You are on page 1of 5

RESUMEN CRONOGRAMA VALORIZADO DE EJECUCION DE PROYECTO

PROYECTO: “MEJORAMIENTO DE LA CARRETERA EMP. PE-3S D (DV. JABONILLO) HUANCAYOJASA - COLCABAMBA - TOCAS - CALLQUI - EMP. PE-3S D (MILPO).RUTA N° HV-102 -TRAMO REPARTICI ÓN PACOPATA – COLCABAMBA
KM. 0+000 AL KM. 26+087, DISTRITO DE COLCABAMBA – PROVINCIA DE TAYACAJA – HUANCAVELICA”
UBICACIÓN : COLCABAMBA - HUANCAVELICA : COLCABAMBA
FECHA : MAYO 2017 : TAYACAJA
: HUANCAVELICA

ITEM DESCRIPCIÓN Parcial (S/.) TRIM 01 TRIM 02 TRIM 03 TRIM 04 TRIM 05 TRIM 06 TRIM 07 TRIM 08
01 OBRAS PROVISIONALES S/. 394,023.02 S/. 394,023.02 S/. - S/. - S/. - S/. - S/. -
02 TRABAJOS PRELIMINARES S/. 1,183,623.34 S/. 27,631.21 S/. 297,134.50 S/. 309,678.90 S/. 284,159.24 S/. 265,019.49 S/. -
03 MOVIMIENTO DE TIERRAS S/. 6,727,990.80 S/. - S/. 399,097.01 S/. 3,511,668.05 S/. 2,817,225.73 S/. - S/. -
04 PAVIMENTOS S/. 23,324,780.19 S/. - S/. - S/. 953,971.68 S/. 3,410,928.95 S/. 10,226,332.05 S/. 8,733,547.51
05 OBRAS DE ARTE Y DRENAJE S/. 4,359,736.77 S/. - S/. - S/. 804,930.70 S/. 1,707,369.03 S/. 1,701,010.99 S/. 146,426.04
06 SEÑALIZACION Y SEGURIDAD VIAL S/. 1,636,001.98 S/. - S/. - S/. - S/. - S/. 938,695.01 S/. 697,306.97
07 VARIOS S/. 129,065.04 S/. - S/. 33,258.86 S/. 95,806.18 S/. - S/. - S/. -
08 TRANSPORTES S/. 10,883,801.23 S/. - S/. - S/. 6,381,860.01 S/. 3,899,410.65 S/. 602,530.57 S/. -
09 PROTECCION SOCIO - AMBIENTAL S/. 1,283,014.57 S/. - S/. 731,501.71 S/. 301,327.49 S/. 197,649.42 S/. - S/. 52,535.96
10 ESTUDIO DE PREINVERSION A NIVEL DE F S/. 369,465.00 S/. 147,786.00 S/. 221,679.00 S/. - S/. - S/. - S/. - S/. - S/. -
11 EXPEDIENTE TECNICO S/. 427,868.00 S/. 85,573.60 S/. 342,294.40 S/. - S/. - S/. - S/. - S/. -
12 SUPERVISION S/. 1,123,189.67 S/. 9,486.75 S/. 32,870.67 S/. 278,069.06 S/. 277,112.86 S/. 308,990.28 S/. 216,660.05
TOTAL DE INVERSION S/. 51,842,559.61 S/. 147,786.00 S/. 307,252.60 S/. 773,435.38 S/. 1,493,862.76 S/. 12,637,312.06 S/. 12,593,855.88 S/. 14,042,578.40 S/. 9,846,476.53

PLAZO DE EJECUCION DEL PROYECTO 690 DIAS (23 MESES) - 08 TRIMESTRES


RESUMEN CRONOGRAMA VALORIZADO DE EJECUCION DE PROYECTO

PROYECTO:
“MEJORAMIENTO DE LA CARRETERA EMP. PE-3S D (DV. JABONILLO) HUANCAYOJASA - COLCABAMBA - TOCAS - CALLQUI - EMP. PE-3S D (MILPO).RUTA N° HV-102 -TRAMO REPARTICI ÓN PACOPATA – COLCABAMBA KM. 0+000 AL KM. 26+087, DISTRITO DE C
TAYACAJA – HUANCAVELICA”

UBICACIÓN : COLCABAMBA - HUANCAVELICA DISTRITO : COLCABAMBA


FECHA :MAYO 2017 PROVINCIA : TAYACAJA
REGION : HUANCAVELICA

ITEM DESCRIPCIÓN Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09 MES 10
01 OBRAS PROVISIONALES S/. 394,023.02 S/. 394,023.02 S/. -
02 TRABAJOS PRELIMINARES S/. 1,183,623.34 S/. 27,631.21 S/. 120,454.84
03 MOVIMIENTO DE TIERRAS S/. 6,727,990.80 S/. - S/. 133,032.34
04 PAVIMENTOS S/. 23,324,780.19 S/. - S/. -
05 OBRAS DE ARTE Y DRENAJE S/. 4,359,736.77 S/. - S/. -
06 SEÑALIZACION Y SEGURIDAD VIAL S/. 1,636,001.98 S/. - S/. -
07 VARIOS S/. 129,065.04 S/. - S/. 33,258.86
08 TRANSPORTES S/. 10,883,801.23 S/. - S/. -
09 PROTECCION SOCIO - AMBIENTAL S/. 1,283,014.57 S/. - S/. 243,833.90
10 ESTUDIO DE PREINVERSION A NIVEL DE F S/. 369,465.00 S/. 36,946.50 S/. 36,946.50 S/. 73,893.00 S/. 221,679.00 S/. -
11 EXPEDIENTE TECNICO S/. 427,868.00 S/. 42,786.80 S/. 42,786.80 S/. 85,573.60 S/. 256,720.80 S/. -
12 SUPERVISION S/. 1,123,189.67 S/. 9,486.75 S/. 11,937.45
TOTAL DE INVERSION S/. 51,842,559.61 S/. 36,946.50 S/. 36,946.50 S/. 73,893.00 S/. 221,679.00 S/. 42,786.80 S/. 42,786.80 S/. 85,573.60 S/. 256,720.80 S/. 431,140.98 S/. 542,517.40

