Professional Documents
Culture Documents
INDEX
3 CEP 7-14
4 HPCF 15-17
5 PW PUMP 18-22
RECOMMISSIONING CHECKLIST
ACW PUMPS
3. Motor is accessible and its surrounding area is safe and satisfactory for plant operation.
7. All bolted joints and cover plates on the stator frame are provided with gasket and properly
tightened.
12. Power cable and earthling connections are complete, secure and tight.
14. Instrumentation on the motor is complete; bearing temperature indication is available at local
and UCB.
15. EPB checked by keeping breaker in test position.
16. Necessary start permissives and trips are bypassed.
17. Breaker control switch is UCB is released from lock position.
ACW PUMP - A
MOTOR NO-LOAD TRIAL CLEARANCES
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
ACW PUMP -B
MOTOR NO-LOAD TRIAL CLEARANCES
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
SIGNATURE/NAME
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
ACW PUMP - C
EM TM C&I OPN
SIGNATURE/NAME
EM TM C&I OPN
SIGNATURE/NAME
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
CEP RECOMMISSIONING
3. Motor is accessible and its surrounding area is safe and satisfactory for plant operation.
7. All bolted joints and cover plates on the stator frame are provided with gasket and properly
tightened.
12. Power cable and earthling connections are complete, secure and tight.
3. GSC minimum recirculation valve operation checked & isolating valves open.
4. Hotwell level control valve (at least one) and their bypass MOV operation checked & isolating
valves open
5. De-aerator level control valve operation checked & isolating valves open.
6. LPHs inlet / outlet and bypass valves operation & interlock checked & isolating valves kept
open.
7. Supply is available for the solenoid operated vent valves at CEP discharge and main
condensate line, before LP bypass attemperation station.
1. Line-up make-up water system for hotwell make-up and CEP seal water.
2. Hotwell level transmitters / switches are charged and UCB indication is available
4. Fill hotwell up to normal level and keep hotwell level control valve in auto.
CEP Charging
1. The pump, suction strainer, valves, NRV and condensate system are boxed up and ready for
charging (The sections which are not available should be properly isolated).
2. Ensure that CEP suction strainer is cleaned and boxed up. Close the suction strainer drain
valve, if open.
3. Provide gland seal water and ensure that the pressure is adequate (> 2 ksc).
4. Open the pump suction side vent valve to condenser (equalizing valve).
6. Gradually open the suction valve. After opening the valve fully, ensure that the corresponding
permissive appears in UCB (while opening, care should be taken to avoid over-traveling of the
butterfly valve).
7. All local and remote instruments are charged. Observe the pump suction pressure.
8. Monitor the condenser hotwell level.
9. Pump is now charged upto the Discharge valve
All the condensate system loops are ready for charging & their isolating valves open.
i) BFP sealing
ii) LP Bypass Spray
iii) Aux. PRDS Spray
iv) Valve Gland Sealing System etc.
(Isolate the systems which are not available.)
Keep one control fluid pump in service, to avoid opening of LP bypass spray valves on pressure (if the
CF system is not available, keep the isolating valve before LP bypass spray station closed).
Extend power and control supply to the CEP to be started
CEP starting
1. CEP is charged fully upto the NRV / discharge valve and suction pressure is normal
2. Keep CEP discharge valve and its bypass closed.
3. Oil level is normal in the motor bearings.
All start permissives and protections checked, cleared and kept in service (Necessary protocols made)
: CEP-A/B/C
4. Local temperature and pressure gauges, UCB instruments are available and all pr. switches are
charged (Necessary protocol made).
5.
Signature :
C&I:
OPN:
1. Keep inlet and outlet valves of GSC, drain cooler and LPH heaters open
2. Keep the GSC minimum recirculation and deaerator level control valves partially (crack) open.
3. Start charging the system. Open CEP discharge valve bypass gradually. Observe the pump
discharge pressure and keep it within limits.
