Professional Documents
Culture Documents
Lecture 1
Project Management
Fundamentals
What is a project?
What is a project?
Operational Work
Operational Works are quite opposite in
nature to Projects. Operations are
ongoing and repetitive. They involve
work that is continuous without an
ending date, and you often repeat the
same processes and produce the same
results.
Project vs. Operations
• Operations …
• are ongoing and repetitive;
• Involve work that is continuous without an ending date;
• Often repeat the same processes and produce the same results.
• Projects vs. Operations …
• Both projects and operations:
• Are performed by people
• Use limited number of resources
• Are planned, executed, and monitored
• Projects and Operations (Hand in Hand) …
• Project usually exist to support the needs of Operations.
• Operations (managers or experts) are usually major stakeholders in projects
• Projects experts often contribute to the success of the turnover stage of
projects (Sometimes projects members transit to careers in Operations later)
What is a Portfolio?
Portfolios are collections of
programs and projects that support
a specific business goal or objective.
Note, projects and programs within Portfolio
a portfolio may not be related. Coordina
Project
Project 6 Operations
A portfolio manager Program1 5 tion/Port
folio
• analyzes the feasibility and profitability Project 3
Manage
ment
of projects in a portfolio and assures
Project 4
their alignment with business objectives
• Selects projects that contribute to Coordination
business objectives. / Program
Management
• Manages resources across projects and
programs (mainly financial resources).
• May decide not to start projects or stop
those that do not contribute to the
business objectives
Project\Program\ Portfolio Relationship
• Project governance is the activity of aligning project
objectives with strategy of higher organization
• Strategy
Definition
Portfolios Risk
Management
• Goals Opportunities
• Benefit
Programs
Project
My Contractors!
Evolution of Project Manager
Constraints
• One of the major changes of PMBOK ® Guide is that it no
longer mentions the triple constraint of scope, schedule
and cost.
• Instead it discusses how PMs must balance scope,
quality, schedule, budget, resources and risk.
• e.g. Constraints may include the date a milestone or the project must be
completed OR the maximum allowable risk a project may have.
• NOTE: Appendices A and B of PMBOK
The project manager
• Why do we need project managers?
• Integrator
• Manager
• Person Accountable of project success
• The ultimate project voice
Organizational Structure
• Just as projects are unique, so are the
organizations in which they’re carried out.
Organizations have their own styles and
cultures that influence how project work is
performed.
Org. Style Most like a functional Blend of both weak Most like a projectized
org and strong matrix org
PM Reports to Functional Manager A functional manager, Manager of project
but shares authority managers
and power
Multi-phase projects
• Project may consist of one or more phases. The phases
of a project are often performed sequentially, but there
are situations where performing phases concurrently, or
overlapping the start date of a sequential phase, can
benefit the project
Projects life cycles range from the perfectly planned (or
plan oriented or predicted), to the totally agile (Change
oriented)
Types of Life cycles
• Sequential relationships (Plan oriented or predictive)
• One phase must finish before the next phase can begin.
• Overlapping relationships
• A variation of the sequential where one phase starts before
the prior phase completes.
• Iterative relationships
• Work for subsequent phases are planned as the work of the
previous phase is performed
Understanding Project Life Cycles Types
and characteristics
• Sequential or predictive.
Project
Performance data
(Project monitoring
plan
measurements and
quality control Execution processes get
measures) the work done as planned.
It generates deliverables
and information about the
project performance (time,
cost, quality,
communication
efficiency…)
Common Project Management Process
Interactions
Lecture 2
Integration management
is an element of project
management that
coordinates all aspects of
a project.
The Key to Overall Project Success:
Good Project Integration Management
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process Groups
Knowledge Area
Initiating Planning Executing Monitoring & Control Closing
✓Market demand
✓Customer Request
✓Strategic opportunity/business need
✓Technological advance
✓Legal requirement
✓Ecological impacts
✓Social need
✓Organizational need
• Peer Review
• Economic Models
• Present Value
• Net Present Value
• Internal Rate of Return
• Payback Period
• Benefit Cost Ratio
• Integer Programming
• Dynamic Programming
• Multi-objective Programming
Net Present Value
• Net present value (NPV) analysis is a method of
calculating the expected net monetary gain or loss from
a project by discounting all expected future cash inflows
and outflows to the present point in time.
Note:
• Projects with a positive NPV should be considered if
financial value is a key criterion.