PLAZO DE EJECUCION DEL PROYECTO 690 DIAS (23 MESES)


AL KM. 26+087, DISTRITO DE COLCABAMBA – PROVINCIA DE

MES 11 MES 12 MES 13 MES 14 MES 15 MES 16 MES 17 MES 18 MES 19 MES 20 MES 21 MES 22 MES 23
S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. -
S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 113,859.49 S/. 107,479.58 S/. 107,479.58 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. - S/. -
S/. 133,032.34 S/. 133,032.34 S/. 133,032.34 S/. 448,207.14 S/. 2,930,428.58 S/. 324,616.23 S/. 2,492,609.50 S/. - S/. - S/. - S/. - S/. - S/. -
S/. - S/. - S/. - S/. - S/. 953,971.68 S/. 715,478.76 S/. 715,478.76 S/. 1,979,971.43 S/. 1,979,971.43 S/. 1,340,728.03 S/. 6,905,632.59 S/. 6,702,492.29 S/. 2,031,055.23
S/. - S/. - S/. - S/. 166,260.44 S/. 638,670.26 S/. 640,242.76 S/. 478,182.33 S/. 588,943.94 S/. 198,228.28 S/. 846,755.37 S/. 656,027.35 S/. 146,426.04 S/. -
S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. 564,176.69 S/. 374,518.32 S/. 367,656.96 S/. 329,650.02
S/. - S/. - S/. - S/. 95,806.18 S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. - S/. -
S/. - S/. - S/. - S/. 2,489,433.87 S/. 3,892,426.14 S/. 1,671,496.38 S/. 2,227,914.27 S/. - S/. - S/. 327,188.28 S/. 275,342.29 S/. - S/. -
S/. 243,833.90 S/. 243,833.90 S/. 243,833.90 S/. 37,783.43 S/. 19,710.15 S/. 6,709.50 S/. 6,709.50 S/. 184,230.41 S/. - S/. - S/. - S/. - S/. 52,535.96

S/. 10,466.61 S/. 10,466.61 S/. 10,466.61 S/. 75,401.62 S/. 192,200.83 S/. 77,981.62 S/. 135,201.01 S/. 63,930.23 S/. 50,994.59 S/. 71,258.17 S/. 186,737.52 S/. 162,364.83 S/. 54,295.22
S/. 475,672.68 S/. 475,672.68 S/. 475,672.68 S/. 3,426,752.16 S/. 8,734,887.21 S/. 3,544,004.82 S/. 6,144,435.21 S/. 2,905,415.84 S/. 2,317,534.12 S/. 3,238,446.37 S/. 8,486,597.90 S/. 7,378,940.11 S/. 2,467,536.42
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA MONTOS INC. GG, UTILIDAD, IGV

PROYECTO:
“MEJORAMIENTO DE LA CARRETERA EMP. PE-3S D (DV. JABONILLO) HUANCAYOJASA - COLCABAMBA - TOCAS - CALLQUI - EMP. PE-3S D (MILPO).RUTA N° HV-102 -TRAMO REPARTICI ÓN
PACOPATA – COLCABAMBA KM. 0+000 AL KM. 26+087, DISTRITO DE COLCABAMBA – PROVINCIA DE TAYACAJA – HUANCAVELICA”

UBICACIÓN : COLCABAMBA - HUANCAVELICA DISTRITO : COLCABAMBA


FECHA : MAYO 2017 PROVINCIA : TAYACAJA
REGION : HUANCAVELICA

ITEM DESCRIPCIÓN Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 7.20 m 4,280.99 S/. 4,280.99
01.02 CAMPAMENTO Y ALMACEN 83,590.91 S/. 83,590.91
01.03 MOVILIZACION Y DESMOVILIZACION EQUIPO 249,471.09 S/. 249,471.09
01.04 LIMPIEZA Y DEFORESTACION R= 1.2 Ha/días 56,680.03 S/. 56,680.03

02 TRABAJOS PRELIMINARES
02.01 TRAZO Y REPLANTEO 55,262.43 S/. 27,631.21 S/. 27,631.21
02.02 TRAZO Y REPLANTEO DURANTE EL PROCESO 63,799.15 S/. 25,519.66 S/. 19,139.74 S/. 19,139.74
02.03 TRAZO Y NIVELACION DE OBRAS DE ARTE 4,483.80 S/. 4,483.80
02.04 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL 1,060,077.96 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83 S/. 88,339.83

03 MOVIMIENTO DE TIERRAS
03.01 CORTE DE MATERIAL SUELTO 532,129.35 S/. 133,032.34 S/. 133,032.34 S/. 133,032.34 S/. 133,032.34
03.02 CORTE ROCA SUELTA 1,082,054.09 S/. 432,821.63 S/. 324,616.23 S/. 324,616.23
03.03 CORTE ROCA FIJA 2,492,609.50 S/. 2,492,609.50
03.04 PERFILADO Y COMPACTADO EN ZONA DE CORTE 15,385.50 15,385.50
03.05 TERRAPLEN CON RELLENO CON MATERIAL PROPIO 56,639.22 S/. 56,639.22
03.06 TERRAPLEN CON RELLENO CON MATERIAL TRANSPORTADO 2,549,173.13 2,549,173.13

04 PAVIMENTOS
04.01 SUB BASE Y BASE
04.01.01 SUB - BASE DE 0.20 m 2,384,929.20 953,971.68 715,478.76 715,478.76
04.01.02 BASE DE 0.15 m 3,959,942.85 S/. 1,979,971.43 S/. 1,979,971.43

