Professional Documents
Culture Documents
RAJKOT DIVISION
NOTICE No. DRM/RJT/2010-11/08 Dt.18.08.10 Sr. No. DRM/RJT/2010/45
Name of Work :- Providing ballast wall from KM. 853/6 to 854/1 between Kanalus- Modpur & KM. 853/16
to 854/1 between Kanalus- Motikhavadi (Total length 1200 mtrs.)
6. Time & Date of start of sale of tender documents : 10.00 Hrs on 30.08.10
7. Time & Date for closure of sale of tender Documents : 12.00 Hrs on 27.09.10
8.Time & Date for closure for submission of tender documents : 15.00 Hrs on 27.09.10
1
Signature of tenderer/’s
Issued to / Downloaded by : -
M/s.
Note : If the tender has been downloaded from the website , the interested bidders should write their
name and address in the space above and enclose cost of tender documents in acceptable
form as mentioned in the tender documents along with the offer.
The price of the tender document is paid for the above tender vide
DD/Money Receipt No. Dated:-____________________________
Note :- (Tenderers to fill details of tender fee in form of Money Receipt for tenders purchased in
person/ by post OR Demand Draft particulars for tenders down loaded from Web site
deposited for the cost of tender)
1. For tenders sold in the office of the tender inviting authority, the tender document is issued on request
of the tenderer/s after having deposited the requisite cost of the tender document as stated above. The
tender document is issued to these tenderers with further condition that they agree to abide by the
conditions laid down in the tender document , before submitting the tender.
2. For tender documents downloaded from the official web site of the Western Railways, the following
conditions strictly apply:-
(a) The document has been downloaded by you from the official website of western railway
http://www.wr.indianrail.gov.in for submitting the bid. A Demand draft (separate Demand Draft other
than that of Earnest Money) for an amount equivalent to cost of tender document mentioned in tender
notice in favour of Sr Divisional Finance Manager, Western Railway, Rajkot payable at Rajkot, towards
the cost of the tender document will have to be enclosed with the tender document. In case, the offer is
not accompanied with the valid demand draft for the cost of the tender document as detailed above,
the tender will be summarily rejected.
(b) Tenderer/s to please note that the document is being allowed to be downloaded with further
condition that he/they agree to abide by the conditions laid down in the tender document, before
submitting his/their tender.
(c) The total document from the first page to the last page where `END OF DOCUMENT' is marked is
to be downloaded and submitted along with the offer. Otherwise the document will be treated as
incomplete and therefore invalid.
(d) The Railway before the due date & time of closure of issue of tender documents on its own or in
response to any clarification requested or suggested by any person including that of the tenderer, may
modify the tender document at its sole discretion. It will be the responsibility of the tenderers who had
downloaded the documents from the website to submit offer in the updated copy of the tender
documents and Railway may not consider the offers downloaded from website if offer is not submitted
in updated tender documents.
3. All tenderer/s shall please also note that if any change/addition/deletion with malafide intention is made
by the bidder and the same is detected at any stage even after award of the tender, all necessary
action including banning of business may be taken against the bidder.
2
Signature of tenderer/’s
4. The tender document comprises various parts and contains pages as under :-
2 Forwarding Letter 2
3 Tender Notice
4
4 Documents for fulfilling eligibility criteria 7
10 Proforma I to V 43-46
11 Schedule of approximate quantities & rates 47-50
5. All the above parts taken together shall constitute the complete tender document hereinafter referred to
as “tender document” and have to be read together and acted upon accordingly. No part of the tender
document can be relied upon or acted upon in isolation.
3
Signature of tenderer/’s
Tender No.DRM/RJT/10/45 : Name of work – Providing ballast wall from KM. 853/6 to 854/1
between Kanalus- Modpur & KM. 853/16 to 854/1 between Kanalus- Motikhavadi (Total length
1200 mtrs.) , approx.cost-Rs. 1596000/-, Earnest money-Rs. 31920/-, Tender fee-Rs.2000/-
.Completion period- 03 months, opening date- 27.09.10. Similar Work ; Not applicable.
Eligibility Criteria: (As given below are applicable only open tenders costing above Rs.20 lakhs)
only such tenderer/firm need to apply who satisfies with following criteria)
Should have completed at the time of opening of At least one similar single work for
tender in the last 3 financial years (i.e. current year minimum value of 35 % of advertised
and three previous financial years) tender value of work
Total contract amount received during the last three Should be a minimum of 150% of
financial years and in the current financial year advertised tender value of work as per
attested payment certificate from the
employer / client, audited balance
sheet duly certified by the chartered
accountant etc.
“If the tenderer fails to submit any proof for meeting with eligibility criteria as
prescribed above with the tender document while submitting the offer, the offers should
be considered as incomplete and should be summarily rejected.”
4
Signature of tenderer/’s
2 The tender notice and tender documents will also be available on western railway’s official web site
http://www.wr.indianrail.gov.in . The same can be downloaded and used as tender document for
submitting the tender. This facility is available free of cost. However the cost of tender document as
mentioned above has to be paid in the form of Demand Draft issued in favour of “Sr Divisional
Finance Manager, Western Railway, Rajkot”, payable at Rajkot and should be enclosed with the
Tender Form while dropping the tender. In case the tender is not accompanied with the valid Demand
Draft for the cost of the tender document downloaded, the tender will be summarily rejected.
3 Eligibility Criteria (Applicable for works costing above Rs.20.00 lacs only) :
3.1 Only those tenderer(s) are eligible who fulfill following eligibility criteria (for works costing above
Rs.20.00 lacs only) for which necessary documents as indicated below should be submitted along with
offer.
(i) Turn Over : The total contract amount received by the tenderer(s) during the last three financial
years and the current financial year should be a minimum of 150% of advertised tender value of work.
Tenderer(s) should submit proof to this effect in form of attested certificates from employer/clients for
payments received by them year wise during the period or audited balance sheet duly certified by the
chartered Accountant.
(ii) Experience in similar work : The tenderer(s) should have completed at the time of opening of
tender in the last three financial years (i.e. current year and three previous financial years), at least one
similar single work, for a minimum value of 35% of advertised tender value of work .
Similar work in this context means : Not applicable.
(Attested copy of satisfactory completion certificates issued by employer/client along with value of
work done shall be submitted along with the offer).
(a) Similar nature of work physically completed within the qualifying period i.e. the last three-financial
years and current financial years (even though the work might have commence before qualifying
period) should only be considered in evaluating the eligibility criteria.
(b) The total value of similar nature of work completed during the qualifying period and not the
payments received within qualifying period alone, should be considered. In case the final bill of similar
nature of work has not been passed and final measurements have not been recorded, the paid
amount including statuary deduction is to be considered. If final measurements have been recorded
and work has been completed within negative variation, then also the paid amount including statuary
deduction is to be considered. However, if final measurements have been recorded and the work has
been completed with positive variation, but variation has not been sanctioned. Original agreement
value or last sanction agreement value whichever is lower should be considered for judging eligibility.
(c) In the case of composite work involving combination of different works, even separate completed
works of required value should be considered while evaluating the eligibility criteria. For example, in
the tender for bridge work where similar nature of work has been defi9ned as the bridge work with pile
foundation and PSC super structure, a tenderer, who has completed one bridge work with pile
foundation of value at least equal to 35% of tender value and also has completed one bridge work with
PSC Super structure of value at least equal to 35% / tender value, should be considered as having
fulfilled the eligibility criteria of having completed single similar nature of work
3.2 Deleted.
5
Signature of tenderer/’s
15 This Tender notice has also been published on the Western Railway’s official website
http://www.wr.indianrail.gov.in.
6
Signature of tenderer/’s
Tenderers shall fill up the following table indicating the details of the firm, EMD submitted and references
of documents attached in support of eligibility criteria i.e. the documents on the basis of which the tenderer
considers himself as eligible for the work as per eligibility criteria laid down in tender documents.
No Item Details/certificates enclosed
4 Satisfactory completion
certificates for completion of
similar works during last 3
financial years and current
financial year.
5 Certificate of turnover
(Contractual payments
received during three
financial year and
current financial year)
7
Signature of tenderer/’s
2 The Tenderer/s is advised to study the Tender Document carefully. The Tenderer(s) shall also acquaint
himself/ themselves with the local conditions, nature of work and all other matters pertaining thereto.
