Professional Documents
Culture Documents
663--{)94
The Reconstruction of
the Exxon Valdez
D. C. McNeill, Member, D. Malmquist,Visitor,
D. Walter, Member, D. Grothen, Visitor,
K. Londot, Visitor, NASSCO, San Diego,
California
When she went aground on March 24th, 1989, The normal evolu ti on of a bid proposal for a
substantial damage was sustained by the ship. repair job like the Exxon Valdez begins with a review of
663
Fig. 4 Area of damage
301m(98T) ~
OUTLINE OF
GRAVING DOCK .----183m (600')
Fig. 3 Rock embedded in hull of the Valdez
p··•
.. ·- ..
the damage repo rts. The magnitude of the work was
replacing extensive steel damage as shown in Figures 1,
TUNNEL I
2, and 3. Tll'INEL 2 44 '
tt-:-===:::::~-:-:':!:::==:!:=:::-:-7~:::=~~==
51m (166') SHORE ~ 1:zi~ (400') ..
(TYP)
The first task was to define the scope of the work
to be performed. The exte nt of the damage required Fig. 5 Two tunnel approach to reconstruction
.... ·.
Fig. 7 Tunnel No. 2
- (PORT) (STBD) - - -
d
'o:~:.:~~t~~n;-
1
\~
6
T""" ![ST
Outfit Planning
Fig. 8 Original key event schedule
The original damage survey reports included
The first reschedule was necessary to reflect the marked-up drawings of outfitting items detailing the
actual arrival date of the ship. During the voyage from extent of the work to be performed. The Outfitting
Alaska to San Diego the bottom shell plates peeled Planner developed an integrated work package
back from the longitudinals and web frames. These containing all the necessary information to organize,
plates were hanging down from the bottom of the ship install, monitor, and inspect the outfitting components
and they prevented entry of the ship into San Diego Bay attached to each new hull block. Typical outfitting
due to limited water depth. The plates would have to included ballast pipes, ladders and gratings, and sluice
be removed before the ship could be towed into valves. A pictorial representation of the work package
NASSCO. In addition, Exxon was required to prove to contents is shown in Figure 9.
WORKPACKAGE TITLE
SCHEDULE.
REFERENCES,
REQUIREMENTS
WORK DEFINITION
INSPECTION/
DISCREPANCY
SIGN-OFF SHEET
BUDGET CRITERIA
SHEET
Fig. 10 Strategy for removal and re-installation of five
MATERIAL LIST blocks in Tunnel No. 1
LOWER STRUT
With knowledge of the design features and the
operating constraints of the material handling system,
the more important constraints were as follows:
SHEAR BRACKET
Initial Prouosals
Fig. 12 Installation of shear brackets
Being aware of the design features and operating
constraints, several ideas for material handling systems
were proposed, one of which was an elaborate system of
hydraulic jacks, multi-ton rollers, and 427 meters (1,400
The primary purpose of the shear brackets was feet) of track. Also, consideration was given to a system
to provide a load path for the ship's weight to the of air or water bearings to convey the steel units fore
docking blocks. Due to the weight of these brackets and aft. Both these systems were short lived as
(approximately one ton), and the difficulty associated principal material handling systems. They were cost
with moving the brackets into place after the ship was prohibitive and deemed too labor intensive to properly
docked, the decision was made to advance this work. meet the requirements of the project. An alternative
The brackets were fabricated, assembled (with excess movement system was proposed.
material for trimming at installation), and placed in the
building dock at their respective locations prior to the
drydocking of the vessel. With the ship docked, the The Finalized System
brackets would be rigged into place. This operation was
made a little easier by the absence of bottom shell The finalized system consisted of two "low-boy"
plating in many of the areas of bracket installation. 50-ton trailers propelled by forklifts. The trailer idea
Upon completion of the new hull blocks, the brackets showed exceptional potential as far as satisfying the
would be burned off just above the weld, and the design features for the material handling system. The
remaining stub would be left on and the sharp edges idea moved rapidly from the conceptual phase to the
ground smooth. identification of major components.
THE STEEL MOVEMENT SYSTEM The material handling system consisted of two
50-ton trailers structurally linked together, two 17-1/2
Defining the Design Requirements ton forklifts, inflatable air jacks, hydraulic 4-point lift
system, low profile tracks and lifting grid. With each
Due to the location of the damaged steel work, component of the system identified, the design and
the gantry cranes were restricted in their usage and this modifications began.