04.02 CARPETA ASFALTICA


04.02.01 IMPRIMACION ASFALTICA 1,340,728.03 1,340,728.03
04.02.02 CARPETA ASFALTICA EN CALIENTE DE 3" 13,404,984.58 6,702,492.29 6,702,492.29

04.03 BERMAS
04.03.01 IMPRIMACION ASFALTICA 203,140.30 203,140.30
04.03.02 CARPETA ASFALTICA EN CALIENTE DE 3" 2,031,055.23 2,031,055.23

05 OBRAS DE ARTE Y DRENAJE


05.01 ALCANTARILLAS
05.01.01 ALCANTARILLAS PROYECTADAS TMC (36" y 48")
05.01.01.01 EXCAVACION PARA ESTRUCTURAS 62,757.80 31,378.90 31,378.90
05.01.01.02 RELLENO Y COMPACTACION 82,188.00 82,188.00
05.01.01.03 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLAS 110,026.05 110,026.05
05.01.01.04 CONCRETO f 'c=210 kg/cm2 EN ALEROS, MUROS Y LOSA CON 325,296.88
PARAPETO 325,296.88

05.01.01.05 ALCANTARILLA DE TMC D=36" 362,383.77 362,383.77


05.01.01.06 ALCANTARILLA DE TMC D=48" 17,366.71 17,366.71
05.01.01.07 EMBOQUILLADO DE PIEDRA ENTRADA/SALIDA ALCANTARILLAS 15,029.67
E=0.20M 15,029.67

05.02 CUNETAS
05.02.01 CUNETAS REVESTIDAS TRIANGULARES
05.02.01.01 ENCOFRADO Y DESENCOFRADO CUNETAS TRIANGULARES 303,980.25 151,990.13 151,990.13
05.02.01.02 CONCRETO FC=175 KG/CM2 1,169,493.78 584,746.89 584,746.89
05.02.01.03 JUNTAS DE DILATACION 71,280.46 71,280.46

05.02.02 CUNETAS REVESTIDAS RECTANGULARES


05.02.02.01 ENCOFRADO Y DESENCOFRADO CUNETAS RECTANGULARES 39,775.59 39,775.59
05.02.02.02 CONCRETO FC=175 KG/CM2 137,992.82 137,992.82
05.02.02.03 JUNTAS DE DILATACION 8,433.22 8,433.22

05.03 MUROS DE SOSTENIMIENTO


05.03.01 ENCOFRADO Y DESENCOFRADO DE MUROS 269,763.07 134,881.54 134,881.54
05.03.02 RELLENO Y COMPACTACION 55,950.30 55,950.30
05.03.03 CONCRETO FC=175 KG/CM2 411,802.06 411,802.06
05.03.04 TUBERIA DRENAJE PVC-SAP 3" 6,263.42 6,263.42
05.03.05 MATERIAL FILTRANTE 8,839.95 8,839.95
05.03.06 JUNTA DE DILATACION E=1 1/2" 895.71 895.71

05.04 PONTON DE 8 MTS (02 UND)


05.04.01 ESTRUCTURAS
05.04.01.01 OBRAS PROVISIONALES
05.04.01.01.01 LIMPIEZA DE CAUCE DE PONTONES 558.17 558.17
0.00
05.04.01.02 OBRAS PRELIMINARES
05.04.01.02.01 TRAZO DURANTE LA EJECUCION DE LA OBRA 12,408.77 12,408.77
05.04.01.02.02 SEÑALIZACIONES PARA LIMITES DE SEGURIDAD 4,784.24 4,784.24
05.04.01.02.03 DEMOLICION DE ESTRUCTURAS EXISTENTES 113,398.15 113,398.15

05.04.01.03 MOVIMIENTO DE TIERRAS


05.04.01.03.01 EXCAVACION DE TERRENO NORMAL CON MAQUINARIA PARA 24,352.82
PUENTES 24,352.82

05.04.01.03.02 RELLENO CON MATERIAL PROPIO SELECCIONADO 13,380.04 13,380.04

05.04.01.04 CONCRETO SIMPLE


05.04.01.04.01 SOLADOS PARA ESTRUCTURA (E = 4") - SUBESTRUCTURA 3,682.40 3,682.40
05.04.01.04.02 CONCRETO CICLOPEO f'c=175 kg/cm2 + 30 % PG ESTRIBOS Y 222,299.15
ALETAS. 222,299.15

05.04.01.05 CONCRETO ARMADO


05.04.01.05.01 CONCRETO FC=210 KG/CM2 PARAPETO - SUBESTRUCTURA 34,457.87 34,457.87
05.04.01.05.02 ENCOFRADO Y DESENCOFRADO DE ESTRIBOS Y ALETAS 49,120.78 49,120.78
05.04.01.05.03 ACERO fy=4200 kg/cm2 GRADO 60 1,516.74 1,516.74

05.04.01.06 DRENAJE
05.04.01.06.01 TUBERIA DE DRENAJE PVC SAP DIAM=3" 22.77 22.77
05.04.01.06.02 RELLENO CON MATERIALGRANULAR PARA SUB-DREN - 1,014.17
SUBESTRUCTURA 1,014.17