• Business case
Provide the necessary information from business standpoint to
determine whether or not the project is worth the required
investment.
• Expert Judgment
Expert judgment is often used to assess the inputs used to develop the
project charter. Expert judgment is applied to all technical and
management details during this process. Such expertise is provided by
any group or individual with specialized knowledge or training and is
available from many sources, including:
• Other units within the organization,
• Consultants,
• Stakeholders, including customers or sponsors,
• Professional and technical associations,
• Industry groups,
• Subject matter experts (SME), and
• Project management office (PMO).
• Facilitation Techniques
Facilitation techniques have broad application within project
management processes and guide the development of the
project charter. Brainstorming, conflict resolution, problem
solving, and meeting management are examples of key
techniques used by facilitators to help teams and individuals
accomplish project activities.
Develop Project Charter: Outputs cont’d
The project charter documents :
• Deviations from baselines are often due to incomplete risk identification and
risk management.
Terms
Project Execution
• During project execution the project team focuses on
completing the tasks assigned.
• The Sponsor protects the project from changes and loss of
resources.
• The Project Manager integrates all the pieces into the project
as a whole.
• Project execution involves managing and performing the
work described in the project management plan.
• The majority of time and money is usually spent on execution.
• The products of the project are produced during project
execution.
Direct & Manage Project Work
• This is the process for performing the work defined in the project
management plan to achieve the project’s objectives
• Change Requests
• Corrective action—An intentional activity that realigns the
performance of the project work with the project management
plan;
• Preventive action—An intentional activity that ensures the
future performance of the project work is aligned with the
project management plan; and
• Defect repair—An intentional activity to modify a
nonconforming product or product component
• Work Performance Reports
• Project Management Plan Updates
• Project Documents Updates
Perform Integrated Change Control
PMIS
Configuration
Management System
Defines how you will manage changes to the deliverables and the resulting
documentation, including which organizational tools you will use.
Configuration Management
• Ensures that the descriptions of the project’s products
are correct and complete.
• Involves identifying and controlling the functional and
physical design characteristics of products and their
support documentation.
• Configuration management specialists identify and
document configuration requirements, control changes,
record and report changes, and audit the products to
verify conformance to requirements.
Lessons Learned
Lecture 3
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Scope Management
Scope Collect Requirements Validate Scope
Management Define Scope Control Scope
Create W.B.S.
Inputs:
Project Management Plan
Approved subsidiary plans of the PMP are used to create the scope
management plan and influence the approach taken for planning scope and
managing project scope.
Project Charter
The project charter is used to provide the project context needed to plan the
scope management processes. It provides the high-level project description
and product characteristics from the project statement of work.
Enterprise Environmental Factors
The enterprise environmental factors that can influence the Plan Scope
Management process
Organizational Process Assets
The organizational process assets that can influence the Plan
Scope Management process
Tools & Techniques:
Expert Judgment
refers to input received from knowledgeable and experienced parties.
Meetings
Project teams may attend project meetings to develop the scope
management plan.
Output:
Scope Management Plan
a component of the project or program management plan that
describes how the scope will be defined, developed, monitored,
controlled, and verified.
The scope management plan is a major input into the Develop Project
Management Plan process, and the other scope management
processes.
5.2 Collect Requirements
Collect Requirements is the process of defining and documenting
stakeholders needs to meet the project objectives.
Collect Requirements
Collect requirements is the process of defining and
documenting stakeholders’ needs to meet the project objectives
These requirements need to be elicited , analyzed, and
recorded in enough detail to be measured once project
execution begins .
Requirements become the foundation of the WBS. Cost ,
Schedule, and quality planning are all built upon these
requirements
The development of requirements begins with an analysis of the
information contained in the project charter and the
stakeholder register .
Collect Requirements – Tools & Techniques
Prototypes :
Prototyping is a technique involving constructing a working
model or mock-up of the final product for participants to
experiment with. The prototype does not usually contain all the
functionality the end product does, but it gives participants
enough information that they can provide feedback regarding
the mock-up. This is an iterative process where participants
experiment and provide feedback and the prototype is revised
and the cycle starts again
Balance Stakeholder’s Requirement
There is a need to balance stakeholder’s requirement.
Some issue are so complex they cannot be resolved by PM alone.
Facilitate the resolution of competing requirement, consider:
1. business case,
2. project charter,
3. project scope statement,
4. project constraints
What you can do:
Conflict resolution, team building, meeting, problem solving skills, escalation, approval
from stakeholder.