3 The Tendere/s must obtain for himself, on his own responsibility and at his own expense, all information
which may be necessary for the purpose of making the Tender offer and entering into Contract.
4 The submission of the Tender shall be deemed to have been done after careful study and examination
of the Tender Document with full understanding of the implications thereof. Any clarification required by
a Tenderer shall be obtained from the Office of the Tender Inviting Authority on any working day during
office hours.
5 The tenderer(s) shall strictly adhere to the form of tender specified by the Railway. Tenders not
submitted in this form are liable to be rejected.
6 Complete tender document along with accompaniments shall be sealed in an envelope , super scribing
boldly :
Tender No
Tender due to open on
Name of work
7 The Tender shall be signed by individual or individuals legally authorized to enter into commitments on
behalf of the Tenderer. Any individual or individuals signing the Tender Documents or other
documents connected therewith should specify whether he is signing
i. As a Sole Proprietor of the firm or Attorney of the Sole Proprietor;
ii. As a Partner or Partners of the firm;
iii. As a Director, Manager or Secretary in a Limited Company.
8 In the case of a firm not registered under the Indian Partnership Act, all the partners or the Attorney
duly authorized by all of them should sign the Tender Document and all other concerned documents.
9 Requisite Power of Attorney or such other documents empowering the individual or individuals to sign
should be furnished along with the Tender.
10 Every Tenderer shall state in the Tender his postal address fully and clearly. Any communication sent
in time to the Tenderer by post at the said address shall be deemed to have reached the Tenderer
duly and in time. He shall also give telephone and fax number for communication. Important
documents shall be sent by Registered post. The tender shall be addressed to the tender issuing
authority.
11 The complete Tender document shall be dropped in the Tender Box placed in the Office of the
Tender Inviting Authority not later than due date and time of closing.
8
Signature of tenderer/’s
13 Tenders sent by post shall be sent by Registered Post acknowledgement due, so as to reach the
Office of the Tender Inviting Authority not later than 15.00 hrs. on date of opening of tender. Tenders
received late will not be considered.
14 Conditional tenders are liable to be rejected. Railway however reserves the right to reject such tenders
summarily without assigning any reasons whatsoever. The Railway also reserves the right to reject any
special conditions stipulated by the Tenderer as considered unacceptable to the Railway and can call
upon the Tenderer to withdraw such conditions. If any deviations from the General conditions/ special
conditions/ specifications are proposed by the tenderer, they should be mentioned statement of
deviation in Annexure`A' and not else where in the tender documents.
15 Evaluation of Tender:
For evaluation of Tenderer's offer, it may be necessary to seek certain clarifications. Railway shall seek
such clarification in writing or through telegram/cable/Telex/FAX.
16 If it is found at any stage of the finalization of the tender or during actual execution of the work that
the information furnished in this tender ,including clarifications, is incorrect, the tenders are likely to
be rejected.
9
Signature of tenderer/’s
To,
The President of India,
Acting through
Divisional Railway Manager (WA),
Western Railway, Rajkot Division,
RAJKOT -360 001
2. I/We also hereby agree to abide by the General Condition of Contract corrected upto Aug 98 with
printed/advance correction slips up to no 4 and to carry out the work according to the special
conditions of contract and specifications of materials and work as laid down by Railway in the
annexed special conditions/specifications and the Western Railway Works Hand Book Part-
III,(1984 edition) corrected upto printed/advanced correction slip number 9 dated 1.11.91, Sanitary
Works Handbook (1977 edition) corrected upto printed/advance correction slip number 1 dated
11.10.84, Schedule of Rates Part-I corrected upto printed/advance correction slip number 2,3 dated
26.5.94&4.9.95,Schedule of Rates Part-II(1993 edition) corrected upto printed/advance correction
slip number 1 dated 11.7.94, for the present contract.
3. The requisite earnest money as specified in the tender notice is herewith forwarded as Earnest
Money. The full value of the earnest money shall stand forfeited without prejudice to any other
right or remedies in case my/our tender is accepted and if:-
a. I/We do not execute the contract documents within 15 (Fifteen) days after receipt of notice
issued by the Railways that such documents are ready and
b. I/We do not commence the work within fifteen days after receipt of order to that effect.
4. Until a formal agreement is prepared and executed, acceptance of this tender shall constitute a
binding contract between us subject to modifications as may be mutually agreed to between us and
indicated in the letter of acceptance of my/our offer for this work.
10
Signature of tenderer/’s
2. Drawings for the work : Drawings for the work can be seen in the office of the Sr. Divisional Enginer,
Divisional Railway Manager’s office, Rajkot Division, Rajkot 360 001 at any time during the office
hours. The drawings are only for the guidance of tenderer (s). Detailed working drawings, if required,
based generally on the drawings mentioned above, will be given by the Engineer or his representative
from time to time.
2.1 The structural drawing of the work if required will be done by the tenderer. He will have to submit
draft drawing along with draft calculation in hard as well as in soft copy to the office of Divisional
Engineer (Works) Rajkot. After scrutiny of the design submitted, tenderer will submit final print on
tracing plan along with corrected design calculation in soft and hard copy to the office of Divisional
Engineer (Works) Rajkot. For this work of design nothing extra will be paid by Railway.
3. The tenderer (s) shall quote his/their rates as a percentage above or below the schedule of rates of the
Western Railway as applicable except where he/they is/are required to quote item rates and must tender
for all the items shown in the schedule of approximate quantities attached. The quantities shown in the
attached schedule are given as a guide and are approximate only and are subject to variations
according to the needs of the Railway. The Railway does not guarantee work under each item of the
schedule.
4. Tenders containing erasures and / or alterations of the tender documents are liable to be rejected. Any
corrections made by the Tenderer (s) in his / their entries must be attested by him/them.
5. The works are required to be completed within the stipulated completion period mentioned in the tender
notice
11
Signature of tenderer/’s
6 EARNEST MONEY :
(a) The tender must be accompanied with requisite Earnest money mentioned in the tender notice,
deposited in cash or in any of the forms as mentioned below drawn in favour of ‘Sr Divisional
Finance Manager , Rajkot Division, Rajkot’ , Payable at Rajkot., failing which the tender will be
summarily rejected.
i) Deposit receipt, Pay orders and Demand drafts. These forms of earnest money could be either of
the State Bank of India or of any Nationalized Banks. No confirmatory advice from the Reserve
Bank of India will be necessary.
ii) Deposit receipt executed by the Scheduled Banks ( other than the State Bank Of India and the
Nationalized Banks ) approved by the Reserve Bank Of India for the purpose. The Railway will
not, however, accept, any such deposit receipt without getting in writing the concurrence of the
Reserve Bank Of India.
iii) The earnest money wherever it is deposited in cash should be remitted to the any Station of the
western railway and the receipt obtained thereof should be enclosed with the tender as a proof of
the deposit of requisite earnest money. The earnest money should not be deposited with Stations.
(c) The Tenderer(s) shall keep the offer open for a minimum period of validity as mentioned in the top
sheet of the tender document. It is understood that the tender document has been sold/issued to
the Tenderer(s) and the Tenderer(s) is / are permitted to tender in consideration of the stipulation on
his/their part that after submitting his/their tender subject to the period being extended further if
required by mutual agreement from time to time, he will not resile from his offer or modify the terms
and conditions thereof in a manner not acceptable to Western Railway. Should the Tenderer fail to
observe or comply with the foregoing stipulation, the amount deposited as Earnest Money for the
due performance of the above stipulation shall be forfeited to the Railway.
(d) If the tender is accepted, the amount of Earnest Money will be retained and adjusted as Security
Deposit for the due and faithful fulfillment of the contract. Clause 16 of General conditions of Contract
the earnest money of the other tenderers shall save as herein before provided be returned to them,
but the railway shall not be responsible for any loss or depreciation that may happen thereto while in
their possession nor be liable to pay interest thereon.
7. Rights of the Railway to deal with tender : The authority for the acceptance of the tender will rest with
the Railway. It shall not be obligatory on the said authority to accept the lowest or any other tender
and no tenderer(s) shall demand any explanation for the cause of rejection of his/their tender nor
does the Railway undertake to assign reasons for declining to consider or reject any particular tender
or tenders.