05.04.02 SUPERESTRUCTURA
05.04.02.01 FALSO PUENTE
05.04.02.01.01 FALSO PUENTE DE ESTRUCTURA 44,813.55 44,813.55

05.04.02.02 CONCRETO ARMADO


05.04.02.02.01 CONCRETO f'c=280 kg/cm2, LOSA, VIGA SARDINEL - 51,935.54
SUPERESTRUCTURA 51,935.54

05.04.02.02.02 ACERO fy=4200 kg/cm2 GRADO 60 13,717.23 13,717.23

05.04.02.03 APOYO MOVIL Y FIJO


05.04.02.03.01 APOYO DE NEOPRENE SHORE 70. DE 0.50 X 0.22 X 0.05 m 5,145.48 5,145.48

05.04.02.04 JUNTA DE DILATACION


05.04.02.04.01 JUNTA DE DILATACION E=1 1/2" 109.13 109.13

05.04.02.05 DRENAJE
05.04.02.06 TUBERIA DE DRENAJE PVC SAP DIAM=3" 683.23 683.23

05.04.02.07 CARPINTERIA METALICA


05.04.02.07.01 BARANDA DE TUBO NEGRO PESADO 3" PARA PONTONES 2,314.62 2,314.62

05.04.02.08 PINTURA
05.04.02.08.01 PINTURA EN BARANDAS METALICAS EN PUENTES 648.21 648.21

05.05 PONTON DE4 MT (02 UND)

05.05.01 ESTRUCTURAS
05.05.01.01 OBRAS PROVISIONALES
05.05.01.01.01 LIMPIEZA DE CAUCE DE PONTONES 409.95 409.95

05.05.01.02 OBRAS PRELIMINARES


05.05.01.02.01 TRAZO DURANTE LA EJECUCION DE LA OBRA 18,304.92 18,304.92
05.05.01.02.02 SEÑALIZACIONES PARA LIMITES DE SEGURIDAD 3,986.87 3,986.87
05.05.01.02.03 DEMOLICION DE ESTRUCTURAS EXISTENTES 32,238.25 32,238.25

05.05.01.03 MOVIMIENTO DE TIERRAS


05.05.01.03.01 EXCAVACION DE TERRENO NORMAL CON MAQUINARIA PARA 17,537.44
PUENTES 17,537.44

05.05.01.03.02 RELLENO CON MATERIAL PROPIO SELECCIONADO 691.14 691.14

05.05.01.04 CONCRETO SIMPLE


05.05.01.04.01 SOLADOS PARA ESTRUCTURA (E = 4") - SUBESTRUCTURA 2,953.33 2,953.33
05.05.01.04.02 CONCRETO CICLOPEO f'c=175 kg/cm2 + 30 % PG ESTRIBOS Y 85,020.69
ALETAS. 85,020.69

05.05.01.05 CONCRETO ARMADO


05.05.01.05.01 CONCRETO FC=210 KG/CM2 PARAPETO - SUBESTRUCTURA 40,832.12 40,832.12
05.05.01.05.02 ENCOFRADO Y DESENCOFRADO DE ESTRIBOS Y ALETAS 25,603.85 25,603.85
05.05.01.05.03 ACERO fy=4200 kg/cm2 GRADO 60 964.02 964.02

05.05.01.06 DRENAJE
05.05.01.06.01 TUBERIA DE DRENAJE PVC SAP DIAM=3" 54.66 54.66
05.05.01.06.02 RELLENO CON MATERIALGRANULAR PARA SUB-DREN - 1,014.17
SUBESTRUCTURA 1,014.17

05.05.02 SUPERESTRUCTURA
05.05.02.01 FALSO PUENTE
05.05.02.01.01 FALSO PUENTE DE ESTRUCTURA 22,406.77 22,406.77
0.00
05.05.02.02 CONCRETO ARMADO
05.05.02.02.01 CONCRETO f'c=280 kg/cm2, LOSA, VIGA SARDINEL - 32,986.34
SUPERESTRUCTURA 32,986.34

05.05.02.02.02 ACERO fy=4200 kg/cm2 GRADO 60 12,770.43 12,770.43

05.05.02.03 APOYO MOVIL Y FIJO


05.05.02.03.01 APOYO DE NEOPRENE SHORE 70. DE 0.50 X 0.22 X 0.05 m 627.50 627.50

05.05.02.04 JUNTA DE DILATACION


05.05.02.04.01 JUNTA DE DILATACION E=1 1/2" 13.31 13.31

05.05.02.05 DRENAJE
05.05.02.06 TUBERIA DE DRENAJE PVC SAP DIAM=3" 68.32 68.32

05.05.02.07 CARPINTERIA METALICA


05.05.02.07.01 BARANDA DE TUBO NEGRO PESADO 3" PARA PONTONES 1,070.35 1,070.35

05.05.02.08 PINTURA
05.05.02.08.01 PINTURA EN BARANDAS METALICAS EN PUENTES 299.75 299.75

06 SEÑALIZACION Y SEGURIDAD VIAL


06.01 SEÑALES PREVENTIVAS (0.60x0.60) 71,886.69 71,886.69
06.02 SEÑALES REGLAMENTARIAS (0.90x0.60) 37,715.49 37,715.49
06.03 SEÑALES INFORMATIVAS 264,916.15 264,916.15
06.04 PINTURA LINEA DE BORDE 91,830.83 45,915.42 45,915.42
06.05 PINTURA LINEA CENTRAL 162,268.06 81,134.03 81,134.03
06.06 PINTURA LINEA DE CRUCE PEATONAL 4,926.01 4,926.01
06.07 PINTURA LINEA DE SIMBOLOS Y FLECHAS 2,465.06 2,465.06
06.08 TACHAS REFLECTIVAS 14,741.38 14,741.38
06.09 GUARDAVIAS DE FIERRO GALVANIZADO 564,176.69 564,176.69
06.10 TERMINALES DE GUARDAVIAS 6,889.42 6,889.42
06.11 PINTADO DE PARAPETOS Y MUROS 13,101.26 13,101.26
06.12 HITOS KILOMETRICOS 12,323.58 12,323.58
06.13 POSTES DELINEADORES 375,718.38 187,859.19 187,859.19
06.14 CONSTRUCCION DE GIBAS 13,043.00 13,043.00

