Professional Documents
Culture Documents
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Contents
1.1 Project Background .................................................................................................................................... 1
1.2 Objectives of the Consultancy Services ..................................................................................................... 1
1.3 Scope of the Civil Works Contract ............................................................................................................ 2
1.4 Supervision Consultancy Services ............................................................................................................. 4
1.5 Contract Management Framework............................................................................................................. 4
1.5.1 Summary of Civil Contract ................................................................................................................ 4
1.6.1 Details of the Insurance & Bond ........................................................................................................ 5
1.7 Contractor’s Monthly Statements / Interim Payment Applications ........................................................... 6
1.8 FINANCIAL PROGRESS ................................................................................................................................. 9
1.9 PHYSICAL PROGRESS ................................................................................................................................. 10
PART 2 – CONSULTANCY SERVICES .......................................................................................................... 11
2.1 Consultancy Services ............................................................................................................................... 11
2.1.1 General ............................................................................................................................................. 11
2.1.2 Contractor’s program ....................................................................................................................... 16
2.1.3 Cash Flow Projections ...................................................................................................................... 16
2.1.4 Materials and Workmanship ............................................................................................................ 16
2.1.5 Permits and Licenses ........................................................................................................................ 16
2.1.6 Measurement and Payment .............................................................................................................. 16
2.1.7 Variations, Extension of Time and Fixing Rates.............................................................................. 16
2.1.8 Design............................................................................................................................................... 16
2.1.9 Contractor’s Claims.......................................................................................................................... 17
2.1.10 Health, Safety and Environment (HSE) ........................................................................................... 17
2.1.11 Social Aspects .................................................................................................................................. 18
2.2 Handing over of Land for the Construction Works. ................................................................................ 18
2.3 Contractor’s Organization ........................................................................................................................ 19
2.4 Utility Diversions ..................................................................................................................................... 19
2.5 Details of Utility Diversions at the End of February 2018 ...................................................................... 20
2.5.1 Utilities ............................................................................................................................................. 20
PART 3 – CIVIL WORKS ................................................................................................................................. 20
3.1 Salient Features and Project Particulars ................................................................................................... 20
3.1.1 Salient Features ................................................................................................................................ 20
3.2 Establishment ........................................................................................................................................... 21
3.2.1 Quarries ............................................................................................................................................ 21
3.2.2 Crusher Plants for Concrete Aggregate and ABC ............................................................................ 21
3.2.3 Asphalt Plants ................................................................................................................................... 22
1
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
2
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
3
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
PART 1 – GENERAL
The objective of this project is mainly to have a link between the commercial city, (Colombo) and the
newly constructed sea port, (Hambantota) & International Airport (Mattala) by extending the already
functioning Sothern Expressway [Colombo-Matara] from Matara to Hambantota.
The Government of the Democratic Socialist Republic of Sri Lanka (GOSL) has applied for a long term
loan from the EXIM bank of China for the Extension of Southern Expressway Project from Mattala to
Hambantota via Andarawewa – Length is approximately 25.0 km. At the request of the GOSL, the Exim
Bank of China has agreed to provide credit facilities to finance, inter alia, infrastructure development
projects with great significance to economic development.
One such project is the Extension of the Southern Expressway from Matara to Hambantota including
expressway link to Mattala. The Exim Bank of China has agreed to finance this project which would
involve the Construction of 96 km long four lanes Expressway split into four sections namely Matara to
Beliatta, Beliatta to Wetiya, Wetiya to Andarawewa, Mattala to Hambantota via Andarawewa.
The Construction would include associated structures such as interchanges, intersections flyovers,
underpasses, overpasses, viaducts etc. It is envisaged that there would be extensive soft ground treatment
where deemed necessary as the trace traverse through marshy areas and flood plains. The construction also
envisages future widening at the outside to six lanes. The construction would entail facilities for tolling at
appropriate locations. The Executing Agency of this Project is the Road Development Authority (RDA)
under the Ministry of Higher Education and Highways.
ESEP Project will be implemented on the basis of a BOQ, measure and pay type contract. The RDA, the
Employer has decided to employ a suitably qualified, national / international consultant to supervise and
monitor the project under FIDIC Conditions of Contract (Regulated Document, First Edition 1999-Red
Book). The cost of the civil works as well as the Consultancy Services will be funded by EXIM Bank of
China.
China Railway First Survey and Design Institute Group Company Limited (FSDI) has been appointed by
the Road Development Authority as Supervision Consultants for the Section 4 (Mattala to Hambantota via
Andarawewa) to provide Consultancy Services and assist in various aspects of project implementation in
accordance with the objectives detailed in the Terms of Reference (TOR) and as summarized in the
Preamble to this report.
1
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
These services include administering the civil works contract as the Engineer, as defined in the contract
documents which is under FIDIC Conditions of Contract (Regulated Document, First Edition 1999-Red
Book).
Mr. Dong Wei has been appointed as the team leader for the Engineer’s Representative with delegated
authorities.
The Deputy Team Leader is the overall in charge of day to day supervision of Contractor’s work under the
guidance and direction of the Team Leader. He will cause action to ensure that the Resident Engineers, Site
Engineers and inspectors exercise supervisory control over the quality of materials and workmanship on a
daily basis.
The major items of work to be carried out by the Contractor include but not limited to the following:
detailed engineering designs for structures, soft soil treatment, if any, treatment and toll system including
all related facilities, and construction of the entire 25 km long new 4 lanes expressway with provision for
expansion of 6 lanes in future.
Initial outer 4 lane expressway comprises of each 3.6 m wide lanes, 2.5 m wide outer hard shoulder, 0.75 m
wide inner hard shoulder and 0.75 m verge on either side with 2.0 m wide center median. Construction of
embankments, cuttings and sub structures of bridges, viaducts etc. where 6 lane facilities is required in
future, will be with the provision for expanding to 6 lanes and an inter change at Andarawewa. All cut area
will have provision of six lane.
Following are the major items involved in the construction of the 4 lane facility with the provision for
expanding to 6 lane facilities in future
2
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Structures
Where
i. Pavements
Construction of all road pavements comprising of sub base course, aggregate base course, asphalt
concrete binder course and asphalt concrete wearing course.
ii. Drainage
Construction of the entire drainage system as per design based on hydrology data.
Construction of suitable toll collection system including all related facilities for all four section.
iv. Interchanges
Construction of all incidental works such as road signs, lighting systems at interchanges, elephants
fencing, right of way fencing, guard rails etc.
3
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
The Consultants will provide comprehensive day to day construction supervision of the Work in
accordance with the Conditions of Contract, FIDIC Conditions of Contract (Regulated Document, First
Edition 1999-Red Book) on which the Contract has been entered into between the Employer, Road
Development Authority and the Contractor, China Harbour Engineering Company Ltd.The Team leader
will function as the Engineer’s Representative to the Contract.
The Project is being executed and managed within the Contract Management Framework (CMF) described
in the Contract agreement, which defines the organizational structure and levels of responsibility. The main
features of the Contract Management Framework are,
4
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Details of Contractor China Harbor Engineering Company Ltd. Level 32, East tower, World Trade
Centre, Echelonssquare, Colombo
VAT Reg. No. 409255051-7000
Details of the Contract
Accepted Contract Amount Rs. 52,156,184,936.52
Date of Agreement 19th November 2013
Date of Commencement 19th January 2016
Date of Completion 19th January 2019
Performance Security Submitted on 27th November 2015
Contract Period 36 Months
Funding Agency EXIM Bank of China
Performance Bond Details
Name of the Bank EXIM Bank of China
Bond Amount SLRs. 1,695,076,010.43 ( USD 7,217,564.73)
Bond Validity Period 15th December 2019
Mobilization Advance
Name of the Bank EXIM Bank of China
Amount of Advance Payment SL Rs. 10,431,236,987.30
Bond Validity Period up to 15th December 2018
1st Instalment SL Rs. 5,215,618,493.65
2nd Instalment SL Rs. 2,607,809,246.83
3rd Instalment SL Rs 2,607,809,246.83
Cumulative Progress at the end of March 2018
Physical Progress Target – 82.45 % Achieved – 65.61 %
Financial Progress Target – 77.02 % Achieved – 41.30 %
Table 1.6.1 – Details of the Insurance & Bond by the End of March 2018
5
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Details of the Contractor’s monthly statements and the interim payment applications certified by the
Engineer up to end of February 2018 are shown in following table.