5. Close the line and LP heater water hose vents after sufficient venting.
8. After proper venting of the line, to increase the flow, open CEP discharge valve (inching)
partially, maintaining the pump discharge pressure within limits.
10. Control the opening of GSC minimum recirculation control valve and deaerator level control
valve to control the pressure
11. If water is to be taken to deaerator, reduce the opening of GSC minimum recirculation valve
and increase the opening of deaerator level control valve.
12. Open the CEP discharge valve to full and close the bypass.
13. Gradually charge the other tappings from condensate line as per requirement.
CEP-A
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
CEP - B
EM TM C&I OPN
SIGNATURE/NAME
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
CEP-C
EM TM C&I OPN
SIGNATURE/NAME
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
1. All start permissives and protections checked, cleared and kept in service.
2. Local temperature and pressure gauges, UCB instruments are available and all pr. switches are
charged (Necessary protocol made).
3. Pump and surrounding area is accessible.
4. Plant area is clean and illuminated properly.
5. Extend power and control supply to the PW to be started
HPCF-A
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
HPCF-B
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
PW SYSTEM RECOMMISSIONING
3. Motor is accessible and its surrounding area is safe and satisfactory for plant operation.
7. All bolted joints and cover plates on the stator frame are provided with gasket and
properly tightened.
12. Power cable and earthling connections are complete, secure and tight.
3. N2 cylinders should be available in sufficient quantity and its purity should be confirmed
by chemistry for N2 purging.
10. Close DM make up line valve. Alkaliser should be lined up for taking DM make up water .
11. Start N2 purging and continue till PW DO reduced to less than 10 ppb.
12. Charge make up water and record DM make up indicator reading. maintain required PW
tank level. When level achieved, close make up valve.
13. Line up alkaliser pump ,it will start/stop in auto as per conductivity. Watch conductivity.
14. PW tank level transmitters / switches are charged and UCB indication is available. Local
gauges are charged.
PW Charging
1. Gradually open the suction valve
2. (while opening, care should be taken to avoid over-traveling of the butterfly valve).
3. All local and remote instruments are charged. Observe the pump suction pressure.
3. All start permissives and protections checked, cleared and kept in service (Necessary
protocols made): PW-A/B
4. Local temperature and pressure gauges, UCB instruments are available and all pr.
switches are charged (Necessary protocol made).
5. Pump and surrounding area is accessible.
6. Plant area is clean and illuminated properly.
7. Extend power and control supply to the PW to be started
PW System Charging:
1. Discharge valve is to be opened just after pump start.
3. Winding and bushing water line valves should be opened as per their requirement.
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
1. Motor is accessible and its surrounding area is safe and satisfactory for plant operation.
4. Motor is undamaged, fitted and satisfactorily mounted with foundation bolts tight.
7. All bolted joints and cover plates on the stator frame are provided with gasket and properly
tightened.
9. Power cable and earthing connections are complete, secure and tight.
4. Pump alignment completed, coupled with motor and coupling guard fixed.
6. Seal oil system mechanical jobs are completed and seals are in place
5. Seal Oil Coolers are charged from oil side & proper venting done.
7. Air side and H2 side seal oil tank (SOT) levels are OK & lined up
8. Intermediate Oil Tank (IOT) (If any) level is OK & lined up.
9. Interconnection between Seal Oil & Lub oil (if any)checked and found ok.
12. AOP / JOP is available for starting for making up seal oil tank level.
C&I OPN
SIGNATURE
7 H2 purity, % :
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
EM TM C&I OPN
SIGNATURE/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
3. Motor is accessible and its surrounding area is safe and satisfactory for plant operation.
7. All bolted joints and cover plates on the stator frame are provided with gasket and properly
tightened.
12. Power cable and earthling connections are complete, secure and tight.
2. ECW tank level transmitters / switches are charged and UCB indication is available. Local
gauges are charged.