07 VARIOS
07.01 REUBICACION Y REPOSICION DE POSTES DE LUZ 33,258.86 33,258.86
07.02 NIVELACION DE TECHO DE BUZON EXISTENTE 7,801.78 7,801.78
07.03 REPOSICION DE CONEXIONES DOMICILIARIAS 88,004.40 88,004.40

08 TRANSPORTES
08.01 TRANSPORTE DE MATERIAL RELLENO, MEJORAMIENTO Y 3,073,993.04
CONCRETO HASTA 1.00 KM 1,536,996.52 1,536,996.52

08.02 TRANSPORTE DE MATERIAL RELLENO, MEJORAMIENTO Y 595,543.03


CONCRETO D > 1.00 KM 595,543.03

08.03 TRANSPORTE DE MATERIAL SUB BASE Y BASE HASTA 1.00 KM 952,437.35 952,437.35
08.04 TRANSPORTE DE MATERIAL SUB BASE Y BASE D > 1.00 KM 1,759,886.59 1,759,886.59
08.05 TRANSPORTE DE AGREGADOS A PLANTA DE ASFALTO HASTA 1.00 163,274.67
KM 163,274.67

08.06 TRANSPORTE DE AGREGADOS A PLANTA DE ASFALTO PARA D > 181,432.60


1.00 KM 181,432.60

08.07 TRASPORTE DE MEZCLA ASFALTICA HASTA 1.00 KM 163,913.61 163,913.61


08.08 TRASPORTE DE MEZCLA ASFALTICA D > 1.00 KM 93,909.68 93,909.68
08.09 TRASPORTE DE MATERIAL EXCEDENTE HASTA 1.00 KM 3,342,992.77 1,671,496.38 1,671,496.38
08.10 TRASPORTE DE MATERIAL EXCEDENTE D > 1.00 KM 556,417.89 556,417.89

09 PROTECCION SOCIO - AMBIENTAL


09.01 PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL 11,100.56 11,100.56
09.02 PROGRAMA DE MONITOREO Y/O VIGILANCIA AMBIENTAL 26,001.30 13,000.65 13,000.65
09.03 PROGRAMA DE SEÑALIZACION AMBIENTAL 6,972.72 6,972.72
09.04 RESTAURACION DE AREAS OCUPADAS PARA CAMPAMENTO Y PATIO 27,334.70
DE MAQUINAS 27,334.70

09.05 RESTAURACION DE AREAS OCUPADAS PARA PLANTA DE ASFALTO Y 25,201.26


CHANCADORA 25,201.27

09.06 ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN BOTADEROS 184,230.41


184,230.41

09.07 PLAN DE COMPENSACION Y REASENTAMIENTO INVOLUNTARIO 948,497.61


(PACRI) 237,124.40 237,124.40 237,124.40 237,124.40

09.08 PLAN DE MONITOREO ARQUEOLOGICO 53,676.02 6,709.50 6,709.50 6,709.50 6,709.50 6,709.50 6,709.50 6,709.50 6,709.50

TOTAL COSTO DE OBRA S/. 49,922,036.94 S/. 421,654.23 S/. 530,579.95 S/. 465,206.07 S/. 465,206.07 S/. 465,206.07 S/. 3,351,350.54 S/. 8,542,686.38 S/. 3,466,023.20 S/. 6,009,234.20 S/. 2,841,485.61 S/. 2,266,539.53 S/. 3,167,188.20 S/. 8,299,860.38 S/. 7,216,575.28 S/. 2,413,241.21
ESTUDIO DE PREINVERSION A NIVEL DE FACTIBILI S/. 369,465.00 S/. 369,465.00
EXPEDIENTE TECNICO S/. 427,868.00 S/. 427,868.00
SUPERVISION 03% S/. 1,123,189.67 S/. 9,486.75 S/. 11,937.45 S/. 10,466.61 S/. 10,466.61 S/. 10,466.61 S/. 75,401.62 S/. 192,200.83 S/. 77,981.62 S/. 135,201.01 S/. 63,930.23 S/. 50,994.59 S/. 71,258.17 S/. 186,737.52 S/. 162,364.83 S/. 54,295.21
TOTAL COSTO DE INVERSION S/. 51,842,559.61 S/. 1,228,473.98 S/. 542,517.40 S/. 475,672.68 S/. 475,672.68 S/. 475,672.68 S/. 3,426,752.16 S/. 8,734,887.21 S/. 3,544,004.82 S/. 6,144,435.21 S/. 2,905,415.84 S/. 2,317,534.12 S/. 3,238,446.37 S/. 8,486,597.90 S/. 7,378,940.11 S/. 2,467,536.42

PLAZO DE EJECUCION DE OBRA 450 DIAS (15 MESES)


CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

“MEJORAMIENTO DE LA CARRETERA EMP. PE-3S D (DV. JABONILLO) HUANCAYOJASA - COLCABAMBA - TOCAS - CALLQUI - EMP. PE-3S D (MILPO).RUTA N° HV-102 -TRAMO REPARTICI ÓN
PACOPATA – COLCABAMBA KM. 0+000 AL KM. 26+087, DISTRITO DE COLCABAMBA – PROVINCIA DE TAYACAJA – HUANCAVELICA”

: COLCABAMBA - HUANCAVELICA DISTRITO : COLCABAMBA


: MAYO 2017 PROVINCIA : TAYACAJA
REGION : HUANCAVELICA

DESCRIPCIÓN Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 MES 13 MES 14 MES 15
OBRAS PROVISIONALES
CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 7.20 m 3,210.58 S/. 3,210.58
CAMPAMENTO Y ALMACEN 62,690.05 S/. 62,690.05
MOVILIZACION Y DESMOVILIZACION EQUIPO 187,093.96 S/. 187,093.96
LIMPIEZA Y DEFORESTACION R= 1.2 Ha/días 42,507.90 S/. 42,507.90

TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO 41,444.75 S/. 20,722.38 S/. 20,722.38
TRAZO Y REPLANTEO DURANTE EL PROCESO 47,846.97 S/. 19,138.79 S/. 14,354.09 S/. 14,354.09
TRAZO Y NIVELACION DE OBRAS DE ARTE 3,362.68 S/. 3,362.68
MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL 795,018.72 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56 S/. 66,251.56

MOVIMIENTO DE TIERRAS
CORTE DE MATERIAL SUELTO 399,077.06 S/. 99,769.27 S/. 99,769.27 S/. 99,769.27 S/. 99,769.27
CORTE ROCA SUELTA 811,499.99 S/. 324,600.00 S/. 243,450.00 S/. 243,450.00
CORTE ROCA FIJA 1,869,363.66 S/. 1,869,363.66
PERFILADO Y COMPACTADO EN ZONA DE CORTE 11,538.55 11,538.55
TERRAPLEN CON RELLENO CON MATERIAL PROPIO 42,477.29 S/. 42,477.29
TERRAPLEN CON RELLENO CON MATERIAL TRANSPORTADO 1,911,784.26 1,911,784.26

PAVIMENTOS
SUB BASE Y BASE
SUB - BASE DE 0.20 m 1,788,607.47 715,442.99 536,582.24 536,582.24
BASE DE 0.15 m 2,969,808.65 S/. 1,484,904.33 S/. 1,484,904.33

CARPETA ASFALTICA
IMPRIMACION ASFALTICA 1,005,495.75 1,005,495.75
CARPETA ASFALTICA EN CALIENTE DE 3" 10,053,235.77 5,026,617.89 5,026,617.89

BERMAS
IMPRIMACION ASFALTICA 152,347.61 152,347.61
CARPETA ASFALTICA EN CALIENTE DE 3" 1,523,215.26 1,523,215.26

OBRAS DE ARTE Y DRENAJE


ALCANTARILLAS
ALCANTARILLAS PROYECTADAS TMC (36" y 48")
EXCAVACION PARA ESTRUCTURAS 47,066.00 23,533.00 23,533.00
RELLENO Y COMPACTACION 61,637.92 61,637.92
ENCOFRADO Y DESENCOFRADO EN ALCANTARILLAS 82,515.41 82,515.41
CONCRETO f 'c=210 kg/cm2 EN ALEROS, MUROS Y LOSA CON 243,960.46
PARAPETO 243,960.46

ALCANTARILLA DE TMC D=36" 271,774.24 271,774.24


ALCANTARILLA DE TMC D=48" 13,024.38 13,024.38
EMBOQUILLADO DE PIEDRA ENTRADA/SALIDA ALCANTARILLAS 11,271.69
E=0.20M 11,271.69

CUNETAS
CUNETAS REVESTIDAS TRIANGULARES
ENCOFRADO Y DESENCOFRADO CUNETAS TRIANGULARES 227,973.79 113,986.90 113,986.90
CONCRETO FC=175 KG/CM2 877,076.48 438,538.24 438,538.24
JUNTAS DE DILATACION 53,457.67 53,457.67

CUNETAS REVESTIDAS RECTANGULARES


ENCOFRADO Y DESENCOFRADO CUNETAS RECTANGULARES 29,830.20 29,830.20
CONCRETO FC=175 KG/CM2 103,489.44 103,489.44
JUNTAS DE DILATACION 6,324.60 6,324.60

MUROS DE SOSTENIMIENTO
ENCOFRADO Y DESENCOFRADO DE MUROS 202,312.19 101,156.10 101,156.10
RELLENO Y COMPACTACION 41,960.63 41,960.63
CONCRETO FC=175 KG/CM2 308,836.10 308,836.10
TUBERIA DRENAJE PVC-SAP 3" 4,697.33 4,697.33
MATERIAL FILTRANTE 6,629.63 6,629.63
JUNTA DE DILATACION E=1 1/2" 671.75 671.75

PONTON DE 8 MTS (02 UND)


ESTRUCTURAS
OBRAS PROVISIONALES
LIMPIEZA DE CAUCE DE PONTONES 418.61 418.61

OBRAS PRELIMINARES
TRAZO DURANTE LA EJECUCION DE LA OBRA 9,306.11 9,306.11
SEÑALIZACIONES PARA LIMITES DE SEGURIDAD 3,588.00 3,588.00
DEMOLICION DE ESTRUCTURAS EXISTENTES 85,044.36 85,044.36

MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO NORMAL CON MAQUINARIA PARA 18,263.70
PUENTES 18,263.70

RELLENO CON MATERIAL PROPIO SELECCIONADO 10,034.53 10,034.53

CONCRETO SIMPLE
SOLADOS PARA ESTRUCTURA (E = 4") - SUBESTRUCTURA 2,761.66 2,761.66
CONCRETO CICLOPEO f'c=175 kg/cm2 + 30 % PG ESTRIBOS Y 166,716.03
ALETAS. 166,716.03

CONCRETO ARMADO
CONCRETO FC=210 KG/CM2 PARAPETO - SUBESTRUCTURA 25,842.11 25,842.11
ENCOFRADO Y DESENCOFRADO DE ESTRIBOS Y ALETAS 36,838.74 36,838.74
ACERO fy=4200 kg/cm2 GRADO 60 1,137.50 1,137.50

DRENAJE
TUBERIA DE DRENAJE PVC SAP DIAM=3" 17.08 17.08
RELLENO CON MATERIALGRANULAR PARA SUB-DREN - 760.59
SUBESTRUCTURA 760.59

