You are on page 1of 32

SNAME Transactions, Vol. 98, 1990, pp.

663--{)94

The Reconstruction of
the Exxon Valdez
D. C. McNeill, Member, D. Malmquist,Visitor,
D. Walter, Member, D. Grothen, Visitor,
K. Londot, Visitor, NASSCO, San Diego,
California

ABSTRACT PART ONE: THE PRODUCTION APPROACH

This paper describes the unusual construction INTRODUCTION


approach taken to repair the extensive damage to the
hull of Exxon Valdez, the very large crude carrier that A typical ship repair contract may include small,
received worldwide notoriety in March 1989 after localized areas of structural damage and are usually
striking a reef in Alaska's Prince William Sound and repaired utilizing a "patchwork" methodology. Very
spilling her cargo of heavy oil. The work was performed seldom does a repair contract include an amount of
by National Steel and Shipbuilding Company, the ship's structural damage sufficient to employ new constru ction
builder, at their San Diego yard. building techniques. The repair of the Exxon Valdez is
unique in this respect. It is also unique in that the
The paper is presented in two parts. Part One repair method embodied an untried steel rip-out and
covers the unique production approach, starting from reconstruction concept. Complex issues dealing with
the receipt of the initial damage survey reports through engineering, environmental, and production concerns
the actual reconstruction of the ship. Part Two · had to be addressed and overcome for the successful
addresses the complicated engineering and completion of this contract.
environmental aspects of this unique ship repair
contract. Part One of this pap e r focuses on the
production-related issues, in basically the chronological
order they were examined. When possible an attempt
will be made to show the thought process involved in
examining each issue and determining th e most cost
effective method/solution. Each step in the overall
BACKGROUND program will be analyzed from pre-contract issues, to
contract award, to the eventual reconstructi on of the
When the Exxon Valdez sailed out of San Diego ship. The principal points covered in this portion of the
Bay in December of 1986, she was the largest tanker paper are the complex production issues, the plans
ever built in a West Coast shipyard, with a deadweight developed to address these issues, and the production
of 211,469 tons, a length of 987 ft (301 m), and a beam methods implemented to ensure successful completion
of 166 ft (51 m). The ship was built with of this unique sh·ip repair contract. The challenges and
state-of-the-art systems including collision avoidance restrictions can often become the stimuli for promoting
radars, inert gas generation system and a segregated innovation.
ballast system. She was one of the safest ships in the
United States Merchant Marine Fleet, meeting the CONSTRUCTION STRATEGY
latest U.S. Coast Guard, American Bureau of Shipping,
IMCO, and Solas requirements. Defining the Scope of Work

When she went aground on March 24th, 1989, The normal evolu ti on of a bid proposal for a
substantial damage was sustained by the ship. repair job like the Exxon Valdez begins with a review of

663
Fig. 4 Area of damage

total replacement of 15 starboard bottom shell center


blocks and ten starboard bilge shell blocks. (Fig. 4)

In addition there were numerous areas of


damage that would be addressed as change orders after
the ship was drydocked and inspection teams had
surveyed the tanks. The detailed damage survey reports
and specifications provided by Exxon Shipping
Company were instrumental in the eventual
development of the reconstruction strategy.

The Tunnel Method

Development of the construction strategy was


assigned to a small team. Brainstorming sessions were
held that produced questions requiring solutions. How
could the ship be drydocked with such severe bottom
damage? How would the steel be removed from under
the ship in the most efficient manner? How could we
minimize the duration the ship was out of service and
Fig. 2 Damage to hull of the Valdez provide our customer with a low cost solution to their
problem? Answers to these questions led to a bold and
innovative construction strategy.

The concept of the "Tunnel Method" began to


take form. If the damaged blocks could be removed in
basically the same configuration as they were originally
built, and new blocks inserted in their place, the cost to
repair the ship would be greatly reduced. In order to
accomplish this task a large area of the ship's structure
would have to be removed. Could the remaining
structure be supported in a manner that would prevent
collapse and minimize distortion. To minimize the
amount of structure removed, and to accommodate the
existing block configuration, a two-tunnel approach was
proposed. (See Figure 5)

301m(98T) ~
OUTLINE OF
GRAVING DOCK .----183m (600')
Fig. 3 Rock embedded in hull of the Valdez

p··•
.. ·- ..
the damage repo rts. The magnitude of the work was
replacing extensive steel damage as shown in Figures 1,
TUNNEL I
2, and 3. Tll'INEL 2 44 '
tt-:-===:::::~-:-:':!:::==:!:=:::-:-7~:::=~~==
51m (166') SHORE ~ 1:zi~ (400') ..
(TYP)
The first task was to define the scope of the work
to be performed. The exte nt of the damage required Fig. 5 Two tunnel approach to reconstruction

664 The Reconstruction of the Exxon Valdez


Due to limitations in the length of the drydock,
- (PORT) (STBD) - - -
portions of the bow would have to be removed to allow
access to the damaged steel. Once the partial bow was
removed, rip-out of the damaged steel could commence.
Tunnel No. 1 would extend from the removed bow to
Frame 42, a distance of approximately 183 meters (600
feet). The width of this tunnel is about 13 meters (44
feet), extending from 1.3 meters (52 inches) off
centerline port to 12.1 meters (39' -9") off centerline
starboard. (See Figure 6)

.... ·.
Fig. 7 Tunnel No. 2
- (PORT) (STBD) - - -

would be re-installed, thus completing the major


portion of the steel reconstruction.

Having developed the reconstruction strategy,


the next step was to consult our Hull Technical
Department to determine the feasibility of the repair
concept. A series of preliminary calculations revealed
that the "Tunnel" method of removing and replacing
Fig. 6 Tunnel No. 1 hull blocks was indeed feasible. Armed with this
knowledge, a senior management team departed for
The existing centerline block configuration is 1.3 Houston, Texas to present the bid package and
meters (52 inches) off centerline starboard to 12.1 construction strategy to officials of the Exxon Shipping
meters (39' -9") off centerline starboard. Because of the Company. The result of this presentation was the award
amount of damage along centerline of the ship, a of a contract on June 11, 1989 for the repair of the
modified centerline block configuration was proposed. Exxon Valdez.
The original design drawings included a symmetrical
break at 1.3 meters (52 inches) off centerline port and PRE-CONTRACT ISSUES
starboard. Utilizing this break allowed a simple flop of
the lofting, thus realizing a savings in engineering and Laydown Space
lofting manhours. Rip-out of the damaged steel would
start at the removed bow and proceed aft to Frame 42. Before proceeding with the Bid Proposal, three
A total of 15 blocks, 12 meters (40 feet) by 13 meters main issues were required to be resolved. The first
(44 feet), averaging 100 tons in weight, would be issue was block laydown space requirements. Laydown
removed. Upon completion of rip-out, the new blocks space had become a serious problem at NASSCO. Like
would be inserted through the tunnel from Frame 42 most modem shipyards, NASSCO had embarked on an
working forward to the removed bow. After the new extensive advanced pre-outfitting program. This
blocks were installed, keel blocks would be placed approach utilizes additional yard space which formerly
under them to add support to the ship's structure before was used for steel construction. The timeframe for the
removing the damaged steel from Tunnel No. 2. repair of the Exxon Valdez coincided with a peak in
laydown space requirements for two existing Navy
Tunnel No. 2 would extend from the removed contracts currently in progress. An analysis of space
bow to Frame 29, a distance of approximately 122 requirements determined the need for additional
meters (400 feet). The width of this tunnel would also laydown area. A decision was made hy Senior
be about 13 meters (44 feet), extending from the Management that, if NASSCO were awarded the
longitudinal bulkhead at 11.9 meters (39 feet) off contract for the repair of the Valdez, a new platen
centerline starboard to the side shell. (See Figure 7). assembly area would be built. This new platen {Table
11), would be 152 meters (500 feet) by 18.3 meters (60
The outboard block configuration did not feet) in area, and include all necessary services. This
change. A total of ten blocks, 12 meters (40 feet) by 13 was a progressive step for a shipyard that had just
meters (44 feet), averaging 80 tons in weight, would be become employee-owned. Upon award of the Exxon
removed. Upon completion of rip-out, the new blocks contract, the order was placed to begin construction of
would be inserted through the tunnel from Frame 29 the new platen. This new assembly area was completed
working forward to the removed bow. After all the new just in time to support the schedule requirements for
blocks were installed, the removed portions of the bow new steel hull blocks.

The Reconstruction of the Exxon Valdez 665


Environmental Issues the Regional Water Quality Control Board (RWQCB)
that the tanks of the Valdez were not discharging any
The third issue to be resolved was environmental oil. These two tasks were accomplished and the ship
consideration and this will be discussed in Part Two of entered the NASSCO facility approximately two weeks
the paper. later than originally scheduled.

DETAILED PLANNING The second reschedule was necessary because of


delays created by litigation procedures between Exxon
Contract award sparked a flurry of activity and the State of Alaska. Rip-out of damaged steel was
setting the detailed planning wheels in motion. A held up while teams of experts surveyed the damage.
kick-off meeting was held assigning action items and Unlike the first reschedule, which only required a two
persons responsible for the various tasks. Some of the week shift to the right, this reschedule required
major issues to be addressed for the reconstruction adjustments within the schedule. Since the docking date
included: schedules, material delivery, drydocking did not change, yet rip-out of damaged steel was
procedure, keel blocking plan, shoring requirements delayed, a three week adjustment in the rip-out and
and internal back-up structure, and development of a erection completion dates occurred.
detailed construction method.
The third and final reschedule was necessitated
Schedules by the condition of the tanks. Hot work could not
commence until a waxy residue was removed (by
Contract specifications required the submittal of scraping), in way of hot work areas. Due to the
various schedules within 30 days of contract award. relationship between rip-out of damaged steel and
This effort proceeded smoothly and all required erection of new blocks, another two week adjustment
schedules were issued in the desired timeframe. From was necessary. After this final reschedule, a firm
this point on, however, a series of delays caused a total undocking date was agreed on between NASSCO and
of three rescheduling efforts. Figure 8 depicts the Exxon.
original key event schedule submitted to Exxon.
The overall effect of those delays, which were
out of the shipowner's and shipbuilder's control, was to
EXXON PRODUCTION SCHEDULE
TIME
re-allocate manpower, delay material processing, and
voocw Cl>Pl....ET£ MEJ..DOl/TV
reorganize detail schedules.
VGAS F"AU CXl'fll.ETE AJR TUT V
V 1JrtSP£CTtC>o C04PLCT[ PAINT V
VKlCJll[ IC*' ti,, PATCN _.. A l.tOXlt' V
f> AJP-?U'! I1MAA9 1'-QO!S Ab PJP·GlJ! MppeeD a.ps A
IU
JNSTll..c:9;?1IIG
llG2 T'ONSI
llll TOGI LEGEND
Material
&....,____.!
_,,
JNSlL SHUP
0A2-M 6
1106 TQNSI
llU TOG) V Ml.L.[STOJEIWl:T (yt:NT

<t' 0 .1.2-102 l:I. 1'97 TDNSl h, STAQT


Material delivery was an important concern. Due
...., 01.2-116 (1 ll TONSI 6 ~
.d CCH'\..E"T[ to the tight lead time between contract award and start
,,./ . 01.2-tlO 197 TCWSI A \
; 0A2·1J6 1121 TONS) l:J. ..,. 6 ERECT of construction, a system was set up to monitor steel
~ 01.2-1 . . ,., TCHSI A ~
delivery to 'the "in-yard need date" for each new hull

d
'o:~:.:~~t~~n;-
1
\~
6

0-Z-1'1• 1125 TCNS}


A
A \
block to be constructed.
A2•2t0 t•l TCNSI .6 t'"
-232 197 TCJlrGI 4. ~
OA.2•2.&I 190 TONSI .4 The detailed construction method firmed up as
oaow •2-ne111• TQNSI A2-l96 ' " TONS~I Ob additional information became available. The
::= :n~: i: :g:: :;_~·:: ,',':, :;.·, : ~ ",. \ development of the docking plan confirmed the need to
Ai-''31 170 TONS! ' 0 ~ 1 remove portions of the bow for access and removal of
A2-606 l 100 f(ltS) SJ 0 A ~
A2·326 ('3 f'ONSJ S 0 6 q_ damaged steel. At this time, the location of the cuts for
A2-21• l 107 lDNSI E0 A ~
1.2-2'2 f~ TCMI er 0 A \e bow removal were determined.
&a-~ 161 TONSI 0 Ii •
.t..2·2"6 l.&9 TOGJ 0 A ~

T""" ![ST

Outfit Planning
Fig. 8 Original key event schedule
The original damage survey reports included
The first reschedule was necessary to reflect the marked-up drawings of outfitting items detailing the
actual arrival date of the ship. During the voyage from extent of the work to be performed. The Outfitting
Alaska to San Diego the bottom shell plates peeled Planner developed an integrated work package
back from the longitudinals and web frames. These containing all the necessary information to organize,
plates were hanging down from the bottom of the ship install, monitor, and inspect the outfitting components
and they prevented entry of the ship into San Diego Bay attached to each new hull block. Typical outfitting
due to limited water depth. The plates would have to included ballast pipes, ladders and gratings, and sluice
be removed before the ship could be towed into valves. A pictorial representation of the work package
NASSCO. In addition, Exxon was required to prove to contents is shown in Figure 9.

666 The Reconstruction of the Exxon Valdez


were re-installed. Again, the reason for these shiploose
WORKPACKAGE pieces was to allow room for the new blocks to be
FOR maneuvered through the tunnel.
EXXON BLOCK
A2-036

WORKPACKAGE TITLE
SCHEDULE.
REFERENCES,
REQUIREMENTS

WORK DEFINITION

INSPECTION/
DISCREPANCY
SIGN-OFF SHEET

BUDGET CRITERIA
SHEET
Fig. 10 Strategy for removal and re-installation of five
MATERIAL LIST blocks in Tunnel No. 1

DRAWING The strategy developed for the removal and


re-installation of the forward ten starboard centerline
hull blocks was significantly different from that
Fig. 9 Work package contents developed for the after blocks. Since the outboard bilge
blocks would be removed and replaced, a portion of the
outboard web frame was removed with the starboard
Construction Details
centerline block during rip-out. (See Figure 11)
Development of the details for the rip-out of the
damaged steel and the installation of new hull blocks
was then analyzed. A careful examination of each step
of the repair process was undertaken to determine
methods to accomplish the work. The first area to be
addressed was the burning method for the rip-out of
damaged steel. The shell plate would be burned
utilizing track mounted semiautomatic burning
machines. The internal structure would be cut by
hand-held torches in a manual operation.