DRYDOCKING
Dock Characteristics
GRAVING DOC!<
--M>T---+-- a D-o----a~-;--D D a a a i a D a
aaaa oa+aaaoa+aaoo
..Jl .,. IL IL..O...Jll ..Jl .,. IL IL..D...Jll ..Jl A.. f-::
a a a a a a a a a y a a a a a Ta a a o
FR FR FR FR
!I 40 47 !II
LE GENO
D STAl'OAllO 42 X 48 8LOCK
SIDE SUPPORT SHORING
GRAVINO DOCK
a a l
a a a a a a a a a l II
all -} L. a_p ...!l L '-" ...!l .IL q_a _JI
+ a a a +a a a
a a
a a
+
a a a a
FR FR FR Fii FR FR
ll 13 3• •o 47 !II
LEGEND
a ST ANOARO 42 X 48 BLOCI<
510£ 51.PPOIH SHORll-G
D D + D D D
o a Ta a a a
D Q T D D
FR Fii FR FR FR
5 IJ 40 47 51
LEGEND
ST Al.()ARO 42 X 48 BLOCK
' J0101~p1a101~
1
l(:JI 'lfj
IOI IOI
-.... .01
IDuCJCJCJl
1DV I I
IOI I I
/ODo CJ o ...
10 v ~ ,,,/
// I~ /01
t-!>01LJIDtQD01d~
~-- - - ------ (_o..) L
~;ft.
""'I'
}Z"""5J'"'""'"4
lJLJILJLJ 4 a
77
I
~~
lib:Qbl)~
.t:.:ro L J I L J U m
71 '5 Si 47 ll
.1~~
I I
L. u _.1
L 7DalD~l
I Cli...Jws.....I' (
L
cA)
Fig. 27 Fine mesh model for the critical area (the area enclosed by the dotted lines in Fig. 26)
L
Fig. 28 First repair condition with reinforcing bracket
Table 2
For the first repair condition, both absolute and
relative deformations of Nodes 4, 15, 2, and 22 (refer to MODE ORIGllAl
DIR ID. ODCKll& COllD. Zld llEllll COID.
Figure 1) are important. The deformations of these 4 0.39573 mm 0.01558" 0.16459 mm 0.00648"
Nodes are listed in Table 1. 15 0 27711 mm 0.01091" 0.09677 mm -0.00381"
y 16 0.26187 mm 0 01031" 0.05689 mm -0.00224"
Table 1 19 0.09093 mm 0.00358" 0.65328 mm -0 02S9S"
20 0 14986 mm 0.00590" 0.65328 mm 0 02572"
IODI ORIGllUl 1SI R!JlllR COID. ISi RENIR COID.
4 2 7114 mm -0.10675" 0.22174 mm 0.0
ID. 011. OOCKll& COID. IWllllOUT IEllF.1 IWllll IEllF.I
4 0 39573 mm 0 01558" 0 7381 mm 0.0290ti" 0.62433 mm 0.02458" IS 2.71171 mm -0.10676" 0 44399 mm -0 01748"
~
15 0277II mm 001091" 0 39548 mm 0.01557" 0.47625 mm 0.01875" l 16 2 5542 mm -0.10056" 0.47269 mm -0 01861"
y
~
21 0.41042 mm 0 01251" 0.00558 mm 000022· 0.14097 mm 0.00558" 19 0 68351 mm -0 02691" 0 sms mm -0 02064"
22 0 30302 mm 0 Oil93" 0.01625 mm -0 00064" 000028 mm 0.00726" 20 0 18288 mm -0 00720" O00939 mm -0.00037"
~
4 2.71145 mm -0.10675" 0.22174 mm -0.0083" 0.15875 mm -0.00625"
15 2.71146 mm -010676" 0.83591 mm -0.03291" 0.72821 mm -0 02867"
l Verification of Dock Floor and Side Walls
~
21 2 6126 mm -0 10286" 1.64008 mm -006457" 1.50800 mm -0.05937"
22 2 71678 mm -0 10696" 0.99720 mm -0.03926" 084937 mm -0.03344"
A task that ran parallel to the ship's structural
analysis was an engineering study of the dock itself,
For the second repair condition (refer to Figure which involved finding a way to provide support to the
10), both absolute and relative deformations of Nodes ship where the bottom was severely damaged, without
4, 15, 16, 19, and 20 are important. The deformations of transferring excessively high concentrated loads to the
these Nodes are listed in Table 2. dock floor. The consulting engineering firm of James
The ship had a hog of about 15 to 23 cm (six to The vessel would arrive at the yard drawing
nine inches) at midship. Consequently, the end shores approximately 7.6 meters (25 feet) of water at an even
made contact with the top hinge pins well before those trim. This draft would ensure that the vessel did not
closer to midship. The jacks had been extended so that ground at the pier during the cycles of the tide and have
contact would take place as early as possible. As the sufficient draft to support ship handling by the tugs and
ship settled, the pressure was allowed to rise to near the pilot. Several cable pendants were installed on the
maximum predicted. During the docking the pressure vessel at the San Clemente Island anchorage prior to
was periodically relieved and allowed to rise again. As entering San Diego Bay to provide hookups to the
the intact bottom portion of the hull firmly contacted tugboats that would allow responsive ship handling.