Stakeholder request to do or add something that is not related to the reason of project
created should be rejected!
Unique identifier
Textual description
Rationale
Owner source
Status
Date Completed
Requirements Traceability Matrix
Figure 5-7. Define Scope: Inputs, Tools & Techniques, and Outputs
5.3 Define Scope
Scope is collectively the product, service, or result of the
project.
Now that you’ve documented the project requirements, you’re
ready to further define the needs of the project in the Define
Scope process. The project scope statement (an output of this
process) is what you’ll use to develop and document a detailed
description of the deliverables of the project and the work
needed to produce them. This process is progressively
elaborated as more detail becomes known.
2.Alternative Identification
Identifying alternatives is a technique used to generate different
approaches to execute and perform the work of the project.
✓Brainstorming
✓Lateral Thinking
✓Pair wise comparison
Lateral Thinking
• Lateral thinking is a form of alternatives
identification that can be used to help define
scope.
• The simplest definition is that it’s thinking
outside the box.
Lateral Thinking
Answer: The question asks how your pet could fall from an 18-
story building and live; however, the question doesn’t state that
your pet fell from the 18th floor. So, your pet Yorkie fell from the
basement-level window.
Define Scope - Outputs
Project Scope Statement
Project scope statements describes, in detail (remember SOW),
project deliverables and work required to create these
deliverables.
It helps to create a common understanding among stakeholders
(avoid scope creep)
Project team can perform detailed planning now
100% rule: WBS includes 100% of the work defined by project scope and capture ALL
deliverables (external, internal, interim) in term of work to be completed including
project management.
Create WBS
How to produce?
What is Work Breakdown Structure
(WBS)?
The PMBOK Guide describes a WBS as “a deliverable-oriented
hierarchical decomposition of the work to be executed by the
project team, to accomplish the project objectives and create the
required deliverables…the WBS defines the total scope of the
project.”
Work that doesn’t fit into the WBS does not fit within the project.
Projects are normally too big to manage and WBS breaks the
project works into smaller more manageable components
arranged according to deliverables.
This is a top down effort, break works down from top to bottom.
Create WBS
Each level of WBS is a smaller piece of the level above.
The top most level of each WBS is the total project itself.
Work is broken down to the lowest level possible till further
division is logically not possible or the work can be confidently
estimated and scheduled.
WBS represents total work specified in the current approved
scope statement and shall be revised if a major scope change
occurs.
Create WBS
• Work package: lowest level WBS component which can be
scheduled, cost estimated, monitored and controlled.
Deliverable
Underlying concept of deliverable is the core of a WBS
Any Unique and verifiable product, result, or capability to
perform a service that must be produced to complete a process,
phase, or project.
Subject to approval by the project sponsor or customer
Benefits of WBS
Better communication to project sponsors, stakeholders and
team members
More accurate estimation of tasks, risks, timelines and cost
Increased confidence that 100% of the work is identified and
included
A foundation for the control processes within the project
100% Rule
If the lowest levels are rolled up to the higher levels, the total
must represents the total work of the project. This is called
100% rule.
This ensures that no work is left out or no extra work is added.
The WBS includes the 100% of the work defined by the project
scope and captures ALL deliverables-internal, external and
interim- in terms of work to be completed including project
management
Develop WBS: Tool & Technique
Decomposition
This technique involves breaking down the deliverables into
smaller, more manageable components of work.
The idea here is to break down the deliverables to a point
where you can easily plan, execute, monitor and control, and
close out the project deliverables.
Each level of WBS is a more detailed definition of the level
above it.
WBS for a Bicycle
WBS Dictionary
In order to more clearly define the work necessary for project completion the WBS Dictionary is
used. The WBS Dictionary includes but not limited to the following: level, WBS element, element
name, description of work, deliverable.
WBS Dictionary
WBS dictionary should include the following elements for each
component of the WBS:
Code of accounts identifier
Description of the work of the component
Organization responsible for completing the component
List of schedule milestones
Required resources
Cost estimates
Quality requirements
Criteria for acceptance
Technical references
Contract information
Output
The Scope Baseline is a component of the
project management plan and include the
following:
Validate Scope
Validate Scope : Tools & Techniques
Inspection
To complete scope verification, the work must be inspected.
This may require measuring, examining, and testing the product
to prove it meets customer requirements.