Next the strategy for removing the damaged


blocks and inserting the new hull blocks was developed.
Since the extent of the damage to the starboard Fig. 11 Strategy for removal and re-installation of ten
centerline blocks extended five full hull blocks aft starboard centerline blocks
beyond the damaged bilge shell blocks, a separate
strategy was developed for removal and re-installation
of these five blocks in Tunnel No. 1. (See Figure 10) Outboard of the longitudinal bulkhead, the web
frames and the bulkheads were cut on a diagonal from
First, the shell seams and butts were burned, 45 cm (18 inches) at the top to 61 cm (24 inches) at the
then the outboard web frames were air-arced loose bottom. The intent of the diagonal cut was to allow
from the longitudinal bulkhead. The inboard web clearance for removing the block. As the block was
frames and transverse bulkheads were double cut at ten lowered the 20 cm (eight inches) down onto the low-boy
centimeters (four inches) off centerline to port and 1.3 trailer, about 8 cm (three inches) of clearance would be
meters (52 inches) off centerline to port. (See Figure opened for removing the block. During the attempt to
10). The 1.2-meter (4-foot) pieces were then removed remove the first block, this clearance was found to be
to allow the damaged blocks room to be maneuvered unsatisfactory. As the forklift backed up with the
out through Tunnel No. 1. Finally, the longitudinals trailers, they would wander from side to side in the
were cut and the blocks were lowered about 20 cm tunnel, causing the structure to bind up. After repeated
(eight inches) onto low-boy trailers. Re-installation of attempts, with similar results, the small piece of the
the five new hull blocks was facilitated by the removal outboard web frame was cut off the longitudinal
of the 1.2-meter (4-foot) pieces of web frames and bulkhead and removed to allow more clearance for
bulkheads as described in the rip-out of the damaged movement in the tunnel. After this minor adjustment,
. blocks. After the new blocks were positioned and locked the remainder of the forward starboard centerline
into place, these 1.2-meter (4-foot) shiploose pieces blocks were removed with no further delays.

The Reconstruction of the Exxon Valdez 667


Re-installation of these ten new hull blocks would not presented a major challenge. The design features,
require any cuts to the new structure or shiploose operating constraints, and characteristics were
pieces. The removed portion of the outboard web identified to develop a material handling system to
frames and bulkheads would provide clearance to move move the damaged steel units and replace them with
the new blocks through the tunnel. new blocks.

The main design features demanded that the


Shear Bracket Installation
material handling system be simple to use, easy to
assemble, and reliable. At the onset of the project the
The next item to be planned was the installation
size and capacity were determined to be 13 meters (44
of the shear brackets. These large brackets, 4.2m X
feet) wide by 12 meters (40 feet) long with the average
I.Sm (14' X 6') were required to be installed prior to the
A-2 unit weighing approximately 100 tons. In addition,
rip-out of the Centerline blocks in Tunnel No. 1. They
all units were to be removed in a tunnel like manner.
would be faired and welded to the lower tank strut, the
The tunnel would start at the bow of the vessel and
longitudinal bulkhead, and the outboard shell web
move towards the stern of the ship. Hence, whatever
frames. (See Figure 12)
material handling system was developed, it had to be
capable of traveling in excess of 198 meters (650 feet).
Clearance around the units was restricted to 23 cm
(nine inches) on each side and a maximum of 20 cm
(eight inches) above the unit.

LOWER STRUT
With knowledge of the design features and the
operating constraints of the material handling system,
the more important constraints were as follows:
SHEAR BRACKET

a. height of the docking blocks


b. the location of the bow in the dock
c. the ship's fore and aft position in the dock
d. extent of the damage to each block
e. cost, availability, flexibility, and safety.

Initial Prouosals
Fig. 12 Installation of shear brackets
Being aware of the design features and operating
constraints, several ideas for material handling systems
were proposed, one of which was an elaborate system of
hydraulic jacks, multi-ton rollers, and 427 meters (1,400
The primary purpose of the shear brackets was feet) of track. Also, consideration was given to a system
to provide a load path for the ship's weight to the of air or water bearings to convey the steel units fore
docking blocks. Due to the weight of these brackets and aft. Both these systems were short lived as
(approximately one ton), and the difficulty associated principal material handling systems. They were cost
with moving the brackets into place after the ship was prohibitive and deemed too labor intensive to properly
docked, the decision was made to advance this work. meet the requirements of the project. An alternative
The brackets were fabricated, assembled (with excess movement system was proposed.
material for trimming at installation), and placed in the
building dock at their respective locations prior to the
drydocking of the vessel. With the ship docked, the The Finalized System
brackets would be rigged into place. This operation was
made a little easier by the absence of bottom shell The finalized system consisted of two "low-boy"
plating in many of the areas of bracket installation. 50-ton trailers propelled by forklifts. The trailer idea
Upon completion of the new hull blocks, the brackets showed exceptional potential as far as satisfying the
would be burned off just above the weld, and the design features for the material handling system. The
remaining stub would be left on and the sharp edges idea moved rapidly from the conceptual phase to the
ground smooth. identification of major components.

THE STEEL MOVEMENT SYSTEM The material handling system consisted of two
50-ton trailers structurally linked together, two 17-1/2
Defining the Design Requirements ton forklifts, inflatable air jacks, hydraulic 4-point lift
system, low profile tracks and lifting grid. With each
Due to the location of the damaged steel work, component of the system identified, the design and
the gantry cranes were restricted in their usage and this modifications began.

668 The Reconstruction of the Exxon Valdez


The trailers were positioned side by side and PRE-ARRIVAL WORK
structurally linked to form a flat bed measuring 9.7
meters (32 feet) long and 7.9 meters (26 feet) wide. The Main Considerations
structural connection afforded each trailer independent
vertical movement in the area of the king pin. Also, A series of four produ ction tasks would need to
with the trailers linked together, they performed as a be accomplished prior to the vessel's arrival to facilitate
single unit when pulled or pushed by the two 17-1/2 ton the docking of the ship, viz.:
forklifts. The beds of the trailers were structurally
modified with 1.2-cm (1/2-inch) steel plates and steel Task 1: Modifications to NASSCO's Building
reinforcing bars. The structural enhancement provided Dock. A few minor modificati ons were required to the
jacking flexibility so that loads were always redistributed building dock to accomm od ate the shoring pl a n.
to the main steel beams. The fifth wheels were Service platforms were cut off and removed from the
modified to allow for the attachment of the forklifts to starboard dock wall. Also, a compressed air pipe
the trailers. Once the modifications were completed running horizontally on the starboard dock wall was cut
the trailers were independently load tested for off and rerouted in way of the shore installation.
structural strengths, and rear axle and main beam
deformation. The rear axles were load tested to a Task 2: Setting of the keel blocks. Soon after
maximum of 62 tons and also operationally tested. the docking plan was issued, NASSCO's Dockmaster
began the process of arranging the keel blocks in
The 4-point lift system which is made up of four preparation for this unusual ship docking.
100-ton jacks, a control console and track, and the
lifting grid made up the transfer system. The tracks Task 3: Fabrication and assembly of the shores,
were redesigned to provide a low profile. The track dock wall back-up structure, and shore supports.
height of 7.6 cm (three inches) made it very easy for Priority was given to this task, as the timeframe to
forklift and trailers to cross with the aid of minimum accomplish the work was very short.
ramping.
Task 4: Installation of shores and dock wall
The lifting grid which is supported on the head back-up structure. Utilizing refe rence points in the
of the jacks was designed to provide multiple lifting building dock, the Shipwrights carefully performed the
points for supporting the transfer link between the layout for locating the shores and back-up structure.
4-point lift system jacks and the crane. Installation of these compo nen ts overlapped the
fabrication and assembly t a s k. As the steel
During the design development of the material subassemblies were completed in the Fabrication Shop,
handling system some constraints were modified. they would be palletized and moved by forklift to the
Modification of the docking plan was necessary. The building dock, where they would be lifted by crane to
block height for docking the ship was 106 cm ( 42 the correct location for installation.
inches). Instead, the blocks were changed to 1.1 m (46
inches) to accommodate the trailer height of 91 cm (36 It is interesting to note that the work outlined in
inches) plus S cm (two inches) of jacks and jacking each of the four tasks would be accomplished in
accessories. The 96.S-cm (38-inch) height of trailer and conjunction with each other. Keel blocks were being set
accessories left a total of 20 cm (eight inches) for as the modifications to the drydock and the installation
vertical movement. This height was more than of the shores progressed. T he e nd result was that all
adequate for the purpose of steel removal. The bow drydock work was completed we ll in advance of the
location and the ship's fore and aft position in the dock ship's arrival. (See Figure 13)
proved critical to the success of the material handling
system.

The overall length of the trailers, forklifts, and


proposed blocks combined was 21.9 meters (72 feet).
At this length of 21.9 meters (72 feet), the ship's final
position on the blocks and the bow location became
very critical. In an effort to provide enough clearance
for the transfer system and the trailer combination, the
sh ip's position was moved inland as far as practicable.
The bow of the ship was positioned toward the dock
gate. These two adjustments provided enough work
area for the material handling system to be effective.
Additional advantages were gained as a result of
optimizing the docking plan. The need for multiple
crane lifts of blocks was eliminated, and a larger work
area for staging of blocks was realized. Fig. 13 Keel blocks set in dry dock

The Reconstruction of the Exxon Valdez 669


PIERSIDE WORK the shore supports to ensure proper alignment at the
drydocking phase. Teams were established to
Ship's Alignment Condition accomplish the shore support installation. This work
progressed smoothly, and all shore supports were
After contract award, Exxon requested a plan completed, checked, and verified in time to support the
from NASSCO detailing the procedures the shipyard drydocking schedule.
would use for monitoring hull deflections and
maintaining alignment during the reconstruction efforts. Shoring Requirements
A plan was subsequently developed by the Shipwrights
that satisfied the requirements of Exxon. The basic The shoring requirements were determined by
element of the plan was to establish a level plane at a NASSCO's Hull Technical Department working
set height above the main deck. Utilizing the table of together with James R. Libby and Associates, a
offsets, this level plane was established on the house structural engineering consulting firm. These
front and forcastle deck bulkheads, and on permanent requirements will be covered in detail in the
stations at the ship's sides, spaced at approximately Engineering portion of this paper. From a production
30-meter (100-foot) intervals between these bulkheads. standpoint, these shores were a critical path item in the
Two readings per day were taken against this plane to docking of the ship. The material for the shores and
check for hog, sag, rack, and twist. It is interesting to shore supports had to be purchased quickly, fabricated
note that when the ship arrived and the first readings and assembled on a priority basis, and the shores had to
were taken at pierside, the hull deflections indicated the be installed on the drydock wall prior to the arrival of
vessel had a 15-cm (6-inch) hog and a slight twist. After the ship. Upon arrival of the ship, the upper shore
drydocking, and during the reconstruction, the supports would be fit and welded to the hull at pierside
deflections gradually reduced to an acceptable level as before the ship could be drydocked. The shore supports
the ship settled on the keel blocks. (See Figure 14) were installed using reference points on the ship, while
the shores were installed using references in the dock.
If there were any inaccuracies in either installation, the
brackets and shores would not fit properly. Careful
planning paid off, and the two structures mated as
required during docking.

DRYDOCKING

Immediately after the arrival of the Exxon Valdez


at NASSCO's facility, discussions were underway to
select a drydocking date. The first available high tide
FAIRED POSITION capable of supporting the drydocking requirements
DEFLECTED POSI TJON
would occur on August 15, 1989. This date was
mutually agreed upon since it allowed sufficient time to
Fig. 14 Alignment condition accomplish the pre-drydocking tasks. The engineering
and environmental issues associated with this unusual
ship drydocking will be addressed in detail in Part Two
The Exxon Valdez arrived at NASSCO's facility of this paper. The careful planning and preparation in
the evening of July 31, 1989. Prior to the ship's arrival, support of the drydocking operation contributed to the
pallets containing the shore supports that were to be successful completion of this very difficult task.
installed on the vessel were arranged on the pier in the
general location of their installation. Before the
installation could commence, the tanks would have to BOW REMOVAL
be gas-free and certified safe for hot work by a Marine
Chemist. The bow of the Exxon Valdez was removed in
three sections utilizing the 4-point lift system previously
The following day, brows were attached to the described. These bow sections were removed to provide
vessel for access, and some preliminary work began. access for the rip-out of damaged blocks and the
Both Exxon and NASSCO were extremely interested in re-installation of the new hull blocks. (See Figure 15)
the alignment condition of the ship after its voyage, and After the bow sections were removed from the drydock
prior to drydocking. The first production task and moved to storage locations, the assembly of the
accomplished was to establish the alignment procedure steel movement system began. The low-boy trailers
and record the actual condition of the vessel. were lowered individually to the dock floor along with
the forklifts and assembly of the trailers commenced.
After the tanks had been certified and ready for They were positioned side by side and the structural
hot work, the installation of the shore supports began. tie-in was installed to secure the trailers together. Next,
Special care was given to the layout and installation of the trailers were outfitted with 16 inflatable jacks which

670 The Reconstruction of the Exxon Valdez


were then covered with two sheets of 2.5-cm (1-inch) completed, the jacks were deflated, lowering the
steel plate. The inflatable jacks were tied together in damaged steel onto the trailers away from the ship. The
pairs and supplied from nitrogen bottles mounted on forklifts began the removal by moving toward the open
the gooseneck of the trailers. The steel plates provided bow with the damaged steel, continuing until the
a large surface for the jacks to operate. With the fifth mangled section was positioned under the lifting grid
wheel assembly already on the trailer, the forklifts for attachment. In this position, the hydraulic jacks
positioned the entire rig under the first steel section to lowered the lifting grid just above the removed section.
be removed; the next task was putting together the Attachment of the section was completed and the
transfer system. trailers were withdrawn. (See Figure 16)

Fig. 16 "Low-boy" trailer in dry dock

The lifting grid, now supporting the unit, was


elevated in excess of 8.2 meters (27 feet). This height
provides enough clearance between the bottom shell of
the unit and the highest part of the trailers. The trailers
Fig. 15 Section of bow removed
were then lowered on the modified fifth wheels. In this
position, a small forklift pulled the trailers back into the
The low profile tracks were positioned under the tunnel clear of the low profile tracks. Following the
bow at 90° to the fore and aft direction of the ship. withdrawal of the trailer, the hydraulic jacks were
After leveling the tracks, the hydraulic jacks were lowered to bring the unit as close to the dock floor as
placed on the tracks. Finally the lifting grid was placed possible. Inter-connecting the hydraulic bases, the
on top of the jack heads. This assembly was moved into transfer system was ready to travel. The system was
position forming an archway to the forklifts and trailer propelled to the port side of the dock where the 160-ton
assembly. portal crane had clear access to the damaged steel
block. Once at the dock wall in the blue sky area, the
THE TUNNEL RIP-OUT AND RECONSTRUCTION block was lowered on 1.2-meter (4-foot) stands and
attachment to the crane began. The crane slings were
Rip-out and Re-installation of Tunnel No. 1 hooked up to the top of the lifting grid and the damaged
unit was removed from the drydock. The average time
With the bow removal complete and the steel to perform the removal process, which included set-up,
movement system assembled and positioned, the next was one day. Removal proceeded from the bow aft
step was to begin the rip-out of damaged steel from until all 15 centerline blocks were removed. This
Tunnel No. 1. The track mounted semiautomatic completed the rip-out of Tunnel No. 1. (See Figure 17)
burning of the shell seams and butts was accomplished
during the assembly of the steel movement system. A-2 Unit Installation
After the material handling components were checked
and positioned under the damaged block to be Prior to installation of the new hull blocks in
removed, the jacks were inflated. Load distribution on Tunnel No. 1, the remaining structure accepting the
the trailers was controlled to ensure that the total load new blocks was beveled and prepared fo r welding.
on each forklift did not exceed 17-1/2 tons and each Installation of the new hull blocks in Tunnel No. 1
trailer was carrying approximately 50% of the block's would now commence. (See Figure 18) This process
weight. Burning the block away from the ship required further enhancement to the material handling
continued and the jacks were inflated to carry the system. Added to the trailers and forklifts was a driver
weight of the damaged block. Once burning was visibility system which included two cameras, two split

The Reconstruction of the Exxon Valdez 671


screen monitors, and a painted line . The cameras were Maintenance and Repair Items/Change Orders
mounted on the trailers while the monitors were
positioned on the forklifts. The line was painted on the Included in the Bid Specifications were a
floor on the dock along the center of the tunnel. The number of normal maintenance and repair items. Items
driver visibility system provided the forklift drivers the such as ranging the anchors and chains, taking tailshaft
ability to trail forward tracking only to the painted line. readings, valve repairs, propeller inspection, and typical
Once the new A-2 units were within centimeters of the open and inspect tasks were included. As survey teams
final erection location, they were loaded onto air inspected the vessel, change orders were generated that
bearings. increased the scope of the work. In addition to the
replacement of 25 hull blocks, there were numerous
areas of localized structural damage identified that
would be repaired utilizing traditional crop and renew
techniques. The tonnage associated with this crop and
renew work totaled over 335 tons.

