You are on page 1of 18

Three Types of Project Management

Organizations

by eric.shaw » Sun 27 Feb 2011 5:19 am
Post

The current types of organizational structure of project management are: functional organizational
structure, project-based organizational structure and matrix organizational structure.

1. Functional organizational structure.


Functional organizational structure is to be managed in the current organization hierarchical structure,
once the project begins operation, the various components of the project are taken by the functional units,
each unit is responsible for its charged component. If the the project established, a functional area play a
dominant role, functional areas on completion of the project, senior managers will be responsible for
project coordination.

Advantages of this structure: First, the use of personnel with greater flexibility, as long as the choice of a
suitable functional departments as the project supervisor, the department will be able to provide
professional and technical personnel required by the project, and technology experts can also be used by
different projects and after completion of the work can go back to his original work; Second, when the
project team members leave or leave the company, the functions can be used as the basis for
maintaining the continuity of the project; third, functional department can provide a normal career path for
professionals.

The disadvantage of this structure is: First, projects often lack of focus, each unit has its own core
functions of general business, sometimes in order to meet their basic needs, responsibility for the project
will be ignored, especially when the interest taken in the project brought to the unit not the same interest;
Second, such organization has certain difficulties in the inter-departmental cooperation and exchanges;
Third motivation is not strong enough for project participants, they think the project is an additional
burden, and not directly related to their career development and upgrading; Fourth, in such organizational
structure, sometimes no one should assume full responsibility for the project, often the project manager is
only responsible for part of the project, others are responsible for the other parts of the project, which
leads to difficulties in coordination situation.

2. Project-based organizational structure.

Project organizational structure refers to the creation of an independent project team, the team’s
management is separated from the parent organization’s other units, have their own technical staff and
management, enterprise assigns certain resources to project team, and grant project manager of the
largest free implementation of the project .

The advantages of this structure: First, focus on this project team, project manager is solely responsible
for the project, the only task for project members is to complete the project, and they only report to the
project manager, avoiding the multiple leadership; Second, the project team’s decision is developed
within the project, the reaction time is short; Third, in this project, members work with strong power, high
cohesion, participants shared the common goal of the project, and individual has clear responsibilities.

The disadvantage of this organizational structure: First, when a company has several projects, each
project has its own separate team, which will lead to duplication of efforts and the loss of scalable
economies; Second, the project team itself is an independent entity, prone to a condition known as
“Project inflammatory” disease, that is, there is a clear dividing line between the project team and the
parent organization, weakening the effective integration between project team and the parent
organization; Third, the project team members lack of a business continuity and security, once the project
ended, return to their original functions may be more difficult.

3. Matrix organizational structure.

Matrix organizational structure is a hybrid form, it loads a level of project management structure on the
functional hierarchical structure. According to the relative power of project managers and functional
managers, in practice there are different types of matrix systems, respectively, Functional Matrix: in this
matrix, functional managers have greater powers than project managers); Project Matrix: in this matrix,
project managers have greater powers than functional managers); Balance Matrix: in this matrix,
functional managers and project managers have the equal powers.

The advantages of this organizational structure: First, it is the same as functional structure that resources
can be shared in multiple projects, which can significantly reduces the problem of redundant staff;
Second, project is the focus of work, with a formal designated project manager will make him give more
attention to the project, and responsible for the coordination and integration work between different units;
Third, when there are multiple projects simultaneously, the company can balance the resources to ensure
that all the projects can progress to complete their respective costs and quality requirements; Fourth, the
anxiety of project members is reduced greatly after the end of the project, while they are strongly
associated with the project, on the other hand, they have a “home” feeling about their functions.
The disadvantage is that this organizational structure: First, the matrix structure has exacerbated the
tensions between functional manager and project manager; Second, under any circumstances, sharing
equipment, resources and personnel among different projects will lead to conflict and competition for
scarce resources; Third, in the process of project implementation, the project manager must negotiate
and consult with the department managers on various issues, which leads to the delay in decision
making; Fourth, matrix management is not according to the principles of unified management, project
members have two bosses, the project manager and functional managers, when their commands are
divided, it will make members at a loss.

