PT.

BINTANG SUKSES ENERGI


MAL - COAL MINE PROJECT #001
MINEPLAN ENGINEERING SECTION
ENGINEERING DEPARTMENT

PERIOD : WEEKLY_50

EQUIPMENT PRODUCTIVITY
Original
DESCRIPTION UNIT 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec Total REMARKS
Distributed to : Date Mon Tue Wed Thu Fri Sat Sun Week_50
PM, DPM, Production Sect. Head, Client Days in week days 1 1 1 1 1 1 1 7
Total Idle day days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Independent day days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Idhul Fitri days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Natal days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
New Year days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Idhul Adha days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Pemilu days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Change Shift days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Others days 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Total Av days days 1.0 1.0 1.0 1.0 1.0 1.0 1.0 7.0

Schedule hour hours 24 24 24 24 24 24 24 168


Total operational delays Hours min 598 568 568 568 598 568 568 4006
hours 10 9 9 9 10 9 9 67
Overshift min 10 10 10 10 10 10 10 70
Refueling min 10 10 10 10 10 10 10 70
Blasting min 0 0 0 0 0 0 0 0
Rest & Meal min 120 120 120 120 120 120 120 840
Traveling min 0 0 0 0 0 0 0 0
Safety talk min 30 0 0 0 0 0 0 0
Rain min 209 209 209 209 209 209 209 1463
Sliperry min 209 209 209 209 209 209 209 1463
Pre Start Check min 10 10 10 10 10 10 10 70
Breakfast/Sahur min 0 0 0 0 0 0 0 0
Jum'at praying min 0 0 0 0 30 0 0 30
Others min 0 0 0 0 0 0 0 0
Working Hours/Month (Include BD) hours 14.03 14.53 14.53 14.53 14.03 14.53 14.53 101.23
No of Shift/Day 2 2 2 2 2 2 2 2
Total Standby hours hours 9.97 9.47 9.47 9.47 9.97 9.47 9.47 66.77

FLEET CONFIGURATION (HAULER) Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Total
REMARKS
HAULER GROUP (OB) On Site No Of Truck No Of Truck No Of Truck No Of Truck No Of Truck No Of Truck No Of Truck No Of Truck
DT MERCY 4 4 4 4 4 4 4 4 4 OB HAULER PIT DONGGANG
DT MERCY 3 3 3 3 3 3 3 3 3 OB HAULER PIT DONGGANG
DT VOLVO - - - - - - - - OB HAULER PIT DONGGANG
Available
DT VOLVO - - - - - - - - OB HAULER PIT DONGGANG
DT VOLVO - - - - - - - - OB HAULER PIT DONGGANG
TOTAL 7 7 7 7 7 7 7 7 7
HAULER GROUP (COAL)
DT COAL Available
TOTAL
WASTE REMOVAL
PRODUCTIVITY (DIGGER) Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Total
DOOSAN S500LCV (BSE-103) 220 220 220 220 220 220 220 220 OB DIGGER PIT DONGGANG
DOOSAN S500LCV (BSE-104) 220 220 220 220 220 220 220 220 OB DIGGER PIT DONGGANG

220 220 220 220 220 220 220 220


FLEET CONFIGURATION (HAULER) TRUCK COMBINED Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Total
REMARKS
EXCAVATOR COUNT TYPE COUNT TYPE (BCM) (BCM) (BCM) (BCM) (BCM) (BCM) (BCM) (BCM)
DOOSAN S500LCV (BSE-103) 4 DT MERCY 2,757 2,869 2,869 2,869 2,757 2,869 2,869 19,857 OB HAULER PIT DONGGANG
DOOSAN S500LCV (BSE-104) 3 DT MERCY 2,068 2,151 2,151 2,151 2,068 2,151 2,151 14,893 OB HAULER PIT DONGGANG

4,825 5,020 5,020 5,020 4,825 5,020 5,020 34,750


FLEET CONFIGURATION (DIGGER) Distance Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Total
LOADING REMARKS
EXCAVATOR TRUCK (Meter) (BCM) (BCM) (BCM) (BCM) (BCM) (BCM) (BCM) (BCM)

DOOSAN S500LCV (BSE-103) 4xDT MERCY+ 100% 900 2,691 2,801 2,801 2,801 2,691 2,801 2,801 19,388 OB DIGGER PIT DONGGANG
DOOSAN S500LCV (BSE-104) 3xDT MERCY+ 100% 900 2,691 2,801 2,801 2,801 2,691 2,801 2,801 19,388 OB DIGGER PIT DONGGANG

5,382 5,602 5,602 5,602 5,382 5,602 5,602 38,775


COAL MINING
FLEET CONFIGURATION (DIGGER) Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Total
QTY REMARKS
EXCAVATOR TRUCK (MT) (MT) (MT) (MT) (MT) (MT) (MT) (MT)
DOOSAN S500LCV (BSE-108) DT COAL COAL GETTING PIT DONGGANG
- - - - - - - -

DOOSAN DX225LCA (BSE-101) PIT SERVICE


DOOSAN DX225LCA (BSE-102) PIT SERVICE
- - - - - - - -

SUMMARY
PLANNING SUMMARY UNIT Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Dec-14 Total REMARKS
TOTAL WASTE STRIPPING BCM 4,825 5,020 5,020 5,020 4,825 5,020 5,020 34,750
GRAND TOTAL MATERIAL MOVED BCM 4,825 5,020 5,020 5,020 4,825 5,020 5,020 34,750
- - - - - - - -

Bayung Lencir, 01 December 2014

PT. BINTANG SUKSES ENERGI PT. MANGGALA ALAM LESTARI


Prepared By, Approved By, Approved By,

Arif Rahman Whisnu Kuswidyarto Winarto Wiratmo


Engineering Sect. Head Project Manager General Manager