The maintenance and repair items, along with


the change order work, was integrated very smoothly
into the production schedule. A large portion of the
change order crop and renew steel work (32 tons) was
located adjacent to, and aft of, Tunnel No. 1. Upon
completion of the rip-out of damaged steel from Tunnel
No. 1, the tunnel opening was utilized to transport
material by forklift to the areas of localized steel
repairs. The conventional method of handling the steel
would be to load the steel into the drydock by crane and
then drag the steel under the ship to the repair location.
A savings in material handling costs was realized by
transporting the repair steel by forklift through the
Fig. 17 Completed rip -out of Tunnel No. 1 tunnel. All maintenance and repair items, including the
change orders, are well contained within the steel
rip-out and reconstruction schedule.

Assembly of New Blocks

On September 18, 1989 the assembly of the new


hull blocks for the Exxon Valdez started on the recently
constructed Table 11. The 183-meter (600-foot) long
table is subdivided into ten building spaces 18.2 meters
(60 feet) by 18.2 meters (60 feet). Of the ten building
spaces, three spaces were set aside to build the large
web frame and bulkhead subassemblies. The remaining
seven spaces were used to build the new hull blocks.
Jigs were built to facilitate construction of the web
frames. These jigs were similar in design to those used
in the original construction of Valdez. The building
Fig. 18 "Low-boy" trailer in d ry dock approach for constructing the new hull blocks was
similar to that used in the original construction, with
minor modifications. The modifications to the building
approach, mentioned above, consisted of changing the
The air bearings provided the final horizontal method of assembly. The original block assembly
movement in both the fore / aft and athwartship method utilized was to "egg-crate" the longitudinals to
directions. Four air bearings rated at 40 tons each were the web frames and bulkheads at one process lane. The
inverted on an equal number of 1-m (40-inch) keel completed "egg-crate" assembly would then he lifted out
blocks. The units were lowered on the inverted air of the jig with a crane and moved to the ne xt process
bearings which were in turn inflated. The inflated lane. At this process lane the "egg-crate" assembly
bearings provided air lubricated surfaces on which the would be fitted and welded to the bottom sh e ll plate
A-2 unit was moved. The force required to finally panel assembly to form the completed hull block .
position these units was approximately one lb. per 1,000
lbs. of load. Once in place, the units were scribed, cut, The modified assembly method eliminated the
and locked in position. "egg-crate" jig process lane. The web fr a me and

672 The Reconstruction of the Exxon Valdez


bulkhead subassemblies would now be positioned on PART TWO
the bottom shell plate panel assembly, elevated
approximately one inch on wedges, and held INTRODUCTION
perpendicular to the bottom shell plate panel with
temporary braces. Next, the longitudinals would be In planning the drydocking of the Exxon Valdez,
held with the crane, positioned at the cut-out slot in the many problems beyond the scope of a normal
web frame or bulkhead, and pushed through the slots drydocking had to be faced. One of the more significant
with a forklift to the desired location. After the questions faced by NASSCO in the docking of the
longitudinals were tack welded to the bottom shell plate Exxon Valdez was "How do you support a ship when
panel, the elevated web frames were lowered until the nearly 30% of its bottom is missing?" Several NASSCO
brackets were resting hard on the longitudinals. The departments and two outside consultants worked
web frames, bulkheads, brackets, and collars were then together on a solution, and the result was a smooth and
fitted, and the assembled block was welded out. The successful docking.
requirement for modifying the assembly method was
necessary because the jig used to construct the Normally, an intact ship is supported on an array
"egg-crate" assemblies was dismantled to improve of docking blocks that transfers the loads to the dock
laydown space for other construction activities. For floor. Due to the severe damage suffered by the Valdez,
clarity, differences between th.e original and the about 30% of the bottom was not expected to contact
modified assembly methods are depicted in Figure 19. any dock blocks, and some method had to be found to
support that portion of the ship. Fortunately, the
damage was confined to the bottom of the hull. The
side shell and internal structures were mainly intact.

FACILITIES CON SID ERATIO NS

NASSCO's Building Basin No. 1, where the ship


was originally constructed in 1986, is the only local dock
large enough to accommodate the ship. The sheet pile
and concrete dock was built in 1975 to be used primarily
for new construction work and has the following
characteristics:

Dock Characteristics

ORIGINAL METHOD MDO!FIEO METHOD Length 304.8 meters (1,000 ft.)


Nominal width 54.8 meters (180 ft.)
Fig. 19 Construction method Clear between fenders 52.4 meters (172 ft.)
Dock floor 4.9 meters (16 ft.) below
Mean Lower Low Water
An optimum material flow was achieved in the (MLLW)
reconstruction of Tunnel No. 1. Block assembly would Tidal Range + 2.1 meters (7 ft.) to
be completed on Table 11, followed by a structural -0.61 meters (2 ft.) MLLW
inspection. Next, outfitting components such as ballast Slab Semi-relieved concrete slab
piping, sluice valves, gratings, platforms, and ladders Walls Sheet pile with waivers and
would be installed. The hull block would then move tie-backs
from Table 11 to the gritblast pit. After all applications
of hull coatings were complete, the new hull block The depth of the dock and the strength of the
would be loaded into the drydock by crane for slab in particular were designed specifically for new
installation. As each new hull block was installed, the construction of VLCCs.
next adjoining hull block would be completed as
described above, and be in position and ready for its In order to determine if docking of the damaged
scheduled erection date. ship was feasible, three questions had to be answered:

CONCLUSIONS 1. Could the ship be brought to a draft condition


that would allow it to fit into the dock?
With any major project utilizing unique
techniques, the question always arises, "Was it 2. How could adequate support be provided for the
successful?" In terms of cost, schedule, quality, and ship where the bottom was severely damaged?
safety this method of reconstructing an extensively
damaged bottom shell, the answer is a resounding 3. How could the dock floor be protected against
"Yes!" unusually high concentrated loads?

The Reconstruction of the Exxon Valdez 673


While the condition of the ship was being the dock floor, (described elsewhere in this section) the
determined, a number of brainstorming sessions were docking plan showed in Figure 20 was developed.
held to discuss possible approaches to these problems.
Methods of Support
DOCKING CONSIDERATIONS
Three distinctly different methods of supporting
The extent, distribution, and severity of the the ship were utilized. In way of the virtually
damage described in Part One significantly influenced undamaged port side conventional concrete blocks with
the approach used in docking the ship. The shipyard's timber capping were used with the level plane set at
knowledge of the extent and severity of the damage was l.2m (46 inches) above the dock floor at center. The
based almost entirely on videotaped records taken ability to dock the ship at an attainable draft on a
during an extensive bottom survey that was done in reasonable tide height; under ship accessibility, and
Alaskan waters using a Remotely Operated Vehicle being able to vary the timber capping to meet certain
(ROV) equipped with a TV camera. The video tapes other requirements were all considered in deciding
provided the means for obtaining a fairly accurate upon the appropriate block height. Conventional
definition of the distribution of damage but were largely blocks are shown as small squares on Figure 20 and it
ineffective for determining severity of damage. The can be seen that two rows of blocks are also provided on
severity of the damage shown on the TV screen was the starboard side in way of the damaged area. Except
unmistakable. However, NASSCO had very limited for those between Frames 34 and 40, these blocks were
means of translating this pictorial record into a almost totally ineffective during the actual docking.
meaningful representation of damage, deformation, and However, as soon as the dock had been dewatered,
hence into accurate contours in way of the damaged additional timber capping and in some cases lengths of
portion of the ship. Nevertheless, a lot of important timber shoring, were wedged in place to help improve
information was gleaned from the survey. First the the overall load distribution.
shipyard was able to determine with reasonable
confidence that the damage was limited to the starboard In areas where the bottom of the ship appeared
side of the ship and that the Centerline Vertical Keel to be reasonably flat but substantial bearing contact in
(CVK) was intact and structurally effective. The way of precisely located blocks could not be assured
longitudinal extent of damage was also definable, and to with any degree of confidence, a system which
some extent within the damaged zone, it was possible to permitted random contact was devised. The system,
at least categorize the condition of the bottom into identified as "Block Tables" in Figure 20 consisted of
areas where support blocks would be totally ineffective conventional concrete docking blocks with an overlay of
and areas where blocks might possibly be effective; steel plate ranging from 31.88 lbs. to 34.43 lbs. and
effectiveness being a measure of how much contact area sheathing of 1.9-cm (3/4-inch) plywood. The system
between docking blocks and ship structure could be effectively allowed for minor undulations in the hull
expected. Given this information it was possible to surface and also allowed for random areas of
decide where conventional docking blocks could be undisturbed plating to find useful support.
used and where a specially devised method of support
was necessary. Reconciling this with the special needs The damage to starboard between Frames 13
of the reconstruction process as described in Part One and 34 was so severe that there was clearly no hope at
of this paper, and the required loading parameters of all of placing support points under the ship that would

GRAVING DOC!<

--M>T---+-- a D-o----a~-;--D D a a a i a D a
aaaa oa+aaaoa+aaoo
..Jl .,. IL IL..O...Jll ..Jl .,. IL IL..D...Jll ..Jl A.. f-::
a a a a a a a a a y a a a a a Ta a a o

FR FR FR FR
!I 40 47 !II

LE GENO
D STAl'OAllO 42 X 48 8LOCK
SIDE SUPPORT SHORING

c::::J BLOCK TABLE

Fig. 20 Stage I docking plan to accommodate damaged hull

67 4 The Reconstruction of the Exxon Valdez


be in any way effective. At the same time, whatever first stage being the rebuilding of the starboard side of
form of support was provided had to be permanent for the center tanks and the second stage the rebuilding of
the duration of the reconstruction and completely clear the damaged wing tanks. Figure 21 shows the pattern of
of the damaged parts. The side support shoring shown supports after completion of stage 1, in preparation for
on Figure 13, between Frames 13 and 33, and 41, 42 and stage 2 and Figure 22 shows the pattern of supports
43, as small solid squares was developed, and is after reconstruction is complete.
described in detail in Part Two of this paper.
ENGINEERING CONSIDERATIONS
The Docking Plan
The docking plan developed was not only quite
The docking plan shown in Figure 20 represents unconventional, it also had to be suitable for long term
the arrangement of the different types of support that docking. There were, therefore, aspects of the
were put in place and on which the damaged ship was procedure that had to be validated by analysis before
eventually landed. Aside from the special consideration proceeding. With the structurally weakened ship being
of ship strength and dock floor strength, the plan had to supported on a system that featured unusual methods of
accommodate the first stage of the reconstruction support combined with very wide spacing of supports,
process. That portion of the ship that would eventually the stress and deflection levels had to be shown to be
comprise the tunnel described in Part One of this paper within tolerable limits. Also, the pattern of point
is clearly identifiable on the figure. The block table loadings on the dock floor differed from the parameters
between Frames 9 and 10 was utilized only for the specified by the dock's builder and designer so special
actual docking evolution and as soon as the dock had analyses of the dock floor strength were needed. Since
been dewatered and compensating supports installed, it the loads from the side shoring system were to be
was removed. As described in Part One of this paper, diverted into the vertical sheet piling that comprised the
the reconstruction was a multi-stage process with the dock wall, it too required verification.

GRAVINO DOCK

a a l
a a a a a a a a a l II
all -} L. a_p ...!l L '-" ...!l .IL q_a _JI
+ a a a +a a a

a a
a a
+
a a a a

FR FR FR Fii FR FR
ll 13 3• •o 47 !II

LEGEND
a ST ANOARO 42 X 48 BLOCI<
510£ 51.PPOIH SHORll-G

Fig. 21 Stage 2 docking plan

D D + D D D
o a Ta a a a
D Q T D D

FR Fii FR FR FR
5 IJ 40 47 51

LEGEND
ST Al.()ARO 42 X 48 BLOCK

Fig. 22 Stage 3 docking plan

The Reconstruction of the Exxon Valdez 675


Verification of the Ship's Structure The series of analyses included studies of the
intact web frame, the damaged web frame, the web
A comprehensive program of analysis using finite frame as it would be during the first phase of the
element methods was undertaken to determine the reconstruction process, and the web frame as it would
stress level and deflection in the ship's structure. A be during Phase II of reconstruction. Each adaptation
two-dimensional mathematical model (Figure 23) of the model was subjected to the appropriate loadings
representing the web frame was developed which was and controlled by boundary conditions that best
systematically modified to represent the various stages represented actual circumstances. Figures 24 through
of the reconstruction process. 29 show these various models and their boundary
conditions. Two local fine mesh analyses were
conducted; one in way of the side shore brackets which
confirmed the adequacy of the structure, and one in way
of the longitudinal bulkhead where the first structural
rip-out was to occur. The second analysis revealed the
possibility of high shear stresses in the traverse web
outboard of the longitudinal bulkhead, therefore the
brackets shown in Figure 28 were installed. These
additional brackets which were installed throughout the
cargo length as far aft as Frame 42 represented all of
the additional structure that was installed as a result of
the analyses. The data gathered during the regular
monitoring of hull girder deflection as described in Part
One of the paper confirm that considering the damage
to the ship and the wide spacing of supports, the
structure was stiff enough and had retained sufficient
strength to be essentially self-supporting.