Three different forms of the matrix organizational structure does not necessarily have the advantages and
disadvantages described above: Project Matrix can increase the project’s integration, reduce internal
power struggle, its weakness is poor control of their functional areas and prone to “project inflammation”;
Functional Matrix can provide a better system for managing the conflict between different projects, but
maintaining the control of functions is at the cost of inefficient integration of projects; Balanced Matrix can
achieve the balance between technology and project requirements better, but its establishment and
management is very subtle, is likely to encounter many problems related to matrix organization.

Describe the Advantages and Disadvantages of Project Management

by Andra Picincu - Updated June 25, 2018

More and more companies are either outsourcing project management or hiring professionals to
handle this task. With the changes in the industry, it can be difficult to find qualified people who
are on top of the latest trends and strategies. Only 2.5 percent of organizations successfully
complete all of their projects. A staggering 70 percent of projects fail. Considering these
numbers, you might wonder whether or not it's worth hiring a project manager. Just like
everything else, there are advantages and disadvantages to consider. A skilled project manager
can reduce your expenses, streamline workflow management and help grow your business.

Project Management Pros


Whether you're running a small business or an established organization, you might not
be able to handle all types of projects from start to finish. Certain projects are extremely
complex and have a tight deadline or require special skills that your team may not have.
A qualified project manager can help you organize and manage the most time-
consuming tasks. He will also supervise your team, provide feedback and find ways to
cut costs. Other project management pros include timely and efficient goal setting,
improved communication, greater customer satisfaction, high level of expertise and
accurate risk assessment.
Timely and Efficient Goal Setting
Most projects fail simply because managers lack a clear goal. In 2013, less than a third
of all projects were delivered on time and within the allocated budget. For this reason,
setting SMART goals is paramount.
Project management experts can set goals that are specific, measurable, attainable,
realistic and time-bound. That's what the acronym SMART stands for. They will ensure
that your projects are ready on time without exceeding the budget. These professionals
have the expertise and tools needed to create forecasts, manage project costs and
determine the risks.

Improved Communication
Project management allows for more efficient communication between leaders and
other employees involved in the project. They work as a cohesive team, brainstorm
ideas and receive feedback in real-time. As your team becomes stronger, more
opportunities will open up within the industry.

Greater Customer Satisfaction


Since project management methodologies ensure on-time delivery and higher
completion rates, companies experience greater customer satisfaction. This translates
into more revenue and business growth. Your organization will be known for delivering
excellent results.

High Level of Expertise


By hiring a project manager or outsourcing projects, your company will benefit from a
high level of expertise. The people within your organization will learn new things and
gain a new perspective that will contribute to their professional growth. Additionally,
project management will free up your time so you'll be able to focus on the core aspects
of your business.

Accurate Risk Assessment


Over 75 percent of companies lack confidence in project success. Excessive rework,
poor communication and unclear objectives are often the culprits.
Project management allows you to take calculated risks and allocate resources more
efficiently. You will know what the risks are before even getting started. This way, you
can solve any problems in the early stages and make smarter decisions.

Project Management Cons


Loss of control, coordination breakdowns, security issues and interpersonal conflicts are
major disadvantages of project management. Additionally, your organization may incur
higher costs by outsourcing work or by hiring new employees to complete the project.
Sometimes, project management can interfere with your daily operations or go
drastically wrong.

High Costs
If you're hiring a project manager, expect to invest in specialty software. These
programs can be costly and difficult to implement. Since your team will use them too,
they may need training.

Increased Complexity
Project management is a complex process with multiple stages. Some experts have a
tendency to complicate everything, which may confuse your team and cause delays in
project delivery. They can also become too rigid or precise in their plans, creating a
stressful environment within the organization.