Table 1.7.1 – Summary of Interim Payment Applications by the End of March 2018
6
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Organization
The organization structure of the Construction supervision services and staff is indicated in t Annexure 1.
7
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Percentage
Cumulative work
IPC Valuve of Advance Recovery of IPC Cumulative Recovery Advance Recovery of Advance to be
done + Price
No. Cumulative work Y=(X-0.2)*Z/(0.8-0.2) of IPC (SLR) Current IPC (SLR) Recovered (SLR)
Escalation
done (X)
1 - - -
2 850,660,995.29 0.016 - - - 10,431,236,987.31
3 - - - - 10,431,236,987.31
4 1,172,523,122.86 0.022 - - - 10,431,236,987.31
5 1,619,104,186.66 0.031 - - - 10,431,236,987.31
6 2,239,965,899.98 0.043 - - - 10,431,236,987.31
7 2,708,894,318.17 0.052 - - - 10,431,236,987.31
8 3,606,940,771.07 0.069 - - - 10,431,236,987.31
9 4,936,581,587.86 0.095 - - - 10,431,236,987.31
10 5,986,219,385.66 0.115 - - - 10,431,236,987.31
11 7,029,916,996.79 0.135 - - - 10,431,236,987.31
12 8,200,632,728.91 0.157 - - - 10,431,236,987.31
13 9,243,176,100.10 0.177 - - - 10,431,236,987.31
14 10,351,507,778.75 0.198 - - - 10,431,236,987.31
15 12,355,025,689.73 0.237 - - 10,431,236,987.31
16 - 10,431,236,987.31
17 15,766,605,207.77 0.302 1,773,310,287.84 1,773,310,287.84 1,773,310,287.84 8,657,926,699.47
18 18,208,057,451.58 0.349 2,590,423,851.85 2,590,423,851.85 817,113,564.01 7,840,813,135.46
19 19,532,359,323.36 0.374 3,025,058,726.32 3,025,058,726.32 434,634,874.47 7,406,178,260.99
20 19,789,904,971.24 0.379 3,111,985,701.21 3,111,985,701.21 86,926,974.89 7,319,251,286.10
21 20,548,259,450.62 0.394 3,372,766,625.90 3,372,766,625.90 260,780,924.68 7,058,470,361.41
22 21,540,691,735.94 0.413 3,703,089,130.50 3,703,089,130.50 330,322,504.60 6,728,147,856.81
23 21,540,691,735.94 0.413 3,703,089,130.50 3,703,089,130.50 330,322,504.60 6,728,147,856.81
Cumulative Recovered Advance Payment in SLR 3,703,089,130.50
8
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
May-16
36.79 May-17
83.81 May-18
Aug-16
Nov-16
Aug-17
Nov-17
Aug-18
Nov-18
Mar-16
Mar-17
Mar-18
Dec-15
Dec-16
Dec-17
Dec-18
Apr-16
Apr-17
Apr-18
Feb-16
Sep-16
Feb-17
Sep-17
Feb-18
Sep-18
100.00 Feb-19
Oct-16
Oct-17
Oct-18
Jun-16
Jun-17
Jun-18
Jan-16
Jan-17
Jan-18
Jan-19
Jul-16
Jul-17
Jul-18
Month
11.80
14.17
16.54
21.41
24.26
27.02
30.19
33.37
40.56
44.33
48.21
51.82
56.22
60.11
64.36
68.73
72.90
77.02
80.57
86.48
89.38
91.84
94.41
95.95
97.06
98.17
99.24
0.41
1.76
2.62
3.96
5.74
7.62
9.64
18.9
Financial Planned/
0
Progress (%)
35.08
37.45
37.94
39.40
41.30
11.53
13.54
15.80
17.81
19.95
23.81
25.27
30.38
Actual /
1.64
1.64
1.64
1.64
2.26
3.12
5.22
6.95
9.47
-
-
(%)
100.00
98.17 99.24
100 97.06
95.95
94.41
95 91.84
89.38
90 86.48
83.81
85
80.57
80 77.02
75 72.90
68.73
70
64.36
65
60.11
60 56.22
Percentage (%)
55 51.82
48.21
50 Planned/ (%)
44.33
45
40.56
40 36.79
Actual / (%)
41.30
33.37 39.40
35 37.45 37.94
30.19
35.08
30 27.02
24.26 30.38
25 21.41
18.9 25.27
20 23.81
16.54
14.17 19.95
15 11.80 17.81
9.64 15.80
10 7.62 13.54
5.74 11.53
3.96 9.47
5 1.76 2.62 6.95
0 0.41
5.22
0 1.64 3.12
-
-
- - - 1.64 1.64 1.64 2.26
-
Duration in Months
9
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
May-16
88.45 May-18
Aug-16
Nov-16
Aug-18
Nov-18
Mar-16
Dec-17
Dec-18
Apr-16
Apr-17
Apr-18
Feb-16
Sep-16
Feb-17
Sep-17
Feb-18
Sep-18
100.00 Feb-19
Oct-16
Oct-17
Oct-18
Jun-16
Jun-17
Jun-18
Jan-16
Jan-17
Jan-18
Jan-19
Jul-16
Jul-17
Jul-18
Month
10.75
13.25
16.25
19.75
25.08 28.25
33.53 38.75
37.77 44.35
53.05 55.35
59.19 60.55
62.07 70.35
64.07 74.85
64.81 78.85
85.65
90.85
92.95
94.75
96.25
97.50
98.50
99.25
99.75
0.10
0.50
1.00
2.00
3.25
4.75
6.50
8.50
Planned/
-
Physical (%)
10.74
14.22
16.70
19.25
Progress Actual /
0.19
0.42
0.49
0.62
1.04
2.13
6.49
8.46
-
-
(%)
Duration in Months
10
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
China Railway First Survey and Design Institute Group Company Limited has been appointed by the
Road Development Authority as Supervision Consultants for the Section 4 (Mattala to Hambantota via
Andarawewa) to provide Consultancy Services and assist in various aspects of project implementation
in accordance with the objectives detailed in the Terms of Reference and as summarized in the
Preamble to this report.
These services include administering the civil works contract as the Engineer, as defined in the contract
documents which is under FIDIC Conditions of Contract (Regulated Document, First Edition 1999-Red
Book).
The Consultant shall act as the Engineer with delegated Authorities defined in the FIDIC Conditions of
Contract and supervise the construction works according to the Contract Documents.
1) Administration of Civil Works Contract and ensure that the works are constructed in accordance
with its provisions requirements.
2) Performing the following services of construction supervision
i. Control of Works
Checking and approving the Contractor’s detailed Engineering designs for structures,
toll system including all related facilities and soft ground treatment
Considering possible reducing the cost of the works, enhancing safety by making such
adjustments to the designs
Checking and approving Contractor’s all working drawings
Checking that performed work and furnished materials meet Contract requirements &
specification.
Checking that materials and workmanship meet the required quantities, plan
dimensions and Contract requirements
Checking, evaluating and agreeing with the Contractor’s work plans and progress
schedules for the most effective and expeditious methods of carrying out the work
Providing assistance to prepare comprehensive schedule and sequence of work for the
utility diversion
Providing assistance to coordinate activities with utility agencies
Incorporating the designs of utility agencies in relevant construction drawings
Checking whether the Contractor cooperates with the utility owners to remove and
rearrange underground or overhead utilities to avoid service interruption or duplicate
work by the utility owner
Checking whether the Contractor protects existing utilities that remain in place during
construction
Provide the Contractor with necessary datum points and benchmarks for setting out
the works
Ordering the Contractor that certain sections of project be opened to traffic before the
work is completed or accepted, with the Employer’s concurrence
12
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
m) Project acceptance
n) Claims
o) Instructing the Contractor to complete As-built drawings in time is the acceptable manner.
3) Training :
Overseas training / workshops for at least 10 RDA Engineers and on-the job training for at least 5
Engineers and 5 Technical Officers.
Preparing a complete Operation and Maintenance (O&M) manual for Section 4 Mattala to
Hambantota via Andarawewa under the Project.