9. If the tenderer(s) expires after the submission of his tender or after the acceptance of his tender, the
Railway shall deem such tender as cancelled. If a partner of a firm expires after the submission of their
tender or after the acceptance of their tender the Railway shall deem such tender as cancelled unless
the firm retains its character.
10. Income Tax Clearance Certificate : Since deleted.
12
Signature of tenderer/’s
12. Non compliance with any of the conditions set forth therein above is liable to result in the tender
being rejected.
13. Execution of Contract Documents : The successful tenderer(s) shall be required to execute an
agreement with the President of India acting through the Divisional Railway Manager (Works
account), Rajkot, Western Railway for carrying out the work according to “General conditions of
Contract “ Special conditions /Specifications annexed to this tender, and specification for work and
materials as laid down in the “ Work Hand Book Part III ” and Sanitary Works hand book of Western
Railway as amended /corrected with correction slip mentioned in the tender form (First Sheet).
14. Partnership deeds, Power of Attorney etc: The tenderer shall clearly specify whether the tender is
submitted on his own or on behalf of a partnership concern. If the tender is submitted on behalf of a
partnership concern, he should submit the certified copy of partnership deed along with the tender
and authorization to sign the tender documents on behalf of partnership firm. If these documents are
not enclosed along with tender documents, the tender will be treated as having been submitted by
individual signing the tender documents. The Railway will not be bound by any power of attorney
granted by the tenderer or by changes in the composition of the firm made subsequent to the
execution of the contract. It may, however recognize such power of attorney and changes after
obtaining proper legal advice, the cost of which will be chargeable to the contractor.
15. The tenderer whether a sole proprietor, a limited company or a partnership firm, if they want to act
through agent or individual partner/partners should submit along with the tender or at a later stage, a
power of attorney duly stamped and authenticated by a Notary Public, or by Magistrate in favour of the
specific person whether he/they be partner/partners of the firm or any other person specifically
authorizing him/them to submit the tender, sign the agreements, receive money, witness
measurements, sign measurement books, compromise , settle, relinquish any claim or claims preferred
by the firm and sign “ No Claim Certificate ” and refer all or any disputes to arbitration.
13
Signature of tenderer/’s
(b) Should a tenderer or contractor being an individual on the list of approved contractors have a
relative or relatives, or in the case of partnership firm or company of contractors one or more of his
shareholders or relatives of the shareholders employed in a Gazetted capacity in the Civil
Engineering Department of the Western Railway , the authority inviting tenders shall be informed
of the fact at the time of submission of tender , failing which the tender may be disqualified or if
such fact subsequently comes to light, the contract may be rescinded in accordance with the
provisions in Clause 62 of the General Conditions of Contract.
14
Signature of tenderer/’s
For works estimated to cost up to Rs. 1 2% of the estimated cost of the work
Crore.
For works estimated to cost more than Rs. 2 lakhs plus 1 / 2 % ( half percent) of
Rs. 1 Crore. the excess of the estimated cost of the
work beyond Rs. 1 crore subject to a
maximum of Rs. 1 crore.
2. Standing LSEM is dispensed forthwith. Separate EMD is to be submitted with each tender.
3. Security deposit will be at a flat rate of 5% of the contract value. (See para 4 of special conditions
of contract Part-I (B).
4. A new clause of performance guarantee in the form of bank guarantee for 5% of the contract
value has been introduced. ( See para 5 of Special conditions of contract Part-I(B).
15
Signature of tenderer/’s
1.1 In these Special Conditions of Contract the following terms shall have the meaning hereby assigned
to them except where the context otherwise requires:
(a) "General Condition of Contract" shall mean General Conditions of Contract –1998 as contained
in Western Railway, Engineering Department “Works Hand Book Part I & II “ as amended vide
correction slips mentioned in Tender form ) First Sheet. (b) Standard Specifications shall mean
"Western Railway specifications for materials and Works – 1984 As laid down in Western
Railway Works Hand Book Part III 1984) and Sanitary Works Hand book (1984), as amended
vide correction slips mentioned in Tender form (First sheet).
(c) Standard Schedule Items/Rates shall mean the Items/Rates in the Western Railway Standard
Schedule of Rates - 1993.
(d) All other terms shall have the same meaning as assigned to them in the General Conditions of
Contract and Standard Specifications.
1.2 Where there is any conflict in conditions/Specifications contained in various parts, order of
precedence will be as given below-
i. Any footnote given by the Railway in the schedule of quantities and rates.
ii. Description of item in the Schedule of Quantities and rates.
iii. Special Specifications.
iv. Additional Special Conditions/of Contract.
v. Standard Specifications.
vi. Special Conditions of Contract.
vii. General Conditions of Contract.
1.3 Where there is any conflict in the description, Unit, rate etc. of items based on schedule of rates, as
included in the “Schedule of items, Quantities and rate “ incorporated in the tender/Contract
document on the one hand and the Standard Schedule of Rates on the other hand, Standard
schedule of rates should prevail.
2.0 Every endeavor has been made to avoid any error which can materially affect the basis of the Tender
and it is understood that the Contractor has taken upon himself and provided for the risk of any error
which may be subsequently and shall make no subsequent claim on account thereof.
3. DEVIATIONS :
3.1 Unless specifically provided otherwise in the Tender, any and all exception which the Tenderer may
have to any of the Clauses of the Special Conditions of Contract or the additional special condition
of the contract as included in the tender shall be clearly stated. Such exceptions shall be listed in the
format, enclosed with the tender as annexure A titled “Schedule of deviation”. If the Tenderer has no
exceptions, the annexure shall be submitted with a “Nil” statement. If the tenderer does not include
the Annexure with the Tender it shall be conclusive evidence that the Special Conditions of Contract
and the Additional Special Conditions of Contract are entirely acceptable to the Tenderer.
3.2 Any Deviations from these Special Conditions of Contract and the Additional Special Conditions of
Contract if any stated by the Tenderer in his Tender or subsequently introduced by the Railway shall
be a part of the Contract only to such extent as have been explicitly accepted by the Railway and
incorporated
in the contract.
16
Signature of tenderer/’s
4.2 The Earnest money deposit of successful tenderer will be retained as a part of security deposit.
The amount over and above the Earnest money so retained to make up the full security deposit will
be recovered from each running bill at the rate of 10% of the bill amount till the full securit y deposit is
recovered. The balance to make up the full security deposit will be recovered only from the running
bills. Bank Guarantee, Fixed Deposit, Government securities etc. will not be accepted for Security
deposit.
5. PERFORMANCE GUARANTEE:
The procedure for obtaining performance guarantee is outlined below:-
(a) The successful bidder should give a performance guarantee amounting to 5% of the
contract value in any of the following forms:- .
(i) a deposit of cash
(ii) Irrevocable Bank guarantee.
(iii) Government Securities including State Loan Bonds at 5% below the market value.
(iv) Deposit receipts, pay orders, demand Drafts and guarantee Bonds. These
forms of Performance Guarantee could be either of the State Bank of India or
any of the Nationalized Banks.
(v) Guarantee Bonds executed or deposits receipts tendered by all Scheduled
Banks. (vi) a Deposit in the Post Office Saving Bank.
(vii) a Deposit in the National Savings Certificates.
(viii) Twelve years National Defence Certificates.
(ix) Ten years Defence Deposits.
(x) National Defence Bonds and
(xi) Unit Trust Certificates as 5 per cent below market value or at the face value whichever is
less. Also FDR in favour of Senior Finance Manager, Westren Railway, Rajkot. (free from any
encumbrance) may be accepted.
A performance Guarantee shall be submitted by the successful bidder after the letter of
acceptance has been issued but before signing of the agreement. The agreement should normally
b signed with 15 days after the issue LOA and the Performance Guarantee shall also be submitted
within this time limit. This guarantee shall be initially valid up to the stipulated date of completion
plus 60 days beyond that. In case the time for completion of work gets extended the contractor
shall get the validity of Performance guarantee extended to cover such extended time for
completion of work plus 60 days beyond that. In case the time for completion of work gets
extended the contractor shall get the validity of Performance Guarantee extended to cover such
extended time for completion of work plus 60 days.