Communication Overhead
When you hire a project management team, new employees join your company. This
adds an extra layer of communication and may not always match your organizational
culture. That's why experts recommend keeping your team as small as possible. The
larger a team is, the higher the communication overhead.

Lack of Creativity
Sometimes, project management leaves little or no room for creativity. Team leaders
either focus excessively on the management processes or set tight deadlines, forcing
their staff to work within strict parameters. This can discourage creative thinking and
hamper innovation.
An organization can grow and achieve success without a project management team in
place. However, hiring a skilled professional to handle these aspects can open up new
opportunities and help your company reach its goals faster.

PROJECT SUCCESS AND FAILURE:


WHAT IS SUCCESS, WHAT IS FAILURE, AND HOW CAN YOU
IMPROVE YOUR ODDS FOR SUCCESS?
We know why projects fail, we know how to prevent their failure – so why do they
still fail?”(2)This statement could be applied to the recent Space Shuttle disaster,
or the 2003 collapse of a large portion of the U.S. electrical grid. But the author
was talking about Information Technology and Information System project failures,
as they existed in 1994. Information Technology and Information System failures
have been the topic of many articles, conferences, symposiums, studies, and
research initiatives. The literature of the IT and IS community is rife with articles
and commentary about project failures. But just how bad is the situation? Do a
large percent of projects really fail or do we only hear the bad news? What is
failure and what is success? And lastly, what can you do to improve your success
quotient? Let’s start by looking at project failure rates and why projects fail.
There are many writers who tell us why projects fail. For instance,
Field(12) tells us that “projects fail too often because the project scope was not
fully appreciated and/or user needs not fully understood.” Hulme(13) tells us that
“MIS projects and associated procurements take place in an environment
characterized by the following: Lack of management continuity and an incentive
system that encourages overly optimistic estimates of the benefits that can be
attained from doing the project.” And Leicht(5) tells us that high user expectations
can actually be the cause of project failure. Hoffman(15) tells that projects fail
because of poor alignment between IT departments and business users. And in
another article Hoffman(9) tells us that project managers too often act as “process
cops and report compilers and loose sight of what they’re supposed to be doing –
to make sure projects are running effectively”. Hodgson(23) style='mso-bidi-font-
weight:normal' tells us that “projects fail – that’s the fact of life. Too many fail
because the average project is like an iceberg – 9/10ths of it lay hidden from
view”. All of these writers are correct. But none of these authors are reporting
systematic research of the mechanisms that cause project success or
failure. And none of them provide insight into the rate of project failures.
How Often Do Projects Fail and How Can This be Measured?
In a 2003 article Julia King(10) reports, “At companies that aren’t among
the top 25% of technology users, three out of 10 IT projects fail on
average. Translation: for these companies an amazing 30% of IT projects
fail. Now if you are an extremely optimistic person you might conclude the good
news is that 70% of these projects succeed. But note that King does not tell us
how many of the 70% of the “successful” projects were over budget, over time, or
defective in function upon completion. There are many ways to measure success
and failure, but there is no strict dividing line between the two.
Baker(20) concludes, “Like everything else, the definition of project failure is in a
state of flux.” And O’Brochta(18) tells us that “the big problem with assessing
project success is that it is not precise.” O’Brochta continues, “This dynamic can
often be the Achilles heal for a project. Without a dependable understanding of
what constitutes success, the project is placed in the untenable position of being
judged against differing criteria, and invariably becomes one more failure statistic
reported by research firms such as Standish, Gartner, Forrester, and others.”

