Professional Documents
Culture Documents
Questionnaire for
Government of Eastern Provincial Council
Ex-Post Evaluation on
Emergency Natural Disaster Rehabilitation Project (SL-P103)
Contact Person on the Sri Lanka Side: *Please correct if the information is wrong.
Please prepare the answers to each question in writing together with supporting data/documents
accordingly. If information or data requested in this Questionnaire is not readily available, please
provide alternative indicators and data, which meet the objectives of this questionnaire survey under
the five evaluation criteria.
1
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
(2) Efficiency Measure how efficiently the various inputs are converted into outputs of the project in
the implementation process (productivity of implementation process). This criterion
will examine the appropriateness of inputs such as project cost and its volume,
implementation schedule, timing, institutional/organizational function. Also the
Internal Rate of Return (IRR) of the project is re-calculated.
(3) Effectiveness Examine the extent to which the project objectives have been achieved in relation to the
project outputs. This criterion will include quantitative analysis based on operation and
effect indicators as well as qualitative analysis.
(4) Impact Identify the extent to which the overall goal of the project has been achieved, and
verify intended and unintended, direct and indirect, positive and negative changes in
technical, socio-economic, institutional and environmental aspects as a result of the
project.
(5) Sustainability Questions whether project benefits are likely to continue after completion of the
project. This criterion will include a study of institutional, technical, and financial
aspects in operation & maintenance agency /organization, condition and status of
equipment/facilities procured/constructed by the project, technology transfer, and
ownership of beneficiaries. It will also include an analysis of issues and constraints
that may impede sustainability of the project.
Project Summary:
(1) Background
In Sri Lanka, the heavy rain from December 2010 through February 2011 caused major damage,
destroying infrastructure including roads and irrigation facilities in Central, North Central and Eastern
Provinces. There were more than 1.2 million victims and 430,000 damaged buildings, ranking next to
the tsunami damage of the Sumatra Earthquake in December 2004. The flash floods destroyed
approximately 18,237km of roads and 1,752 agricultural and irrigation facilities, which blocked
transportation access and impeded daily life in rural areas. The rice farming areas mainly in Eastern
Province were severely damaged, and there was a concern of crop failure for the following year unless
the irrigation facilities were rehabilitated in time to prevent water shortage in the dry season.
(2) Project Objectives
To promptly recover the economic and social activities of the damaged areas by rehabilitating
damaged roads and irrigation facilities in Central, North Central and Eastern Provinces of Sri Lanka,
thereby contributing to the recovery of safety and livelihood of the residents, rehabilitation of the
economy and society from the disaster and to prevent further damages/losses.
(3) Project Scope
The project includes the following components:
Project site/target districts: Central, North Central and Eastern Provinces
Project Components
Rehabilitation of national roads, provincial roads and community roads (approximately
1,018km)
Rehabilitation of irrigation facilities (approximately 244 locations)
2
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
3
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Block A: Relevance
(Note) The Block A examines whether or not the project objectives and goals were/are in line with the
priority needs of India at the time of ex-post evaluation.
Table A-1: Relevance to Development Policies, Plans and Needs at Ex-Post Evaluation
Relevance at the time of ex-post evaluation (2017)
a) At the provincial policy level
(Please explain the priority of provincial/rural road development and irrigation scheme development
in the latest development plan of EasternProvince)
For the economic and social development of a region the provincial/rural road network should be in
good condition to link national highways to internal areas.
(2) In relation to the above question, please provide a set of copy of:
(i) Latest development policy/plan of Provincial Road Development Department
Vision:
Quality & User Satisfactory Provincial Road Network towards regional development
Mission:
Providing Safe, Comfortable and time saving transportation for the socio economic
development through improvement and proper maintenance of road network in a sustainable
manner
4
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Block B: Efficiency
(Note) In the Block B, the appropriateness of inputs such as project cost, the schedule and mechanism
of the project are examined.
Were the subprojects of this project selected according to the above criteria? If there are any
exceptional cases, please brief them.
5
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
b) Do you think the above Institutional Arrangements contributed to smooth and timely
implementation of the project? Please elaborate your opinion.
Yes.
The problem and issues, practical problems during the implementation were discussed & sorted out
at the above meetings.
6
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
(Note) Block C examines the extent to which the project objectives have been achieved.
(3) Reasons for Difference between the status before and after the project
a) If there was a difference between the baseline value and actual values after project implementation
for the supplement indicators, please state possible reasons including external factors as well as
remedial actions/plans to achieve the target values.
7
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Table C-2: Possible Reasons for Difference between Baseline Value and Actual Values
Items Reasons and Remedial Actions
1. AADT Reasons:
Due to convenient travelling, alternative road users.
Those who used alternative roads started to use the actual roads after rehabilitation
due to its best present condition.
Remedial Actions/Plans:
Remedial Actions/Plans:
Remedial Actions/Plans:
4. Volume of Reasons:
agricultural products
Remedial Actions/Plans:
8
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Block D: Impact
(Note) Block D examines to which extent the overall goals of the project have been or are expected to
be achieved, and identifies direct and/or indirect, positive and/or negative impacts, including socio-
economic issues that are likely to be related to the project.
