Attachment #13

CLARIFICATION SHEET

BECHTEL JOB NO.: 26132


PROJECT : DRIFTWOOD LNG PROJECT DATE OF RECEIPT : 04-10-18
REQUISITION NO.: 26132-140-MRA-MVB2-00001 DATE OF RETURN : 00-10-18
PO NO.: 116162

Serial Comment Seq.


Document No. Page Item Tag No. CONTRACTOR COMMENT / OBSERVATION VENDOR RESOLUTION / ACTION Status (Close/Open)
No. No.
1 Lifting Trunnion at 30 & 210 Degree Will Incorporate.
2 skirt height is 4'-8" per o&e. Will Incorporate.
3 name plate elevation & orientation hold removed. Elevation given of -1' Clarify nameplate Bracket will be fouling with Bottom Head to skirt weld joint
4 Calculate and locate lifting lug at nozzle N1 pipe spool assembly CG. Will Incorporate.
PROVIDE BLIND FORGING PER DATA SHEET. AVOID POST WELD HEAT TREATMENT ON
5
BLIND

6 By Vendor

THIS ELEVATION TO BE CONFIRMED BY L&T BASED ON CONFIRMATION FROM GRID


7
SUPPLIER

MINIMUM TO TOP WELD LINE AFTER ALLOWING 12" CLEARANCE FOR BOLT
8 Will Incorporate.
TENSIONING FROM BACK OF 36" FLANGE AND THE TOP OF LIFTING TRUNNION.

9 PER UDS, SKIRT TO HEAD SHALL BE PER FIG 4.2.4 (E) OR (F), 100% RT REQUIRED. Clarify
10 PROVIDE BORE & THICKNESS AS REQUIRED (min) BY NOZZLE PIPE DESIGN Will Incorporate.
11 Rating to be 150# as per datasheet. 150 psig @ 535 F will fit in 150# rating Kindly Refer MDR Seq No. 7
12 Nozzle M2 SHOULD BE 150# PER DATA SHEET Kindly Refer MDR Seq No. 7
6. WELD CONSUMABLES SHALL BE IMPACT TESTED AT OR BELOW MDMT PER HEAT
13 Will Incorporate.
AND/OR LOT.
1 LTHE-ROSE-03650000_R0 SPECIFY IF SOLUTION ANNEALED REQURIED AFTER COLD FORMING PER VESSEL
1 1V-2005 14 Will Incorporate.
(26132-140-V1A-MVB2-00026_001) SPECIFICATION PARA 2.3.2.3