And so, Lewis(7) tells us that “On average, about 70% of all IT-related
projects fail to meet their objectives.” In this case Lewis includes not only projects
that were abandoned (failed), but also those that were defectively completed due
to cost overruns, time overruns, or did not provide all of the functionality that was
originally promised. Amazingly, Lewis does not consider this 70% failure to meet
objectives a serious issue, and compares it to the batting average of a major
league player. Lewis contends major league coaches are happy with a 30% at-
bat success rate for a player, and Lewis thinks the same standard should apply to
IT projects. There seems to be only one problem with Lewis’ outlook, and that is
that the customer, the bill payer, may not share this sentiment.
There are other reports of project failure rates. A 1997 seminar
paper(3) states that “In 1992 the Unites States General Accounting Office (GAO)
reviewed Management Information Systems (MIS) projects and concluded:
Developing and modernizing government information systems is a difficult and
complex process. Again and again, projects have run into serious trouble, despite
hard work by dedicated staff. They are developed late, fail to work as planned,
and cost millions – even hundreds of millions – more than expected”. In the same
article we are told that research by the Standish Group indicates only16.1 percent
of all MIS projects are completed on time and within budget. Translation: 83.9
percent of projects fail either to some extent or fail completely. So this leads to
several questions. Regardless of measurement semantics, why do projects
fail? Is there one cause or are there many causes? If the overall failure rate is
going to remain high, then how can you, the reader, become the exception to this
rule of failure and achieve a much higher success rate for your projects? Your
career may well depend on it.
Let’s look at the Standish Group’s CHAOS Report(1) and see what it has to
say. For the Standish Group not only published failure and success rates, but
also pointed to indicators for success and failure. Their original report was done in
1994 and published as THE CHAOS Report. The Standish Group studied 365
companies with a total of 8,380 Information System applications under
development. The resultant report divides projects into three distinct outcomes –
which they called Resolutions.
Resolution Type 1 is a “Project Success” – it completed on time and budget,
with all features and functions as specified. Only 16.2% of projects fell in this
category.
Resolution Type 2 is “Project Challenged.” These were completed, but were
over cost, over time, and/or lacking all of the features and functions that were
originally specified. 52.7% of all studied projects fell into this Resolution Type 2
(Challenged) category.
Resolution Type 3 is termed “Project Impaired/Failed.” These projects were
abandoned or cancelled at some point and thus became total losses. A disturbing
31.1% of all studied projects fell into this category.
For the purposes of this paper we will use the above three Standish Group
measures of project outcome: A successful project must be on time, on budget,
and deliver quality (features and functions) as promised. Anything less will be
either a failed project or a challenged project.
The disturbing conclusion from this Standish report is that only 16.2% of
projects were successful by all measures, and that of the 70% of projects that
were not successful, Over 52 percent were partial failures and 31% were complete
failures. This should certainly give project managers both food for thought and
motivation to action.
So now that we have information about project success and failure rates,
are there any significant differentiators found between successful and failed
projects? According to the 1994 Standish CHAOS Report, there are.
The top 5 factors found in successful projects are:
1. User Involvement
2. Executive Management Support
3. Clear Statement of Requirements
4. Proper Planning
5. Realistic Expectations
These are the top 5 of 10 listed in the report. The report concludes that
these were the elements that were most often pointed to as major contributors to
project success. Will these elements alone guarantee success? Never. But if
these are done well, a project, according to the Standish Group, will have a much
higher probability of success.
The next category of differentiators from the Standish report deals with
projects that proved to be “Challenged;” that is they were completed buy were
over budget, over time, or did not contain all functions and features originally
required.
The top 5 indicators found in “Challenged” projects are:
1. Lack of User Input
2. Incomplete Requirements & Specifications
3. Changing Requirements & Specifications
4. Lack of Executive Support
5. Technical Incompetence
And finally a list of all the top factors found in “Failed” projects