The renovated roads improved the travelling condition & Minimize the risk of accident
Ex.
Pavatkodichenai, Valayiravu link road etc.; Farmers, villagers, sellers, etc ; Easy Transportation
9
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
b) If you answered Yes in the previous question, please state your observations on how the project
contributes to prevent further damages and losses in the affected areas. It is very informative if you
can quote some actual cases (location, beneficiary, the type of benefit, etc.) on the contribution of this
project.
a) Observation
N/A
b) Mitigation measures
b) Mitigation measures
- Safety Construction
- Minimize/ not allowed cutting of trees, Prohibit excavation of soil/gravel from nearby land.
(2) Please state the environmental monitoring system and activities during and after the project
implementation.
During project implementation
a) Environmental Monitoring system
Monitoring by Executive Engineer & Chief Engineer & Technical Officers
b) Monitoring activities
b) Monitoring activities
10
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
b) Please brief the land acquisition and resettlement process implemented by the project, if any.
N/A
c) Please brief how to handle and settle the claims from the affected peopleassociated with civils
works during the project implementation, if any.
N/A
11
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Block E: Sustainability
(Note) Block E examines the sustainability of the project from institutional, financial, and technical
perspectives.
Total
Irrigation Schemes:
12
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
During the defect liability period (1 year) the maintenance come under PRDD and this was attended
through the respective contractors. Thereafter, the Pradesiya sabha should maintain their
roads.
Table E-5: Maintenance Program for Irrigation Scheme by Provincial Irrigation Department
Section/Divisi
Type Contents Frequency
on in charge
Routine
Maintenance
Periodic
Maintenance
Other
( )
13
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
b) If you outsource operation and maintenance (O&M) to private contractors/service providers and/or
CBO, how do you evaluate their technical capacities in O&M of provincial and rural roads?
ICTAD grade. Their records for past experiences
Frequency of
Name of Training Target Staff No. of
Purpose Training Program
Program (Qualification, etc.) trainees
per year
Quality control road To enhance the Engineers, TOs 3-5 1 or 2
construction knowledge.
Procurement To enhance the Engineers 2-3 1 or 2
knowledge.
Table E-7: Training Program for Provincial Irrigation Department (Irrigation Svhmes)
Frequency of
Name of Training Target Staff No. of
Purpose Training Program
Program (Qualification, etc.) trainees
per year
14
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
a) Did Provincial Road Development Department establish the O&M manual and guideline for
provincial and rural roads?
b) Are the O&M manual and guideline for provincial and rural roads utilized by the staff of Provincial
Road Development Department and PradeshiyaSabhas in their work place?
Yes. It is followed by PRDD wherever necessary and as much as possible.
c) Did Provincial Irrigation Department establish the O&M manual and guideline for irrigation
schemes?
d) Are the O&M manual and guideline for irrigation schemesutilized by the staff of Provincial
Irrigation Departmentin their work place?
(6) Handover the necessary project information from the Ministry of National Policies and
Economic Affairs (MNPEA)to Provincial Road Development Department and Provincial
Irrigation Department
Did Provincial Road Development Department and Provincial Irrigation Department receive the
necessary project information from MNPEA or PMU such as specification of rehabilitated roads and
irrigation facilities, necessary maintenance procedures, etc. in order to ensure a proper maintenance of
the project facilities?
General information of project received from PMU
b) If there are any critical problems in each facility under the management of provincial government,
please describe it details.
Table E-8: Problems occurred to the Project Facilities
Section/item Problems Remedial action plan
N/A
15
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
c) Ifthere are any specific issues, such as types of breakdown and problems that occur frequently,
please describe them in the box below.
N/A
16
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Table E-11: Income and Expenditure of PradeshiyaSabhasin Eastern Province(a typical case)
(Unit: )
Item FY2014 FY2015 FY2016
Plan Actual Plan Actual Plan Actual
Revenue
1) Total
2) From Province
3) From Central
Government
4) Others (specify)
Expenditure
1) Total
2) O&M of rural roads
3) Others ( )
If possible, please provide actual information of Table E-11 for the respectivePradeshiyaSabhaswhich
is responsible for O&M of the rural roads rehabilitated by the project inEasternProvince.
Lack of fund for the maintenance for provincial/rural roads is a common problem.
To solve this problem to some extent, the maintenance period of the work of the contract by
contractors may be increased up to 5 years .
17
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
18
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
(1) Recommendations
Please kindly provide recommendations for JICA and/or National Planning Department, Ministry of
National Policies and Economic Affairs (MNPEA) in order to ensure the sustainability of the project.
1.Sufficient fund allocation and release of imprest for proper maintenance of roads
2.Adopt arrangements/system in the original contract to maintain the road at least to 3 years by
contractors.
Allocate money in the project component to adopt arrangements/system in the original contract to
maintain the road at least to 3 years by contractors
19
Questionnaire for JICA’s Ex-Post Evaluation on
Government of Eastern Provincial Council Emergency Natural Disaster Rehabilitation Project
(SL-P103)
Name:
Organization and Title:
TEL/FAX:
E-mail:
Data of Answer:
This questionnaire is prepared with Microsoft Word. If you need the electric file, please do not hesitate
to contact us by e-mail.
20