(b) The Performance Guarantee (PG) shall be released after the physical completion of the
work based on the Completion Certificate issued by the competent authority stating that the
contractor has completed the work in all respects satisfactorily. The security deposit, however,
17
Signature of tenderer/’s
(c) Wherever the contract is rescinded, the security deposit shall be forfeited and the
Performance guarantee shall be en-cashed and the balance work shall be got done independently
without risk and cost of the failed contractor. The failed contractor shall be debarred from
participating in the tender for executing the balance work. If the failed contractor is a JV or
partnership firm, then every member/ partner of such a firm shall be debarred from participating in
the tender for the balance work either in his/her individual capacity or as a partner of any other
JV/Partnership firm.
(d) The engineer shall not make a claim under the Performance guarantee except for amounts
to which the President of India entitled under the contract (not with standing and / or without
prejudice to any other provisions in the contract agreement) in the event of:
i) Failure by the contractor to extended the validity of the Performance guarantee as described
herein above, in which even the engineer may claim the full amount of the Performance guarantee.
ii) Failure by the contractor to pay President of India any amount due, either as agreed by the
contractor or determined under any of the clauses/ conditions of the agreement, within 30 days of
the service of notice t this effect by engineer.
iii) The contract being determined or rescinded under provision of the GCC the Performance
guarantee shall be forfeited in full and shall be absolutely at the disposal of the President of India.
6. Renewal Of Deposits By Contractor:- The fixed deposit receipt submitted by the successful tender
as EMD will be converted into Security deposit and it shall be the responsibility of the tenderer to
advise, the Sr.Divisional Finance Manager, Rajkot for renewal and revalidation of the currency period
of the fixed deposit as required. Such advice by the Contractor shall be made well in advance so as to
reach
the Sr.Divisional Finance Manager, Mumbai Central not later than one month before the maturity of
the currency period. If the contractor, fails to do so, the loss of interest on the fixed deposits, if any
shall be solely on the contractor’s account and the railway shall not in any way be responsible for the
loss of interest suffered by the contractor.
7. Renewal of Bank Guarantee: - The Bank guarantee submitted towards performance Guarantee shall
be renewed from time to time as per the extension of contract granted to the contractor either on
Railway account or contractor account as otherwise the same will be deducted in full from the dues of
the contractor.
8. PLEA OF CUSTOM
The plea of custom prevailing will not on any account be permitted as an excuse for an infringement of
any of the conditions of the contract and/ or special conditions of contract.
18
Signature of tenderer/’s
The same charges will be recoverable for scrutiny of all such documents.
No power of attorney in favour of any individual person will be acceptable if it is irrevocable except when
it is in favour of bank.
In case where the power of attorney/partnership deed has not been executed in Hindi or English, the
true and authenticated copies of the translation of the same by advocate, authorised translators of
Courts and Licensed petition writers should be supplied by the contractor (s) while tendering for the
work.
10. AGREEMENT : All expenses in drawing up the agreement and the cost of stamp duty if any shall be
borne by the Western Railway Administration.
11. CHANGE IN ADDRESS : Any change in the address of the contractor shall be forthwith intimated in
writing to the Railway. The Railway will not be responsible for any loss/ inconvenience suffered by the
Contractor on account of his failure to comply with this.
12. INCOME TAX CLEARANCE CERTIFICATE :- The tenderer(s) if possible should also submit along
with their offer an authorized copy of the Income tax clearance certificate or a sworn affidavit duly
countersigned by the income tax office to the effect that he has/they have no taxable income.
13. MEASUREMENTS : All measurements, method of measurement, meaning and intent of specifications
and interpretation of Special conditions of contract given and made by the Railway or by the Engineer
on behalf of the Railway shall be final and binding and shall be considered as “Excepted Matter” in
terms of condition No. 63 of General Conditions of contract.
15. DISSOLUTION OF CONTRACTOR’S FIRM : If the contractor’s firm is dissolved due to death or
retirement of any partner or for any reason before duly completing the work or any part of it undertaken
by the Principal Agreement, the partners shall remain jointly severally and personally liable to complete
the whole work to the satisfaction of the Railway and to pay compensation for loss, sustained if any, by
the Railway due to such dissolution. The amount of such compensation shall be decided by the
Engineer and his decision in the matter shall be final and binding on the Tenderer(s)/Contractor(s).
16. HANDING OVER WORK SITE : The site of work shall be handed over to the contractor free of
obstruction according to progress of work. Contractor however, shall not have any claim whatsoever
against the Railway for any delay in the execution of the work, on this account except for extension of
the completion period under the General Conditions of Contract.
17. OCCUPATION AND USE OF RAILWAY LAND : Use of Railway land required by the Contractor(s) for
constructing temporary offices, quarters, hutments, etc., for the staff and for storing materials, etc. will
19
Signature of tenderer/’s
18. NOTICE TO PUBLIC BODIES : The Contractor(s) shall give to the municipality, police and other
authorities all notices that may be required by law and obtain all requisite licenses for temporary
obstructions, enclosures and pay all fees, taxes and charge which may be leviable on account of
his/their operations in executing the Contract. He/they should make good any damage to adjoining
premises whether public or private and supply and maintain any lights, etc. required at night.
19. TRESPASS: The contractor shall at all times be fully responsible for any damage or trespass
committed by his agents or workmen in carrying out the work, even if such trespass is authorized by
the Engineer.
20. ACCESS TO WORK SITE : Contractor shall have acquainted himself with the availability of roads and
their condition for transportation of materials, machinery, etc. to the work sites.
21. NIGHT WORK : Further to the provisions in the General Conditions of Contract regarding execution
of work between sunset and sunrise, if the Railway is satisfied that the work is not likely to be
completed in time except by resorting to night work, by a special order the Contractor shall carry out
the work at night without conferring any right on the Contractor for claiming for extra payment for
introducing night working. The decision of the Engineer in this regard will be final and binding on the
Contractor.
22. PROCUREMENT OF MACHINERY BY CONTRACTOR : It is entirely contractor’s responsibility and
liability to find and procure all the machinery, tools and plants and their spare parts that are required in
connection with execution of work. Delay in procurement of such items due to their non-availability or
import difficulties or any other cause, whatsoever shall not be taken as an excuse for slow progress or
non-performance of the work.
23. HIRE OF PLANTS, MACHINERY AND OTHER FACILITIE S: The contractor shall make his
arrangements for all plants and machinery, equipment’s, including spare parts, fuel and consumable
stores and all labour required to ensure efficient and methodical execution of the works. The rates
quoted and accepted shall be deemed to be inclusive of all charges for such items.
Without any commitment on the part of the Railway to do so, on the contractors request, the Railway
may give on hire, plant and machinery, other facilities , equipments and tools if available separable
with the Railway. The hire charges for such equipment will be as determine by the Railway on the
terms and condition specified by the Railway.
The hire charges will be payable from the day the plant is handed over to the day it is returned to be
Railway Administration. The Contractors shall enter into a separate agreement with the Railway in this
respect and the terms and conditions as per the agreement will be final and binding on the
contractor.
In the event of a plant or equipment or facility given on hire to the Contractor not being returned to the
Railway in a reasonably good working order/depreciation that it would have suffered for the period of
hire, the Railway reserves right to recover 1.5 times the cost of procurement at the time issue or latest
procurement rate in the division which ever is higher increased by 7% freight & 12.5% supervision
charges .
20
Signature of tenderer/’s
24. DAMAGE BY ACCIDENT/ FLOOD/ TIDES OR NATURAL CALAMITIES : The Contractor shall take
all precautions against damages from accidents, floods tides or other natural occurrences. He shall
not be entitled to any compensation for his tools, plants, materials, machines and other equipment
lost or damaged by any cause whatsoever. The Contractor shall be liable to make good the damage
to any structure or part of a structure, plant or material of every description belonging to the Railway
covered under the Contract, lost or damaged by him due to any cause during the course of execution
of work. The Railway Administration will not be liable to pay the contractor any charge for rectification
or repair to any damage which may have occurred from any cause what so ever.
25. DRAWINGS:
25.1 Figures and dimensions on Drawings shall supersede measurements by scale and Drawing
to a large scale shall take precedence over those to a smaller scale. Special dimensions or
directions in the specifications shall supersedes all else.
25.2 The Railway reserves the right to alter/modify the drawings/designs to suit site conditions. If
due to changes in drawings or designs, there is any increase/decrees in quantities in the items of
schedule, payment shall be made only for the actual quantities executed at the accepted rates. If
there is sufficient ground for granting extension to the completion period on this account, the Railway
will consider such request on the merit of each individual case. Such circumstances shall in no way a
fact or vitiate the contract or alter the character thereof or entitle the contractor to damages or
compensation therefore.