1. Incomplete Requirements
2. Lack of user involvement
3. Lack of Resources
4. Unrealistic Expectations
5. Lace of Executive Support
6. Changing Requirements & Specifications
7. Lack of Planning
8. Didn’t Need it Any Longer
9. Lack of IT management
10. Technical Illiteracy
Notice in the above three project outcomes, user involvement is listed as
the first or second item in each.
ANOTHER PERSPECTIVE TO SUCCESS AND FAILURE:
The results of a research paper(6), presented at a 1991 PMI symposium,
found that “there are areas that should be emphasized by project managers who
are committed to the success of their projects.” The research method used
Content Analysis of showcase articles featured in pmNETwork and Project
Management Journal. The researchers studied 24 areas of project management
and found that 3 of the 24, if done well, clearly indicated that a project had a high
probability of success. The paper states “it may be inferred that these three
variables (Good Planning, Clear Responsibility and Accountability, and Schedule
Control) in particular have the greatest impact on the performance of the
project.” Do not, however, conclude that all of the other areas were then not
important to project success. The paper also tells us “the data suggests that
many different variables are needed to accomplish a successful project. Let’s look
at the three key areas that, if done well, point to a successful project completion.
Good Planning
The first indicator, Good Planning, requires excellent forward planning,
which includes detailed planning of the process implementation stages, task
timeliness, fall-back positions, and re-planning. Notice that initial planning is not
enough. Projects often take wrong turns, or initial solutions prove
unfounded. The project manager who does not prepare to re-plan, or has not
considered and planned fall-back positions when initial plans fail, will often find
that the project first stalls, and then fails. We must remember that project
management is not a straight-line process, but an iterative process that requires
agile rethinking as the known environment changes before your eyes.
Clear Responsibility and Accountability of Team Members
This requires that all team members have a clear understanding of their
roles and duties in the project. They must understand how expectations vs.
achievements will be measured and graded. It is left to the project manager to
properly implement the communication of these responsibilities, to provide
feedback, and to assure all understand that for which they will be held
accountable.
Schedule Control
This requires the continual monitoring and measurement of time,
milestones, people, and equipment schedules. Properly done schedule control
will also give the first hint that initial planning may not be going according to
schedule. If you pickup on these hints, you have an opportunity to implement a
fallback position and/or re-plan to get back on track.
The same paper finds two attributes that appeared equally for projects that
succeeded or failed. These two were: Use of Consultants, and Well Qualified
Personnel. Equal numbers of successful and failed projects used consultants,
and the same was true for well-qualified personnel. It is perhaps disappointing
that these two attributes did not portend project success. Obviously there are
many other variables that hold great weight in determining the ultimate outcome of
an IT project.
Lastly this same study listed four things that foreshadowed a failed
project. There were: Lack of Efficient Internal Communication Links, Lack of
Efficient External Communication Links, Lack of Responsive Decision Making, and
Lack of Effective Teamwork. These appeared most frequently in a negative
context in failed projects.
So at this point we have several lists of things that might indicate project
success and others that might indicate project failure. But there is one thing
primarily that you must recognize in all of these lists. There are no stock answers,
and there is no one list that will guarantee success. IT and IS projects are
complex by nature, and each is unique. It is very difficult to plan with complete
certainty something that has never before been done. Every single factor in all of
these lists is important and must be considered for each project. The most difficult
part may be prioritizing the factors. Which are most important? Which must be
done first? Hopefully the lists will help you answer these questions. But in each
case you must ultimately make the decisions based upon the unique
circumstances of your immediate project.
COMMUNICATION
B. Elenbaas(17) tells us that “projects are about communication,
communication, communication.” In 1973 I was speaking with a gentleman who
had recently retired from Monsanto Chemical Company. His career with
Monsanto began back in 1933. As we spoke, the subject of communication