SUPERESTRUCTURA
FALSO PUENTE
FALSO PUENTE DE ESTRUCTURA 33,608.48 33,608.48

CONCRETO ARMADO
CONCRETO f'c=280 kg/cm2, LOSA, VIGA SARDINEL - 38,949.71
SUPERESTRUCTURA 38,949.71
ACERO fy=4200 kg/cm2 GRADO 60 10,287.41 10,287.41

APOYO MOVIL Y FIJO


APOYO DE NEOPRENE SHORE 70. DE 0.50 X 0.22 X 0.05 m 3,858.92 3,858.92

JUNTA DE DILATACION
JUNTA DE DILATACION E=1 1/2" 81.84 81.84

DRENAJE
TUBERIA DE DRENAJE PVC SAP DIAM=3" 512.40 512.40

CARPINTERIA METALICA
BARANDA DE TUBO NEGRO PESADO 3" PARA PONTONES 1,735.88 1,735.88

PINTURA
PINTURA EN BARANDAS METALICAS EN PUENTES 486.13 486.13

PONTON DE4 MT (02 UND)

ESTRUCTURAS
OBRAS PROVISIONALES
LIMPIEZA DE CAUCE DE PONTONES 307.45 307.45

OBRAS PRELIMINARES
TRAZO DURANTE LA EJECUCION DE LA OBRA 13,728.00 13,728.00
SEÑALIZACIONES PARA LIMITES DE SEGURIDAD 2,990.00 2,990.00
DEMOLICION DE ESTRUCTURAS EXISTENTES 24,177.48 24,177.48

MOVIMIENTO DE TIERRAS
EXCAVACION DE TERRENO NORMAL CON MAQUINARIA PARA 13,152.42
PUENTES 13,152.42

RELLENO CON MATERIAL PROPIO SELECCIONADO 518.33 518.33

CONCRETO SIMPLE
SOLADOS PARA ESTRUCTURA (E = 4") - SUBESTRUCTURA 2,214.89 2,214.89
CONCRETO CICLOPEO f'c=175 kg/cm2 + 30 % PG ESTRIBOS Y 63,762.33
ALETAS. 63,762.33

CONCRETO ARMADO
CONCRETO FC=210 KG/CM2 PARAPETO - SUBESTRUCTURA 30,622.56 30,622.56
ENCOFRADO Y DESENCOFRADO DE ESTRIBOS Y ALETAS 19,201.93 19,201.93
ACERO fy=4200 kg/cm2 GRADO 60 722.98 722.98

DRENAJE
TUBERIA DE DRENAJE PVC SAP DIAM=3" 40.99 40.99
RELLENO CON MATERIALGRANULAR PARA SUB-DREN - 760.59
SUBESTRUCTURA 760.59

SUPERESTRUCTURA
FALSO PUENTE
FALSO PUENTE DE ESTRUCTURA 16,804.24 16,804.24

CONCRETO ARMADO
CONCRETO f'c=280 kg/cm2, LOSA, VIGA SARDINEL - 24,738.52
SUPERESTRUCTURA 24,738.52

ACERO fy=4200 kg/cm2 GRADO 60 9,577.34 9,577.34

APOYO MOVIL Y FIJO


APOYO DE NEOPRENE SHORE 70. DE 0.50 X 0.22 X 0.05 m 470.60 470.60

JUNTA DE DILATACION
JUNTA DE DILATACION E=1 1/2" 9.98 9.98

DRENAJE
TUBERIA DE DRENAJE PVC SAP DIAM=3" 51.24 51.24

CARPINTERIA METALICA
BARANDA DE TUBO NEGRO PESADO 3" PARA PONTONES 802.72 802.72

PINTURA
PINTURA EN BARANDAS METALICAS EN PUENTES 224.80 224.80

SEÑALIZACION Y SEGURIDAD VIAL


SEÑALES PREVENTIVAS (0.60x0.60) 53,912.32 53,912.32
SEÑALES REGLAMENTARIAS (0.90x0.60) 28,285.20 28,285.20
SEÑALES INFORMATIVAS 198,677.18 198,677.18
PINTURA LINEA DE BORDE 68,869.68 34,434.84 34,434.84
PINTURA LINEA CENTRAL 121,694.96 60,847.48 60,847.48
PINTURA LINEA DE CRUCE PEATONAL 3,694.32 3,694.32
PINTURA LINEA DE SIMBOLOS Y FLECHAS 1,848.70 1,848.70
TACHAS REFLECTIVAS 11,055.48 11,055.48
GUARDAVIAS DE FIERRO GALVANIZADO 423,111.36 423,111.36
TERMINALES DE GUARDAVIAS 5,166.81 5,166.81
PINTADO DE PARAPETOS Y MUROS 9,825.45 9,825.45
HITOS KILOMETRICOS 9,242.22 9,242.22
POSTES DELINEADORES 281,774.70 140,887.35 140,887.35
CONSTRUCCION DE GIBAS 9,781.76 9,781.76

VARIOS
REUBICACION Y REPOSICION DE POSTES DE LUZ 24,942.90 24,942.90
NIVELACION DE TECHO DE BUZON EXISTENTE 5,851.04 5,851.04
REPOSICION DE CONEXIONES DOMICILIARIAS 66,000.00 66,000.00

TRANSPORTES
TRANSPORTE DE MATERIAL RELLENO, MEJORAMIENTO Y 2,305,379.51
CONCRETO HASTA 1.00 KM 1,152,689.76 1,152,689.76

TRANSPORTE DE MATERIAL RELLENO, MEJORAMIENTO Y 446,634.94


CONCRETO D > 1.00 KM 446,634.94

TRANSPORTE DE MATERIAL SUB BASE Y BASE HASTA 1.00 KM 714,292.30 714,292.30


TRANSPORTE DE MATERIAL SUB BASE Y BASE D > 1.00 KM 1,319,848.95 1,319,848.95
TRANSPORTE DE AGREGADOS A PLANTA DE ASFALTO HASTA 1.00 KM 122,449.88
122,449.88