Arranging or attending the consultations and meetings listed in the Consultant’s agreement,
preparing minutes of the meetings and forwarding them to the Project Director within 5 days,
with copies to all participants.
13
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Date of Date of
No Name Designation
Mobilization Demobilization
1 Mr.Dong Wei Team Leader (E1) 14-Dec-2015
Senior Structural Design Engineer
2 Mr.Wang Liming 26-Sep-2015
(E2)
3 Mr.JiangWangang Claim / Contract Specialist (E6) 17-Nov-2015
Mr.Wang Yong
4 Senior Highway Design Engineer(E9) 3-Dec-2015 26-Sep-2016
Dong
5 Mr.WangLiquan Pavement Specialist (E8) 1-Mar-2016
6 Mr.WangShuchen Material Specialist (E7) 24-Mar-2016 21- June 2016
7 Mr.Zhang Tao Senior Quantity Surveyor(E16) 24-Mar-2016 21- June 2016
Mr. Zhang Senior Geotechnical Engineer
8 24-Mar-2016 21- June 2016
Zhendong (Investigations & Design) (E4)
Health, Safety & Environmental
9 Mr.WangDayu 18-Aug-2016
Manager (E21)
10 Mr.LiuEnji Structural Design Engineer (E18) 29-Aug-2016 28-Nov-2016
Senior Highway Construction
11 Mr.BaiXiande 31-Aug-2016
Engineer (E10)
12 Mr.Gu Cheng Peng QA/QC Manager(E22) 31-Aug-2016
Senior Geotechnical Engineer
13 Mr.ZhangHui (Construction Quality Control & 03-Sep-2016
Monitoring) (E5)
14 Mr.WangFeng Material Specialist (E7) 06-Sep-2016
15 Mr.Xu Zhan Lei Highway Design Engineer(E15) 26-Oct-2016 20-Nov-2017
Senior Structural Engineer
16 Mr.PanGuotao 23-Nov-2016
(Construction) (E3)
17 Mr Zhu Dadong Resident Engineer (E14) 28-Mar-2017
18 Toh Teck Boon Senior Quantity Surveyor 31-Mar-2017
19 Ma Xialong Translator 17-July-2017
Table 2.1.1.2 Mobilization of Consultant’s Local Professional and Technical Staff by the End of
March 2018.
Date of Date of
No Name Designation
Mobilization Demobilization
1 Mr. T.J. Bandula Resident Engineer (L2) 01-Dec-2015 20-Feb-2018
14
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Date of Date of
No Name Designation
Mobilization Demobilization
5 Mr. W.M.SarathWijesinghe Environmental Specialist (L14) 01-Mar-2016
Date of Date of
No Name Designation
Mobilization Demobilization
33 Mr. T.J. Bandula Deputy Team Leader (L1) 20-Feb-2018
Progress is being monitored based on the latest approved, contractor’s master programmer (Rev 03)
dated 22nd June 2016.
The Engineer is responsible for checking and approving Contractor’s work measurement and payment
claims and certify to the Employer in accordance with the civil works Contract. He will maintain
records of as built drawings with reference to measurement sheets, quantifies and record any deviations
or approved variations to Contract drawings with reasons for such changes. He will administer the
completion of the contract including all activities in relation to issue of the Taking over Certificate and
Defects Notification Certificates. He will take action to check and submit As-Built-Drawings; all detail
records pertaining to the contracts and maintenance manuals to the Employer.
The Engineer has to obtain Employer’s prior approval for ordering variations to Contract above the
limits stated in the Contract, determine extension of time, approving sub-contractors and fixing new
rates and prices. The Engineer will evaluate claims for extension of time and additional payment in
accordance with Sub Clause 8.4 and Sub Clause 3.5 of the Conditions of Contract.
2.1.8 Design
2.1.8.1 Review of Geometric Designs
The Senior Highway Design Engineer, Pavement Specialist & other Design Engineers in association
with the RDA design office review the geometric designs prepared by the Contractor and approve the
designs & working drawings.
16
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
The structural designs for four lane widening of structures are done by the Contractor. The Senior
Structural Design Engineer and Structural Design Engineers review all structural designs of bridges,
underpasses and culverts that need to be widened or constructed, check the setting out and supervise
construction of structures in accordance with the approved designs and drawings.
The Consultant will ensure that the design assumptions, conditions and specifications set for
construction is strictly followed by the Contractor.
The Consultant’s Pavement Specialist reviews the pavement designs for adequacy of pavement layers
thickness and material specifications. He will supervise the pavement construction for conformance to
Contract specifications and drawings. Further he will review the design of pavement structure for local
roads listed for improvement to provide economical pavement design.
The Consultant’s Senior Geotechnical Engineer and the Geotechnical Engineer review the design
documents of engineering geological and hydrogeological conditions of project site and along the line,
check whether they can meet the preliminary design and construction goals of the project. They also
supervise the Contractor to make technical disclosure for engineering, geological conditions of
construction area or surrounding area and make a summary of technical disclosure.
The Consultant’s Drainage Engineer in association with hydrologist will cheek the submission of
contractor design economical and feasible drainage facilities to mitigate flooding, inundation, siltation
or erosion problems associated with the site condition. He will liaise with the Irrigation Department,
Central Environmental Authority, Mahaweli Authority and Sri Lanka Land Reclamation and
Development Corporation when providing design solutions to these problems.
Contractor’s and Employer’s claims are evaluated by Engineer with assistance of Claims Specialist
subject to the provisions of the Contract agreement. In consultation with contractor and Engineer if
necessary.
The Consultant’s Health, Safety and Environmental Manager and the Environmental Specialist have to
ensure that, the Contractor complies with the environmental and safety standards and guidelines, effects
on ground water levels and water quality in the project area. Theyguide the Contractor to conduct
awareness programmes/tool box meeting for all employees in health, safety and environmental
procedures to be followed at the place of work. The Engineer examines the Contractor’s site offices,
staff accommodations, laboratories and construction equipment to ensure they comply with contract
requirements. The Contractor carry out periodic checks on air quality, water quality and noise and
17
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
vibration levels due to construction activities and rock blasting in accordance with CEA and GSMB
requirements.
The Contractor takes action to mitigate all environmental impacts due to construction activities in
accordance with the Environmental Management Action Plan (EMAP) of the project and the relevant
legislation. The Contractor is responsible for compensating damages due to environmental impacts as a
result of his construction activities and compensation in lieu of environmental mitigation measures.
Contractor has to fulfill the requirement of the Environmental Monitoring Plan (EMP) as well. The
contractor submits a separate monthly environmental report in addition to the monthly progress report.
Inspection and meeting on monthly basis are held.
The Employer and the Contractor engaged with the other agencies for the implementation of the Social
Impact Management Plan.
Land acquisition for six lanes facility will be made, if any additional land acquisition and resettlement
activities are required in the future. The consultant will assist the RDA and report the progress in
monthly progress meeting and reports.
Table 2.2.1 –Handing over of Land & Taking Over of office & accommodation building by the End
of March 2018
Table 2.2.1 – Land Handing Over for the expressway construction by the End of March 2018
18
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
The Contractor has to coordinate activities with utility agencies for the smooth implementation of
utility diversions without obstruction to the Contractor’s program of work. The relocated utility
services will be shown on the drawings for future identifications. The Engineer will obtain approval
from the Employer before incurring expenditure for utility diversion by the Contractor. The Employer
has decided to coordinate the utility relocation work and make arrangement to pay the cost directly to
the utility agencies, if there is any delay in payment by the contractor.
19
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
20
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Chainage Features
Pavement Design
There are only one System Interchange at Andarawewa for the Expressway segments -
Mattala – Matara & Andarawewa- Hambantota.
Viaducts
Other Structures
3.2 Establishment
3.2.1 Quarries
Before commissioning a quarry, the Contractor has to obtain Industrial Mining License and Transport
License from Geological Survey and Mines Bureau (GSMB), Environment Protection License (EPL)
from Central Environmental Authority (CEA) and other local authorities (if any). Permission from the
Wild Life Conservation Department (WLCD) is required when the quarry is within the Managed
Elephant Range (MER).