entered our conversation and this fine gentleman related the following story: “In
1933 when I was brand new to Monsanto, my boss told me that the biggest
problem at Monsanto was (the lack of) communication. And 40 years later when I
retired, the biggest problem at Monsanto was still the lack of
communication.” This gentleman emphasized the fact that a lack of
communication is very costly to a company. Sure, a company may still succeed,
but without good internal and external communication I submit that the cost of
success will be much higher than necessary. Another consequence is that
success often takes much longer than necessary to achieve. Sometimes success
never arrives.
Lack of good communication can easily turns a corporate strategy, or an IS
project, into a modern day Towel of Babel. Lavine(8) tells us that “The warring
factions in Africa have a better chance of communicating with each other than
many of the user and technology groups that ‘work together’ in today’s project
development environment.” Lavine also relates that some years ago he was hired
as a developer for a large bond-processing bank. He was told on his third day
that the development team was no longer allowed to speak to anyone from the
business community. It seems that relations between the two groups had become
so bad that communication had come to a complete halt. In fact, negotiations had
begun in an attempt to find an acceptable liaison to work between the two
groups. This may seem like an extreme example, but this happens in
projects. Sometimes it if overt, but all too often it is on a subtle level. Subtle
dysfunction is probably harder to correct because it is more difficult to
pinpoint. You know something is wrong, but it’s difficult to tell exactly what it is or
to pinpoint the root cause of the problem. This often makes the problem
intractable.
Kirksey (3) tells us that one predictor of project success is when
communications are kept honest and open between customer and vendor. His
major indicator of project failure in this area is when an IS project manager fails to
correctly read warning signs that communication is breaking down. The result is a
missed opportunity to correct the situation before it becomes too late.
Wixom(4) argues that User Participation and Team Skills are two of seven
imperative implementation factors that determine project success or failure, and
that these two are essentially communication skills. “User Participation occurs
when users are assigned project roles and tasks, which lead to a better
communication of their needs, and help ensure that the system is implemented
successfully”. This is what Wixom(4) has to say about Team Skills: “People are
important when implementing a system and can directly affect its success or
failure. Team skills include both technical and interpersonal abilities”. These
interpersonal abilities include, without exception, interpersonal communication
skills. Who do you know that communicates effectively? Watch them and
determine why their communication is effective. Also watch those who do poorly
at communicating, and make every effort to avoid their bad habits. There is one
last point that involves communication and how it must be used to put user
expectations into perspective. Hayes(11) provides additional insight by
noting, “executives expect sales efforts and product development efforts to fail,
but not IT projects. He also tells us that we must convince managers that system
development today is a gamble, but one the may have a big payoff. Hayes tells
us that we must “market” our efforts and manage user expectations. If the user
understands that there is risk, then “you’ll have a better chance of delivering what
the users expect.” And if you want psychological insigits into people and projects,
review Wastell's(16) insight into learning dysfunction and its association with
project success or failure.
AVOID AT ALL COST
Here are a few things that should never happen to you but probably will at one
point or another. If you ever hear yourself tell a client “No, you’re wrong, that was
never part of the scope! It’s clearly a scope expansion!”(21), then you have
violated one of the cardinal rules about controlling scope expansion. If you find
yourself talking more than listening, then “stop talking”(22) “because the outcome
of having your view prevail” may not ultimately be wise. Two or three heads are
often better than one, so listen to the others – you might learn something. “If a
project manager wants to fail, operate in a vacuum”(24). Operating in a vacuum,
intentionally or not, is a sure way to make sure communication dies on your
project. And lastly there is this favorite quote, “The Lone Ranger had Tonto, Yogi
Bear had Boo-Boo, so why do some PMs run without adequate help”?(25) Think
about this next time you don’t want to share the load, perhaps because no one
can do it better than you.