4. Fill ECW tank up to normal level and keep ECW tank level control valve in auto.
ECW Charging
1. Gradually open the suction valve. After opening the valve fully, ensure that the corresponding
permissive appears in UCB (while opening, care should be taken to avoid over-traveling of the
butterfly valve).
2. All local and remote instruments are charged. Observe the pump suction pressure.
ECW starting
1. ECW Pump is charged fully upto the NRV / discharge valve and suction pressure is normal
3. All start permissives and protections checked, cleared and kept in service (Necessary
protocols made):
4. Local temperature and pressure gauges, UCB instruments are available and all pr. switches are
charged (Necessary protocol made).
2. Keeping PHE outlet valve closed & vent open, crack open PHE inlet valve till fully primed.
close vents.
3. Open PHE outlet valve fully. Discharge header vent should be open & till header is fully
primed. Charge any available coolers of turbine side equipment. Keep long recirculation valve
in auto with its isolating valve open.
TG ECW-A
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TG ECW-B
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TG ECW-C
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
SG ECW-A
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
SG ECW-A
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
1. Motor is accessible and its surrounding area is safe and satisfactory for plant operation.
2. Illumination is adequate.
4. Motor is undamaged, fitted and satisfactorily mounted with foundation bolts tight.
7. All bolted joints and cover plates on the stator frame are provided with gasket and properly
tightened.
9. Power cables and earthing connections are complete, secure and tight.
2. Pump and motor alignment completed, coupled & coupling guard fixed
a. EM:
3. TM:
4. Vacuum pump cooling water connections (ECW) given and valves kept open.
9. Operation / indications :
Air Iso. Valve :
Ejector by pass valve :
Ejector inlet valve :
10. Separator tank level indicator and floats are functioning properly.
11. Separator tank make-up water line charged and tank filled up to 50% level.
12. Vacuum breaker operation is available and control fluid system is in service.
13. Condenser air extraction valves and vacuum pump manual isolating valve are open.
14. All instruments (vacuum system) in UCB and local are available
15. Ejector inlet and bypass valves auto operation checked.
16. Vacuum pumps operation as per SGC evacuation checked and found OK.
VACUUM PUMP-A
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
VACUUM PUMP-B
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP RECOMMISSIONING
JOP RECOMMISSIONING
MOTOR NO-LOAD TRIAL CHECKS.
1. Motor and its surrounding area is accessible, clean and properly illuminated.
2. Motor is undamaged, fitted and satisfactorily mounted with foundation bolts tight.
5. Power cables and earthing connections are complete, secure and tight.
5. All bolted joints and cover plates on the stator frame are provided with gasket and properly
tightened.
Signature
k) Booster PP thrust DE
l) Booster PP thrust NDE
m) BFP journal DE
n) BFP journal NDE
o) BFP thrust act
p) BFP thrust non act
SIGNATURE
6. VIBRATION READINGS:
7. Turbine rolled upto 4000 rpm after soaking.
8. On load vibrations at 4000 rpm
9. Abnormality noticed if any, during rolling.
10. BFP speed raised further and pump loaded.
11. Date/Time:
12. Discharge pressure:
13. Speed rpm:
14. Flow TPH:
15. TSI readings at 5000 rpm taken.
TDBFP-A LOP-A
MOTOR NO-LOAD TRIAL CLEARANCES
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-A LOP-B
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP- A EOP
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-A JOP
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-A VEF-A
MOTOR LOAD TRIAL CLEARANCES:
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-A VEF-B
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-B LOP-A
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-B LOP-B
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP- B EOP
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-B JOP
EM TM C&I OPN
Signature/Name
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-A VEF-A
MOTOR LOAD TRIAL CLEARANCES:
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
TDBFP-A VEF-B
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
EM TM C&I OPN
Signature/Name
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE
VIBRATION READINGS
LOCATION DECOUPLED TRIAL COUPLED TRIAL
H V A H V A
MOTOR DE
MOTOR NDE
PUMP DE
PUMP NDE