blocks fore and aft, the deflection of the ship decreased
and the center shores made contact with the top hinge The maximum draft of the vessel entering the
pins. Gradually the loads equalized, indicating that the graving dock was limited to 5.5 meters (18 feet). The
ship deflections had been primarily due to elastic strains vessel required pumping up to lower the vessel draft. A
in the ship structure. 91.4-cm (36-inch) and 1-m (42-inch) floating oil booms
were placed completely around the vessel and pier. The
Once the ship was firmly settled on the blocks booms were anchored away from the vessel and pier to
and shores, final jack load settings were established. ensure a safe distance to allow any escaping oil to rise
During the next several days, as the ship made its final to the surface inside the booms. Oil skimmers and
settlements, heating and cooling in the sun, the pressure cleaning equipment were located within the boomed
changes were recorded and periodic adjustments were area. The Exxon Valdez was stabilized at the NASSCO
made. A setting was found that kept the loads within pier for two days to facilitate separation of any residual
the desired range, and shims were installed beside the oil which might be in the tanks.
jacks below the lower hinge pin. The jacks were
depressurized and removed. To ensure vessel stability during the voyage from
Alaska, certain undamaged tanks were ballasted with
ENVIRONMENTAL ISSUES AND slightly contaminated water, which under the
CONSIDERATIONS agreement, had to be removed from the vessel prior to
lowering the vessel draft. The water could not be
Pre-docking pumped into the bay or taken away from the yard by
conventional tanker trucks, due to the extremely large
The damage to the Valdez was such that the quantity.
NASSCO shipyard would be the first harbor that the
vessel would enter after departure from Alaskan waters. Exxon Shipping Company arranged vessel
schedules that would allow the tanker Exxon Washington
The Valdez had been under close observation to be brought to the yard in a light draft condition and
and scrutiny by all the various environmental and local berthed at the same NASSCO pier as the Exxon Valdez.
Government agencies. The Regional Water Quality The Exxon Washington was moved inside the booms and
Discussion
Phil Rynn, Member 1. Drydocking support requirements for a ship with
Overall the paper is an excellent description of the re- 30% of its bottom damaged.
construction of the Exxon Valdez and the authors are to 2. Access and method of transfer in the graving dock of
be commended for their concise presentation. The infor- removed sections and erection of new hull bottom units.
mation presented will undoubtedly be of value to builders 3. Environmental protection.
faced with large reconstruction tasks in environmentally For a ship with extensive bottom damage, it can be diffi-
sensitive locations. cult to determine how much contact will occur with the
dock's blocking arrangement. The inability to clearly de-
As is apparent in the paper, accurate assessment and
documentation of the extent of the damage was crucial in fine the extent of damage (other than general location)
compounds this problem. Support requirements for the
a repair of the magnitude of the Exxon Valdez. Knowledge
ship must prevent overstressing of the dock floor, as well
of the damage was necessary to develop a successful dry-
as maintain alignment as bottom units are removed and
docking strategy that would maintain the structural ade-
replaced. NASSCO's combined use of traditional blocking
quacy of both the hull and the drydock and still accommo-
with side shoring and blocking tables was shown to effec-
date removal and replacement of structures while
tively provide these support requirements.