JIANG’S LIST
One concise literature study by Jiang, et al(19) produced a list of 13
success factors. Jiang’s conclusion at the end of this study was that “the literature
suggests that IS users and IS professionals are remarkably identical in their
importance rankings of success factors. The similarity extends to comparisons
across experience level and gender. The similarity across these demographic
considerations allows a confidence in the rankings obtained. These rankings can
thus be used as guidance in establishing policies and procedures.” Here is the list
that I will call Jiang’s 13.
1. Clearly defined goals (including the general project philosophy or general
mission of the project, as well as commitment to those goals on the part of
the team members).
2. Competent project manager. The importance of initial selection of skilled
(interpersonally, technically, and administratively) project leader.
3. Top Management Support. Top or divisional management support for the
project that has been conveyed to all concerned parties.
4. Competent project team members. The importance of selecting and, if
necessary, triaging project team members.
5. Sufficient resource allocation. These are Resources in the form of
money, personnel, logistics, etc.
6. Adequate communication channels. Sufficient information is available
on the project objectives, status, changes, organizational coordination,
clients’ needs, etc.
7. Control Mechanisms. (Including planning, schedules, etc.). Programs are
in place to deal with initial plans and schedules.
8. Feedback capabilities. All parties concerned with the project area able to
review project status, make suggestions, and corrections through formal
feedback channels or review meetings.
9. Responsiveness to client. All potential users of the project are consulted
with and kept up to date on project status. Further, clients receive
assistance after the project has been successfully implemented.
10. Client consultation. The project team members share solicited input from
all potential clients of the project. The project team members understand
the needs of those who will use the systems.
11. Technical tasks. The technology that is being implemented works
well. Experts, consultants, or other experienced project managers outside
the project team have reviewed and critiqued the basic approach.
12. Client Acceptance. Potential clients have been contacted about the
usefulness of the project. Adequate advanced preparation has been done
to best determine how to sell the project to the clients.
13. Trouble-shooting. Project team members spend a part of each day
looking for problems that have surfaced or are about to surface. Project
team members are encouraged to take quick action on problems on their
own initiative.
The Future is Getting Brighter Every Day
What does the future hold? According to Johnson(14) the success rate for
projects has actually increased since the original Standish CHAOS
report. Johnson attributes this increased success rate to more project people
using the Standish “Recipe for Success” that was established in 1998. Johnson
tells us that the overall project success rate has increased from 16% in 1994 to
28% in 2000. What then are the top 5 factors that have caused this significant
increase? According to Johnson’s report the top 5 are:
1) Executive Support: This is now the No. 1 factor in project failure. Lack of
executive support can and does jeopardize projects. Positive Executive support
positively influences project outcome.
2) User Involvement: Lack of user involvement traditionally has been the No. 1
reason for project failures. Although it is now No. 2, its importance has not
decreased. Johnson feels that project professionals better handle and solve this
major problem.
3) Experienced Project Manager: Johnson reports that ninety-seven percent of
successful projects have an experienced project manager at the helm.
4) Clear Business Objectives: Better control of objectives is attributed to
experienced project managers.
5) Minimized Scope: Do not allow your scope to grow. Johnson claims that
minimized scope has replaced small milestones.
Conclusion
There are many things that lead to project success and many that lead to
failure. Jiang’s list of 13 is a good list to use as a starting point for your projects. But
like any of the lists, it is not enough in and of itself. Good project management is a
process of continuous improvement. It is a process of making mistakes and learning
from those mistakes. It is a process of continuous study and learning. For those who
cannot devote themselves to this never-ending process, there will be few successes.