Inspection usually involves the project manager and customer
inspecting the project work for verification, which in turn results
in acceptance.
Depending on the industry, inspection may also be known as:
Reviews, Product Reviews, Audits & Walkthroughs.
Lecture 4
Project Time Management
“the processes required to accomplish timely
completion of the project.” PMI-PMBoK 5th Ed.
Estimating
Time management involves a bottoms-up approach. Estimate
the duration of each activity and combine that with the network
diagram to build up the schedule to determine overall project
duration.
• Note: Top-Down estimating is not a recommended PMI method
for establishing overall project duration.
• Qualified exception: When there is a limited amount of detailed
information about the project.
Estimate Activity Durations: Tools and Techniques
Expert Judgment
Analogous Estimating
Parametric Estimating
Three-Point Estimating
Activity Duration Estimating
Expert judgment guided by historical information used
whenever possible.
Anything less is inherently uncertain and risky.
“Expert judgment can also be used to determine whether to
combine methods of estimating and how to reconcile differences
between them, PMI-PMBoK”
Analogous Estimating
a technique for estimating the duration or cost of an activity or a
project using historical data from a similar activity or project.
.
Parametric (Quantitative) Estimating
an algorithm is used to calculate cost or duration based on
historical data and project parameters.
Parametric estimating uses a statistical relationship between
historical data and other variables (e.g., square footage in
construction) to calculate an estimate for activity parameters,
such as cost, budget, and duration.
PERT Approach
Calculation of PERT PROBABILITIES
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Schedule Management
Define Activity
Sequence Activity
Time
Activity Resource Estimating Control Schedule
Management Activity Duration Estimating
Develop Schedule
Define Activity
Figure 6-5. Define Activities: Inputs, Tools & Techniques, and Outputs
Activity Definition
An activity or task is an element of work normally found on the WBS
that has an expected duration, a cost, and resource requirements.
Project schedules grow out of the basic documents that initiate a
project.
The project charter includes start and end dates and budget information.
The scope statement and WBS help define what will be done.
Activity definition involves developing a more detailed WBS and
supporting explanations to understand all the work to be done, so
you can develop realistic cost and duration estimates.
Milestones are typically major accomplishments of the project and mark the
completion of major deliverables or some other key event in the project.
Milestones are useful tools for setting schedule goals and monitoring
progress.
Activity Sequencing
Involves reviewing activities and determining dependencies or
relationship between activities .
External Dependency
The term resources in this case does not mean just people; it
means all the physical resources required to complete the
project.
People
Equipment
Materials
Estimate Activity Resource
The RBS Chart shows you the hierarchy of your resource pool
in a hierarchical tree.
Analogous Estimating
Analogous Estimating, is a form of expert judgment and is also
known as Top-down Estimating. Analogous estimates are typically
less time consuming and less costly than other estimating
techniques, but it’s also less accurate.
Three-Point Estimates
Three-point estimates, as you can probably guess, use three
estimates that when averaged come up with a final estimate.
The three estimates you’ll use in this technique are the most
likely estimate, an optimistic estimate, and a pessimistic
estimate.
For example, you know it will take 100 hours to run new cable,
you also know that sometimes you hit problem areas when
running the cable. To make sure you don’t impact the project
schedule, you build in a reserve time of 10 percent of your
original estimate to account for the problems you might
encounter.
Develop Schedule
The Develop Schedule process is the heart of the Planning process
group.
The creation of the project schedule is iterative. It’s rare for a
schedule to get created, approved, and implemented without
some iterative examination, arrangement, and management input—
though on smaller projects it may be possible.
Develop Schedule
Gantt Chart for Software Launch
Project
Develop Schedule
(Tools & Techniques)
Schedule Network Analysis
There can be more than one critical path if the lengths of two or
more paths are the same.
Floats
Floats are not the same as lead or lag.
DURATION
ES EF
FORWARD PASS
ES
BACKWARD PASS
LS LF
The critical path may change as you enter actual start and finish
dates.
If you know the project completion date will slip, negotiate with
the project sponsor.
Critical Path
Float
Exercise 1
A project has the following activities: Activity A takes 5 days and
can start after the project starts. Activity B takes 3 days and
starts the same as A. Activity C is 6 days and must happen after
activity B. Activity D with 10 days will start after A starts. Activity
E can start after Activity D & C finish with duration of 3 days.