Fig.23 Mathematical model used for the stress


analysis in drydocking condition

' J0101~p1a101~
1

l(:JI 'lfj
IOI IOI
-.... .01
IDuCJCJCJl
1DV I I
IOI I I
/ODo CJ o ...
10 v ~ ,,,/
// I~ /01
t-!>01LJIDtQD01d~
~-- - - ------ (_o..) L
~;ft.

Fig. 24 Initial drydocking condition

Fig. 25 Fine mesh model for the bracket area

676 The Reconstruction of the Exxon Valdez


L
Ch)
Fig. 26 First repair condition without reinforcing bracket

""'I'
}Z"""5J'"'""'"4
lJLJILJLJ 4 a
77
I

~~
lib:Qbl)~
.t:.:ro L J I L J U m
71 '5 Si 47 ll

.1~~
I I
L. u _.1
L 7DalD~l
I Cli...Jws.....I' (
L
cA)
Fig. 27 Fine mesh model for the critical area (the area enclosed by the dotted lines in Fig. 26)

L
Fig. 28 First repair condition with reinforcing bracket

In the first repair condition, the center block will


Figure 24 shows the boundary conditions and the be cut away as shown in Figure 26. In this condition all
deformed shape for the initial drydocking condition, the supporting load (2.7 x lOS lbs) will be resisted by the
where the critical area was in way of the side shell shear area which is the length between Nodes 15 and 21
bracket. A fine mesh analysis was performed for this (Figure 24), multiplied by the thickness. That is, the
area applying the deformations obtained from the area is not continuous structurally. Therefore
original course mesh analysis as boundary conditions as reinforcing shear brackets were introduced as shown in
shown in Figure 20. This fine mesh analysis shows that Figure 28. Figure 27 shows the fine mesh model and
the structure near the side shell bracket is satisfactory deformed shape of the critical area. The shear brackets
and that reinforcement is not necessary. can also be seen in Figure 30.

The Reconstruction of the Exxon Valdez 677


10101~p1w101~
101 'lai
101 IOI
IObc:JDCJI
1CJV
lc:JI
I
I
I
I
!CJ~CJCJCJ
1C:::JV ~ I
II I~ IOI
Lo1LJIDI
-- --.--
Fig. 29 Second repair condition

Fig. 30 Location of shear brackets

Table 2
For the first repair condition, both absolute and
relative deformations of Nodes 4, 15, 2, and 22 (refer to MODE ORIGllAl
DIR ID. ODCKll& COllD. Zld llEllll COID.
Figure 1) are important. The deformations of these 4 0.39573 mm 0.01558" 0.16459 mm 0.00648"
Nodes are listed in Table 1. 15 0 27711 mm 0.01091" 0.09677 mm -0.00381"
y 16 0.26187 mm 0 01031" 0.05689 mm -0.00224"
Table 1 19 0.09093 mm 0.00358" 0.65328 mm -0 02S9S"
20 0 14986 mm 0.00590" 0.65328 mm 0 02572"
IODI ORIGllUl 1SI R!JlllR COID. ISi RENIR COID.
4 2 7114 mm -0.10675" 0.22174 mm 0.0
ID. 011. OOCKll& COID. IWllllOUT IEllF.1 IWllll IEllF.I
4 0 39573 mm 0 01558" 0 7381 mm 0.0290ti" 0.62433 mm 0.02458" IS 2.71171 mm -0.10676" 0 44399 mm -0 01748"
~

15 0277II mm 001091" 0 39548 mm 0.01557" 0.47625 mm 0.01875" l 16 2 5542 mm -0.10056" 0.47269 mm -0 01861"
y
~

21 0.41042 mm 0 01251" 0.00558 mm 000022· 0.14097 mm 0.00558" 19 0 68351 mm -0 02691" 0 sms mm -0 02064"
22 0 30302 mm 0 Oil93" 0.01625 mm -0 00064" 000028 mm 0.00726" 20 0 18288 mm -0 00720" O00939 mm -0.00037"

~
4 2.71145 mm -0.10675" 0.22174 mm -0.0083" 0.15875 mm -0.00625"
15 2.71146 mm -010676" 0.83591 mm -0.03291" 0.72821 mm -0 02867"
l Verification of Dock Floor and Side Walls
~
21 2 6126 mm -0 10286" 1.64008 mm -006457" 1.50800 mm -0.05937"
22 2 71678 mm -0 10696" 0.99720 mm -0.03926" 084937 mm -0.03344"
A task that ran parallel to the ship's structural
analysis was an engineering study of the dock itself,
For the second repair condition (refer to Figure which involved finding a way to provide support to the
10), both absolute and relative deformations of Nodes ship where the bottom was severely damaged, without
4, 15, 16, 19, and 20 are important. The deformations of transferring excessively high concentrated loads to the
these Nodes are listed in Table 2. dock floor. The consulting engineering firm of James

678 The Reconstruction of the Exxon Valdez


R. Libby and Associates was retained to help develop the jacks and the upper hinge was suspended beneath
acceptable solutions. NASSCO estimated the loads the welded hull bracket, allowing space for shimming.
involved at each damaged frame. Fortunately, since the The half-pipe socket section on the shores was kept as
major damage was confined to the bottom structure of short as possible to limit strong-axis bending in the
the hull, the side shell and the internal struts were, for shore in the event that the pin and socket did not make
the most part, in good condition. The finite element uniform contact. The upper hinge pin, mounted on the
analysis of the ship structure showed that the loads ship, was made long to allow for tolerance in the
could be safely supported by special brackets to be fore-and-aft positioning of the ship.
installed on the hull at the level of the lower strut,
without overstressing the internal structure of the ship.
The ship itself would act as a bridge spanning between
the side shell brackets and the row of blocks just to the
port side of the keel line. (See Figure 30) SHIP SIDE SHELL---

The dock floor was incapable of supporting the


resulting loads, expecially so near the edge of the slab.
UPPER BRACKET HOUNTED
Libby Engineering proposed that brackets be installed ON SHIP SIDE SHELL
on the sheetpile wall of the dock. The concept was
readily accepted and the design efforts accomplished.

Side Shoring Design and Development

A design load of 250 tons was established for


each shore and bracket assembly. the design criteria
included provisions for monitoring and controlling the
load on each shore. The shores had to support enough
weight to prevent overloading the blocks on the dock
floor. However, too much load could overstress the
shoring system. Of particular concern was the
possibility of dimensional innaccuracies. The upper
brackets were installed using reference points on the
ship, while the lower brackets were installed using
references in the dock. Any innaccuracies would have LOWER HINGE ASSEMBLY
2" PLATE. 6" ROUND BAR
to accommodated.
250 TON JACK

The Freyssinet Company, recommended by


Libby as a supplier of heavy duty jacks, designed a
WI 2x79 wl th
system of hydraulic pumps, gages, manifolds, and st l ff ener s
250-ton capacity jacks that could provide control and
feedback for each of the 24 shores. The jacks had a
maximum piston travel of about three inches. It was
agreed that the shores would be designed a few inches
Fig. 31 General arrangement of shoring structures
short, with the remaining space to be taken up by
pre-cut shims. This would allow several inches
adjustment either up or down during the docking PERFORMANCE DURING DOCKING
operation by adjusting the jacks and by installing or
removing shims. NASSCO Steel Department fabricated all the
required parts and assemblies. The brackets were
The final design of the shoring system included mounted on the dock wall and ship side shell
the sheetpile-mounted brackets, jacks, upper and lower respectively. The jacks were positioned in the dock
shims, the shores themselves, and the upper bracket brackets and the lower hinge pin assembly was mounted
attached to the ship (See Figure 31 ). Sections of the on top of the jacks. Finally the shores were set in place
existing sheet pile were welded together at the seams to with the lower socket mating to the hinge pins and
make them act as a unit. A beam was installed to secured against the side fenders with turnbuckles. The
distribute the horizontal component of the shore load to 24 jacks were connected in groups to six manifold and
the soil behind the sheet pile. The upper and lower pump assemblies to be operated from the top of the
brackets had 15-cm (6-inch) diameter hinge pins that dock. (See Figure 32)
mated to sockets on the ends of the shores, to prevent
the possibility of weak-axis bending in the shore. The With all equipment and systems in place, the
hinge pins top and bottom, were mounted on heavy docking could commence. Six operators manned the
bearing plates. The lower hinge assembly sat on top of six pump stations to control the jacks and keep records

The Reconstruction of the Exxon Valdez 679


of the jack pressures. Engineers from NASSCO and Control Board (RWQCB) for the San Diego area was
Libby were in radio contact with the operators. The immediately contacted by NASSCO to discuss the
ship was hauled into the dock, the caisson was replaced, arrival and handling of the Valdez at the shipyard piers
and dewatering started. and drydock. The initial plans were discussed far in
advan~e of the arrival and the environmental guidelines
and nsk areas were identified for assessment and
solutions. The RWQCB mandated that the terms of the
PUMP NASSCO National Pollutant Discharge Elimination
System (NPDES) permit would be strictly enforced.
There would be zero discharge of oil into San Diego
SIX PORT MANIFOLD Bay.

Prior to departure from Alaska, the Exxon Valdez


was cleaned by a high pressure water wash in all tanks
that had cargo oil and also those ballast tanks
GAGE. TYPICAL
EACH LIN! contaminated as a result of the grounding. The exterior
of the vessel was also completely cleaned of all oil
fI
r r r r r So' OR 75" LIN!
TO EACH JACI(

15m (50') OR 23m (75') LINE TO EACH JACK


residue by high pressure water blast machines.

The areas below the water level in the tanks


could not be washed, but these areas had been
Fig. 32 Typical six-jack hydraulic station somewhat scoured by the rise and fall of the tide while
grounded and with the changing draft of the vessel.

The ship had a hog of about 15 to 23 cm (six to The vessel would arrive at the yard drawing
nine inches) at midship. Consequently, the end shores approximately 7.6 meters (25 feet) of water at an even
made contact with the top hinge pins well before those trim. This draft would ensure that the vessel did not
closer to midship. The jacks had been extended so that ground at the pier during the cycles of the tide and have
contact would take place as early as possible. As the sufficient draft to support ship handling by the tugs and
ship settled, the pressure was allowed to rise to near the pilot. Several cable pendants were installed on the
maximum predicted. During the docking the pressure vessel at the San Clemente Island anchorage prior to
was periodically relieved and allowed to rise again. As entering San Diego Bay to provide hookups to the
the intact bottom portion of the hull firmly contacted tugboats that would allow responsive ship handling.
blocks fore and aft, the deflection of the ship decreased
and the center shores made contact with the top hinge The maximum draft of the vessel entering the
pins. Gradually the loads equalized, indicating that the graving dock was limited to 5.5 meters (18 feet). The
ship deflections had been primarily due to elastic strains vessel required pumping up to lower the vessel draft. A
in the ship structure. 91.4-cm (36-inch) and 1-m (42-inch) floating oil booms
were placed completely around the vessel and pier. The
Once the ship was firmly settled on the blocks booms were anchored away from the vessel and pier to
and shores, final jack load settings were established. ensure a safe distance to allow any escaping oil to rise
During the next several days, as the ship made its final to the surface inside the booms. Oil skimmers and
settlements, heating and cooling in the sun, the pressure cleaning equipment were located within the boomed
changes were recorded and periodic adjustments were area. The Exxon Valdez was stabilized at the NASSCO
made. A setting was found that kept the loads within pier for two days to facilitate separation of any residual
the desired range, and shims were installed beside the oil which might be in the tanks.
jacks below the lower hinge pin. The jacks were
depressurized and removed. To ensure vessel stability during the voyage from
Alaska, certain undamaged tanks were ballasted with
ENVIRONMENTAL ISSUES AND slightly contaminated water, which under the
CONSIDERATIONS agreement, had to be removed from the vessel prior to
lowering the vessel draft. The water could not be
Pre-docking pumped into the bay or taken away from the yard by
conventional tanker trucks, due to the extremely large
The damage to the Valdez was such that the quantity.
NASSCO shipyard would be the first harbor that the
vessel would enter after departure from Alaskan waters. Exxon Shipping Company arranged vessel
schedules that would allow the tanker Exxon Washington
The Valdez had been under close observation to be brought to the yard in a light draft condition and
and scrutiny by all the various environmental and local berthed at the same NASSCO pier as the Exxon Valdez.
Government agencies. The Regional Water Quality The Exxon Washington was moved inside the booms and