TRANSPORTE DE AGREGADOS A PLANTA DE ASFALTO PARA D > 136,067.65


1.00 KM 136,067.65

TRASPORTE DE MEZCLA ASFALTICA HASTA 1.00 KM 122,929.06 122,929.06


TRASPORTE DE MEZCLA ASFALTICA D > 1.00 KM 70,428.74 70,428.74
TRASPORTE DE MATERIAL EXCEDENTE HASTA 1.00 KM 2,507,119.22 1,253,559.61 1,253,559.61
TRASPORTE DE MATERIAL EXCEDENTE D > 1.00 KM 417,292.55 417,292.55

PROTECCION SOCIO - AMBIENTAL


PROGRAMA DE CAPACITACION Y EDUCACION AMBIENTAL 8,325.00 8,325.00
PROGRAMA DE MONITOREO Y/O VIGILANCIA AMBIENTAL 19,500.00 9,750.00 9,750.00
PROGRAMA DE SEÑALIZACION AMBIENTAL 5,229.28 5,229.28
RESTAURACION DE AREAS OCUPADAS PARA CAMPAMENTO Y PATIO 20,500.00
DE MAQUINAS 20,500.00
RESTAURACION DE AREAS OCUPADAS PARA PLANTA DE ASFALTO Y 18,900.00
CHANCADORA 18,900.02

ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN BOTADEROS 138,165.90


138,165.90

PLAN DE COMPENSACION Y REASENTAMIENTO INVOLUNTARIO 711,337.64


(PACRI) 177,834.41 177,834.41 177,834.41 177,834.41

PLAN DE MONITOREO ARQUEOLOGICO 40,255.00 5,031.88 5,031.88 5,031.88 5,031.88 5,031.88 5,031.88 5,031.88 5,031.88

COSTO DIRECTO S/. 37,439,655.72 S/. 316,224.87 S/. 397,915.07 S/. 348,887.11 S/. 348,887.11 S/. 348,887.11 S/. 2,513,387.24 S/. 6,406,694.45 S/. 2,599,387.43 S/. 4,506,700.32 S/. 2,131,007.66 S/. 1,699,819.66 S/. 2,375,272.39 S/. 6,224,584.06 S/. 5,412,160.86 S/. 1,809,840.43
GASTOS GENERALES 8% S/. 2,995,172.46 S/. 25,297.99 S/. 31,833.21 S/. 27,910.97 S/. 27,910.97 S/. 27,910.97 S/. 201,070.98 S/. 512,535.56 S/. 207,950.99 S/. 360,536.03 S/. 170,480.61 S/. 135,985.57 S/. 190,021.79 S/. 497,966.72 S/. 432,972.87 S/. 144,787.23
UTILIDADES 5% S/. 1,871,982.79 S/. 15,811.24 S/. 19,895.75 S/. 17,444.36 S/. 17,444.36 S/. 17,444.36 S/. 125,669.36 S/. 320,334.72 S/. 129,969.37 S/. 225,335.02 S/. 106,550.38 S/. 84,990.98 S/. 118,763.62 S/. 311,229.20 S/. 270,608.04 S/. 90,492.02
SUB TOTAL S/. 42,306,810.96 S/. 357,334.10 S/. 449,644.02 S/. 394,242.43 S/. 394,242.43 S/. 394,242.43 S/. 2,840,127.58 S/. 7,239,564.73 S/. 2,937,307.80 S/. 5,092,571.36 S/. 2,408,038.65 S/. 1,920,796.22 S/. 2,684,057.80 S/. 7,033,779.98 S/. 6,115,741.77 S/. 2,045,119.68
IMPUESTOS IGV 18% S/. 7,615,225.97 S/. 64,320.14 S/. 80,935.92 S/. 70,963.64 S/. 70,963.64 S/. 70,963.64 S/. 511,222.96 S/. 1,303,121.65 S/. 528,715.40 S/. 916,662.84 S/. 433,446.96 S/. 345,743.32 S/. 483,130.40 S/. 1,266,080.40 S/. 1,100,833.52 S/. 368,121.54
TOTAL COSTO DE OBRA S/. 49,922,036.93 S/. 421,654.24 S/. 530,579.94 S/. 465,206.07 S/. 465,206.07 S/. 465,206.07 S/. 3,351,350.54 S/. 8,542,686.38 S/. 3,466,023.20 S/. 6,009,234.20 S/. 2,841,485.61 S/. 2,266,539.54 S/. 3,167,188.20 S/. 8,299,860.38 S/. 7,216,575.29 S/. 2,413,241.22
ESTUDIO DE PREINVERSION A NIVEL DE FACTIBILIDAD S/. 369,465.00 S/. 369,465.00
EXPEDIENTE TECNICO S/. 427,868.00 S/. 427,868.00
SUPERVISION 03% S/. 1,123,189.67 S/. 9,486.75 S/. 11,937.45 S/. 10,466.61 S/. 10,466.61 S/. 10,466.61 S/. 75,401.62 S/. 192,200.83 S/. 77,981.62 S/. 135,201.01 S/. 63,930.23 S/. 50,994.59 S/. 71,258.17 S/. 186,737.52 S/. 162,364.83 S/. 54,295.21
TOTAL COSTO DE INVERSION S/. 51,842,559.60 S/. 1,228,473.99 S/. 542,517.39 S/. 475,672.68 S/. 475,672.68 S/. 475,672.68 S/. 3,426,752.16 S/. 8,734,887.21 S/. 3,544,004.82 S/. 6,144,435.21 S/. 2,905,415.84 S/. 2,317,534.13 S/. 3,238,446.37 S/. 8,486,597.90 S/. 7,378,940.12 S/. 2,467,536.43

PLAZO DE EJECUCION DE OBRA 450 DIAS (15 MESES)

You might also like