26.2 The work shall be set out by the contractor to the satisfaction of the Engineer or his
representative but his approval thereto shall not ,nor shall his joining with the Contractor in setting out
the work, relieve the Contractor from his entire and sole responsibility thereof.
26.3 Maintenance of Layout: The Contractor shall also provide, fix and be responsible for the
maintenance of all stakes, templates, profiles, levels, marks, points etc. and must take all necessary
precaution to prevent these being removed, altered or disturbed and will be held responsible for the
consequence of such removal, alterations or disturbances should the same take place and for their
efficient reinstatement.
21
Signature of tenderer/’s
27.2 Wastage of or damage to such materials in any manner shall be avoided. If any material issued
become surplus to the requirement and not returned in good condition immediately after completion of
the work or if any quantity of materials supplied by the Railway is consumed in excess or wasted or
damaged or lost or not satisfactorily accounted for recovery shall be made for this material from the
contractor towards the cost of material at double the cost of procurement at the time issue or latest
procurement rate in the division which ever is higher increased by 7% freight & 12.5% supervision
charges .
27.3 Maximum of percentage of cut pieces which can be returned by the contractor without any
deduction should not be more than 5% of the quantity issued when full length bars are supplied . Any
excess over this quantity of cut pieces, deduction at the rate of 50% of the recovery rate as worked out
in above sub para will be made.
27.4 In case the quantity of cement, steel or any other items issued by Railway and actually used in
the work is less than the quantity specified to be used, the cost of cement, steel or any other such
items not so used shall also be recovered from the contractor at the rate stipulated in above Clause.
This action will be without prejudice to the rights of the Railway to take action against the Contractor
under the Contract for not doing the work according to the prescribed specifications and approved
Drawing.
27.5 In case of excess usage of Railway materials than those prescribed in SOR/ Specifications in
tender documents/ works hand book part-III, recovery for excess usage of Railway materials be made
at double the cost of procurement at the time issue or latest procurement rate in the division which
ever is higher increased by 7% freight & 12.5% supervision charges .
28 PRODUCTION OF TEST CERTIFICATES : The contractor shall have to produce Test Certificates for
any items of material procured by him for use in the work as may be called for by the Engineer or his
representative to establish that the materials conform to the specification for the works. The Contractor
shall produce Test Certificates issued by an authority acceptable to the Engineer in regard to the
relevant properties of high tensile steel wires, reinforcement steel or structural steel (as supplied and
used by the Contractor) including the country name of manufacturer) .
29 RATES:
29.1 The rates entered in the accepted Schedule of Quantities and Rates, are intended to provide for
works duly and properly completed as per contract conditions and specifications for the whole of the
work as described under Scope and Details of work.
29.2 The contractor should note that the rates quoted shall accept as otherwise provided in contact
embrace all operations necessary for the satisfactory completion of the work to finish and shall include
all charges for handling, loading, transport, lead, lift, labour housing, sanitation, materials, machinery,
tools and plants, fuel, electric power, workshop facilities, security, lighting etc. all other expenses of
every kind.
29.3 The rates as given for the different items of work are deemed to be workable rates for the
respective item of work without being dependent in any manner whatsoever on the quantity specified
22
Signature of tenderer/’s
29.4 The rates quoted shall take into account the precautions and special arrangements necessary for
execution of works under traffic conditions, with least disruption to traffic. No extra payment shall be
admissible on this account under any circumstances. Railway will however, arrange for blocks of traffic
during work only to the extent as considered sufficient for the works by the Railways. The Contractor
will not be entitled for any compensation, if there be any delay in arranging these blocks or the block
period be of shorter duration as considered by the Contractor.
29.5 Service Roads: The contractor will be permitted to make use of the service roads already existing
in possession of the Railway. If construction of any additional roads within Railway premises is
considered necessary and agreed to at contractors request ,the contractor will be required to make
them at his own cost and maintain them till the work is completed. Contractor shall construct any
service roads, required outside the Railway boundary, at his own cost. Railway reserves the right to
make use of service roads, made by the contractor, as and when necessary without any additional
payment to the contractor. Any damages caused to the existing roads, due to use by contractor, shall
have to be made good by the contractor, at his own cost.
30 PAYMENT OF ROYALTY CHARGES : All taxes, royalty charges, etc. of whatever nature in connection
with the work including extraction and supply of rubble stone/stone ballast/sand/moorum/earth or
any other material used on the work shall have to be borne by the Contractor.
The contractor would be required to furnish the name,with complete bio-data including the work
experience of the Engineer/Supervisor to the Divisional/Executive Engineer in charge of work. For his
approval. The technical supervisor given above shall be available at site during the execution of the
work to ensure quality, quantity of work as also ensure safety at work site and that of the workers and
whenever required by the Engineer in charge to take instructions. In case the contractor fails to
employ the technical supervisor as aforesaid, a sum of Rs. 10,000/- per Engineer/Supervisor per
month will be recovered from the contractor’s dues . The decision of Engineer-in – charge as to
23
Signature of tenderer/’s
32.2 If the contractor fails to appoint a suitable agent as directed by the Railway Engineer, the latter
shall have full power to suspend the execution of works, until such date a suitable agent is appointed
and the contractor shall be held responsible for the delay so caused to this works. The successful
tenderer shall state the name of the technical supervisor along with him technical qualification, while it
may not be necessary for the technical supervisor to reside at site, he should be available at the site of
work during the working part of the day. Normally no change in the technical personnel during the
period of construction would be acceptable to the Railway except under very special circumstances.
The Railway reserves the right to stop the work in case the technical supervisor of tenderer is not
available.
33 COMPLETION CERTIFICATE :
33.1 The work shall not be considered to have been completed in accordance with the terms of
contract, until the Engineer incharge shall have issued a certificate in writing to that effect. No approval
of materials or workmanship or approval of any kind of work during progress or execution shall bind the
Engineer incharge or in any way prevent him from rejecting whole or a part of the work. The Engineer
incharge may with hold the issuance of the completion certificate, till such time such alteration
modifications and / or reconstruction have been carried out ordered by him. All such alterations,
modifications and / or reconstruction shall be carried out by the contractor at his own cost.
33.2 After the work is completed, the contractor/s shall give notice of such completion to the Engineer-
in-charge and on receipt of such notice the Engineer-in-charge shall have the work inspected and if
there is no defect in the works ,shall furnish the contractor/s with a certificate indicating the date of
completion. However, if there are any defects which in the opinion of the Engineer-in-charge are
rectifiable he shall inform the contractor/s the defects noticed. The contractor/s after rectification of
such defects shall notify the Engineer-in-charge and then the Engineer-in-charge on his part shall have
it inspected again and issue the necessary completion certificate if the defects are rectified to his
satisfaction, and if not be shall inform the contractor/s indicating defects yet to be rectified. The time
cycle as above, shall continue.
33.3 In case defects noticed by the Engineer-in-charge, or representative which in his opinion are not
rectifiable but otherwise acceptable at reduced payment, work shall be treated as completed. In such
case completion certificate shall be issued by the Engineer-in-charge within 30 days indicating the
unrectifiable defects for which specified reduction in payment is being made by him.
34 DEDUCTION FOR TAXES:
34.1 In respect of works, the contract value of which is more than Rs. 5000/- each, a deduction of 2%
on the gross payment from each of the contractor’s bills shall be made in terms of Section 194 (c) of
the Income Tax Act of 1961. Surcharge on Income Tax if applicable will also be deducted as per the
prevailing rates.
34.2 The Railway will deduct sales tax if leviable in a particular state where the work is going on, the
gross amount of each bill while making payment to the contractor(s). The recovery shall be governed
as per the guide lines & rates prescribed by the concerned State Government..
34.3 All taxes as prescribed by Central or State Government from time to time shall be applicable.
24
Signature of tenderer/’s
35 EXCISE DUTY OR ANY OTHER TAXES/DUTIES : The contractor shall bear full excise duty, sales tax
and / or any other taxes/ duties levied by State Government and / or Central Government/Local bodies
from time to time. This would be entirely a matter between the contractor and the State / Central
Government./Local bodies. No claim, what so ever, on this account shall be entertained by Railways.