680 The Reconstruction of the Exxon Valdez


made secure port side to the pier. The two vessels were night by increasing air pressure to keep the ship at the
connected to 20-cm (8-inch) and 15-cm (6-inch) cargo 5.5-meter (18-foot) draft.
hoses at the midship cargo manifolds with the hoses
secured to each vessel and laid on the pier. The area Pre-drydocking
where the hoses crossed the pier was made water tight
and both vessels provided a constant watch during The drydock is a graving dock that can be
pumping operations. Each hose was tested to 150 psi completely isolated from the bay after installation of the
and proved tight. gate. The bay outside the gate could be isolated by a
90-cm (36-inch) oil boom to eliminate any accidental
The Exxon Washington took off all 13,000 tons of discharge outside the NASSCO facility. The firm of
water. PDS Engineering was hired to develop plans and
systems to make the drydock totally separate from any
After all contaminated water and oil was outside or underground water source. The original
removed from intact tanks, the Valdez crew and salvage design of the graving dock allowed for a cross flow of
team commenced pumping air into the tanks to raise ground water from under the dock into a sump area that
the vessel to the drydocking drafts. The pumping is continuously pumped to maintain no more than 5.2
evolution was restricted to daylight hours by the meters (17 feet) of water pressure against the drydock
RWQCB to ensure that no contaminates were forced floor. The floor of the dock is fitted with relief
out of the tanks into San Diego Bay. Throughout this chambers that allow ground water to vent to the
evolution, the R WQCB Inspectors monitored progress drydock floor if the water pressure exceeds the
and found no discharge. The vessel was raised from 9.7 5.2-meter (17-foot) level. The drydock floor was cross
meters (32 feet) of draft to 5.2 meters (17 feet) of even connected to the sump area where excess water could
draft removing 55,717 tons of water without a trace of be pumped away. The drydock had to be modified to
discharge. separate the ground water from the interior of the
drydock and still allow a safety vent system. The cross
The grounding of the vessel and subsequent flooding trunks were sealed by installing a 25-cm
ripping of loose plates during the voyage to San Diego (10-inch) gate valve in the drydock sump and all floor
from Alaska had left plates and frames below the flat vents were sealed. The ground water pressure would be
bottom plane. With the vessel at an even draft of 5.5 relieved by external pumps on automatic service and
meters (18 feet) at the maximum high tide of 2.2 meters monitored throughout the drydock evolution. The
(7'-2") there was only minimum clearance over the drydock was inspected thoroughly by R WQCB
blocks which had been set at 1.2 m (46 inches). Inspectors prior to docking the vessel. For approval
purposes it had to be assumed that water remaining in
In discussion with the salvage divers and salvage the tanks after initial dewatering would contain
master aboard the vessel en route from Alaska it was significant quantities of oil and wax residue. When the
determined that there could be significant steel hanging Exxon Valdez is situated in the drydock only 90 cm (36
below the bottom plane and that the divers could not inches) of clear area is left on either side between the
ensure that they could trim the plates within an sheetpile bulkhead and the vessel sides which
acceptable tolerance. The effort of the divers was significantly reduces the water area that would have to
hampered while cutting at sea by the rise and fall of the be moved.
vessel and the lack of reference points. A straight edge
that could be ballasted down to 5.5 meters (18 feet) and PDS Engineering installed a 10-cm (4-inch) air
drawn along the bottom by divers and air tuggers was pipe line with air holes along the entire length. The
designed by the salvage master. The straight edge was pipe was installed along the drydock floor adjacent to
fabricated from 45.7-cm (18-inch) schedule 40 pipe into the dock gate. Compressed air at 100 psi was connected
a U-shape 6.4 X 54.5 meters (21' x 179') with roller pins to provide continuous yard air. Throughout the docking
at the horizontal ends to allow rolling the unit along the evolution when water was present in the drydock, air
vessel's bottom. was circulated through the pipe causing a constant
agitation of the water at the lowest point allowing
The salvage divers using "go/no go" jigs contaminants to rise to the surface. Water hoses from
measured and cut off any steel that was below the the pumping systems were secured and fastened so that
bottom plane. Each piece was marked and a retrieval their flow was directed toward the gate. This force of
line attached to ensure that each piece was saved and water kept the surface water and any potential floating
that no steel was allowed to remain on the bay floor material moving forward in the dock. The prevailing
after the vessel departed the pier. The damage to the wind direction in the drydock moves from the gate to
bottom at Frame 25, extended up the vertical side to a the forward end of the dock. The constant wind and
level just below 4.9 meters (16 feet). The ever changing water pressure would move everything away from the
air temperature in the tanks by the sun beating on the dewatering pump intakes on the floating barge. At the
deck and hull constantly changed the drafts and shape forward end of the dock an oil skimmer with an endless
of the ship. Extreme care was taken by the crew to loop mop was installed across the full width of the
release air during daylight hours and compensate at drydock. As needed, this continuous mopping

The Reconstruction of the Exxon Valdez 681


operation could remove any significant amount of the positions were reversed as each was emptied and filled.
oil and wax and allow the remainder to be put into The Exxon New Orleans and Exxon Washington took on
tanks. The drydock at high tide with the gate open has 50,000 tons of water until only 1.2 m (46 inches) of
a water depth of 7 meters (23 feet). The gate water remained in the drydock. The Exxon tankers
reinstalled at high tide and at the start of the ebb tide departed with their cargo. There had again been zero
will stay seated only if the water level inside the drydock discharge of water or oil into the bay and all activities
is maintained at least six inches lower inside than the were observed by the R WQCB Inspectors.
level outside. The water in the dock was drained
through the open sluice valves as the tide went down. The cargo tanks and those tanks breached by the
The Exxon Valdez tank air pressures were held constant, grounding still contained residue below the water level
the drydock gate sluice valves were closed just prior to maintained during the voyage south from Alaska.
low tide, and the dewatering pump continued pumping These tank structural members had to be cleaned prior
at 84,0001/min. (18,000 GPM) when the ship was to any work being done and it was not practical to clean
centered. Any water in the vessel remained in the them after all the water had been removed from the
vessel as the tide went down and landed the vessel at 5.2 dock. The most effective method of cleaning the tanks
meters (17 feet). As the weight was transferred from was to use the Exxon Valdez tank washing system.
hull flotation to the blocks, the air pressure in the tanks Because all water generated by the ship and shipyard
was gradually released to atmosphere. The pumping would be considered contaminated, bay water or fresh
continued until the water level was at 4.3 meters (14 water could not be used to wash the tanks.
feet) inside the dock and 4.9 meters (16 feet) outside.
The vessel was held in this condition and no evidence of The remaining 1.2 m (46 inches) of water (16,807
contaminated water outside the vessel was noted. The tons) in the drydock was used as the reservoir to supply
second major phase had been completed with zero the tank washing system. The water level in the drydock
discharge of oil or contaminants. was too low to provide suction for the ship's pumps and
an outside pump source was required. The 46-cm
Under the agreement with the WQCB, the (18-inch) pipe previously used as the floating straight
remaining water in the drydock, approximately 70,000 edge was disassembled and reinstalled on the pier
tons, was to be considered contaminated regardless of alongside the bow. The 46-cm (18-inch) pipe was
actual test results, and removed from the vessel and connected with 25-cm (10-inch) and 20-cm (8-inch)
drydock for disposal. Exxon Shipping Company again 1N/m2 (150 psi) flexible cargo hose from the pier to the
made tankers available to use for hauling water from vessel. The hose was connected into the main cargo
San Diego, back to Valdez, Alaska for treatment. handling pipe on the main deck at Frame 5 and then to
the tank washing units.
The pier and drydock configuration of NASSCO
did not allow for the direct connection of hoses to
Crowley Barge 274 was connected to the 46-cm
transfer water from the tankers Exxon Washington and
(18-inch) pipe at the gate and completed the circuit. As
Exxon New Orleans to the drydock or the Exxon Valdez.
the water was pumped to the vessel it was draining back
The large 84,0001/min. (18,000 GPM) dewatering
into the drydock out of the holed tanks. The water
pumps could not be used as they could not pump water
draining into the drydock contained the oil and wax
under pressure. The dewatering of the drydock was
residue water blasted from the tank structure.
done by placing four large diesel pumps on a floating
barge inside the gate with suction lines into the drydock.
The bubbler at the gate end and prevailing wind
The dewatering sump at the gate end was bordered with
continuously moved any material from the gate to the
a 60-cm (24-inch) steel fence to eliminate the possibility
floating skimmer where it was picked up and pumped
of any oil or wax not floating on the surface of entering
into tanks for disposal.
the pump intakes. The pumps were connected to a
manifold using 15-cm (6-inch), 1N/m 2 (150 psi) cargo
hoses connected directly to the port cargo manifold of Each tank took four to six hours to clean using
Crowley Barge 274, with a 50,000 barrel capacity. The this method and the tanks required very little cleaning
second barge, Exxon Barge 502, with a 80,000 barrel after being pumped dry and wiped down.
capacity was moored alongside the Crowley Barge and
connected to the starboard cargo manifold. Water was The 46-cm (18-inch) pipe and hoses to the vessel
then pumped from the drydock to the Crowley Barge were disconnected. Pumping to Crowley Barge 274 was
and then to Exxon Barge 502 using the Crowley 274 commenced to lower the water level to 46 centimeters
pump system. When Exxon Barge 502 was full, the (18 inches). Men and equipment were allowed to work
barge was shifted to Exxon New Orleans at Pier 5. The on the drydock floor and herd the oil residue and wax
water was discharged from Exxon Barge 502 to Exxon out from under the vessel and around the blocks. Short
New Orleans. oil booms and rakes were used and the oil was moved to
the skimmer for extraction. The final 46 cm ( 18 inches)
While Exxon Barge 502 was discharging, the of water was pumped to Crowley Barge 274 and
pumps continued to fill Crowley Barge 274 and the removed from the shipyard for disposal.

682 The Reconstruction of the Exxon Valdez


The drydock interior, the drydock blocks, and cleaning was done using water hose and yard water
the exterior of the vessel were contaminated with some pressures. The water was pumped from the drydock
oil and wax as a result of tank washing. Six 69N/m 2 sumps into truck trailers for disposal.
(10,000 psi) water blast machines were placed along the
drydock walls and the entire drydock was washed with Following these procedures, throughout the
cleaning solutions and blasted with high pressure water. cleaning of the vessel in the drydock and in the drydock
The residual water was washed to the drydock sumps cleaning process itself, there had been zero discharge of
and pumped into Crowley Barge 274. The final contaminated water into San Diego Bay.

Discussion
Phil Rynn, Member 1. Drydocking support requirements for a ship with
Overall the paper is an excellent description of the re- 30% of its bottom damaged.
construction of the Exxon Valdez and the authors are to 2. Access and method of transfer in the graving dock of
be commended for their concise presentation. The infor- removed sections and erection of new hull bottom units.
mation presented will undoubtedly be of value to builders 3. Environmental protection.
faced with large reconstruction tasks in environmentally For a ship with extensive bottom damage, it can be diffi-
sensitive locations. cult to determine how much contact will occur with the
dock's blocking arrangement. The inability to clearly de-
As is apparent in the paper, accurate assessment and
documentation of the extent of the damage was crucial in fine the extent of damage (other than general location)
compounds this problem. Support requirements for the
a repair of the magnitude of the Exxon Valdez. Knowledge
ship must prevent overstressing of the dock floor, as well
of the damage was necessary to develop a successful dry-
as maintain alignment as bottom units are removed and
docking strategy that would maintain the structural ade-
replaced. NASSCO's combined use of traditional blocking
quacy of both the hull and the drydock and still accommo-
with side shoring and blocking tables was shown to effec-
date removal and replacement of structures while
tively provide these support requirements.
preventing undue hull deflections and torsions. Along with NASSCO's use of the "tunnel method" for removal of
accurate damage assessment, the fact that the repair took damaged structure and the erection of new hull units was
place in the shipyard where the ship was constructed and an innovative solution to the restriction imposed by the
information on the undamaged hull was readily available size of the graving dock. The cost effectiveness of this
most likely contributed to the success of the repair. method, however, depends somewhat on how much un-
In the case of the Valdez the construction planning was damaged ship must be removed to provide access to the
designed to replace specific damaged block sections using damaged portions. In this case, since damage to the star-
a tunnel approach. Damaged blocks were cut away and board and starboard/center bottom sections was so exten-
replaced efficiently and quickly. With the advent of the sive, only minimal undamaged structure was required to
Oil Pollution act of 1990, it would be interesting to know be removed.
if the authors could advise the relative cost of fitting a The measures taken to protect the environment during
completely new bottom as opposed to replacing only one docking and repair are noteworthy. Unconventional steps
side as in the case of the Valdez. The replacement tech- such as the use of a compressed air and hose system to
niques utilized on the Valdez repair may enable vessels agitate the water and establish flow into the drydock dur-
currently in service to comply with the new laws. Also of ing docking operations, modification of venting systems to
value would be the authors' opinion as to what technical provide isolation of the drydock, and pumping of all dock
problems could arise in a different shipyard environment water to other ships for disposal were very effective in
than that of NASSCO. preventing an incident. NASSCO demonstrated that strict
The authors have provided a very descriptive paper environmental regulations can be complied with in a ship
presenting all of the steps needed to reconstruct the bot- repair situation even with damage as severe as that which
tom hull, taking into account the environmental and existed on the Exxon Valdez.
strength considerations and pointing out necessary techno- There have been other noteworthy occasions when ships
logical decisions that needed to be made. The success and with extensive structural damage have been repaired uti-
rapid completion of the repair procedure is indicative of lizing new construction modular techniques. In 1987 in
the use of proper planning as outlined in the paper. It is the Persian Gulf, the USS Stark (FFG 31) was struck on the
an apparent conclusion that with proper planning any task port side forward by two Exocet missiles. Upon her return
can be completed successfully. The useful content and ben- to the United States, Stark was repaired during the period
eficial applications associated with the paper will no doubt November 1987 to August 1988 by Ingalls Shipbuilding
be of great benefit to the industry. division of Litton Industries in Pascagoula, Mississippi. Al-
though the damage was extensive, unlike Valdez, it was
Robert R. Fargo, 1 Visitor topside, primarily to the main deck and forward super-
structure from frames 93 to 153. Thus it was relatively
The reconstruction of the Exxon Valdez by NASSCO easy to scope the extent of repairs for planning purposes.
provides some interesting and innovative solutions to the Docking of the ship could be done in a normal manner and
unusual problems encountered in this repair situation. Of there were no unusual environmental hazards.
particular interest were the creative approaches taken in Stark was not repaired in a graving dock. Instead, the
addressing three primary concerns: ship was raised on the yard's launch platform, a floating
drydock, and then translated onto land using a motorized
1
Ingalls Shipbuilding, Inc., Pascagoula, Mississippi. pallet car system. On land, the damaged structure was cut