Table 3.2.2.1 – Status of the Crusher Plants by the End of March 2018
21
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Asphalt plant at Kurudana, Andarawewa is producing 120 tons per hour and 1.7 tons per batch.
The status of the Concrete Batching Plants Approved / Pending Approval is as follows.
Table 3.2.4.1 – Status of the Concrete Batching Plants by the End of March 2018
The Contractor shall obtain the permission before operating any borrow pits from relevant
authorities as well as the Engineer. Further to the approval the Contractor has to adhere to the
subjected conditions of the approvals and any instruction from Engineer from time to time.
Summary of the status of borrow pits has been tabulated as follows.
22
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Table 3.3.1 – Status of the Borrow Sites by the End of March 2018
23
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
21 Pahala Andarakala
Pending Pending Approved
Borrow Pit Embankment Completed Pending
22 CHEC, Kurudana, Waiting for
Pending Pending
AndarawewaBorrow Pit Embankment Completed Pending approval
29 Hamuduruwewa Tank
N/A N/A Completed Currently
Bed -Borrow Pit Embankment Approved
Using
30 Dasathawewa Tank Bed
N/A N/A Completed Sample
-Borrow Pit Embankment Rejected
Failed
31 Aluth Karametiya wewa
N/A N/A Completed Complete Complete
Tank Bed -Borrow Pit Embankment
42 Currently
Nugawela Tank Embankment N/A N/A Completed Approved
Using
43 Not yet
Kapukinissa Tank Embankment N/A N/A Completed Approved
started
44 Not yet
Padawgama tank Embankment N/A N/A Completed Approved
started
Excavated unsuitable material shall be disposed properly to avoid unnecessary environmental issues
such as water logging, mosquito breeding, unexpected erosion and canal system silting etc. Hence,
according to the contract the Contractor shall obtain permission from CEA and other relevant local
authorities for disposal yard and dumping of unsuitable material.
25
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Picture 3.4.1 – Status of the Disposal Yards by the End of March 2018
Table 3.4.1 – Status of the Disposal Yards by the End of March 2018
Table 3.3.1 – Status of the Borrow Sites by the End of March 2018
26
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
3.5 Facilities.
a) Laboratory for the Engineer & Contractor
The Construction works of main laboratory and secondary laboratory have been completed.
1000KN steel tensile machine has been calibrated and testing 32mm rebar sample is being
carried on.
The Offices and Accommodations have been occupied by the Engineer. However, the contractor has
to attend to the minor defects and small extension work.
The Contractor’s office and accommodation have already been established at Pahala Andarawewa,
Mattala and presently is being used by them.
Quality Observation Reports (QOR) have been issued by the Engineer up to end of March 2018 as
follows.
The details of the Non-conformance reports (NCR) up to end of March 2018 are shown in
Annexure 3.
During month of March 2018, all the soil, aggregate, reinforcement steel and concrete testing
have been carried out in the Engineer’s Main and Secondary laboratories.
4 Material technicians, 10 Lab assistants, 15 Supporting Staff have been assigned to carry out
lab & field tests jointly.
Quality confirmation tests such as Re-bar, Cement, Admixture and 7 wire Strands have been
carried out at Independent laboratories for each consignment lots / frequent basis. Material
sampling & testing for the month of March 2018 are shown in Annexure 4.
Almost all Lab Equipment have already been purchased and handed over by the Contractor.
Main Lab 01 in front of the Botanical Garden, Sooriyawewa Road, Katuwewa, Hambantota –
Testing works in operation.
Secondary Lab 02 – CHEC yard, Kurudana, Andarawewa – Testing works are in progress.
Asphalt binder Course design has been approved & the work is in progress.
Asphalt Wearing Course design has been approved and trial was done.
27
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Concrete
11 Ice Cube Lanka Ice Com.Pvt.Ltd temperature 2016.04.28 Currently using
control
Pre
Chengdu XinzhuRoad& Stressed
12 Anchorage system 2016.04.02 With comments
Bridge Machinery Co. Ltd Concrete
members
Structural Steel
13 Coupler Splices CABR Technology Co. Ltd 2016.04.19 With comments
Works
Pre Stressed
Post-Tensioning
Liuzhou OVM Machinery Concrete
14 System 2016.05.04 Currently using
Co. Ltd members
28
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
29
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
52 Chain Link fence Mascon Mesh Industries for Bridges 2017.12.18 Approved With
(PVT) LTD comments
53 Geotess-270 TESSILBRENTA S.R.L For embankment 2017.12.19 Approved With
Geotextiles comments
54 110 mm UPVC PIPE S-LON LANKA (PVT) UTILITY 2018.1.29 Approved With
LTD DUCTS comments
30
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
The Contractor shall take action to mitigate all environmental impacts due to construction activities
in accordance with the Environmental Management Action Plan of the (EMAP) project and the
relevant legislation. The Contractor is responsible for compensating damages due to environmental
impacts on the construction activities and compensation in lieu of environmental mitigation
measures.
The contractor has to fulfill the requirements of the Environmental Monitoring Plan (EMP) as well.
31
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
3.8 Operations
3.8.1 Surveying
The progress of surveying work is shown in Annexure 5.
3.8.2 Design
Table 3.8.2.2 – Progress of Drainage Design Works by the End of March 2018
i. Construction of Viaduct 2 was started on 25th July 2016 and the work in progress.
ii. Construction of Viaduct 1 was started on 24th August 2016 and the work in progress.
3.11.2 Bridges
i. Construction of Bridge (BR-1) at CH 2+800 was started on 06th November 2016 and the work
in progress.
ii. Construction of Bridge (BRU-2) at CH 77+015 was started on 19thDecember 2016 and the work
in progress.
iii. Construction of Bridge (BRO-2) at CH 2+072 was started on 22nd December 2016 and the work
in progress.
iv. Construction of Bridge (BRU-1) at CH 5+200 was started on 19th December 2016 and the work
in progress.
v. Construction of Bridge (BRI-6) at CH 73+269 was started on 30th January 2017 and the work in
progress
vi. Construction of Bridge (BRI-5) at CH 73+217 was started on 1st of February 2017 and the work
in progress
vii. Construction of Bridge (BRI-1) at CH 73+217 was started on 20th of April 2017 and the work in
progress
viii. Construction of Bridge (BRI-2) at CH 73+217 was started on 18th of April 2017 and the work in
progress
ix. Construction of Bridge (BRI-4) at A0+859 was started on 02nd May 2017 and work in progress
x. Construction of Bridge (BR0-1) at CH0+280 was started on 07th of July 2017 and work in
progress
The progress of key activities progress up to end of March 2018 is shown in Annexure 8.
The progress of culvert & Bridges up to end of March 2018 is shown in annexure 9.
33
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
i. The Contractor’s Key Staff for the month of March 2018 is shown in Annexure 10.
ii. The Contractor’s Labor Return for the month of March 2018 is shown in Annexure 11 &
Annexure 12.
iii. The Contractor’s Machinery & Equipment for the month of March 2018 is shown in Annexure 13.
i. The Progress Photographs for the month of March 2018 is given in Annexure 14.
Progress update on Master Program for the month of March 2018 is shown in Annexure 15.
Weather Report for the month of February 2018 available from the Dept. of Meteorology is shown in
Annexure 16.
