You are on page 1of 7

PROTECTION AND CONTROL

PART 2: OVERCURRENT PROTECTION OF TRANSFORMERS


TRADITIONAL AND NEW FUSING PHILOSOPHIES
FOR SMALL AND LARGE TRANSFORMERS
By Carey J. Cook and James K. Niemira

T
his is the second of two articles
that concern new and traditional Table 1: Relationship Between Per-Unit Primary-Side Line Current and Per-Unit
fusing philosophies for protecting Transformer Winding Current for Various Types of Secondary Faults
transformers. Issue 6’s article (Part I) Transformer Connection Ratio of Per-Unit Primary-Side Line
served as an introduction to the applica- Current to Per-Unit Transformer Winding Current *
tion principles that must be considered
when selecting a transformer-primary Type of Fault Three-Phase Phase to Phase Phase-to-Ground
fuse, in particular, the voltage rating, the
short-circuit interrupting rating, and the
ampere rating and speed characteristic of 1.0 1.0 1.0
the fuse. It also covered how to select a
transformer-primary fuse to withstand
the various inrush currents it may experi- 1.0 0.87 Not applicable
ence in service, such as magnetizing
inrush, hot-load pickup inrush, and cold-
load pickup inrush. This article covers 1.0 1.15 0.58
how to select a transformer-primary fuse
to protect the transformer in accordance
with industry-accepted through-fault *Line current and winding current values are expressed in per unit of their respective values for
protection curves, the principles of coor- a “bolted” three-phase secondary fault.
dination as they relate to the proper
selection of a primary-side fuse and primary fuse for a three-phase power
power fuses, and how to protect load- transformer is that it must protect the
side conductors and cables. transformer against damage from
mechanical and thermal stresses resulting
PROTECT TRANSFORMER AGAINST from secondary-side faults that are not
DAMAGING OVERCURRENTS promptly interrupted. A properly selected
Fusing philosophies, as they relate primary fuse will operate to clear such a
specifically to secondary-fault protec- fault before the magnitude and duration
tion, can vary significantly depending on of the overcurrent exceed the through-
the type of transformer under considera- fault current duration limits recommend-
tion. For small three-phase power trans- ed by the transformer manufacturer or
formers used on industrial, commercial, published in the standards. Curves repre-
and institutional systems, and small-to- senting these limits can be found in
medium size three-phase power trans- ANSI/IEEE Standard C37.91-1985,
formers used in utility substations, it is “Guide for Protective Relay Applications
generally appropriate to use tight fusing to Power Transformers,” and ANSI/IEEE Figure 1: Infrequent-fault incident through-
(i.e., a low fusing ratio) to provide maxi- C57.109-1993, “Guide for Transformer fault protection curves for: grounded-
mum protection to the transformer Through-Fault Current Duration.” wye/grounded-wye transformers (A);
against secondary-side faults. On the The degree of transformer protection delta/delta transformers (B); and
other hand, for small-kVA single-phase provided by the primary fuse should be delta/grounded-wye transformers (C).
overhead distribution transformers, larg- checked for the level of fault current and
er fuse ratings are generally recommend- type of fault (i.e., three-phase, phase-to- current than will the windings and, as a
ed, particularly if the arrester is mounted phase, or phase-to-ground) producing the consequence, the primary fuses must be
on the transformer tank to enhance over- most demanding conditions possible for carefully selected to operate fast enough
voltage protection. each particular application, viz., those for to avoid damage to the transformer wind-
which the ratio of the primary-side line ings. Table 1 lists the ratio of per-unit pri-
Three-Phase Power Transformers and currents to the transformer winding cur- mary-side line currents to per-unit trans-
Utility Substation Transformers rents is the lowest. For these situations, former winding currents for three com-
The most important application prin- one or more of the primary fuses will
ciple to be considered when selecting a “see” a proportionately lower level of