The Reconstruction of the Exxon Valdez 683


and removed in one section of about 150 tons and new the docking personnel. A very commendable job by all
structural units were erected. Unlike Valdez, the repair of concerned.
Stark required significant replacement of outfitting sys- The clincher to this outstanding repair job was how the
tems. Much of this work was accomplished by preoutfitting environmental issues were organized, planned, and exe-
of the structural units prior to erection. cuted. It's almost unbelievable that the environmental pro-
On land, much better access was provided to the dam- cedures could be carried out from the arrival of the vessel
aged areas than would have been afforded in a dry dock. through the drydocking procedure and the cleaning pro-
The damaged section was lifted from the ship using 200 cess of the drydock itself with zero discharge of contami-
and 300 ton gantry cranes. New structural units were simi- nated water into San Diego Bay-my hat's off to the Na-
larly set. If bottom units had required replacement, the tional Steel employees and the authors.
increased accessibility would allow relatively simple trans-
lation or trucking of units into position. If it is possible in a M. E. Young,2 Visitor
particular situation where extensive bottom damage exists One cannot help being impressed with the team effort
and a graving dock with adequate dimensions is not avail- between Exxon and NASSCO in developing the plan for
able, translating the ship onto land would eliminate the this extensive reconstruction project. This effort should
need for a "tunnel method" of repair and the possible need receive the Nobel Price of planning.
for removal of undamaged structure in order to provide The amount of damage sustained to the hull created
accessibility. However, handling environmental concerns a difficult drydocking that was readily addressed by the
such as existed in the Valdez situation during docking and NASSCO team, assuring structural integrity both in the
tank cleaning would be more difficult since it would not be drydocking and subsequent tunneling operations.
possible to contain the contaminated water in the floating The eventual tunnel method certainly was the best ap-
drydock or shiplift platform. proach that could have been used both from the sense of
limiting costs, and production efficiencies. To attempt this
M. L. Ingwersen, Member project on other than a graving dock would have been
costly and would have required more extensive engi-
What a great ship repair accomplishment. The amount neering.
of hull damage involved with its jaggedness and torn areas This project was probably one of the most complex engi-
hanging below the baseline; the added publicity and public neering projects in recent history. The decisions reflected
awareness of the environmental aspects of this very large a great deal of work that was flawlessly executed. The
crude carrier of worldwide notoriety made this a challeng- environmental considerations were similarly well man-
ing job. aged, and establishes some benchmarks for the rest of the
The company, realizing that this was not the usual bot- industry to target towards.
tom damage repair job, had the presence of mind to assign The steel director, Mr. Duncan McNeill, should be com-
a small knowledgeable team to review the detailed damage mended for his extensive planning, contingency planning,
reports and specifications. and coordination of the project. His extensive training,
The team's arrival at the Tunnel Method concept was in experience, and background probably makes him one of
my estimation a "brainstorming" that must have taken the best qualified persons in the world to take on a project
many hours of innovative thinking to deviate to this degree such as this. The successful conclusion certainly vouches
from the standard bottom damage repair. for his capabilities.
The damage being in a reasonable straight line fore and
aft and conforming somewhat to the original centerline
and outboard block configurations supported the two- Authors' Closure
tunnel approach that was arrived at by the team. Mr. Rynn correctly points out that maintaining the struc-
The team having arrived at the tunnel method of repair tural adequacy of the dock and the ship were major issues.
and then challenging the hull technical department and We assure him that these issues were treated as such and
the outside consultant to determine a feasible way to sup- given very serious consideration.
port the ship and its structure must have caused some Regarding Mr. Rynn's first question, we are of the opin-
sleepless nights. ion that the relative costs of fitting a completely new dou-
The detailed planning for the job was well thought out ble bottom using the tunnel approach would be roughly
and reasonably executed. Experience dictates that in any proportional to the tons of steel involved. Schedule, on the
job of this magnitude you're going to find that on the job other hand, would not necessarily suffer since if the entire
alterations or changes to the detail planning had to be bottom of the ship is being retrofitted it could be arranged
made. This job was no exception, changes had to be made; such that two tunnels are being worked simultaneously.
they were made in a timely fashion and the job proceeded. Another possible source of savings is likely to be realized
In addition to the repair and the supporting of the ship due to the easier workability of an undamaged ship.
the steel movement system required considerable innova- Mr. Rynn's second question relates to the technical prob-
tive brainstorming and a unique method to accomplish the lems that might be encountered by other shipyards when
moving in and out of large hull blocks in a constricted area attempting to use similar techniques to those used by NAS-
where cranes were of little value. SCO. We feel that any such problems would be related to
The total handling method was innovative and accom- and a consequence of differences in facilities. The ability
plished the job; however, from the paper it is hard to visual- to do this type of repair work is very much facility depen-
ize and comprehend the operation of the various compo- dent and requires that individual shipyards adapt the pro-
nents of the system. I would have appreciated seeing better cess to match their particular facilities. We feel, however,
pictures of this operation and a clearer description. that NASSCO's approach to this repair problem is trans-
The three different methods of supporting the ship ferrable to other facilities, subject to appropriate adapta-
couldn't have been better conceived and engineered by
hull technical and the outside consultant or executed by 2 Portland Ship Repair Yard, Portland, Oregon.

684 The Reconstruction of the Exxon Valdez


tion, and applicable to other situations such as retrofitting tional bottom damage repairs and was the product of con-
double bottoms. siderable brainstorming sessions. The Engineering Depart-
Mr. Fargo-The authors wish to express their apprecia- ment confirmed the production tunnel method approach
tion to Mr. Fargo for his comments. He zeroed in on some was technically sound in terms of dock loading, support of
of the unusual problems we encountered in this recon- the damaged vessel, and the ability to maintain the ship's
struction project. The drydocking support requirements structural integrity. The extent of pre-planning and careful
and the measures taken to protect the environment were preparation by all concerned was crucial to the successful
two of several problems requiring innovative solutions. completion of the reconstruction.
It is interesting to note that new construction building The authors regret that the pictures and description of
techniques were utilized in the repair of the USS Stark the Steel Movement System made it hard to visualize and
(FFG 31). The authors are not sure if we see any merit in comprehend the operation of the various components of
Mr. Fargo's comparison between the Exxon Valdez and the system. We hope that during the actual presentation
the Stark repair problems. The principal difficulties with of the paper, the additional slides shown helped to clarify
the Valdez problems involved simultaneously supporting, the system.
removing, and renewing a large percentage of the bottom This was certainly a team effort integrating planning,
of the ship. This situation did not exist with the Stark engineering, production, and materials altogether as one
project. unit which contributed to the successful completion of the
vessel.
Noteworthy was the reference to the yard's launch plat-
Mr. Young-Our thanks to Mr. Young for his complimen-
form, a floating drydock, and the subsequent translation
tary remarks. He quickly assesses the team effort between
onto land of the ship using a motorized pallet car system. Exxon and NASSCO in the evolution of the reconstruction
In a case of damage where strict environmental considera- project. His conclusion that the tunnel method was the best
tions are not required, this system could possibly be used approach from the sense of limiting costs and maximizing
as an alternative to a drydock. production efficiencies is considered high praise. Also, the
Mr. Ingwersen-The authors wish to express their thanks comment that the environmental considerations were well
to Mr. Ingwersen for his in-depth analysis of the paper. His managed, and establish some benchmarks for the rest of
remarks fully captured the atmosphere of this project. As the industry to target towards, is very much appreciated.
he correctly points out, the review of the damage survey The success of this reconstruction project is a direct result
reports and the eventual arrival at the Tunnel Method of of the teamwork and dedication of the employees of
reconstruction was indeed a major deviation from tradi- NASSCO.

Panel Discussion
Society President Arthur J. Haskell presiding

[EDITOR'S NOTE: After formal discussions on the paper and the authors' closure, a
panel discussion was convened on the broader topic of oil spill prevention and tanker
construction. Following are the major contributions to the panel debate.]

Thomas R. Hagner, Jr., Member


MID-DECK TANKERS
J
I am very pleased to address SNAME on the subject of
mid-deck tankers.
I've been watching the recent budget debate in Con-
l
gress. I think probably the most important question for
naval architects and shipbuilders is: Do we really want
these people designing our oil tankers for us?
l
I would like to thank NASSCO for their excellent paper
on the Exxon Valdez repair. I particularly liked a sentence
on the first page which has meaning for more than ship
repair. It says "The challenges and restrictions can often
become the stimuli for promoting innovation." With the
new oil spill law, we certainly have the challenges and Fig. 33 Typical transverse section
restrictions-so let's get on with the innovation.
Figure 33 shows a mid-deck tanker. As you can see it's
essentially a double-sided ship with an additional deck The basic concept (Figs. 34, 35) is very simple. The cargo
somewhat below mid-depth. Ballast is all in the wing tanks oil level in the lower tank is well below the waterline.
and fairly conventional structure is used in the cargo tanks. Thus the seawater exerts an upward pressure on the ship's
At the current stage of design, no unusual structural prob- bottom in loaded condition. When the bottom is pene-
lems have been noted. trated, seawater enters the cargo tank until hydrostatic

The Reconstruction of the Exxon Valdez 685


balance is reached. Folks, this ain't rocket science. There
will be no oil pollution in the example shown. If the ship
is stranded and the tide falls, it is very easy to design a
system to transfer the cargo to an adjacent ballast tank.
There would be plenty of time, so risky automatic devices
would be unnecessary.
Designed in this fashion, the Exxon Valdez would have
lost no oil. After looking at NASSCO's pictures today, I
don't think we can reasonably say the same for any practi-
cal double hull design. My first exposure to the mid-deck
concept was in June of 1990. I was a member of the API
Tank Vessel Committee which sponsored the Forum on
Alternative Tank Vessel Design. Mitsubishi Heavy Indus-
tries presented model test results and outline details for
mid-deck tankers. In my personal opinion, it was the best
concept for new construction presented that day. Mitsubi-
shi subsequently presented mid-deck tankers to the Na-
tional Academy of Sciences, and will talk this month to
IMO's Marine Environment Protection Committee. I un-
P SW > poi I derstand MHI's presentation will be on behalf of the Japa-
nese government.
Fig. 34 Basic concept The mid-deck concept is under serious consideration by
Amoco Transport Company for use in its new construction.
However, Amoco is not presently advocating mid-deck
tankers pending completion of our study. The advantage of
this concept clearly is pollution prevention. Disadvantages
are mostly operational in nature.
The upper and lower tanks are interconnected and
drained by the same cargo manifold. There is nothing re-
ally unusual about the piping and valving. On the other
hand, major maintenance areas of concern have always
been the cargo tank tops and bottoms. In this ship, we have
essentially added an extra top and extra tank bottom with
no operational advantage nor any increase in oil carrying
capacity. (See Figs. 36, 37).
One of my major concerns with this design is tank clean-
ing. There is a lot of extra structure in the cargo tanks. Gas
freeing, on the other hand, should be no problem. Tank
inspection should be no more hazardous than for a single
hull.
Why should Amoco be interested in this? The answer is
technical uncertainty of double hulls. No VLCC's have
ever been built with double hulls. No construction has com-
menced for any double hull oil tanker larger than a Suez-
max. There are scale problems in applying 40 000 DWT
ton product carrier structural details at the VLCC size. In
Amoco's ongoing parallel study on VLCC double hulls, we
are finding very heavy plate in the web frames in the
double bottom area. This raises serious questions about
fabrication even before we tackle the issues of dynamic
response and fatigue for the double hull structure.
Designing a vast horizontal inner bottom that will always
either be holding up the entire weight of the cargo or
resisting the reverse hydrostatic head of the draft in bal-
last-this causes concern.
Everyone knows that under the new oil spill law; if an
owner acts reasonably quickly, he could still build and op-
erate a single hull VLCC in offshore U.S. waters for her
entire economic life. Technical uncertainty could more
than justify such a decision.
Safe and efficient maintenance of ballast tank coating
also is a serious concern, and double hull VLCC's have
over 2'l2 times the ballast coating surface area compared to
S e a W a L e r
single hulls. The mid-deck tanker has less than l 'l2 times
the surface area. A mid-deck tanker also offers significantly
Fig. 35 Mid-deck tanker improved collision protection.
686 The Reconstruction of the Exxon Valdez
• 1 sum 01 IRArol /

Fig. 36 Transverse section schematic (looking aft)

T.lEYl:l W'1:
ilii.-l£VU Al.All:Kl C.O T. HATCll
(C.11.l.T.l , ;Tc.O:cn I ' KATCL.
( c. 0. L.T.J '·

'' - -

.,
..,,
,,

Fig. 37 Longitudinal section schematic (profile)

The Reconstruction of the Exxon Valdez 687


tanks are slack. Damage stability needs to be further stud-
Energy E [kJ] ied. A trim and stability booklet almost certainly will be
Critical Speed
v., [kn] required. Direct calculation of the free surface effect
5
8. 10 8 rather than simple formulas will be necessary for this type
Absorbed Energy E and Critical Impact Speed ver of structure.
for Various Wing Tank Breadths b The steel weight of mid-deck tankers will be a few per-
7 cent higher than an equivalent double hull. However,
overall construction cost will be somewhat lower.
Well, it might be nice to say this is a brand-new innova-
5
6. 10 6 tion, and that one could get rich on the patent. However,
this concept dates back to the infancy of bulk oil transporta-
ver tion. Here is an 1886 mid-deck tanker (Fig. 41). A British
5
5. 10 5 technical journal of the day had the following to say (by the
way, I would have trouble saying it better today). Quote:
4. 10
5
4 In the oil tanker Gluckauf, it would be possible to
imagine the ship's bottom entirely knocked out,
and yet, she would float and come to her port
3. 10
5
3 of destination without any serious casualty. The
lightness of the oil itself is such that it will remain
in the upper part of the damaged tank. Only a
2 few months ago, I was speaking with a Russian
gentleman who owns a vessel in which that very
thing occurred. The vessel struck an anchor ...
1 . 10
5 Ratio Wing Tank Breadth b and had her bottom completely torn along; but
Ship's Breadth B not withstanding this serious damage, the loss of
0.02 0.04 0.06 0.08 0.10 0.12 0.14 0.16 oil was extremely small.
0 2 3 4 5 6 In closing, I would like to thank Mitsubishi Heavy Indus-
Wing Tank Breadth b [m] tries for their technical support in my presentation today.
I don't know what is going to happen to the mid-deck
Fig. 38 Critical impact speed (source: Germanischer Lloyd) tanker concept, but its apparent attractiveness should
serve as a challenge for all of us to look for something even
better.
A mid-deck VLCC will have 6-m-wide wing tanks where I consider myself an optimist despite the fact that every-
as a double hull VLCC would only have three. As can be thing is going to hell in a handbasket.
seen in this study by Germanischer Lloyd, increasing the And, if we look at it optimistically, Congress is saying
wing tanks from three to six meters increases the collision that we have to spend 20 percent more on our tankers to
energy that can be absorbed without an oil spill fourfold. reduce oil spills. That's a lot of money. So let's take back
The critical relative velocity of a ship in a perpendicular our authority as naval architects and shipbuilders and find
collision with her sister goes from 4 to 7 knots which moves ways to spend that money wisely. Thank you.
it well within the normal range of channel maneuvering.
(See Fig. 38.) Charles Corbett,3 Visitor
By the way, this doesn't mean that we have done any OIL POLLUTION ACT
good, if we make ships unnecessarily larger with needless
empty space, or if we restrict carrying capacity so much The thrust of my remarks will be a little bit of a history
that many additional ships would be needed. on how we got this act, how it evolved before the Exxon
Many of you are probably wondering what happens on Valdez, and a principal provision of the act which is largely
that dark day when someone pumps the lower tanks out illusory, and that is the matter of limits of liability, where
with the upper tanks still full? Will she roll over? My ver- perhaps the word "limit" shouldn't really be used.
sion of Herbert Engineering's Cargomax Loading Program Some of you may know that the legislation was being
has the ability to simulate voids anywhere in the ship. worked on in the Congress for nearly 15 years before the
So it was fairly easy to computer fit a middle deck on Exxon Valdez. In fact, I heard one staffer earlier this year
Amoco's double sided Aframax ship, the Ocean Leader. when the Hubble telescope went up remark that this won-
This is the stability for the Ocean Leader as-built with 46 derful instrument, the Hubble telescope, is going to let us
percent full tanks. This would be the same as a mid-deck see so far back into the past that we might even get a
tanker with only the lower tanks full. (See Fig. 39.) glimpse of the first oil spill legislation that was tried in the
Figure 40 shows data for the mid-deck tanker with the Congress.
46 percent cargo shifted to the upper tanks. Stability is still The Reagan Administration at one stage set back the
no problem. All IMO minimums are exceeded by a large process when in about 1982, I think it was, they sent me
margin. It is interesting to note that you might very well to the Hill to testify that we didn't need oil spill legislation,
want to operate this way. The bottom of the upper tank is contrary to what the previous two Presidents from both
smooth and is fitted with a sump while the bottom of the parties had said. However, Elizabeth Dole came into the
lower tank has a conventional bottom. You could reduce Department of Transportation following that, or about that
overall pumping time if you stripped the lower tank while time, and became very interested in oil spill legislation.
pumping out the upper. She was quite interested in the international regime, often
The mid-deck tanker also has plenty of intact stability in
normal loaded condition even when all upper and lower 3
Captain, USCG (Ret.); Temple, Barker & Sloane, Inc.