Activity F will start after Activity D finishes having a duration of 2
days. Activity E&F are the last activities.
What is the critical path?
What is the duration of the project?
Analyze the network diagram and as PM what changes can you
suggest?
The project is currently being delayed by 3 days. As a PM what
strategies can you suggest to the sponsor?
Exercise 2
ACTIVITY PREDECESSOR DURATION (MOS)
START NONE 0
A START 1
B START 4
C START 5
D A 6
E B,C 8
F C 7
G D 1
H E 10
I F 5
END G.H.I 0
Schedule Compression
Crashing – This approach adds more resources to activities on
the critical path to complete the project earlier. Crashing almost
always result in increased cost. Many options are considered
and the option with maximum compression with minimum cost
impact is selected.
Schedule Control
Control Schedule
( Tools & Techniques)
Performance Reviews- Performance reviews
measure, compare, and analyze schedule performance
such as actual start and finish dates, percent complete, and
the remaining duration for the work in progress .
Lecture 5
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Cost Management
Cost Estimate Cost
Control Cost
Management Determine Budget
Types of Cost
Variable Costs
Change with the amount of production/work e.g. material, supplies,
wages.
Fixed Costs
Do not change as production change e.g. set-up, rental.
Direct Costs
Directly attributable to the work of project e.g. team travel,
recognition, team wages.
Indirect Costs
overhead or cost incurred for benefit of more than one project. E.g.
taxes, fringe benefit, janitorial services
Estimate Cost
Developing an approximation or estimate of the costs of the resources
needed to complete a project.
Estimate Cost: Tools & Techniques
Bottom-up Estimating
Analogous Estimating
Parametric Estimating
Reserve Analysis
Determine Budget
Allocating the overall cost estimate to individual work items
to establish a baseline for measuring performance.
Cost Aggregation
Activity costs are rolled up
to work package costs.
Work package costs are
rolled up to control account
costs and finally into project
costs.
Contingency Reserves
part of the budget intended to address the “known-unknowns” that can
affect a project. Included in the Cost Baseline.
Management Reserves
intended to address the “unknown unknowns” that can affect a project.
NOT included in the Cost Baseline.
Determine Budget: Tool & Technique
Funding Limit Reconciliation
Funding limit reconciliation involves reconciling the amount of
funds to be spent with the amount of funds budgeted for the
project. The organization or the customer sets these limits.
Reconciling the project expenses will require adjusting the
schedule so that the expenses can be smoothed. You do this by
placing imposed date constraints on work packages or other
WBS components in the project schedule.
Question?
Control Cost
Controlling changes to the project budget.
Progress Report
Progress/ performance report (output from communications
management)
Where work cannot be measured, estimate could be done by a
guess.
Percent complete
- 50/50 Rule
- 20/80 Rule
- 0/100 Rule
Activity is considered X percent complete when it
begins and get credit for the last Y percent only when it is
Completed.
More and more organizations around the world are using EVM to help
control project costs.
Control Cost: Tools & Technique
Earned Value Management
Earned value management will indicate status and health of
project at any time and can predict possible outcomes.
EVM can be used for analysis of cost and schedule
baselines
Earned Value Management is carried out using the three
main inputs:
➢ Planned Value (PV)
➢ Earned Value (EV)
➢ Actual Cost (AC)
Budget at Completion (BAC) How much did we budget for the total project
effort.
Estimate to Complete (ETC) From this point on, how much more do we expect
= EAC- AC it to cost to finish the project
Simple EAC calculation( EAC= BAC/CPI) assume that the cumulative CPI
adequately reflects past performance that will continue to the end of the
project.
AC+(BAC-EV)
- used when current variances are thought to be atypical of the future.
Lecture 6
What Is Quality?
What is Quality ?
The International Organization for Standardization (ISO) defines
quality as the totality of characteristics of an entity that bear on
its ability to satisfy stated or implied needs
Quality Theorists
To ensure that the Project will satisfy the needs for which it was
undertaken.
Scope
Cost
Performance
Meet or exceed Customer Satisfaction
The customer ultimately decides if Quality is Acceptable.
Addresses (i) the management of the project and (ii) the product
of the project.
Addresses (i) the management of the project and (ii) the product
of the project.
Management Responsibility
“Success requires the participation of all members
of the team, but it remains the responsibility of
management to provide the resources needed to
succeed.”