preventing undue hull deflections and torsions. Along with NASSCO's use of the "tunnel method" for removal of
accurate damage assessment, the fact that the repair took damaged structure and the erection of new hull units was
place in the shipyard where the ship was constructed and an innovative solution to the restriction imposed by the
information on the undamaged hull was readily available size of the graving dock. The cost effectiveness of this
most likely contributed to the success of the repair. method, however, depends somewhat on how much un-
In the case of the Valdez the construction planning was damaged ship must be removed to provide access to the
designed to replace specific damaged block sections using damaged portions. In this case, since damage to the star-
a tunnel approach. Damaged blocks were cut away and board and starboard/center bottom sections was so exten-
replaced efficiently and quickly. With the advent of the sive, only minimal undamaged structure was required to
Oil Pollution act of 1990, it would be interesting to know be removed.
if the authors could advise the relative cost of fitting a The measures taken to protect the environment during
completely new bottom as opposed to replacing only one docking and repair are noteworthy. Unconventional steps
side as in the case of the Valdez. The replacement tech- such as the use of a compressed air and hose system to
niques utilized on the Valdez repair may enable vessels agitate the water and establish flow into the drydock dur-
currently in service to comply with the new laws. Also of ing docking operations, modification of venting systems to
value would be the authors' opinion as to what technical provide isolation of the drydock, and pumping of all dock
problems could arise in a different shipyard environment water to other ships for disposal were very effective in
than that of NASSCO. preventing an incident. NASSCO demonstrated that strict
The authors have provided a very descriptive paper environmental regulations can be complied with in a ship
presenting all of the steps needed to reconstruct the bot- repair situation even with damage as severe as that which
tom hull, taking into account the environmental and existed on the Exxon Valdez.
strength considerations and pointing out necessary techno- There have been other noteworthy occasions when ships
logical decisions that needed to be made. The success and with extensive structural damage have been repaired uti-
rapid completion of the repair procedure is indicative of lizing new construction modular techniques. In 1987 in
the use of proper planning as outlined in the paper. It is the Persian Gulf, the USS Stark (FFG 31) was struck on the
an apparent conclusion that with proper planning any task port side forward by two Exocet missiles. Upon her return
can be completed successfully. The useful content and ben- to the United States, Stark was repaired during the period
eficial applications associated with the paper will no doubt November 1987 to August 1988 by Ingalls Shipbuilding
be of great benefit to the industry. division of Litton Industries in Pascagoula, Mississippi. Al-
though the damage was extensive, unlike Valdez, it was
Robert R. Fargo, 1 Visitor topside, primarily to the main deck and forward super-
structure from frames 93 to 153. Thus it was relatively
The reconstruction of the Exxon Valdez by NASSCO easy to scope the extent of repairs for planning purposes.
provides some interesting and innovative solutions to the Docking of the ship could be done in a normal manner and
unusual problems encountered in this repair situation. Of there were no unusual environmental hazards.
particular interest were the creative approaches taken in Stark was not repaired in a graving dock. Instead, the
addressing three primary concerns: ship was raised on the yard's launch platform, a floating
drydock, and then translated onto land using a motorized
1
Ingalls Shipbuilding, Inc., Pascagoula, Mississippi. pallet car system. On land, the damaged structure was cut
Panel Discussion
Society President Arthur J. Haskell presiding
[EDITOR'S NOTE: After formal discussions on the paper and the authors' closure, a
panel discussion was convened on the broader topic of oil spill prevention and tanker
construction. Following are the major contributions to the panel debate.]
T.lEYl:l W'1:
ilii.-l£VU Al.All:Kl C.O T. HATCll
(C.11.l.T.l , ;Tc.O:cn I ' KATCL.
( c. 0. L.T.J '·
'' - -
.,
..,,
,,
~re3 ta 3 degrees
1_ 1 .•. 1 1.57'5 m-r·ad. 1). •)55 m-r·ad. 7'.·'·. m-r---d,
Are~ t(~ 4•:•.•:• degrees :: • 3:.~.q m-rad. 1_1. j)q1:1 m·-t·ad. •:•', _ 111 -1 _.,u ..
~r~~ :•_1 •. _•-4•).•Y degrees 1_1. q48 m-r3d. '-'. O -~·:1 m-r·acJ.
11.48M
111 ,,,.
,,..-
_..,~-
~---··--- 5.3611
3
.e __ _,,.-· ..--·--· . ......
.,,,..
""'",-:-:-·-...~-_--;-::::--:-?..,..--------._____~........
t ~'r
e
I'
s
/~.po"'
,-/'~
----------- ----..
----~--....
e
t
e
fl ,,.~ ......
.. ..