34
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Team Leader(E1)
Mr. Dong Wei
Team Leader Design Review Office Construction Laboratory Resident Resident Engineer
Office Supervision Office Engineer Office No.2
Office No.1
Office Manager Claim/Contract Office Manager Soil/Materials Engineer Resident Resident Engineer
Specialist (E6) (TBA) Engineer (L2) (E14)
Mr.Ma xiaolong (L7)
Mr.Zeng Biao Mr Jiang Office Manager Mr. S.Murugendran Mr W.A Mr Zhu Dadong
Wangang (TBA) Samarasinghe
Senior Hydrologist (L8)
Dr. R.L.H.L. Rajapakse
Secretary Senior Geotechnical Engineer
Ms.P.M.Nadeeka (E5) Mr Zhang
Claim/Contract Senior Geotechnical
Ms.K.L.Nilupa Senior Geotechnical
Specialist (L18) Engineer
Lakrani Engineer Material Technician (L21) Geotechnical Engineer (L17)
(TBA) (Investigations and (Construction quality
4 PPL (TBA)
Design) (E4) control and
Mr.B.M.Asanka Jayarathna
monitoring) (E5)
Administrator Mr.M.Priyanthan
Geotechnical Engineer Mr.Zhang Hui Highway Construction
/Clerk Mr. H.A. Harsha Kumara
Accounting (Design) (E19) Engineer (L4)
Mr. R.M.S.K. Bandara
Manager (E20) (TBA) (TBA)
Office Assistants Ms.Deng Hui
5 PPL Geotechnical Structural Engineer
Senior Highway Design Engineer Construction (L6)
Mis H.A.K.P Gawri
Engineer (E9) (Construction quality (TBA)
Mr Udara Shashimal
(TBA) control and
Mr K. Asantha Health,Safety Lab Assistant (L22)
Kumara monitoring) (L17) Site Engineer (L13)
& Environment 10 PPL
Mr. Sandaruwan Manager (E21) 4 PPL
Highway Design Mr.W.M.P.S.B.Widanageadara
Sudusinghe Mr. Wang da Mr. H.J.D. Karunarathna
Engineer (E15) Mr.H.R.K.T.Senanayake
Mr Sadun Asela yu Mr. K.A. Deshapriya
(TBA) Mr.B.W.Sarath Kumara
Mr. K.Mithunan
Mr.S.A.R.N. Kumara
Mr. L.P.R. Srimal
Draughtman Mr. A. Prabath Ranaweera
Material Specialist Mr. D.J.N.G. Witharana
Mis Y.G.S Suvini Quality (E7) Senior Quantity Surveyor (E16)
Mis.U.P.Dissanayaka Mr. J.P.S. Pemasiri
Assurance/Qua Highway Design Mr.Wang Feng Mr. Toh Teck Boon
Mr.K.K.D.A.P. Kumara
lity Control Engineer (L3)
Mr. A.N.L. Dayarathne
Manager (E22) (TBA)
Mr.L.D. Iresh Rangana Quantity Surveyor (L10)
Mr. Gu Cheng
Senior Highway Mr R Dinesh Kumara Mr. M.M.Y. Bandara
Peng
Construction Engineer Mr P.G Nadeesh Anuruddha
Senior Structural Mr Kelum Galappthi
(E10) Technical Officer (L20)
Design Engineer (E2) Mr Omila Thusantha 8 PPL
Mr.Bai Xian de
Mr.Wang Liming Mr Dileep Kumara Mr. R.P.Priyantha
Environmental Mr H.N Janaka Mr. P.M.H.S.Senevirathne
Specialist (L14) Senior Structural Mr Chamath Prabodh Mr. K.L.Piyathilaka
Mr. W.M. Engineer Construction Mr D.D.P.H Sajith Udayanga Mr. U.A. Kithulgoda
Sarath Structural Design Mr M.A.R.R Desappriya
Engineer (E18) (E3) Mr. U.R.G.M. Thilakarathna
Wijesinghe Mr.Pan Guotao Mr Sampath Kumara Mr. U.D. Deeman
(TBA)
Mr. Anil Prasann
35
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
36
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
37
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
38
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
41
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
10+000
11+000
12+000
13+000
13+900
0+000
1+000
2+000
3+000
4+000
5+000
6+000
7+000
8+000
9+000
Est. GPS Con. Points
Traversing(N,E,Z)
CL Setting out
TOPO SURVEY
Cross Sections
72+000
73+000
74+000
75+000
76+000
77+000
77+640
Est. GPS Con. Points Work Completed
Traversing(N,E,Z)
CL Setting out Work in Progress
TOPO SURVEY
Cross Sections NA
2+000
3+000
4+000
5+000
42
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
Cl Additional Cost due to Tax 6/11/20 10/12/2015 10/12/2015 Claim for 0 996,763,731. No No Rejected(2)
001 of mines 15 Cost 70
Cl Additional Cost and Time 11/05/2 30/05/2016 30/05/2016 extension of 3 0 10/26/2017 10/26/2017 The claim was Approval 3
009 as a result of the 016 time accepted and
Exceptionally Adverse reported to the
Climatic Conditions Employer
Cl Additional Cost as a result 12/05/2 04/06/2016 06/06/2016 additional 0 125,374.02 9/9/2016 No Request
010 of the Delayed Tax 016 payment supplementary
Exemption for Bamboo evidence
Plywood.
43
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
Cl Additional Cost and Time 23/05/2 07/06/2016 07/06/2016 extension of 12.79 0 No No Rejected
011 as a result of the Potential 016 time
loss due to Operations of
Quarry at Ch.8+250 to
Ch.8+500
Cl Losses due to Bridge 27/05/2 08/06/2016 09/06/2016 Withdrawal No No
012 Design Amendments 016
Cl Potential Loss due to 09/06/2 23/06/2016 24/06/2016 No Claims 0 0 No No Rejected
013 Laboratory Test 016
Cl Losses due to Stockpile 01/06/2 28/06/2016 28/06/2016 No Claim No No
014 016 Particulars
Cl Losses due to Aluminum 17/06/2 06/07/2016 07/07/2016 No Claims 0 0 No No Rejected
015 Partitions in Engineer's and 016
Employer's Office
Cl Losses due to Rejection of 07/07/2 20/07/2016 21/07/2016 additional 0 353,088.00 No No Rejected
016 C20 Concrete in Engineer's 016 payment
and Employer's Office
Cl Losses. due to 40 mm 05/07/2 01/08/2016 02/08/2016 No Claims 0 0 No No Rejected
017 Asphalt Concrete layer on 016
Internal Roads in
Engineer's and Employer's
Office
Cl Losses due to the 29/07/2 04/08/2016 06/08/2016 additional 0 323,787.42 No No Rejected To DAB
018 Deductions of Provisional 016 payment
Sums in Issued IPC3
Cl Losses due to Withholding 22/08/2 29/08/2016 05/09/2016 additional 0 2,731,767.72 No No Rejected To DAB
019 of IPC4 016 payment
Cl Losses due to Public 01/09/2 06/09/2016 08/09/2016 extension of 3.2 0 No No Rejected
020 Protest at CH71+000 to 016 time
CH73+300
Cl Loss due to Delayed 11/08/2 10/09/2016 13/09/2016 No Claim No No
021 drawing instruction(CDS 016 Particulars
235,237)
Cl Losses due to Adjustment 02/08/2 14/09/2016 14/09/2016 No Claim No No
022 of Sight Distance 016 Particulars
44
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
Cl Losses due to the Changes 08/10/2 19/10/2016 25/10/2016 No Claim No No
026 of the Design length of 016 Particulars
Piles at VD 01
Cl The loss in exchange of 14/10/2 24/10/2016 25/10/2016 Claim for cost 0 70,681,269.6 No No The claim was To DAB
027 Advance payment 016 7 accepted and
reported to the
Employer
Cl Additional Cost and Time 26/10/2 21/11/2016 21/11/2016 No Claim No No
028 Due to Design Instruction 016 Particulars
for Andarawewa
Interchange
Cl Additional Cost and Time 26/10/2 21/11/2016 24/11/2016 No Claim No No
029 due to Approval Delay of 016 Particulars
Pavement Design
Cl Losses due to the 18/11/2 09/12/2016 10/12/2016 Claim for cost 0 937,137.27 No No Rejected To DAB
030 Deductions of Provisional 016
Sums in Issued IPC5
Cl Losses Due to the Arbitrary 06/12/2 09/12/2016 10/12/2016 No Claim No No
031 Deduction of Unclassified 016 Particulars
Borrow Excavation on
Interim Application 7
Cl Losses due to the Changing 19/11/2 09/12/2016 14/12/2016 No claims 0 0 No No Not replied
032 Instruction of Approved 016
Alignment Design of
Diversion Road- 8 (CH6
+220 RHS)
Cl Suspension of Work as per 07/12/2 14/12/2016 15/12/2016 No claims 0 0 No No Not replied
033 the Engineer's letter 016
ref;FSDIS4-CHEC -1043
Cl Instruction for Design of 07/12/2 21/12/2016 22/12/2016 No claims 0 0 No No Not replied
034 Anderawewa Interchange 016
Variation
Cl Suspension of Walsapugala 07/12/2 28/12/2016 29/12/2016 No claims 0 0 No No Not replied
035 Barrow pit Material due to 016
Non Plastic Material as per
Engineer's Letter
ref.FSDIS4-CHEC-1095
Cl Losses due to the 05/12/2 29/12/2016 30/12/2016 Claim for cost 0 827,319.79 No No Rejected
036 Deductions of Provisional 016
Sums in Issued IPC6
Cl Suspension of Walsapugala 12/10/2 1/5/2017 1/6/2017 No Claim No No
037 Barrow pit Material due to 016 Particulars
Non Plastic Material as per
Engineer's letter ref;
FSDIS4-CHEC -1095
45
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
Cl Losses due to the 12/27/2 1/11/2017 1/13/2017 Claim for cost 0 47,930.97 No No Rejected To DAB
038 Deductions of Provisional 016
Sums in Issued IPC6
Cl Losses due to the 1/16/20 1/20/2017 1/20/2017 Claim for cost 0 63,548.68 No No Rejected To DAB
039 Deductions of Provisional 17
Sums in Issued IPC 8
46
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
Cl Extension to the Time for 3/31/2017 4/4/2017 does not 255 Rejected
T01 Completion No 1 comply with
the contract
Cl Losses due to the 4/17/20 5/5/2017 5/5/2017 No Claim Rejected To DAB
052 Deductions of Provisional 17 Particulars
Sums in Issued IPC 11
Cl Losses due to the 5/17/20 5/24/2017 5/24/2017 No Claim Rejected To DAB
053 Deductions of Provisional 17 Particulars
Sums in Issued IPC 12
Cl Diversion Road 01 Design 5/9/201 5/26/2017 5/26/2017 No Claim
054 Changes( 7 Particulars
Cl Delay by the NWS & DB 5/23/20 5/31/2017 6/5/2017 No Claim
055 for the Shifting of Purafic 17 Particulars
Water Pipe Line PVC/DI
along the Expressway
Cl Delay due Trial works for 5/31/20 6/2/2017 6/7/2017 No Claim
056 sub base 17 Particulars