Quality Management includes:
Plan Quality - Identifying which quality standards are relevant
to the project and how to satisfy them.
External failure cost: cost that relates to all errors not detected and have
to be corrected after customer receives the product.
e.g. DOE helps identify which variables have the most influence on
the overall outcome of a process
Standard deviation (sigma) – measure how far away from the mean
(dotted vertical line)
PERT FORMULA
(Triangular Distribution)
OT + 4MT +PT
________________
6
Standard Deviation =
P - O
----------------
6
Statistical Sampling and Standard Deviation
Flowcharting
It helps to analyze how problems occur.
A flowchart is a graphical representation of a process.
It shows how various elements of a system interrelated and the
order of processing.
It helps the project team anticipate what and where quality
problems might occur.
Quality Control(Tools & Techniques)
Flowcharting
Run Chart
QC Tools and Techniques
Scatter Diagram
➢ Shows the pattern of the relationships between two variables.
Quality Concepts
Philosophy: definition of quality, avoidance of “Gold plating” – giving
customer extras, this practice is not recommended.
Marginal Analysis – optimal quality is reached at the point when
revenue from improvement equals the costs to secure it.
Just in Time (JIT) - just when they are needed or just before, it
decrease amount of inventory/decrease investment.
Total Quality Management (TQM) – company and their employees
focus on finding ways to continuously improvement the quality of their
business practices and products.
W. Edwards Deming
Lecture 7
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Negotiation
Project Management team may need to negotiate with:
✓ Functional Manager to ensure availability of component staff.
✓Other Project Management teams to assign scarce / specialized
resources.
Acquire Project Team:
Tools and Techniques
Acquisition
From Internal /External resources. Acquiring from outside may
take place due to shortage / lack of staff in-house
Virtual Teams
This is the possibility of having groups of people in different
geographic locations, with little or no time spent to meet face to
face. Electronic communication, Such as e-mail and video
conferencing, has made such teams feasible.
❖Communication planning becomes increasingly important
in a virtual team environment.
WIFI
Motivational Theory:
Maslow’s Hierarchy of Needs
ENHANCED
Conflict Management
Problem Solving
The important thing to realize about problems is if they are not
resolved completely they just return, again and again.
Democratic(Participative)
- Encourage team participation in the decision making process.
- Best used for people whose behavior fit with theory Y.
Important Terms
Halo Effect- The assumption of because a person is good in a
technical field, they will be a good project manager.
Arbitration- A method to resolve conflict. A neutral party hears
and resolve a dispute.
Expectancy Theory by Victor. H. Vroom- This is a
motivational theory, which states that people put in more effort
because they expect to be rewarded for their efforts.
Perquisites (Perks)- Some employees receive special rewards
e.g. parking spaces, corner offices, executive dining.
Fringe Benefits- Standard benefits formally given to all
employees, such as insurance, educational benefits and profit
benefits.
PM Responsibility (PMI-ism)
Lecture 8
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan
Communication Control
Communication Manage Communications
Management Management
Communications
Plan Communication
The Plan Communications process involves determining the
communication needs of the stakeholders by defining
• the types of information needed
• the format for communicating the information,
• how often it’s distributed, and
• who prepares it.
Stakeholder Register
• Stakeholder Register
Other
Stakeholders
Determine and limit who will communicate with whom and who will receive what information.
Communication Requirement Analysis
N ( N 1)
Formula: 2
Noise
Encode Decode
Project manager cannot control all communications but should try to control or
prevent miscommunication, unclear directions, and scope creeps.
Manage Communications
• Manage Communications is the process of creating, distributing,
storing, retrieving and the ultimate disposition of project
information in accordance to the communications management
plan
Information Management Systems-
(Tools &Techniques)
Report Performance
The process of collecting and distributing performance
information, including:
Status Report
Progress Report
Trend Report
Forecasting Report
Variance Report
Earned Value
Lessons Learned
Report Performance
Performance reporting keeps stakeholders informed
about how resources are being used to achieve project
objectives
Status reports describe where the project stands at a
specific point in time.
Progress reports describe what the project team has
accomplished during a certain period of time.
Forecasts predict future project status and progress
based on past information and trends
Control Communications
• Control Communications is the process of monitoring and
controlling communications throughout the entire project life cycle
to ensure the information needs of the project stakeholders are
met.