36 ROAD TAX CHARGES : Road Tax/Charges levied by Government for movement of vehicles of
contractor, used in transportation, shall be borne by the contractor and no re-imbursement on this
account will be made by the Railways.
38 SUPPLY OF WATER
38.1 The contractor shall be responsible for the arrangements to obtain water necessary for his
laborers engaged in execution of work. No arrangement will be made by the Railway Administration for
supplying water to the contractor either for drinking purpose or execution of work. Rates quoted shall
include the cost of arranging water with all lead and lift.
38.2 Water available locally in wells, creeks or nallahs may be brackish water at some locations. It
should be noted that the brackish water shall not be used in all classes of masonry, reinforced and
plain cement concrete work. In addition, water used for the above works shall be free from earthy,
vegetable or organic matter, oils, acids and alkaline substances in solution or in suspension and
impurities and shall be fit for drinking. Contractor shall have to arrange the suitable for successful
execution of the work.
39 SUPPLY OF ELECTRICITY :
39.1 The contractor has to make his own arrangements with the local Electricity body for power supply
required for carrying out the work including lighting arrangements. The work may be required to be
carried out round the clock, if it is considered necessary by Engineer due either to requirement of the
work or for speeding up the progress of the work so as to adhere to the target date of completion of all
the items of the work.
39.2 The Contractor should also keep sufficient standby generators ready so that the progress of work
is not affected or stopped in the event of interruption in the power supply due to power cut or any other
failure. All these arrangements at site including those required for lighting will have to be done by the
Contractor at his own cost. The rates quoted by the Contractor shall be deemed to include cost of
providing all the above arrangements including standby generators. The Contractor shall however,
be responsible for ensuring that none of the statutory labours laws or electricity acts are infringed.
40 EMERGENCY WORKS : In the event of any accident or failure occurring in the execution of work/
arising out of it which in the opinion of the Engineer requires immediate attention, the Railway may
bring its own workmen or other agency/agencies to execute or partly execute the necessary work or
carry out repairs if the Engineer-in-charge considers that the contractor(s) is/are not in a position to do
so in time without giving any notice and charge the cost thereof, to be determined by the Engineer-in-
charge, to the contractor.
25
Signature of tenderer/’s
44 TIME IS THE ESSENCE OF CONTRACT : Time being the essence of contract all the works are
required to be completed in all respect as stipulated by the Railway within the completion date.
Progress shall be maintained strictly in accordance with program given by the Engineer-in-charge from
time to time.
46 CUTTING/UP ROOTING OF TREES : No extra rate shall be paid for cutting or up-rooting trees but the
contractor would be authorized to take away the tree observing the forest laws of the land.
47 ACCEPTED RATES : The rates quoted by tenderer and accepted by the Railway Administration shall
hold good till the completion of the work and no additional, individual claim shall be admissible on
account of fluctuation in market rates, increase in taxes any other levies/tolls etc.
49.2 It is the responsibility of the Contractor to ensure safe loading, transportation and unloading of
materials and equipment etc. Any loss or damage caused to adjacent Railway property will have to be
made good by the contractor at his/their own cost, failing which recoveries shall be effected from the
running bill of the contractor as per the Clause No. 13(iii) of the General Conditions of Contract.
49.3 The liability arising out of accidents, if any, to persons will be met by the contractors and the
Railway will not be responsible for any damage or compensation thereof. The contractor shall follow
the provisions laid down in Contract Labour Act, 1972.
49.4 The contractor shall be entirely responsible for ensuring safety of his labour, vehicles, plant or
equipment while working along or near the track and highways and shall programme his working so as
not to interfere with the movement of trains and road traffic. No extra payment shall be allowed to the
contractor for all safety precautions to be observed during the executionof the work. The cost of all
such precautions shall be deemed to be included in the rates for all items of the schedule.
26
Signature of tenderer/’s
50.2 It shall be obligatory for the tenderer to submit his programme of work and time schedule as to
how he proposed to complete the work within stipulated time.
50.3 Within 10 days of the acceptance of the tender and before the work is commenced, the contractor
shall have to submit a detailed programme for each major element of the work for approval of the
Engineer. The programme shall clearly provide for and indicate the time required for the preliminaries
before starting the work and shall indicate the dates of commencement and completion of the various
sections of the work.
50.4 The agreement or the approval of the programme by the Engineer shall not relieve the contractor
of any of his responsibilities to complete the whole by the prescribed time.
50.5 If the work does not commence within specified date of starting or if at the subsequent time the
rate of execution falls below the specific programme as indicated above, the Railway Administration
will have the power to determine the end of the contract at any stage without incurring any liability on
the part of the Railway Administration for any sort of compensation for the money invested by the
contractor (s) or the loss incurred by him/them due to such termination of the contract. In all cases of
incomplete work, either by termination of contract by the Railway Administration under consideration
stated above or due to failure on the part of contractor(s) to complete the work within stipulated date of
completion of Agreement the Railway shall be entitled to :-
i) Forfeit the whole of such portion of the security deposit as it may consider
ii) Encash the bank guarantee furnished as Performance Guarantee.
iii) Execute the balance work independently without risk and cost of the original contractor. The original
contractor however will be debarred from participating in the tender for executing the balance work.
In case the failed contractor is a Joint Venture or a partnership firm , then each member / partner of
such firm would be debarred from participating in the tender for the balance work either in his/her
individual capacity or as a partner of any other Joint venture/ partnership firm. The contractor cannot
make any legal claims against the same.
51.2 It shall be ensured that the works are carried out according to the agreed programme and no
change are made except with the prior approval or at the instance of the Engineer.
27
Signature of tenderer/’s
52.3 To cover up monsoon period, the maintenance period will be extended in cases when required
and contractoshall remain responsible for maintenance for this extended period also. The contractor
shall make good and remedy at his own expense within such period as may be stipulated by the
Engineer, any defect which may develop or may be before the expiry of this period and intimation of
which has been sent to the contractor within seven days of the expiry of the said period by a letter, sent
by hand deliveryor by registered post. In case the contractor fails to make adequatearrangements to
rectify the defects within seven days of the receipt of such notices, the Engineer without further notice
may make his own arrangement to rectify the defects and the cost of such rectification shall be
recovered from the Security Deposit of the contractor or from any other money due to the contractor
under this or any other contract.
(i) Individual NS items in contracts shall be operated with variation of plus or Minus 25% and
payment would be made as per the agreement rate. For this, no finance concurrence would be
required.
(ii) In case of increase in quantity of an individual item by more than 25% of the agreement
quantity is considered as unavoidable, the same shall be got executed by floating a fresh
tender. If floating a fresh tender is considered not practicable, negotiations may be held with
the existing contractor for arriving at reasonable rates for additional quantities in excess of
125% of agreement quantity.
(iii) The limit for varying quantities for minor value items shall be 100% ( as against 25%
prescribed for other items) . A minor value item for this purpose is defined as an item whose
original agreement value is less than 1% of the total original agreement value.
(iv) No such quantity variation limit shall apply for foundation items.
(v) As far as SOR items are concerned, the limit of 25% would apply to the value of SOR
schedule as a whole and not on individual SOR items. However, in case of NS items, the limit
of 25% would apply on the individual items irrespective of manner of quoting the rate ( single
percentage rate or individual item rate).
54.2 The contractor shall not be entitled to ask for reference to arbitration before the completion of
the work assigned to him under this contract.
54.3 The contractor shall seek reference to arbitration to settle the disputes only once within the
ambit of the above conditions.
54.4 These special conditions shall prevail over existing clauses 63 and 64 of General Conditions of
Contract.
55. JURISDICTION OF COURTS : If any dispute arises between the parties with respect to this contract,
any application or suit shall be instituted only in the court within the local limits of whose jurisdiction,
the Western Railway Divisional Headquarters Office is situated and both the parties shall be bound by
this clause.
28
Signature of tenderer/’s
56.2 Site Order Register: The Contractor/s shall promptly acknowledge by putting his signature in the
site order against any order given therein by the Engineer or his representative or his superior
officers and comply with them. The Compliance shall be reported by the Contractor/s to the Engineer
in good time so that it can be checked.
56.3 Labour Register: This register will be maintained to show daily strength of labour in different
categories employed by the Contractor/s.