Cl Diversion Canal 2 Design 6/7/201 7/4/2017 7/4/2017 No Claim
057 Changes CH3+ 440- 7 Particulars
CH3+866 RHS
Cl Diversion Canal 01 Design 6/7/201 7/4/2017 7/4/2017 No Claim
058 Changes At CH0+ 625- 7 Particulars
CH1+ 198 RHS
Cl Delay due Sub Base Layer 6/20/20 7/1/2017 7/2/2017 No Claim
059 Rejection at Ch 14+000- 17 Particulars
14+ 050
Cl Delay due to late 6/28/20 7/1/2017 7/2/2017 No Claim
060 Instruction of Road 17 Particulars
facilities
Cl Delay due to Design 6/17/20 7/6/2017 7/6/2017 No Claim
061 Revision of Box Culvert at 17 Particulars
CH0 +132 Arabokka
Cl Losses due to the 7/31/20 8/13/2017 8/15/2017 No Claim To DAB
062 Deduction of Provisional 17 Particulars
Sums in IPC 14
Cl Loss Due to the Deduction 6/19/20 7/14/2017 7/17/2017 additional 39,131,353.7 No No Rejected To DAB
063 of Provisional Sums in IPC 17 payment 5
13
Cl Delay Due to Late 6/30/20 7/24/2017 7/27/2017 No Claim
064 Instruction forCH8+ 340- 17 Particulars
CH8+500 Variation Works
Cl Additional Cost and Time 6/24/20 7/27/2017 7/27/2017 extension of 2 1,394,654.58 No No Rejected
065 due to the Public Strike of 17 time and
Ceylon Petroleum additional
Cooperation payment
47
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
Cl Additional Cost and Time 7/26/20 7/27/2017 7/27/2017 additional 6,048,196.52 No No Rejected
066 due to the Royalty Charges 17 payment
for Rock Excavated within
ROW by GSMB
067 Additional Cost and Time 9/13/20 10/9/2017 10/10/2017 No Claim
due to the Delayed 17 Particulars
Approval of Tax
Exemption
068 Losses caused due to the 9/13/20 10/24/2017 10/10/2017 No Claim
Implementation of changes 17 Particulars
to National Building Tax
069 Losses due to the 10/24/2 11/1/2017 11/2/2017 No Claim To DAB
Deduction of Provisional 017 Particulars
Sums in IPC 17
070 Losscs Caused due to 10/26/2 11/16/2017 11/17/2017 No Claim
Unfair Deduction of 017 Particulars
Advance Payment
071 Additional Time and Cost 11/17/2 11/18/2017 11/19/2017 No Claim
Caused due to the Location 017 Particulars
Change for Toll Gate at
Mattala End
072 Losses Caused due to the 11/30/2 12/8/2017 12/9/2017 extension of 1 0 1/3/2018 1/4/2018 The claim was Approval 1
Exceptionally Adverse 017 time accepted and
Climate Conditions in reported to the
November 2017 Employer
073 Losses due to the 11/27/2 12/13/2017 12/14/2017 additional 0 43,560,478.9 No No Rejected To DAB
Deduction of Provisional 017 payment 8
Sums in IPC 18
074 Losses Caused by the 12/26/2 12/27/2017 12/28/2017 No Claim
Protest at CH 77+084 due 017 Particulars
to the Delay of the
Compensation of Land by
the Employer
075 Additional Cost and Time 01/20/2 01/21/2018 01/22/2018 No Claim
due to the Delayed 018 Particulars
Instruction for Toll System
and Toll Booth
Clai Description Date of Date of Acknowledge Contractor's EOT Cost Claimed Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m Claim Claim ment of view Claimed (LKR) Substantiation Substantiation Determination Claim is Approved Approved
No. Event Notice Claim Notice (days) requested on Received on Accepted or (days) (LKR)
Rejected by
Employer
076 Losses due to the 12/23/2 01/18/2018 01/21/2018 No Claim To DAB
Deduction of Provisional 017 Particulars
Sums in IPC19
48
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Clai Descriptuion Date Date of Acknowledge Contractor's EOT Cost Contractor's Contractor's Engineer's Whether EOT Cost Remarks
m of Claim ment of view Claimed Claimed Substantiatio Substantiatio Determination Claim is Approved Approved
No. Claim Notice Claim Notice (days) (LKR) n requested n Received Accepted or (days) (LKR)
Event on on Rejected by
Employer
077 Losses due to Employer's 1/4/201 01/19/2018 01/21/2018 No Claim
Failure to Compensate 8 Particulars
the Residence near
CH77+060-CH77+ 100
078 Additional Time and Cost 1/17/20 01/25/2018 01/26/2018 No Claim
Caused due to 18 Particulars
Engineer's Instruction for
Additional Weighing
Bridge for Toll Gate Area
079 Losses due to the 1/30/20 02/06/2018 02/07/2018 No Claim To DAB
Deduction of Design Cost 18 Particulars
of
Andarawewa Interchange
Design Variation in IPC20
080 Additional Time and Cost 2/08/20 02/22/2018 02/23/2018 No Claim
Caused due to 18 Particulars
Engineer's Instruction for
Additional Design and
Construction of the Ramp
at Mattala
Interchange
081 Additional Cost and Time 3/03/20 3/03/2018 3/04/2018 No Claim
due to Delayed 18 Particulars
Drawing/Instructions for
the Biological and Electric
Fencing for Elephants
49
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
51
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Sub grade
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) Cu.m
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
0+000 - 1+000 1+000 - 2+000 2+000 - 3+000 3+000 - 4+000
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Cu.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
Sub grade
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
7+000 - 8+000 8+000 - 9+000 9+000 - 10+000 10+000 - 11+000
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Cu.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
52
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Sub grade
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) Cu.m
Exavation Unclassified/Rock sq.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
4+000 - 5+000 5+000 - 6+000 6+000 - 7+000
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Cu.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
Sub grade
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
11+000 - 12+000 12+000 - 13+000 13+000 - 14+000
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Cu.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
53
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Description unit
wearing Course tonne
Binder Course tonne
Prime Coat Litre
Aggregate Base Course Cu.m
Grannular Sub Base Cu.m
sq.m
LHS
Sub grade
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unsuitable/Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
71+000-72+000 72+000 - 73+116
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unsuitable/Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Cu.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
54
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
Genaral Clearing ha
Site possession
L73+116-L74+202
Site possession
Genaral Clearing ha
55
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Embankment filling(RUC3)/RUC4/UnclasifiedCu.m
sub grade (Exsisting) sq.m
ExavationUnclassified/Rock Cu.m
Genaral Clearing ha
Site possession
R73+116-R74+202
Site possession
Genaral Clearing ha
Embankment filling(RUC3)/RUC4/UnclasifiedCu.m
RHS
56
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Description unit
wearing Course tonne
Binder Course tonne
Prime Coat Litre
Aggregate Base Course Cu.m
Grannular Sub Base Cu.m
sq.m
LHS
Sub grade
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unsuitable/Unclassified/Rock Cu.m VD I VD II
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
74+202 -75+000 75+000-76+000 76+000 - 77+000
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unsuitable/Unclassified/Rock Cu.m VD I VD II
sub grade (Exsisting) sq.m
Cu.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
57
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m BRI 04
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
A0 + 000 - A1+000 A1+ 000 - A2+000 A2+000 - A2+708
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m BRI 04
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
RHS
58
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
B1+000 B2+000 B2+346
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
RHS
59
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
C0+000 - C1 + 000 C1+000 - C2+000 C2+180
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
RHS
60
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
LHS
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
sub grade (Exsisting) sq.m
Exavation Unclassified/Rock Cu.m
Cearing & Grabbing ha
Genaral Clearing ha
Site possession
D0+920
Site possession
Genaral Clearing ha
Cearing & Grabbing ha
Exavation rock ( to embankment ) Cu.m
Unclassified excavation Cu.m
Exavation Unclassified/Rock Cu.m
sub grade (Exsisting) sq.m
RHS
Embankment filling(RUC3)/RUC4/Unclasified Cu.m
Sub grade sq.m
Grannular Sub Base Cu.m
Aggregate Base Course Cu.m
Prime Coat Litre
Binder Course tonne
wearing Course tonne
61
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 0+148 Base
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
62
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 1+428 Base
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 1+700
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 2+436
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
63
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 2+640