CM651 – Project Management
Lecture 9
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Risk Management
Identify Risk
Risk
Perform Qualitative Risk Analysis Control Risk
Management Perform Quantitate Risk Analysis
Plan Risk Response
Risk Management Processes and their main
Outputs
TERMINOLOGY
Risk Assessment – the stage in our risk management process
where the importance of each risk is evaluated.
Identify Risk
The process of determining which risk may affect the project
and documenting their characteristics.
Identify Risks
Risk should be continually reassessed (iterative) such as in integrated change
control activity, when working with resources, when dealing with issues.
Information gathering techniques
Brainstorming
Root cause analysis: Reorganizing the identified risk by their root cause may
help identify more risks.
Influence diagrams
An influence diagram is a visual representation of a decision. Influence
diagrams offer a way to identify and display the essential elements,
including decisions, uncertainties, and objectives, and how they influence
each other. Unlike flowcharts, influence diagrams do not show paths in
any sequential order.
Risk Register (Output)
After Indentify Risk process the output is initial
entries into the risk register.
It includes:
List of risk
List of POTENTIAL responses
Root causes of risks
Updated risk categories
-Relative ranking/priority
• For an example, let's assume that there is a carnival game in which there
are three shells but only one has a ping-pong ball under it. The game
costs $1 to play and the winner will receive $2 if he correctly picks the
shell with the ball hidden under it. There are two outcomes based on the
one-in-three chance of choosing the correct shell: either the player loses
66.66% of the time or he wins two dollars 33.33% of the time. The EVM
for this game is:
Share
Allocate some or all of the ownership of the opportunity to a third party
who is best able to capture the opportunity for the project benefit.
Enhance
Increase the probability and/or the positive impacts of an opportunity.
Accept
Not actively pursuing an opportunity
Control Risk
The process of implementing: risk response plans, tracking identified
risks, monitoring residual risks, identifying new risks, and evaluating
risk process effectiveness throughout the project.
Requested changes.
Recommended corrective and preventive actions.
Updates to the risk register, project management plan, organizational
process assets and project documents.
Monitor & Control Risks (Tools & Techniques)
Risk audits review the overall risk management policies,
procedures, and processes. Audits review the effectiveness of the
project risk management plan. Risk audits can also refer to analyzing
whether the risk response actions were effective and what impact
they had on the project's overall risk level.
Lecture 10
PROCUREMENT
PROCUREMENT MANAGEMENT
Many project managers lack the knowledge and skills to
procure goods and services effectively.
Poor procurement often results in poorly delivered scope,
schedule delays, cost overruns and poor quality of the goods
and services that the project is intended to deliver.
The Sequential Procurement Processes
Plan Procurements
Conduct Procurements
Control Procurement
Close Procurements
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Procurement
Procurement Conduct Control Close
management
Management Procurements Procurement Procurement
Plan Procurements
Is the process of documenting project purchasing decisions,
specifying the approach, and identifying potential sellers.
Procurement planning is the process of identifying which part of
the project should be procured from resources outside of the
organization. It is concerned with determining what to procure,
when, and how.
Cost-reimbursable Contract
The seller's cost are reimbursed, plus an additional amount.
The buyer has the most cost risk because the total costs are
unknown.
This form of contract is often used when the buyer can only
describe what is needed, rather than what to do.
The seller will therefore write the detailed contract
statement work.
Cost-reimbursable Contract - Variations
Procurement Documents
• Special Provisions (Special Conditions)
• The project manager should determine what needs to be
added, changed or removed from the standard provisions, so
that the resulting contract addresses the particular needs of the
project.
• Letter of Intent- NOT a contract but a letter, without legal
binding, that says the buyer intends to hire the seller.
• Privity- Contractual relationship.
• Example - Company A hires company B to do some work for
them. Company B subcontracts to company C. The project
manager for A is at the job site and tells company C to stop
work. Generally, does company C have to listen?
Conduct Procurements
Is the process of obtaining seller responses, selecting a seller
and awarding a contract.
In this process the team will receive bids or proposals and will
apply previously defined selection criteria to select one or more
sellers who are qualified to perform the work and acceptable as
a seller.
Conduct Procurement
Conduct Procurements is the process of obtaining seller responses,
selecting a seller, and awarding a contract .
Conduct Procurements
Selected Sellers
Control Procurements
This process consists of assuring that the performance of both
parties to the contract meets contractual requirements.
The Contract Administration process concerns monitoring the
vendor’s performance and ensuring that all the requirements of
the contract are met.
