Min Seok Kim1, Seung Kyu Yoo1, Ju Hyung Kim2, and Jae Jun Kim2*
1
Department of Sustainable Architectural Engineering Hanyang University, Seoul, Korea
2
Department of Architectural Engineering, Hanyang University, Seoul, Korea
* Corresponding author (jjkim@hanyang.ac.kr)
ABSTRACT: There are many variations and risks in construction work and the risk is getting increased in accordance of
big scale, variation and complexity for the construction work. If the process management is not planned thoroughly, it
affects the construction period. . The delay of construction period causes the increase of project budget and low productivity
and it is the cause of poor construction for recovering the long-term suspension of construction in construction work. There
are various problems such as low quality, negligent accidents, etc. Especially, the delay of finishing work can be fatal before
the completion of construction. It is study on analysis of the influence factor for delay of construction period and how to
apply in real work site in finishing work. It is regarded that this study will lead to thorough process movement in work site
and critical data.
1507
P2-31
Table 1. Existing studies referring the contract and precedent, common practice, etc.
Title of study and writer Contents So, the cause of delay for construction period should be
Influence of the Structural Influence of the structural analyzed precisely and tabl3 2.1 shows the cause of delay
framework on the work for construction period by each category. It is necessary to
set the range for reviewing the related project document by
period of critical path of
finding relevant causes for each issue if there is claim of
finish works
delay for construction period.
A Case Study on Reason Estimating the delayed days
Analysis for Schedule of construction period and Table 2.1 Cause of delay for construction period
Delay of Apartment House, analyzing the cause of delay
Categories Cause of delay
Park, Chang-Wook (2009) for the construction period
Engineering Inaccurate drawings
by Questionnaire survey for
Incomplete drawings
relevant site in the
Late engineering
construction of apartment
Management Equipment breakdowns
house.
Equipment delivery
Delay Factors Based on Prioritizing the delay of
Improper equipment
Importance of Finish Work final works with importance
Shortage of equipment
in Apartment Construction level of each types of
Exterior Environmental issues
Project, Lee, Seung-Hoon construction by dividing
Delays Later than planned start
(2010) finishing work into wet
Regular change
construction and other
Permit approval
finishing works.
An Analysis on Delay Management Construction methods
Establishing the cause of
factors of Major Trades in More than planned
delay of construction period
Quality assurance/quality control
Apartment Housing from the point of view of
contractor and analyzing Schedule too optimistic
Projects, Han, Jong-
the main cause of delay of Not working on critical tasks
Kwan(2003)
construction period on each
process and the status of Labor Craft shortages
company in Korea Labor productivity
Labor strike
2.2 CONSIDERATION OF THEORY FOR THE Rework
DELAY OF CONSTRUCTION PERIOD
Materials Damaged goods
Improper tools
2.2.1 Cause of the delay for construction period
The Delay of construction period means the period when Material delivery
the part of whole project is extended or it’s not executed Material quality
due to unpredictable environment factors.(Callahan, 1992). Weather Freezing
As for the analysis of delay for construction period, the Heat and humidity
related data is analyzed according to the cause of delay for Rain
the construction period and it is important stage to decide
Snow
where the responsibility lies. Also, it is carried out by
1508
P2-31
types of construction
3. ANALYSIS ON DELAY FACTOR FOR Wrong construction due to
CONSTRUCTION PERIOD BY TYPES OF discordance of drawing
CONSTRUCTION Shortage of labor experience
Doors and Shortage of labor plan
3.1 Factor of delay of frame work period windows Poor or bankrupted subcontractor
The factor of frame work period is shown as below table construction Shortage of plan for establishment
3.1. There are impossible factors to be managed by prior fund
management because the most of frame work is carried out Interior finishing Shortage of labor plan
indoor so it is directly related to climatic condition and construction Shortage of labor experience
involves unpredictable negligent accidents or civil Establishment fund
complaints, etc. Shortage of plan
1509
P2-31
REFERENCES
1510