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 3+143
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 3+660
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
64
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 4+131
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 4+170
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 4+500
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
65
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 4+580
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 4+652
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 4+900
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
66
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 5+293
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 5+462
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 5+800
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
67
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 5+800
Base
Extended
Shell Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 6+205
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 6+220
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
68
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 6+690
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
69
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 7+000
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 7+310
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 7+349
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
70
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 7+660
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 8+040
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 8+250
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
71
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 8+856
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 9+180
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 9+180 Base
Extended
Wall
Shell Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
72
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 9+550
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 9+650
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 10+970
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
73
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Extended
Base
Cell
CH 10+970 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 11+695
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 12+150
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
74
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 13+350
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 13+510
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 13+510 Base
Extended Wall
cell Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
75
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 71+299
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 71+299
Base
Extended
cell Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 71+385
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
76
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 71+600
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 71+700
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
77
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 71+917
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
72+028 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
78
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
72+210 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S1 S1 S1 S1 S1 S1 S1 S1
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
72+262 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 72+382
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
79
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 72+500
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 72+567
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 72+603
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
80
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 72+800
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 73+148
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 73+448
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
81
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 74+253
Base
Extended
cell Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation 12-08-2016
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 74+390 Base
(R) Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
Base
CH 74+808
Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
82
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH 74+808
Base
Extended
Cell Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9 S10
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
77+084 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
77+150 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
83
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
77+410 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
CH WW
77+644
Base
[Extension
Wall
of Existing Form Work
Culvert] Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
84
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling
ConcreteBase
Re
Wall
bar
work Deck
WW
CH Base
A1+430 Form Wall
Work Deck
WW
Base
Concr Wall
eting Deck
WW
Backfilling
Setting out
Excavation
Leveling
ConcreteBase
Re
Wall
bar
work Deck
WW
CH Base
A1+792 Form Wall
Work Deck
WW
Base
Concr Wall
eting Deck
WW
Backfilling
Setting out
Excavation
Leveling
ConcreteBase
Re
Wall
bar
work Deck
WW
CH Base
A2+024 Form Wall
Work Deck
WW
Base
Concr Wall
eting Deck
WW
Backfilling
85
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
A2+388 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
CH WW
B0+223 Base
One cell Wall
extended Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
86
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
C0+488 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
C0+748 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
C1+084 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
87
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Section (L to R)
Cul.No Description
S1 S2 S3 S4 S5 S6 S7 S8 S9
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
C1+920 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
D0+300 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
Setting out
Excavation
Leveling Concrete
Base
Wall
Re bar work
Deck
WW
CH Base
D0+791 Wall
Form Work
Deck
WW
Base
Wall
Concreting
Deck
WW
Backfilling
88
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Bridges Progress
Overpass Bridge BRO-01 at CH1+280
Date of Spread Found. Pile cap Pier Abt.Wall Pier Head Deck Slab
Scrd Pile Pile
DESCRIPTION SYMBOL LOCATION Commencemen Exc. Back Fill
Con. R/ Bor. Con. F R/ F/ R/ F/ R/ F Co R/ F Co
t F/W Con R/F Con Con Con
F W F W F W F W n F W n
Completed up to end of
Item Total/ (Nos) % of Completed
February 2018
Spread Footing 03 03 100.0%
Abutment 02 02 100.0%
Pier Stems 03 03 100.0%
Pier Head 01 01 100.0%
Beam Launching 12 12 100.0%
Deck Slab 02 -
89
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Spread Found. Pile cap Pier Abt.Wall Pier Head Deck Slab
Date of Scrd Pile Pile Back
DESCRIPTION SYMBOL LOCATION Exc.
Commencement Con. Bor. Con. R/ F Co Fill
R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con
F W n
Abutment A1 G0+055 22/12/2016
Completed up to end of
Item Total/ (Nos) % of Completed
February 2018
Spread Footing 03 03 100.0%
Abutment 02 02 100.0%
Pier Stems 03 03 100.0%
Pier Head 01 01 100.0%
Beam Launching 12 12 100.0%
Deck Slab 02 -
90
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Deck
Date of Scrd Spread Found. Tie Beam Pier Stem Abt.Wall Pier Head Slab
LOCATIO Pile Pile Back
DESCRIPTION SYMBOL Commencemen Exc. Con R C
N F Bor. Con. R/ F R/ F R/ F R/ F Fill
t . R/F Con Con Con Con FW Con / o
W F W F W F W F W
F n
Abutment A1 2+710 04/11/2016
Completed up to end of
Item Total/ (Nos) % of Completed
February 2018
Pilling 30 30 100.0%
Tie Beam 10 10 100.0%
Abutment 2 02 100.0%
Pier Stems 30 30 100.0%
Pier Head 10 10 100.0%
Beam Launching 72 -
Deck Slab 12 -
91
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Spread Found. Pile cap Pier Abt.Wall Pier Head Deck Slab
Date of Scrd Pile Pile Back
DESCRIPTION SYMBOL LOCATION Exc.
Commencement Con. Bor. Con. Fill
R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con
R
Abutment A1 5+181 15/02/2017
L
R
Abutment A2 5+216 19/12/2016
L
Completed up to end of
Item Total/ (No’s) % of Completed
February 2018
Pilling 16 16 100.0%
Spread Footing 1 01 100.0%
Pile Cap 2 02 100.0%
Abutment 2 02 100.0%
Beam Launching 12 12 100.0%
Deck Slab 2 01 50.0%
92
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Spread Found. Pile cap Pier Abt.Wall Pier Head Deck Slab
Date of Pile Pile Back
DESCRIPTION SYMBOL LOCATION Bor. Con.
Exc. ScrdCon.