- - -...
--~ 5 g /"_,,...,......
_/-~
.,
-...
18 z0 38 40 -.....··.50 &0
9 :L:----'-~~111~--'-~~2-9~-'-----'3-9~~~4~11~-'-~~59~~---:69 ·.... degrees
-L ··....
degrees _
"·
····...
"·.
··.... ,
-5 -3 ~
@~~B!~>
on the Outer Banks. It was a big surprise, the last day of
the conference committee. It caused a big brouhaha. But
it carried and it carries with it this provision. It's a very
Ef11Jdsatpi§~
short part of the bill, but it's a moratorium on drilling in
that area.
It revamped the national response mechanisms very
GJucksuf much. It gives the President much more authority with
Steam Tanker, Built 1888 respect to oil spills and directs the President to direct the
Double Bottom Under Aft Macntnery Space,
Single Skin Cargo spaces
response to oil spills when the public health and welfare is
significantly affected or threatened.
Now to liability and compensation, just for a minute.
When we talk about liability, I'm talking about what the
owner or operator or the responsible party is liable for, and
compensation refers to the one billion dollar fund that was
established through a 5-cent-per-barrel levy on oil. The
liability for tanker owners was eventually set at $1200 per
gross ton. And you might be interested in how the Congress
got there.
Prior to the day that the Senate passed their bill, S-686,
all of the bills, including 686 on that date, the President's
C!N rRe BUUU1Lio0
bill, the House bill, and the 686, all called for liability limits
Fig. 41 Mid-deck tanker, 1886 of $500 per gross ton. That fit in nicely with the interna-
tional scenario. Everything was consistent. It was fairly
rational. Insurance would be available. And nobody was
referred to as "the protocols." Perhaps Admiral Kime men- saying anything else. Howard Metzenbaum took the floor
tioned in his address. And she really wanted to see oil spill in the 11th hour of the discussions, pounded the table with
legislation enacted, and she worked real hard on it. In fact, his fist, and much to the surprise to me and to George
I had the pleasure of being her special assistant on oil spill Mitchell and to practically everyone else in the room said
legislation for the last two years of my regular Coast Guard that if $500 a ton is good, then $1000 per gross ton has got
service. to be doubly good. And it passed in the blink of an eye.
So in 1984 we had really a whole new era of oil spill Then the Senate went to the press that evening and the
legislation initiatives. It looked like things might go some following day throughout the country you read how well
place. But as it turns out, the Congress couldn't agree on the United States Senate had stuck it to the oil companies.
one principal issue, that's the matter of state preemption. And I can guarantee you that I don't think Senator Howard
The House had always favored state preemption. Senator Metzenbaum and perhaps the majority of the Senate had
George Mitchell and the very powerful Senate Environ- even a clue that oil is carried by others than oil companies.
ment and Public Works Committee opposed preemption
Then you heard recently with the budget business that
of any kind, and the Administration was somewhere in the
the House and the Senate often vie for attention. Perhaps
middle.
Now comes Exxon Valdez. Most insiders predicted that some of you know that the boys over in the House often
we would have oil spill legislation following the Exxon Val- refer to the Senate as the House of Lords. So it got over to
dez. In fact, at that state, then Commandant, Admiral Paul the House now and they said, "Well, we can't let the Senate
Yost, asked to return from the private section into uniform outdo us here. We've got to do better. So we're going to
and be Sam Skinner's advisor on the legislation. And we make it $1200 a gross ton and we're going to slice that in
took legislation to the Hill on the 11th of May, which was the middle and we're going to assign part of that to cargo
largely a liability and compensation regime. Few predicted interests." How they figured they were going to enforce
that it would take Congress almost a year and a half to see that, I haven't a clue. But the final readout is it's $1200 per
oil spill legislation enacted, and I certainly don't know of gross ton for tanker owners.
anyone who predicted the shape that the legislation would Now, as I said a minute ago--and there would be no
eventually take. But soon we were stuck in the same quag- preemption of state governments-seventeen states have
mire over state preemption. unlimited liability. But the important part of this whole
During these months that followed, everyone wanted thing-perhaps for you, perhaps not, perhaps for some of
into the act, and most of the people got into the act. Again, you anyway-are the standards for breaking liability. And
as you may have heard last night, in addition to liability and I want to read you those right out of the act.
compensation, the act covers oil spill prevention, removal, First of all, there's a couple of fairly rational standards of