Contracts are legal relationships, so it is important that legal
and contracting professionals be involved in writing and
administering contracts.
Control Procurements
Claims Administration
✓ A claim is an assertion that the buyer did something that has
hurt the seller and the seller asking for compensation.
✓ Another way of looking at claims is that they are a form of
seller's change requests
✓Claims can get nasty. Imagine a seller that is not making as
much profit as he hoped for, issuing claims for every action
taken by the buyer.
✓Claims administration involves documenting, monitoring, and
managing changes to the contract.
Claims Administration
Changes that cannot be agreed upon are called contested
changes.
Contested changes usually involve a disagreement about the
compensation to the vendor for implementing the change.
You might believe the change is not significant enough to justify
additional compensation, whereas the vendor believes they’ll
lose money by implementing the change free of charge.
Claims Continue
Contested changes are also known as disputes, claims, or
appeals. These can be settled directly between the parties
themselves, through the court system, or by a process called
arbitration.
Arbitration involves bringing all parties to the table with a third,
disinterested party who is not a participant in the contract to try
to reach an agreement.
The purpose of arbitration is to reach an agreement without
having to go to court.
Records Management System
A contract is a formal, legal document. Recording keeping can
be critical if actions taken or situations faced during a project
are ever in question after the work is completed.
This can happen related to unresolved claims or legal actions,
or even in order to satisfy insurance needs.
A record management system can be quite extensive, with one
person assigned just to manage these records.
They can also include indexing systems, archiving systems and
information retrieval systems for projects with extensive
documentation.
Close Procurements
This process consists of finishing all the loose ends of the contract.
This process is part of the close project process described in
integration.
Close Procurements
Close Procurements : Tools & Techniques
The Contract Closure process has three tools and techniques:
• Procurement audits – structured review of entire procurement process;
identify successes and failures that warrant transfer to other procurement
items
CONTRACTS
An agreement between competent parties for the consideration
to accomplish lawful purpose with the terms clearly set forth.
The Procurement Process is sometimes referred to as the
Contract Process
One of the main output of the Procurement Process
RULES OF CONTRACTS
A formal agreement – buyer and seller
Oral or written – written is preferred
Clearly state all requirements
Changes –formally approved, controlled, documented
Not fulfilled until all requirements are met
Be executed by someone with capacity and authority.
Lecture 11
Executing
Processes
Process Groups
Knowledge Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Control
Stakeholder Indentify Manage Stakeholders
Stakeholder Stakeholder
Management Stakeholder
Management
Engagement
Engagement
Identify Stakeholders
Identify Stakeholders is the process of identifying all people or organizations
impacted by the project and documenting relevant information regarding their
interest, involvement and impact on project success.
Stakeholder Analysis
A technique of systematically gathering and analyzing quantitative & qualitative
information to determine whose interests should be taken into account throughout
the project. High
•F •D
• Step 1: Identify all potential project
stakeholders and relevant Keep Satisfied Manage
information Closely
•C •G •A
Power
support each stakeholder could
generate and classify them so as to •H
define an approach strategy. •B
Monitor • E Keep
(Minimum Effort) Informed
• Step 3: Assess how key stakeholder
are likely to react or respond in
various situation
Low
Interest High
Stakeholder Register
This is the main output of the identify stakeholders process and
it contains all details related to the stakeholders such as name,
organizational position, location, role in the project, contact
information.
It also contains the major requirements, main expectations,
potential influence in the project. It also classify them as
internal, external, supporter, neutral, resistor etc.
Departme
Contact Role in Attitude
nt/ Main Major
Name Informa Project Company Impact Influence about the
Superviso expectations requirement
tion project
r
Plan Stakeholder Management
Actions and communication required to close the gap can be identified by the
project team using expert judgment
Outputs: Stakeholder Management Plan
• Reason for the distribution of that information and the expected impact to
stakeholder engagement
• Method for updating and refining the stakeholder management plan as the project
progresses and develops.
Manage Stakeholder Engagement
• Addressing potential concerns that have not yet become issues and
anticipating future problems that may be raised by stakeholders. Such
concerns need to be identified and discussed as soon as possible
to assess associated project risks.
The key benefit of this process is that it will maintain or increase the efficiency and
effectiveness of stakeholder engagement activities as the project evolves and its
environment changes.
Information, however, is
correlated and contextualized
and provides a sound foundation
for project decisions.