688 The Reconstruction of the Exxon Valdez


OCEAN LEADER From: GALEOTA To: TE.:AS CITY OCEAN LEADER To: T~·t~-3 CTT':
1•11)•:"=1gE·: lES r

STATXCAL BTABXLXTV BTATXCAL BTABXLXTV


DEF'f'iFTU~:E AT 46i: FULL Mii_•-DE::":t.i' ft1HI !--i: l•tf ;HI 1Jl1Jb"t•':"-3 EMF'!;

A·nu l.==.ble IMO A167 i :.• ~' l f~ I!·lO f:._1_:;1

~re3 ta 3 degrees
1_ 1 .•. 1 1.57'5 m-r·ad. 1). •)55 m-r·ad. 7'.·'·. m-r---d,
Are~ t(~ 4•:•.•:• degrees :: • 3:.~.q m-rad. 1_1. j)q1:1 m·-t·ad. •:•', _ 111 -1 _.,u ..
~r~~ :•_1 •. _•-4•).•Y degrees 1_1. q48 m-r3d. '-'. O -~·:1 m-r·acJ.

1;r11.J le? ;:i.t_ M::.•:'l!'nttm '31.. :::;:,:.o deg _:5_,-, 'jE~Q


t-i111Jl-::· .:.1t M-0:1:.l:l!L'f11 GJ: -::. 7. ·f d ~(~ ..:.::..•:• :.JEU
Ma:: Lrnum GZ ~•• 5'...: in •). -=·=· In M ::..· .' 1nt\:T1 l37.. .2 • ~~ .:i. '-' • ..::'.·-~ m
Int ti.:- l GM l 1t.48 in 0.15 m ~:: .l I l ;;' i Gt-it ··•• l..:. m
Dowr1fl0o(j1nq ~ngle 63.9 deg

11.48M
111 ,,,.
,,..-

_..,~-
~---··--- 5.3611
3
.e __ _,,.-· ..--·--· . ......
.,,,..
""'",-:-:-·-...~-_--;-::::--:-?..,..--------._____~........
t ~'r
e
I'
s
/~.po"'
,-/'~
----------- ----..
----~--....
e
t
e
fl ,,.~ ......
.. ..
- - -...
--~ 5 g /"_,,...,......
_/-~
.,
-...
18 z0 38 40 -.....··.50 &0
9 :L:----'-~~111~--'-~~2-9~-'-----'3-9~~~4~11~-'-~~59~~---:69 ·.... degrees
-L ··....
degrees _


····...
"·.
··.... ,

-5 -3 ~

Fig. 39 As-built 85 000-ton vessel Fig. 40 Mid-deck tanker, 85 000 tons


plate gauging, overfill devices, tank level monitoring de-
Earty Slngle Skin Tanker vices, double hulls, research and development, contin-
gency planning for tankers-and I'm just naming a few of
these now. It has an entire title on Prince William Sound
which establishes the Prince William Sound Oil Spill Insti-
tute. I'll leave it for yourselves to read the act and see what
the Oil Spill Institute is supposed to be doing.
It calls for the establishment of a light on Blyth Reef,
and it would improve the vessel traffic system in Prince
William Sound. The bill also contains something that was
added at the very last minute by Chairman Jones, a real
smell of pork to this. It's a moratorium on offshore drilling

@~~B!~>
on the Outer Banks. It was a big surprise, the last day of
the conference committee. It caused a big brouhaha. But
it carried and it carries with it this provision. It's a very

Ef11Jdsatpi§~
short part of the bill, but it's a moratorium on drilling in
that area.
It revamped the national response mechanisms very
GJucksuf much. It gives the President much more authority with
Steam Tanker, Built 1888 respect to oil spills and directs the President to direct the
Double Bottom Under Aft Macntnery Space,
Single Skin Cargo spaces
response to oil spills when the public health and welfare is
significantly affected or threatened.
Now to liability and compensation, just for a minute.
When we talk about liability, I'm talking about what the
owner or operator or the responsible party is liable for, and
compensation refers to the one billion dollar fund that was
established through a 5-cent-per-barrel levy on oil. The
liability for tanker owners was eventually set at $1200 per
gross ton. And you might be interested in how the Congress
got there.
Prior to the day that the Senate passed their bill, S-686,
all of the bills, including 686 on that date, the President's
C!N rRe BUUU1Lio0
bill, the House bill, and the 686, all called for liability limits
Fig. 41 Mid-deck tanker, 1886 of $500 per gross ton. That fit in nicely with the interna-
tional scenario. Everything was consistent. It was fairly
rational. Insurance would be available. And nobody was
referred to as "the protocols." Perhaps Admiral Kime men- saying anything else. Howard Metzenbaum took the floor
tioned in his address. And she really wanted to see oil spill in the 11th hour of the discussions, pounded the table with
legislation enacted, and she worked real hard on it. In fact, his fist, and much to the surprise to me and to George
I had the pleasure of being her special assistant on oil spill Mitchell and to practically everyone else in the room said
legislation for the last two years of my regular Coast Guard that if $500 a ton is good, then $1000 per gross ton has got
service. to be doubly good. And it passed in the blink of an eye.
So in 1984 we had really a whole new era of oil spill Then the Senate went to the press that evening and the
legislation initiatives. It looked like things might go some following day throughout the country you read how well
place. But as it turns out, the Congress couldn't agree on the United States Senate had stuck it to the oil companies.
one principal issue, that's the matter of state preemption. And I can guarantee you that I don't think Senator Howard
The House had always favored state preemption. Senator Metzenbaum and perhaps the majority of the Senate had
George Mitchell and the very powerful Senate Environ- even a clue that oil is carried by others than oil companies.
ment and Public Works Committee opposed preemption
Then you heard recently with the budget business that
of any kind, and the Administration was somewhere in the
the House and the Senate often vie for attention. Perhaps
middle.
Now comes Exxon Valdez. Most insiders predicted that some of you know that the boys over in the House often
we would have oil spill legislation following the Exxon Val- refer to the Senate as the House of Lords. So it got over to
dez. In fact, at that state, then Commandant, Admiral Paul the House now and they said, "Well, we can't let the Senate
Yost, asked to return from the private section into uniform outdo us here. We've got to do better. So we're going to
and be Sam Skinner's advisor on the legislation. And we make it $1200 a gross ton and we're going to slice that in
took legislation to the Hill on the 11th of May, which was the middle and we're going to assign part of that to cargo
largely a liability and compensation regime. Few predicted interests." How they figured they were going to enforce
that it would take Congress almost a year and a half to see that, I haven't a clue. But the final readout is it's $1200 per
oil spill legislation enacted, and I certainly don't know of gross ton for tanker owners.
anyone who predicted the shape that the legislation would Now, as I said a minute ago--and there would be no
eventually take. But soon we were stuck in the same quag- preemption of state governments-seventeen states have
mire over state preemption. unlimited liability. But the important part of this whole
During these months that followed, everyone wanted thing-perhaps for you, perhaps not, perhaps for some of
into the act, and most of the people got into the act. Again, you anyway-are the standards for breaking liability. And
as you may have heard last night, in addition to liability and I want to read you those right out of the act.
compensation, the act covers oil spill prevention, removal, First of all, there's a couple of fairly rational standards of

690 The Reconstruction of the Exxon Valdez


gross negligence or willful misconduct or a failure to report in the design and operation of double-hull vessels that must
an oil spill. Well and good. Also, you lose your limits of be addressed.
liability if you fail to comply with an order of the President We don't know all the answers concerning double hulls,
or if you do not provide all reasonable cooperation and but I think we know a lot of the questions. The public, we
assistance required by responsible officials. Unfortunately, believe, perceives that the double-hull vessel will end oil
the act doesn't say who a responsible official is, whether pollution from tank vessels. We believe that if we don't
it's the Federal on-scene coordinator, a state flunky, or a come up with the right answers to serious issues regarding
local fire chief. double-hull design that the double-hull tanker may be-
However, this is the section that I think might interest come part of the problem rather than part of the solution.
you. It says Subsection 8, which is the limits. It does not In this brief presentation, I'll present some of the issues
apply if the incident was approximately caused by "the involved and give you one owner's perspective.
violation of an applicable federal safety, construction, or The first issue that we have to struggle with is what
operating regulation." So far so good. I'll read that again. should a double hull look like. Should it be like the one on
"The violation of an applicable federal safety, construction, the right or perhaps more like the one on the left? The
or operating regulation by the responsible party, an agent important point I'd like to make is that both designs have
or employee of the responsible party, or a person acting problems.
pursuant to a contractual relationship with the responsible What we'd obviously like to have happen in any double
party." Now I'll leave it for you to decide if any of those hull is something more like on the right there where you
persons are you, for instance. have crumple rather than the double hull really acting
Well, what are the implications of this act? First of all, more like a thick single hull. Now the industry hasn't done
the availability of insurance certificates is really in ques- much work on this issue, and I think it's one of the issues
tion. The act provides for direct access to insurance compa- that cries out for work to be done to define how to better
nies. What with the standards for breaking liability what or best build double-hull tankers whereby you will have
they are, the insurance companies, the clubs in London, crumple and the inner hull will remain intact in any kind
are saying, "We're not going to play this game. We're not of a collision or grounding.
going to issue certificates." Whether they'll back down or Access, we think, is one of the very important issues in
not on that remains to be seen. double hull design. Absent the work required to better
How will the independents obtain evidence of financial define what sort of dimensions would allow crumple rather
responsibility? A major question. than breakage of double hulls, we believe that B/15 is
Will some states have trouble receiving oil? There are a reasonable dimension and it does certainly satisfy one
two carriers of oil in this country that recently stopped requirement where it does allow you reasonable access
serving, at least black oil movements, in Maine and Rhode into your double-hull tanks.
Island. Whether or not they will maintain that posture or Now here's a midship section of the Chevron 130 000-ton
not remains to be seen. vessel. Obviously being able to design in incline ladders,
Will responsible operators leave the market to bucket no problem. You get down into the double bottom area, we
shop operators, particularly the companies that are owned have 2 m clearance between the longitudinals, so walking
by individual families? The Greeks, for example, are talk- across or stepping across longitudinals is not a problem.
ing that "we don't really want anything to do with this. There's reasonable access, as reasonable perhaps as you can
We're very wealthy as it is, and we just simply can't take get in a double-hull tanker.
the chance on losing everything that we've got." Will at- Now this is a tank section aft, and you have similar sec-
tempts be made to shield liability through one ship compa- tions forward. Now the going gets a little tougher. The
nies, and will it work? shape of the hull starts to play a part and access down about
Will there be a cost at the gas pump? I suspect that half way is really easy-getting down to the lower sections
there will be a cost, although things being what they are becomes a little more difficult, but with B/ 15 type dimen-
internationally it doesn't seem likely that we'll be able to sions it's still not really a problem.
identify them. This is a cartoon. We just moved the bulkhead out to
And then perhaps the most important question of all is, show what it might look like if you only had 2 m. Obviously
Will there be a reduction in oil spills? I think the answer access becomes nearly impossible or certainly very diffi-
to the last question is somewhere between maybe and cult. In our small double-hull tankers we have problems of
probably. access, but I don't think they're anything like you would
find in this kind of an arrangement.
John Kimble, Member This is a midship section of a vessel currently being built
[EDITOR'S NOTE: The discusser frequently refers to figures, or in the Far East. Now here they've solved some of the prob-
slides, that were part of his presentation at the meeting. Although lem of having a very shallow double bottom and having
copies of these graphics were not received by us to include here encroachment of the longitudinals into it to make access
in the printed TRANSACTIONS, we decided to leave standing Mr.
Kimble's references to them instead of risking eviscerating his
very difficult. They've made the longitudinals shallower,
important discussion.] but then you get into very frequent frame spacing, about
half what we have, and you have the series of longitudinal
DOUBLE HULLS girders. So basically what you've done is built yourself a
We all know the law is passed, but the law simply states bunch of boxes. On a Suez max-type vessel, you may have
that new vessels trading in the U.S. must have double hulls. as many as 500 boxes. And if you don't specify something
It's significant that it doesn't define what a double hull differently, the access from box to box is probably going to
must be. be a hole about 600 mm by 400 mm. Access is going to be
Now, Chevron has operated five 40 000-ton double-hull certainly difficult.
tankers for 15 years. And we just recently completed the Here's a photo of a fellow doing a little inspection work
contracts for two 130 000-ton double-hull tankers. Those in one of our double-hull vessels, the 40 000-tonners. It's a
experiences have convinced us that there are serious issues little tight. Here's another one. Now these photos show
The Reconstruction of the Exxon Valdez 691
some of the tight access perhaps. What they don't show is vessel that would have at least the capability in a damaged
the heat, the lack of ventilation, the smell, and the down- condition to survive that a single-hull vessel would. Now,
right slimy conditions that are found in these tanks. we're talking about a case here where the vessel is fully
The whole point here is that unless we design double-hull loaded to 98 percent, it grounds on an object, it clears the
vessels with consideration for good access, inspections object and floats free.
won't be made or they won't be made properly. And if We took a look at a single-hull vessel and found that
they're not made properly, we're going to have lots of basically we could damage it to full cargo length. We ended
problems. If I were a class surveyor and ships were going up with about 33~-deg heel, and we have taken on an
to be built without consideration of access, I'd be working awful lot of water because we flooded both those large
on my resume right about now. ballast tanks here on the starboard side, but the vessel
Getting air into these spaces, not only in the event you survives. Then we looked at the 130 000 ton double-hull
have to purge out hydrocarbon vapors in the event of a vessel with L-type tank configuration subdivided in the
leak, but simply for normal inspections. Anywhere you middle and no cargo tank subdivision longitudinally, and
have the configuration where you have a tank dead end at we found it doesn't fare quite as well. Here we can damage
the centerline of the vessel, you have that long dead leg back through number 6. We end up with about a 20-deg
that is going to be very difficult to get ventilation into it. heel. We have a displacement in this case of about 180 000
In our case we decided that the only way we felt we could tons. It survives. If you hit number 7, it's over. You capsize.
reasonably get ventilation in there is to put a purge pipe Then we look at what happens if perhaps you don't load
in. The idea here would be to put a ventilator on that purge your tanks quite full and you're carrying a little bit heavy
pipe, suck air out, put another ventilator on a Butterworth cargo, you leave them a little slack. In this case we've got
opening in the tank and blow air in. Even at that, it's going 98 percent full tanks, so we've got some free surface. Now
to be difficult. And this is a design without all the boxes. If we damage. By the time we hit number 2 cargo tank, it's
you have a design with the boxes, I don't know how in the all done. We've capsized. As you can see by the righting
world you're ever going to get adequate ventilation in that arm curve there, no righting energy left. Don't know that
space for inspection. it will float neatly upside down like that but ... [Laughter]
Tom mentioned the coating areas, and that's a problem. . .. it's not going to float right side up either.
Here showing our 150 000-ton single-hull vessel and the Now we took the case, we widened out the double-hull
130 double hull, obviously the coating areas are tremen- sections as per the Chevron design. We have now 3.75-m-
dously different. Now the industry hasn't had a very good wide wing tanks and 3.295 m height of double bottoms.
track record in being able to maintain ballast tanks, coated It's still the same configuration though subdivided in the
or not. As a matter of fact, it's been so pitiful in some cases, double-hull structure on the centerline and no centerline
whole sections of the side of the vessel have fallen off. It's subdivision in the cargo tanks. The damage it can withstand
a little embarrassing to have the side of your vessel fall off. is about the same. However, you'll note that the displace-
It's a little worse if half the bottom falls off. ment in the damaged condition is worse. Now rather than
This issue was the big issue that was being talked about 180, it's about 186. And the heel is greater, rather than
wildly at the time when the debate still raged-Should we being about 20 deg heel, you've got a 26-deg heel. And this
have double hulls or not? This was the case of we poke a is the detrimental case for wider and wider double sides or
hole in the ship somewhere and, oh my God, we're going deeper and deeper double bottoms. When you do damage
to flood all this water into the double bottom, the vessel's them, your situation in a damaged condition is obviously
going to sink, it's going to be harder to salvage, and it's worse than if they are narrower.
going to eventually break up and we're going to lose the Now this slide just gives you a little terminology here so
whole shooting match. you'll understand what we're talking about when I get to
We agonized over a subdivision in the double bottom, the slide on the Chevron vessel. First, it indicates there the
came up with the arrangement shown on the top of this U-tank, it's simply a tank that has no internal subdivision
slide. As you can see, the worst case, the worst single place port to starboard. The L-tank is the standard configuration
we could hit the ship was right there between 6 and 7. we see an awful lot of. It's a U-tank with a centerline subdi-
Those tanks would flood the way across. We would flood vision. The one that is a little unusual is this S and J tank
approximately 15 000 tons. Imagine a VLCC with rather arrangement which is really an L-tank, taking a portion of
minimum subdivision. Hit is in the wrong place, you could that and subdividing it, and we called it a side or an S-tank.
perhaps flood as much as 50 000 tons. Obviously, you would Now, this is the Chevron 130 000-ton arrangement of
need to light her 50 000 tons and more to ever refloat the double-hull tanks. As you can see, a lot ofU-tanks. We don't
vessel. I think consideration should be given to what kind have any L-tanks. We decided against the L-tanks because
of subdivision you provide in those ballast spaces for the of the difficulty in ventilating those tanks and the axisym-
case where you may put a single hole in the vessel and take metrical flooding they present if flooded, one side or the
on quite a bit of water. other.
Now damage stability and capsize: In a single-hull vessel Now the U-tanks present some problems as well. If you
it just wasn't an issue. We didn't have to worry about it. It do damage a U-tank, of course, you now flood symmetri-
was almost impossible to capsize a single-hull vessel. But cally, sink evenly, but, of course, you take on more water
in a double-hull vessel you've got a combination of things and there is no now reserved buoyancy left. That's why we
that are going to affect what happens. You've got a higher went to these S-tanks, two pairs ofS-tanks in number 2s and
center of gravity of the cargo. You've got a large free sur- number 4s, to provide buoyancy in the event of damage to
face area in those center cargo tanks if you don't subdivide those U-tanks.
them. And if you do subdivide the bottom ballast tank and The U-tanks also present a bit of a problem during load-
then damage it port or starboard, you're going to have ing and discharge. You can't flood too many of those tanks
axisymmetric flooding and potential for capsize. or you create a lot of free surface and you could end up
Now when we got into the design of our 130s we thought becoming unstable alongside the pier and heeling over,
that what we probably should be trying to do is to build a perhaps breaking a hard arm or whatever. So that's another