56.4 LOG book of events: All events are required to be chronologically logged in this book shift wise
and date wise.
56.6 Any other register considered necessary by the Engineer, shall be maintained at site in which
the representative of the Engineer and the Contractor will have to sign. The register proforma, charts,
etc. will be property of the Railway.
57.1 Price variation clause (PVC) shall be applicable for tenders of value more than Rs. 50 lakhs
irrespective of the contract completion period and PVC shall not be applicable to tenders of value less
than Rs. 50 lakhs.
57.2 No cognizance shall be given for any sort of fluctuation in taxes and other market conditions etc.
for any individual item for the purpose of making adjustment in payments. The contract shall
however, be overned by the General price variation clause as under, in case the same is applicable
in terms of clause 55.1 above.
57.3 The rates quoted by tenderer and accepted by the Railway Administration shall hold good till
the completion of the work and no additional, individual claim shall be admissible on account of
fluctuation in market rates, increase in taxes/any other levies/tools etc. except that payment/recovery
for overall market situation shall be made as per price variation clause given below:
57.4 Adjustment for variation in prices of materials, labour, fuel, explosives/detonators shall be
determined in the manner prescribed below.
29
Signature of tenderer/’s
The percentages of various components in a contract on which variation in prices shall be admissible
are as under :
b) The amount of variation in prices in the several components (labour, material etc.) shall be
worked out by the following formula :
i) L= R x (I - Io) x P
Io 100
ii) M = R x (W – Wo) x Q
Wo 100
iii) U = R x (F – Fo) x Z
Fo 100
iv) X = R x (E – Eo) x S
Eo 100
v) N = R x (D – Do) x T
Do 100
L - Amount of price variation in labour.
30
Signature of tenderer/’s
NOTE: The index number for the base period will be the index number as obtained for the month of
opening of the tender and the quarter will commence fromthe month following the month of opening of
tender. In case negotiations forrates were conducted at the tender stage, date of conducting the
negotiations would be taken to be the date of opening for the purpose of this clause.
Where
Mc= Amount of price variation in material (Cement).
R = Value of Cement supplied by Contractor as per on account bill in the quarter under
31
Signature of tenderer/’s
B) STEEL
A price of Steel is based on SAIL’s ex-works price plus Excise Duty thereof. Henceforth, the formula
for calculating the amount of variation on account of variation in prices of Steel would be as indicated
below.
Ms = Q (Bs-Bso) Where
Ms = Amount of price variation in steel payable/recoverable
Q = Weight of steel in tones supplied by the contractor as per the on account bill for the month
under consideration.
Bs = SAIL’s (Steel Authority of India Limited) ex-works price plus Excise Duty thereof (in rupees per
tonne) for the relevant category of steel supplied by the contractor as prevailing on the first day of the
month in which the steel was purchased by the contractor (or) as prevailing on the first day of the
month in which steel was brought to the site by the contractor whichever is lower.
Bso = SAIL’s ex-works price plus Excise Duty thereof (in rupees per tonne) for
the relevant category of steel supplied by the contractor as prevailing on the first day of the month in
which the tender was opened.
NOTE:
(i) Relevant categories of steel for the purpose of operating the above price variation formula based on
SAIL’s ex-works price plus Excise Duty thereof are as under:
57.7 The demands for escalation of the cost will be allowed on the basis of provisional indices made
available by the Reserve Bank of India. Any adjustment, required to be done, based on the finally
published indices will be made as and when become available.
57.8 The adjustment for variation in prices, if required shall be made once every quarter in the on
account payments. If more than one on account payment is made to the contractor in a quarter the
adjustment, if required, shall be made in each bill.
32
Signature of tenderer/’s
57.8.2 Price variation shall not be paid for the extensions of periods completion granted under any
clause of General Condition of Contract.
33
Signature of tenderer/’s
Debris to be disposed from upper floors shall be brought down by head leading or through hoists
installed by contractor and shall not be thrown from above the floors to the ground below.
Para 63.1- No change in clauses (i) to (xiii) and in para (xiii) (A) and (B) sub clauses (a) to (e). The
para after (e) may be read as under.
Then and in any of the said cases, the Engineer on behalf of the Railway may serve he Contractor with
a notice (Performa at Annexure-III) in writing to that effect and if the contractor does not within seven
days after the delivery to him of such notice proceed to make good his default in so far as the same is
capable of being made good and carry on the work or comply with such directions as aforesaid to the
entire satisfaction of the engineer, the railway shall be entitled after giving 48 hour notice ( Performa at
Anexure (IV) in writing under the hand of the engineer to rescind the contract as a whole or in part or
parts (as may be specified in such notice). The sentence “ and adopt either or both of the following
courses read with provision (x) and (y) stands deleted.
Para 63.2 :- No change in sub clauses (a) and (b). The following line should be added at the end of
subclause (2) (c). The legitimate amount due to the contractor after making necessary deductions and
certified by the engineer should be released expeditiously. Sub Clause (d) stands deleted.
64. Arbitration clause under para 63 & 64 of GCC amended vide correction slip No.3 is reproduced below
:-
CLAUSE 63 & 64 OF GENERAL CONDITIONS OF CONTRACT (GCC) BEEN REVISED IN VIEW
OF THE PROMULGATION OF THE ARBITRATION CONCILIATION ORIDINANCE 1996.REVISED
ARBITRATION CLAUSE IS AS FOLLOWS: -
63. Matters finally determined by the Railway – All disputes and differences of any kind whatsoever
arising out of or in connection with the contract, whether during the progress of the work or after its
completion and whether before or after the determination of the contract, shall be referred by the
contractor to the GM and the GM shall within 120 days after receipt of the contractor’s representation
make and notify decisions on all matters referred to by the contractor in writing provided that matters
for which provision has been made in clauses 8, 18, 22(5), 39, 43(2), 45(a), 55, 55-A(5), 57, 57A,61(1),
61(2) and 62(1) to (xiii) (B) of General Conditions of contract or in any clause of the special conditions
of the contract shall be deemed as ‘excepted matters’ (matters not arbitrable) and decisions of the
Railway authority, thereon shall be final and binding on the contractor; provided further that ‘excepted
matters’ shall stand specifically excluded from the purview of the arbitration clause.
34
Signature of tenderer/’s
35
Signature of tenderer/’s
36
Signature of tenderer/’s
ANNEXURE - A
STATEMENT OF DEVIATION
(Pl .refer Cl.3 of special conditions part-I (General) of the Tender documents)
37
Signature of tenderer/’s
SAFETY RULES
(i) The road vehicles and drivers will ply only between sunrise and sunset.
(ii) Nominated vehicles and drivers will be utilized for work in the presence of at least one flagman
and one supervisor certified for such work.
(iii) The vehicles shall ply 6m. clear of track. Any movement/work at less than 6m and upto minimum
3.5 clear of track centre, shall be done only in the presence of railway employee authorised by the
Engineer-incharge. No part of the road ;vehicle will be allowed at less than 3.5m from track centre .
Cost of such railway employee shall be borne by the railway.
(iv) The contractor shall remain fully responsible for ensuring safety & in case of any accident, shall
bear cost of all damages to this equipment & men and also damages to railway and its passengers.
(v) Semi permanent fencing as approved by the Railway Engineer should be provided by the
contractor at his own cost along the running line at a distance of 3.5 metres from the centerline of the
nearest track at work sites where vehicles/machineries are likely to ply close to the track. This fencing
should remain in position till the vehicles/machinery are required to work adjacent to running line.
Engineer-inch rage may impose any other condition necessary for a particular work or site.
2. Suitable scaffolds should be provided for workmen for all works that cannot safely be done from the
ground or from solid construction except for such short period work as can be done safely from
ladders. when a ladder is used an extra labour shall be engaged for holding the ladder and if the ladder
is used for carrying materials as well, suitable foot holds and hand-holds shall be provided on the
ladder and the ladder shall be given an inclination not steeper than 1/4 to 1 (1/4 horizontal to one
vertical).
3. Scaffolding or staging more than 3.5 meters above the ground or floor, swung or suspended from an
overhead support or erected with stationary support shall have a guard rail properly attached bolted,
braced and otherwise secured at least 1 meter high above the floor or platform or staging and
extending along the entire length thereof with only such opening as may be necessary for the delivery
of materials. Such scaffolding or staging shall be so fastened as to prevent it from swaying from the
building or structure.