REFERENCES
(1) THE CHAOS Report (1994), The Standish
Group, http://www.standishgroup.com/sample_research/chaos_1994_1.php
Viewed Nov 17, 2003

(2) Martin Cobb, (1996). “Unfinished Voyages: a follow-up to the CHAOS


Report”,Standish Group
Report, http://www.standishgroup.com/sample_research/unfinished_voyages_1.p
hp
Viewed Nov 17, 2003

(3) Kirksey, Kirk A, (1990). “Storm Warning: Danger Signs During Software
Implementation”, Health Management Technology, 11, 6; pg 35

(4) Wixom, Barbara H. (2001). “Am Empirical Investigation of the Factors Affecting
Data Warehouse Success”, MIS Quarterly, Vol. 25 No.1, pp 17 – 41.
(5) Leicht, Michael. (1999). “Managing User Expectations.” University
of Missouri St. Louis e-
publication. http://www.umsl.edu/~sauter/analysis/user_expectations.ht
ml,
viewed 11/12/2003

(6) Anil, Iyer and Thomasson, David (1991). “An Empirical Investigation of the Use
of Content Analysis to Define the Variables Most Prevalent in Project Successes
and Failures”, Proceedings of the 1991 PMI Annual Seminar/Symposium, Sept 27
– October 2, 1991

(7)) Lewis, Bob. (2003). “The 70-percent failure”, InfoWorld.


http://archive.infoworld.com/articles/op/xml/01/10/29/011029/opsurvival.xml
Viewed 12/12/2003

(8) Levine, Mordy (1994). “Why Technology Uses and Developers don’t get
along”, Wall Street and Technology, Dec 1994, vol. 12, 7: pg. 56

(9) Hoffman, Thomas “Value of Project Management Offices Questioned”,


Computerworld, July 21,
2003. http://www.computerworld.com/printthis/2003.0,4814,82345,00.html,
Viewed 11/7/2003

(10) King, Julia. “Survey shows common IT woes”, Computerworld, June 23,
2003, http://www.computerworld.com/managementtopics/management/story/0,10
801,82404,00.html. Viewed Dec 13, 2003

(11) Hayes, Frank. (1997). “Managing User Expectations”, Computerworld, Nov 3,


1997, 31,44.

(12) Field, Tom. (1997). “When bad things happen to good projects”, CIO
magazine, Oct 15, 1997, Vol. 11, 2; pg. 54, 6 pgs.

(13) Hulme, Martyn R. (1997). “Procurement Reform and MIS Project Success”,
Journal of Supply Chain Management, Winter 1997; 33, 1; pg 2.

(14) Johnson, Jim, et al. (2001). “Collaborating on Project


Success.” http://www.softwaremag.com/L.cfm?Doc=archive/2001feb/Collaborativ
eMgt.html
Viewed 11/17/2003

(15) Hoffman, Thomas. 2003. “Corporate Execs Try New Ways to Align IT with
Business Units.” Computerworld. October 27, 2003
http://www.computerworld.com/printthis/2003/0,4814,86466,00.html
(16) Wastell, David G. “Learning Dysfunctions in Information Systems
Development; Overcoming the Social Defenses With Transitional Objects”, MIS
Quarterly, Dec 1999; 23, 4; pg 581

(17) Elenbass, B. (2000). “Staging a Project – Are You Setting Your Project Up
for Success?”, Proceedings of the Project Management Institute Annual Seminars
& Symposiums, September 7 – 16, 2000, Houston, TX.

(18) O’Brochta, Michael. (2002). “Project Success – What Are the Criteria and
Whose Opinion Counts?”, Proceedings of the Project Management Institute
Annual Seminars & Symposiums, October 3 – 10, 2002, San Antonio, TX.

(19) Jiang, James J. Gary Klein, and Joseph Balloun (1996). “Ranking of System
Implementation Success Factors”, Project Management Journal, December 1996,
pp 49 – 53.

(20) Baker, Bud. (1997). Great Expectations: Turning Failure into Success – and
Visa Versa. PM Network, May 1997, pp. 25 – 28.

(21) PMTalk Newsletter, (2001), http://www.4pm.com/pmtalk03-19-


02.pdf viewed 12/15/2003

(22) Macomber, Hal (2003), “Reforming Project


Management”, http://weblog.halmacomber.com//
Viewed 12/15/2003

(23) Hodgson, Ian. (2002). “Keeping Your


Head Above Water”, http://www/conspectus.com/2002/november/article19.asp v
iewed 12/15/2003

(24) “The Eight Keys to Project Management Failure”,


(2003), http://workstar.net/library/pm1.htm
viewed 12/15/2003

(25) “Project Failure Warning


Signs”. http://www.bluejeansplace.com/ProjectManagementFailureWarningSigns.
html
viewed 12/15/2003

You might also like