692 The Reconstruction of the Exxon Valdez


reason for having the S and J tanks. It helps heel control; adoption of early industry standards and guidelines devel-
and also to prevent this heeling, we subdivided three of oped by a company now known as Exxon.
the center tanks to reduce the free surface in those center We have come along way in improving our standards,
cargo tanks. not only for the safe carriage of oils and hazardous materials
This is the damage that the Chevron vessel can with- but also for preventing pollution with an eye now toward
stand. We can damage the vessel from bow clean through protecting the environment from the cargo. Change.
the engine room. We heel a bit, we obviously sink quite a There are some 13 to 15 international treaties developed
bit, but we have a lot of stability and the vessel survives over the years which either directly or indirectly go to-
quite nicely. This is a case where you have 98 percent full gether to establish a systematic approach to safety and
cargo tanks. We also looked at the case where you have 96 pollution prevention. These include the SOLAS Conven-
percent, and it does bring that righting arm curve down tions, Intervention on the High Seas, MARPOL, and
quite a bit, but it still survives quite nicely. STCW. Now our latest effort this November will be di-
So Chevron's design may not be the full answer. We rected at MAPC at oil pollution prevention and response.
acknowledge that, and it is not presented as such. We pres- The United States has been a leader in negotiating a rise
ent it to spark interest and commitment-interest in the in worldwide standards to a point that we profess to be
problems of double hull vessels, and commitment to get happy with, and yet somehow we seem to lose focus and
the necessary work done to resolve the outstanding issues. go off in a different direction without reaping the benefit
The other thing we'd like to do is maybe create some of our gains in international negotiations. There are several
worry, some worry that if we don't design and build prop- of these treaties, hard fought, hard negotiated, which we
erly configured double-hull vessels, we're going to have have never ratified. Now the American public is calling for
problems and they're going to be with us a long time. even more at a time when we have become for the most
So we hope that we can resolve the problems. We hope part a port state and not a flag state. Ninety-five percent
we get on with the work necessary to ensure that double of the arriving cargo comes to this country in foreign ves-
hull vessels are built to criteria that will serve the industry, sels; 75 percent of our crude oil comes in foreign tankers.
the environment, and their crew as well. We must continue to seek and rely on international stan-
dards for the problems that are global in nature. And until
Ted Thompson, 4 Visitor recently, our national legislation has been compatible with
the international treaties. With OP A-90 that has changed
[The views expressed herein are the opinions of the discusser and mainly in three areas.
not necessarily those of the Department of Transportation or the
The first area that was discussed by CAPT Corbett is
U.S. Coast Guard.]
liability and compensation for damages resulting from
PROPOSED TANKER REGULATIONS tanker accidents. We have opted for an alternative as old as
Actually I was told that I would be speaking toward the our Constitution, and that is the right of states to prescribe
Oil Pollution Act, so that's a little bit about what I'm going remedies, and we certainly can't argue with that. But it's
to talk about. It will come as no surprise to you that with the interesting to note that this is a time when the European
recent casualties Congressional action and internal studies powers are combining for their mutual good and we are
have occupied much of our time on this subject and promoting separatism and may be endorsing as many as
changes are necessary. 26 different state arrangements to solve a single problem.
Change is a part of our lives. When I was young, Chuck Or maybe not just one problem, considering that some of
Yeager was just probing the sound barrier. When I was in the states are also looking into equipment standards, crew
high school, Alan Shepard and Colonel John Glenn made qualifications, and onboard inspections. And where does
our first manned suborbital and orbital space flights. that leave the Federal Government? Where does that
Shortly after I entered the field of ship operations as an leave the Coast Guard? Where does that leave the owners
ensign in the Coast Guard, we placed a man on the moon. and operators? And where does that leave many who may
Our generation has seen the introduction of television as a truly deserve to be compensated fairly for damages when
medium of instant communication that has shrunk the possibly that is a one-ship company, as we heard discussed
world. We now have contact lenses, Xerox, laser beams, earlier?
boom boxes, and plastic credit cards. Some of you swung The second area is double hulls. Again, a call for unilat-
with the big bands. I remember Elvis. eral action by the United States, double hulls for all ships
We've all handled these changes in our lifestyles over serving the United States. I believe double hulls will pro-
the years, not without some confusion and uncertainty, but vide an extra level of protection from oil spills, and this has
surely we have seen many benefits to our well-being and been a recognized alternative in the segregated ballast and
prosperity. Change is not new to the marine industry and protectively located schemes of MARPOL '73-78, albeit
the maritime field, and change continues today, part of it it's an expensive alternative, 10 to 25 percent more expen-
driven by the Oil Pollution Act. sive depending on who you talk to.
As fresh water, gunpowder, and certain staples of life Double hulls also raise other safety issues that we have
were carried in casks aboard the earliest ships, so, too, was recently heard about here, all of which I believe are solv-
oil, the oil that lit the lamps then and whale oil as cargo. able. They include gas pockets in between hull spaces,
Oil was eventually carried in independent tanks and then potential salvage difficulties, stability, corrosion preven-
directly in the hull of steel ships, all with the view presum- tion, coatings and repair techniques. There is a lot of work
ably to protecting the cargo from the environment. It was to be done, and double hulls are certainly not seen as a
1924 that the first Federal Government regulations were panacea. Double hulls will not guarantee that we do not
issued for the safe carriage of flammable and combustible have accidents, nor will they guarantee that in an accident
materials in bulk. These rules were little more than the that no discharge at all will occur.
The third area that we see as different is people. People
4 Captain, USCG; Marine Technical and Hazardous Materials are the key. People cause accidents, not ships. Ship design
Branch. is critical to the safety in withstanding or surviving of acci-
The Reconstruction of the Exxon Valdez 693
dents, but crew training and crew qualification are among Discussions from the floor
our top priorities. It has been shown time and time again
that crews that are poorly trained or fatigued for whatever Mr. Arthur Haskell (presiding): What I'd like to do now
cause are more prone to have accidents. Eighty to 85 per- is open up for some discussion from the floor, questions or
cent of the casualties that we see involve crew response of comments. They may be directed to any of the members
some sort, either improper actions, lack of training, or just of the panel, that is, either on the reconstruction of the
a plain casualty caused by fatigue or something like that. Exxon Valdez or on the other topics that were raised.
The OPA addresses this matter principally for U.S. crews, Paul Menz (MARAD): Title VII of the act authorizes up to
but we have got to ratify the STCW, the international $27 million for research and development for protection,
convention establishing training, crewing, and watchkeep- mitigation, recovery, and fix. Does the industry support
ing of seafarers. Only then will we have a strong position any appropriation of public funding for this? And if it does,
to enforce standards on foreign vessels entering U.S. ports. how much and do you have any plans for the wise use of
But this is a gathering of professionals in the marine such resources?
industry here, and I am sure that you have recognized Mr. Kimble: Basically we haven't considered that at
these issues yourselves. Some of the real questions are how Chevron. We have considered the need to do something.
do we meet the expectations of the public and the people We were thinking along the lines more of industry funding,
and not destroy our national and international mechanisms perhaps through API or one of the industry groups. But if
for dealing with safety and pollution prevention. Likewise, that money is available and it would be spent in the best
how do we, given past history, sustain the public interest interests of the public in doing the necessary studies that
and national commitment in preparing for events that ac- are just crying to be done, I think that would be a wise
tually occur relatively infrequently, and how much are we investment of that money.
willing to pay to be constantly prepared? A panelist: I'm primarily up here on the technical part,
A central theme of our future work will highlight the role but I have taken part in some of the API deliberations. As
of management in maintenance, quality control, human you well know, we had the PIRO concept and then they
factors engineering, and personnel training and qualifica- ran into some trouble concerning liability for actions of
tion. We will begin to rely more on performance oriented insurance. I'm not really sure where that is. That's handled
standards and the evaluation of the ship itself as a system by different people. But it is a very high level of concern.
through increased use of ship riders. I'm not sure, Paul, whether your focus is on public funds,
Much progress can be made in responding to the Oil but I believe that the numbers that are being run around
Pollution Act of 1990, hopefully before we are faced with for building oil spill response centers are in the couple of
another catastrophic occurrence and another round ofleg- hundred million dollars on the industry by the time the
islation aimed at solving the problem. cost is all added up.
The Coast Guard initially intended to issue standards for Mohr Hussain: My question is directed to Mr. Walter.
double hulls. We were not able to do so, so at this point we Have you done any analysis, do you know of any analysis
have prepared a notice of proposed rule making we expect done to determine that if Exxon Valdez had been fitted
to have published sometime by the end of this month. with a double hull with exactly the same rupture, how
These standards, which essentially are those that we have much of a reduction of spillage we could have expected?
proposed within our NA VAC-292, address the size of dou- And the second question is, would there have been a stabil-
ble hulls, and they're a starting point for discussions not ity problem?
only within our own system, looking for your comment and Mr. Walter: The questions don't relate to the topic of my
your suggestions, but also in the international arena. paper this afternoon. Therefore, I don't have an answer to
The timetable that we are looking for is for phasing out the question. Thank you.
ships as a function of vessel size, age, and construction- Maxwell Chung (MCA Engineers): I have a question to
the size is in gross tons, not deadweight tons-and the age ask Mr. Walter. I noticed that you have extensive shears
considered is after completion of construction or major onboard on the starboard side. As you make a tunnel re-
conversion. The law also requires that we look at opera- moving the material, would the hull start to open up a little
tional and other mechanical techniques to improve the bit? And when you put back the material inside of it, would
safety of hulls during the phaseout time. And we will be you able to close up and line up exactly the hull, or put
looking for input from professional societies such as back in the original strength, or do they have a lot of resid-
SNAME as well as industry as to what some of those tech- ual stress built up after you complete the repair?
niques may be. Mr. Walter: The way we addressed the issue of the defor-
I think there are some areas for input by SNAME. What mation of the hull according to the configuration of the
are the structural implications of double-hull construction? models that we built was to assess the deflections. The
How do you prevent corrosion of ballast tanks? How to deflection levels in the results of the analysis were such
coat tanks in accordance with vapor emission standards that the chance of that type of spreading taking place was
that many of the states are now adopting? The stability virtually nonexistent. But by the same token, very quickly
implications of double-hull construction need to be investi- after the ship was in drydock and the dock was dewatered,
gated further. Dimensions for protective spaces with re- the supports under the wing tanks in way of the damage
spect to protection and to minimum clearance for inspec- were put in place anyway. So it was a non-issue in effect.
tion, ventilation, and maintenance need to be further Mr. Haskell: I would like to thank the authors, the dis-
investigated. And requirements for sounding and ventilat- cussers, and the other people that participated in this for
ing protective spaces, especially in barges, need to be ad- a very, very interesting and noteworthy discussion. Of
dressed. course, all of this will be recorded in the TRANSACTIONS of
Thank you. the Society.

694 The Reconstruction of the Exxon Valdez

You might also like