Fill
Commencement
R/F FW Con R/F F/W Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con
Completed up to end of
Item Total/ (No’s) % of Completed
February 2018
Pilling 44 44 100.0%
Pile Cap 08 08 100.0%
Abutment 02 02 100.0%
Pier Stems 12 12 100.0%
Pier Head 04 04 100.0%
Beam Launching 36 36 100.0%
Deck Slab 06 -
93
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Completed up to end of
Item Total/ (No’s) % of Completed
February 2018
Pilling 28 28 100.0%
Pile Cap 06 06 100.0%
Abutment 02 02 100.0%
Piers Stems 04 04 100.0%
Pier Head 04 04 100.0%
Beam Launching 25 25 100.0%
Deck Slab 05 05 100.0%
94
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Completed up to end of
Item Total/ (No’s) % of Completed
February 2018
Pilling 24 24 100.0%
Pile Cap 05 05 100.0%
Abutment 02 02 100.0%
Piers Stems 09 09 100.0%
Pier Head 03 03 100.0%
Beam Launching 20 20 100.0%
Deck Slab 04 -
95
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
96
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
97
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Pile cap Tie Beam Bored Pier Abt.Wall Pier Head Deck Slab
Date of Pile Pile Scrd Back
DESCRIPTION SYMBOL LOCATION Bor. Con. Con. Fill
Commencement
R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con
Completed up to end of
Item Total/ (No’s) % of Completed
February 2018
Pilling 21 21 100.0%
Pile Cap 02 02 100.0%
Tie Beam 02 02 100.0%
Abutment 02 02 100.0%
Piers Stems 06 06 100.0%
Pier Head 02 02 100.0%
Beam Launching 18 18 100.0%
Deck Slab 03 -
98
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Pile cap Tie Beam Bored Pier Abt.Wall Pier Head Deck Slab
Date of Pile Pile Scrd Back
DESCRIPTION SYMBOL LOCATION Bor. Con. Con. Fill
Commencement
R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con R/F FW Con
Completed up to end of
Item Total/ (No’s) % of Completed
February 2018
Pilling 21 21 100.0%
Pile Cap 02 02 100.0%
Tie Beam 02 02 100.0%
Abutment 02 02 100.0%
Piers Stems 06 06 100.0%
Pier Head 02 02 100.0%
Beam Launching 18 18 100.0%
Deck Slab 03 01 33.3%
99
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Progress of Viaduct - 01
Date of Pile Pile Pile cap Bored Pier Abt.Wall Pier Head Deck Slab
SYMBO LOCATIO Bac
DESCRIPTION Commencemen Bor Con R/ F Co R/ F Co R/ F Co R/ F Co R/ F Co
L N k Fill
t . . F W n F W n F W n F W n F W n
Abutment A1 75 + 031 12/02/2017
Pier P1 75 + 061 30/03/2017
Pier P2 75 + 091 29/03/2017
Pier P3 75 + 121 27/03/2017
Pier P4 75 + 151 27/03/2017
Pier P5 75 + 181 18/03/2017
Pier P6 75 + 211 15/03/2017
Pier P7 75 + 241 11/03/2017
Pier P8 75 + 271 04/03/2017
Pier P9 75 + 301 02/03/2017
Pier P10 75 + 331 07/03/2017
Pier P11 75 + 361 03/02/2017
Pier P12 75 + 391 02/02/2017
Pier P13 75 + 421 15/01/2017
Pier P14 75 + 451 01/12/2017
Pier P15 75 + 481 12/11/2016
Pier P16 75 + 511 22/10/2016
Pier P17 75 + 541 21/10/2016
Pier P18 75 + 571 06/09/2016
Pier P19 75 + 601 06/09/2016
Pier P20 75 + 631 27/09/2016
Abutment A2 75 + 661 28/09/2016
100
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
rogress of Viaduct - 01
101
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Progress of Viaduct – 02
Substructure
102
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
Progress of Viaduct – 02
Superstructure
Completed up to end of
Item Total/ (Nos) % of Completed
February 2018
Spread Footing 18 18 100.0%
Abutment 2 2 100.0%
Pier Stems 28 28 100.0%
Pier Head 14 14 100.0%
Beam Launching 96 96 100.0%
Deck Slab 16 16 100.0%
103
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
104
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
ANNEXURE 11: CONTRCTOR’S FOREIGN STAFF & LABOUR RETURN IN FEBRUARY 2018.
Functioning
Item Description Changes
January February
(+) or (-)
1 Key Staff 21 -7 14
2 Site Engineer 13 0 13
3 QA Engineer 1 0 1
4 QCI 0 0 0
5 Quantity Surveyor 5 -1 4
6 Charge hand 2 0 2
7 Document Controller 0 0 0
8 Office Clark 5 0 5
9 Safety Officer 4 0 4
10 Surveyor 4 0 4
11 Draughtsman 5 0 5
12 Administration Department Officer 0 0 0
13 General Affair Officer 4 0 4
14 Assistant in Equipment Department 2 0 2
15 Coordinator 0 0 0
16 Environmental officer 0 0 0
17 Material Technician 3 0 3
18 Security Supervisor 0 0 0
19 HR Office 1 0 1
20 Financial Accountant 3 0 3
21 Financial Assistant 1 0 1
22 Lab Technician 3 0 3
23 Foreman 2 0 2
24 Secretary 0 0 0
25 Store Keeper 2 0 2
26 Receiving Clerk in Material Department 1 0 1
27 Purchaser in Material Department 2 0 2
28 Laboratory Assistant 1 0 1
29 Survey Helpers 0 0 0
30 Mechanic 1 0 1
31 Electrician 2 0 2
32 Equipment Operator 6 0 6
33 Batching Plant Operator 1 0 1
34 Bar bender 0 0 0
35 Welder 0 0 0
36 Plumber 0 0 0
37 Mason 0 0 0
38 Carpenter 0 0 0
39 Labor 0 0 0
Total 95 -8 87
105
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
ANNEXURE 12: CONTRCTOR’S LOCAL STAFF & LABOUR RETURN IN FEBRUARY 2018.
Functioning
Item Description Changes
January February
(+) or (-)
1 Key Staff 15 0 15
2 Site Engineer 15 0 15
3 QA Engineer 4 0 4
4 QCI 18 0 18
5 Quantity Surveyor 7 0 7
6 Charge hand 5 0 5
7 Document Controller 12 0 12
8 Office Clark 5 0 5
9 Safety Officer 9 0 9
10 Surveyor 10 0 10
11 Draughtsman 4 0 4
12 Administration Department Officer 1 0 1
13 General Affair Officer 4 0 4
14 Assistant in Equipment Department 1 0 1
15 Coordinator 1 0 1
16 Environmental officer 1 0 1
17 Material Technician 24 0 24
18 Security Supervisor 5 0 5
19 HR Office 4 0 4
20 Financial Accountant 2 0 2
21 Financial Assistant 1 0 1
22 Lab Technician 1 0 1
23 Foreman 21 0 21
24 Secretary 2 0 2
25 Store Keeper 5 0 5
Receiving Clerk in Material 5 5
26 0
Department
27 Purchaser in Material Department 4 0 4
28 Laboratory Assistant 64 0 64
29 Survey Helpers 24 0 24
30 Mechanic 4 0 4
31 Electrician 5 0 5
32 Equipment Operator 78 0 78
33 Batching Plant Operator 7 0 7
34 Bar bender 24 0 24
35 Welder 14 0 14
36 Plumber 6 0 6
37 Mason 28 0 28
38 Carpenter 4 0 4
39 Labor 230 -2 228
Total 674 -2 672
106
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
1 Bulldozer nr 14
2 Roller nr 28
3 Loader nr 17
4 Excavator nr 58
5 Motor Grader nr 46
7 Crusher nr 03
8 Air Compressor nr 11
9 Vibrating hummer nr 04
10 Concrete pump nr 01
11 Weighbridge nr 03
12 Generator nr 15
13 Steel bar machine nr 03
15 Mobile crane nr 05
16 Crawler crane nr 03
17 Gantry crane nr 06
18 Transport truck nr 03
19 Ice machine nr 02
20 Paver nr 03
21 Bitumen spray bowser nr 02
22 Tired Roller nr 04
23 Water Bowser nr 39
Total 441
107
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
108
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
109
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
110
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
111
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
112
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
113
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
114
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
115
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
116
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
117
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
118
Consultancy Services for Design Review and Construction Supervision of Monthly Progress Report
Extension of Southern Expressway Project from Mattala to Hambantota via Andarawewa March 2018
119