pit trial.

Pit 1 Pit 2 Pit 3 Pit 4 Pit 5 H-Pit(5) H-Pit(4) H-Pit(3) H-Pit(2) H-Pit(1)
mT 19.5 20.5 19.3 20.3 20.3 18.2 19.6 20.2 20.6 21.3
$'000's Pit 1 Pit 2 Pit 3 Pit 4 Pit 5 H-Pit(5) H-Pit(4) H-Pit(3) H-Pit(2) H-Pit(1)
Sim 1 27 098 25 943 25 770 25 911 25 928 25 157 25 951 26 479 26 578 26 486
Sim 2 25 294 26 589 25 091 25 387 25 291 24 106 25 213 25 955 26 164 26 214
Sim 3 24 702 24 972 26 218 24 851 25 088 24 219 24 872 25 565 25 689 25 487
Sim 4 25 756 26 054 25 973 27 365 25 669 24 707 25 895 26 602 26 756 26 857
Sim 5 23 509 23 871 23 666 23 884 25 240 22 691 23 570 24 386 24 745 24 766
Ave 25 272 25 486 25 344 25 480 25 443 24 176 25 100 25 797 25 986 25 962

Orebody Modelling and Strategic Mine Planning Perth, WA, 22 - 24 November 2004 403
D WHITTLE and A BOZORGEBRAHIMI

the gap will certainly be a function of the variance of the models,


but it will also depend on a great many other economic,
geotechnical and geological factors.
The operations required to complete the trial were found to be
relatively straightforward, though large in number. For this very
small trial, there were five pit optimisations performed, and fifty
life-of-mine schedules, with a good deal of associated data
manipulation in Whittle, GEMS and Excel. To repeat the exact
same exercise for a family of 25 simulated models, would require
only 25 pit optimisations, but 1250 economic evaluations.
Generally speaking, the trial produced results which were in
line with the expectations of the authors. There was one pleasant
FIG 4 - Section showing the spatial relationship between H-Pit(5)
surprise – that when evaluated against the family of simulated
and H-Pit(1).
models, one of the Hybrid Pits outperformed all the original
optimal pits. Prior to the trial, the authors were unable to form a
hypothesis as to whether Hybrid Pits would outperform original
Optimal Pits in this manner, but in this one case, it was found to
CONCLUSIONS be so. Only experience will tell whether it is a common or an
uncommon outcome.
Considering uncertainties presented in any geological models
this paper showed that the Hybrid Pits technique leads to the
creation of pit outlines with quantifiable probability REFERENCES
characteristics, with respect to their spatial relationship to the Dimitrakopoulos, R, 2003. Personal communication. November.
optimal pit for the real resource. The Hybrid Pits can be used as Dimitrakopoulos, R, Farrelly C T, Godoy, M, 2001. I’d rather be
design guides to allow a quantifiable degree of risk avoidance, approximately right than precisely wrong: grade uncertainty, risk
associated with the higher uncertainty in early stages of a mine effects and decision making in open pit design, in Proceedings
development. Strategic Mine Planning Conference, pp 35-42 (The Australasian
The validity of the Hybrid Pits technique is supported by the Institute of Mining and Metallurgy: Melbourne).
set theory model explained in this paper, and by the trial of the Lerchs, H, Grossmann, I F, 1965. Optimum design of open pit mines, The
technique on a small data set. The pits were found to obey the pit Canadian Mining and Metallurgical Bulletin, 58(January):47-54.
slope constraints, so they are technically feasible. The pits were Van Brunt, B H, Rossi, M E, 1997. Optimising conditionally simulated
orebodies with Whittle 4D, in Proceedings Optimizing with Whittle
also found to nest, which is an inherent quality of the pits if they
Conference, pp 119-128 (Whittle Programming: Vancouver BC).
are to conform to the theory presented in this paper.
Van Brunt, B H, Rossi, M E, 1999, Mine planning under uncertainty
The trial produced Hybrid Pits which were quite similar in constraints, in Proceedings Optimizing with Whittle: Strategic Mine
terms of overall size. It is not known on the basis of this sample Planning Conference, pp 181-196 (Whittle Programming: Vancouver
of one, whether this is common, or whether it is more common BC).
for the gap between H-Pit(n) and H-Pit(1) to be great. The size of

404 Perth, WA, 22 - 24 November 2004 Orebody Modelling and Strategic Mine Planning

View publication stats

You might also like