100MW SPP, M/s KEC at P5

Approved/
Date of
S.No Designs & Drawings Status Commented Remarks
submission on

1 Inverter Approved 02.06.2017 -


HT Cables( 3Cx240Sqmm, 3Cx300Sqmm) 27.05.2017(240)
2 Approved -

LT Cable(1Cx300Sqmm, 1Cx185Sqmm) 27.05.2017(300)


3 Approved -
4 Plant Overall Layout Approved 25.05.2017
5 Lightning Protection Layout Approved -
6 2x50MW AC SLD Approved -
7 33KV ICR Switchgear Panels Approved -
8 Inverter Room Equipment Layout Approved -
9 Aux. SLD for ICR & CMCS Approved -
10 Lightning Arrestor
11 Master Drawing List Approved 27.05.2017
12 L2 Schedule Approved 10.04.2017
13 DC Solar Cable(1Cx 6sqmm) Approved 03.06.2017
14 Inverter GA Drawings
15 Inverter Duty Transformer 25.05.2017 Comments 14.06.2017
GA Drawing & Data Sheet of lightning 08.06.2017
16 Arrester Approved 19.06.2017
17 LA Layout Drawing 17.06.2017 Approved 19.06.2017
18 ICR 33KV Switchgear Panels 22.06.2017 Comments 05.07.2017
19 ICR Equipment Layout Drawing 12.07.2017 Approved
20 GA & Control Schematic drawing for CMCs 12.07.2017 Comments
33KV Switchgear Panels 03.08.2017
21 Overall AC cable routing layout 14.07.2017 Comments 16.08.2017
22 Overall DC cable routing layout 14.07.2017 Comments
23 Lightining arester Comments
24 Seefrom & plan for 4 Po'S Structure 10.08.2017
25 PT Documents( GTP&GA) 19.07.2017 Comments
26 Isolator Documents(GTP&GA) 19.07.2017 Comments
27 Current Transformer(GTP&GA) 19.07.2017 Comments
28 ABT Meter (GTP&Panel Drawings)

29 Inverter room and control room Earthing 18.07.2017


Lyout
30 Weatherr monitoring system documents 19.07.2017
31 Module washing system documents 19.07.2017
32 I/O List documents 10.08.2017
Submission of Auxilliry Panel (For ICR&MCR)
33
Dispatch clearances issued

Balance to be
S.No Item Description Total Quantity Quantity Inspected inspected
1 Inverters 80nos 24nos 56nos
2 1Cx6Sqmm DC Cable 450Kms 450Kms NIL
3 3Cx240Sqmm HT Cable 15Kms 5Kms 10Kms
4 1Cx300Sqmm Cable 240Kms 120Kms 120Kms
Remarks

-
-
-
-
-
100MW SPP, M/s MBE at P4

Date of Approved/
S.No Designs & Drawings Status Remarks
submission Commented on
1 L2 Schedule Approved 26.04.2017 -
2 Inverter Approved 06.07.2017 -
3 Inverter Transformer Approved 11.07.2017 -
4 MDL Approved 14.07.2017
5 AC SLD Approved 14.07.2017 -
6 Inverter Control Room GA Drawing Approved 21.07.2017 -
7 Aux. SLD for ICR & CMCS Approved 21.07.2017 -
8 General Plant Arrangement 28.07.2017 -
9 CMCS GA Drawing 27.07.2017 -
10 PV Modules Remarks 16.06.2017
LA Layout Drawing Communicate
11 Approved 31.07.2017
HT Cable Meeting & Trenesh
12 Layout Drawings Approved 29.07.2017
13
14
15
16
17
Remarks

-
-
-

-
-
-
-
-
100MW SPP, M/s VSPL at P4

Approved/
S.No Designs & Drawings Status Commented Remarks
on
1 AC DC SLD Comments -
2 L2 Schedule Approved 22.06.2017 -
3 AC SLD Approved 21.07.2017 -