KUIS MENGAMBAR REKAYASA

TS1B
NAMA : JEPRI

NIM : 151710060

HARGA SATUAN
NO URAIAN PEKERJAAN VOLUME SATUAN (Rp)

1 2 3 4 5

1 PONDASI 1PC:3PS 15.80 M3 603,425.75

LUAS KELILING BANGUNAN : 40.5


LUAS PONDASI : 0.6 0.65
0.39
JADI LUAS PONDASI 1PC:3PS : 15.795

HARGA UPAH DAN BAHAN

DAFTAR ANALISA
NO URAIAN HARGA JUMLAH HARGA
SATUAN BAHAN
(RP) (RP)
1 2 3 4
3.4 1 M Pasang Pondasi Batu Kali, 1 Pc : 3 Ps
3

a. Bahan
1.100 M3 Batu Belah 15/20 c 213,500.00 234,850.00
202.000 Kg Semen Portland 1,000.00 202,000.00
0.485 M3 Pasir Pasang 91,500.00 44,377.50
481,227.50

b. Tenaga
1.500 Oh Pekerja 42,700.00
0.600 Oh Tukang Batu 79,300.00
0.060 Oh Kepala Tukang 88,450.00
0.075 Oh Mandor 70,150.00

Jumlah 481,227.50

UPAH DAN BAHAN


TS1B
No. Uraian Satuan Harga
(Rp)
1 PONDASI BATU KALI M3 213,500.00
2 Pasir Pasang M3 1,000.00
3 Semen Portland M3 91,500.00
A

JUMLAH HARGA
(Rp)

9,531,109.72

DAFTAR ANALISA
JUMLAH JUMLAH
TENAGA BAHAN+TENGA
(RP) (RP)
5 6

234,850.00
202,000.00
44,377.50
481,227.50

64,050.00 64,050.00
47,580.00 47,580.00
5,307.00 5,307.00
5,261.25 5,261.25
122,198.25 122,198.25

122,198.25 603,425.75