4. Working platform gangways and stairways should be so constructed that they should not sag unduly
or unequally, and where the height of the platform or the gangway or the stairway is more than 3.5
meters above ground level or floor level, they should be closely boarded, should have adequate width
and should be suitably fastened as described in the para above.
38
Signature of tenderer/’s
6. Demolition: Before any demolition is commenced and also during the process of the work:
a) All roads and open areas adjacent to the work site shall either be closed or suitably protected;
b) No electric cable or apparatus which is liable to be a source of danger over a cable or apparatus used
by the operator shall remain electrically charged;
c) All practical steps shall be taken to prevent danger to persons employed from risk of fire or explosion
or flooding;
d) No floor, roof or other part of the building shall be so overloaded with debris or materials as to render
it unsafe.
7. All necessary personal safety equipment as considered adequate by the Engineer should be kept
available for the use of the persons employed on the site and maintained in a condition suitable for
immediate use, and the Contractor should take adequate steps to ensure proper use of equipment by
those concerned.
In addition,
a) workers employed on mixing asphalted materials, cement and lime mortar shall be provided with
protective goggle.
b) workers engaged in white-washing and mixing or stacking of cement bags or any materials which is
injurious to the eyes shall be provided with protective goggles;
c) workers engaged in welding works shall be provided with protective goggles;
d) stone breakers shall be provided with protective goggles and protective clothing and seated at
sufficiently safe intervals.
8. The contractor shall submit the methodology proposed to be adopted for execution of works for approval
of the Railway Engineer with a view to ensure safety of trains, passengers & workers and he shall also
ensure the methods and arrangements are actually available at site before start of work and contractor’s
supervisors and workers have clearly understood the safety aspects and requirements to be adopted /
followed while executing the work.
9. The contractor shall maintain an assurance register at each site, which shall be got signed by both
Railway supervisor as well as contractor’s supervisor in token of their having understood the safety
precautions to be observed at site.
39
Signature of tenderer/’s
ANNEXURE - C
In consideration of the President of India (hereinafter called “the Government”) having agreed to accept
from _________________ (hereinafter called “the said Contractor/s), under the terms and conditions of an
Agreement/Acceptance letter dated ___________ made __________ between _____________________
and _______________________ (hereinafter called “ the said Agreement”) the Performance Guarantee for
the due fulfillment by the Contractor/s of the terms and conditions in the said Agreement on production of
Bank Guarantee for Rs ______________________ (Rs. ________________________________ only) we,
__________________________ (indicate the name of the Bank hereinafter referred to as “the Bank) at the
request of_______________________ contractor/s do hereby undertake to pay the government an amount
not exceeding Rs. ___________ against any loss or damage caused to or suffered by or would be caused
to or suffered by the Government by reason of any branch by the said Contractor (s) of any of the terms or
conditions contained in the said Agreement.
2. We _________________________ (indicate the name of the Bank) do hereby undertake to pay the
amounts due and payable under this guarantee without any demur, merely on demand from the
Government stating that the amount claimed is by way of loss or damage caused to or suffered by the
Government by reason of breach by the said contractor/s of any of the terms or conditions contained in the
said agreement or by reason of the contractor/s failure to perform the Agreement, any such demand made
on the bank shall be conclusive as regards the amount due and payable to the Bank under this guarantee.
However, our liability under this guarantee shall be restricted to an amount not exceeding Rs.
_________________.
3. We undertake to pay to the Government any money so demanded notwithstanding any dispute or
disputes raised by the contractor(s)/supplier (s) in any suit or proceeding pending before any Court or
Tribunal relating thereto our liability under this present being absolute any unequivocal. The payment so
made by us under this bond shall be a valid discharge of our liability for payment there under and the
contractor (s)/suppliers (s) shall have no __________ against us for making such payment.
4. We, ________________________________ (indicate the name of the bank) further agree that the
guarantee herein contained shall remain in full force and effect during the period that would be taken for the
performance of the said Agreement, including Maintenance/Warrantee Period, and that it shall continue to
be enforceable till the dues of the Government under or by virtue of the said agreement have been fully
paid and its claims satisfied or discharged or till _____________________________office/Department)
Ministry of Railway certifies that the terms and conditions of the Agreement have been fully and property
carried out by the said Contractor (s) and accordingly discharged this guarantee, unless a demand or claim
under this guarantee is made on us in writing on or before the
________________________________________ we shall discharged from all liability under this
guarantee thereafter.
40
Signature of tenderer/’s
5. We, ________________________________ (indicate the name of the Bank) further agree with the
Government that the Government shall have the fullest liberty without our consent and without affecting in
any manner our obligations hereunder to vary any of the terms and conditions of the said agreement or to
extend time of performance by the said contractor (s) from time to time or to postpone from any time or
from time to time any of the powers exercisable by the Government against the said contract and to
forebear or enforce any of the terms and conditions relating to the said agreement and we shall not be
relieved from our liability by reason of any such variation, or extension being granted to the contractor/s or
for any forbearance act or omission on the part of the Government or indulgence by the Government to the
said contractor(s) or such any matter or thing whatsoever which under the law relating to sureties would,
but for this provision, have effect of so relieving us.
6. This Guarantee will not be discharged due to the change in the constitution of the bank or the Contractor
(s) Supplier (s).
7. We, __________________________ (indicate the name of Bank) undertake not to revoke this
guarantee during its currency except with the previous consent of the Government in writing.
For ______________________
(indicate the name of Bank)
41
Signature of tenderer/’s
I/WE THE UNDER SIGNEG HEREBY SOLEMNLY DECLARE AND CERTIFY THAT I
/WE DO NOT HAVE ANY OF OUR RELATIVE/RELATIVES EMPLOYED IN THE
WESTERN RAILWAY (ENGINEERING DEPARTMENT) EXCEPT THE NAMES
MENTIONED HEREIN UNDER :
1………………..
2………………..
3………………..
AND SO ON ………….
42
Signature of tenderer/’s
PROFORMA-A-I
43
Signature of tenderer/’s
DETAILS OF ALL CIVIL ENGINEERING WORKS CARRIED OUT DURING PAST FIVE YEARS
PROFORMA-III
DETAILS (PLANTS & MACHINERY)
Sr. No. Particular No. of Unit Kind Make Capacity Age and Remarks
of conditions (give present
equipment location if
already
owned if to
be
purchased
give date of
placing order
and tentative
date of
receipt.
44
Signature of tenderer/’s
PROFORMA - IV
PROFORMA-V
45
Signature of tenderer/’s
The Building and other Constructions Workers’ Welfare Cess Rules, 1996.
(As per Railway Boards letter No. 2008/CE-I/CT/6 dtd. 9.07.08 )
The tenderer for carrying out nay construction work in Gujarat must got themselves
registered from the Registering Officer under Section-7 of the Building and Other
Construction Workers’ Act, 1996 and rules made thereto by the Gujarat Government and
submit certificate of Registration issued from the Registering Officer of the Gujarat
Government (Labour Deptt.). For enactment of this Act, the tenderer shall be required to pay
cess @1% of cost of construction work to be deducted from each bill. Cost of material shall
be outside the purview of cess, when supplied under a separate schedule item.
46
Signature of tenderer/’s
Name of Work: Providing ballast wall from KM 853/6 to 854/1 between KNLS - MDPR & KM
853/13 to 853/13 to 854/1 between KNLS - MTKD at. ( Total length 1200 Mt.)
47
Signature of tenderer/’s
I /we offer to carry out the above work __________ % (in figures )
________________________________________% (in words) below/ above the western
Railway schedule of rates part I and II as applicable to Rajkot Division .
Contractor's Address:
2 The contractor should visit the site of work prior to starting of work.
3 All the precautionery measures should be maintained by the contractor during the
execution of work and no claim for any damage or casuly will be born by the Railway.
6 The work should be carried out under the direct supervision and instruction of engineer
incharge.
7 The site of work should be neat and cleaned after completion of work.
48
Signature of tenderer/’s
I/We offer to carry out the above work at the rate quoted in column no. 5 and 6
Place: Tenderer’s Signature:
Date: Tenderer’s name :
Tenderer’s address:
49
Signature of tenderer/’s
50
Signature of tenderer/’s