Electricity Today Issue 7, 2003


PROTECTION AND CONTROL

on a delta/grounded-wye connected fault protection curve at the current level


mon transformer connections under a transformer. corresponding to the maximum three-
variety of secondary-fault conditions. Tip: For a delta/wye connected phase secondary-fault current as deter-
From Table 1, it is clear that a phase- transformer with its neutral grounded mined solely by the transformer imped-
to-phase secondary fault on a delta/delta through a significant impedance, the ratio ance (i.e., an infinite source is assumed).
connected transformer and a phase-to- of per-unit line current to per-unit wind- Another aspect of transformer pro-
ground secondary fault on a ing current for a phase-to-ground sec- tection involves low-current overloads.
delta/grounded-wye connected trans- ondary fault is the same as that discussed Low-voltage protective devices such as
former produce the most demanding con- above for a delta/grounded-wye connect- circuit breakers and current-limiting
ditions possible for those particular trans- ed transformer. However, since the fuses are designed to provide overload
former connections, since the per-unit impedance in the neutral limits the mag- protection for the transformer by operat-
primary-side line cur-
rents are less than the Table 2: Secondary Fault Currents Reflected to Primary Lines
per-unit transformer
Transformer Impedance Arcing Maximum Primary-Side Line Current for Various Types of
winding currents.
Connection Phase-to- Secondary Faults, Percent of Transformer Full-Load Current
Accordingly, to ensure
Ground Fault*
proper transformer pro-
Three-Phase Phase-to-Phase Phase-to-Ground
tection for these two
situations, it is neces-
4% 1000% 2500% 2180% 2500%
sary to “shift” the
5.5% ✖ 1820 1580 1820
appropriate through -
5.75% 700 1740 1510 1740
fault protection curve to
6.5% ✖ 1540 1340 1540
the left (i.e., in terms of
8% 500 1250 1090 1250
current) by the ratio of
the per-unit primary-
4% N/A 2500 2180 N/A
side line current to the
5.5% 1820 1580
per-unit transformer
5.75% 1740 1510
winding current listed
6.5% 1540 1340
in Table 1. The shifted
8% 1250 1090
through-fault protection
curve will then be in
4% 580 2500 2500 1450
terms of the primary-
5.5% ✖ 1820 1820 1050
side line current and, as
5.75% 400 1740 1740 1010
such, will be directly
6.5% ✖ 1540 1540 890
comparable with the
8% 290 1250 1250 730
total-clearing curve of
the primary fuse. For
N/A: Not applicable. *Commonly accepted arcing-fault-current values for secondary-switchboard and other nearby
the grounded-wye /
faults.✖ For transformers with medium-voltage secondaries (2.4 kV or 4.16 kV); the entries in the “Phase-to-Ground”
grounded-wye connect-
ed transformer, the per- column apply.
unit primary-side line
currents and the per-unit transformer nitude of the phase-to-ground fault cur-
winding currents are the same, hence the rent to levels well below the level of cur-
base (unshifted) through-fault protection rent which will damage the transformer,
curve applies. the phase-to-ground through-fault protec-
Figure 1 illustrates the infrequent- tion curve is of no concern and may be
fault incidence through-fault protection ignored. Accordingly, the base (unshift-
curve applicable to a grounded-wye/ ed) through-fault protection curve,
grounded-wye connected transformer applicable to multiphase secondary
(Curve A), as well as through-fault pro- faults, should be used for this trans-
tection curves shifted to reflect the two former.
situations discussed above. Curve B rep- Although the through-fault protec-
resents Curve A shifted to reflect the tion curves are only a guide, they are rec-
reduced level of current (0.87 per unit) ommended as a criterion against which to
flowing in two primary lines during a measure the degree of transformer pro-
phase-to-phase secondary fault on a delta tection provided by the primary fuse. To
/delta connected transformer. Similarly, meet this criterion for high-magnitude Figure 2: The effect of fusing ratios on the
Curve C represents Curve A adjusted to secondary-side faults, the total-clearing degree of protection provided a
reflect the reduced level of current (0.58 curve of the primary fuse should pass delta/grounded-wye connected trans-
per unit) flowing in two primary lines below the point (historically called the former against a phase-to-ground sec-
during a phase-to-ground secondary fault ANSI Point) on the appropriate through- ondary fault.

Electricity Today Issue 7, 2003


ing at currents only slightly larger than The primary fuse having the lowest The results of published studies [1] arcin
their minimum-pickup settings or fusing ratio of the three fuses that pass [2] [3] indicate that under arcing condi- prima
ampere ratings. In contrast, medium- beneath the ANSI Point will provide the tions, secondary-switchboard and other 230 p
voltage fuses are not intended to provide maximum protection for the transformer nearby faults on 480/277Y-volt circuits the tr
overload protection. Accordingly, the against secondary faults located between may have magnitudes as low as 38 per fusin
total-clearing curve of the primary fuse the transformer and the secondary-side cent to 40 per cent of the maximum thoug
will cross the through-fault protection overcurrent protective device — as well available phase-to-ground fault current rent i
curve at some low level of current. as maximum backup protection for the at the point of the fault. This corresponds load
Because the primary fuse does not pro- transformer in the event the secondary- to 290 per cent of the full-load current of may
vide overload protection for the trans- side overcurrent protective device fails to the transformer in Figure 2, as seen by form
former, this should not be a concern; operate, or operates too slowly due to an the primary fuse. Hence, a primary fuse unde
however, efforts should be made to keep incorrect (higher) rating or setting. with a fusing ratio of 1.0 will provide with
the current value at which the two curves From Figure 2, it may be seen that a protection for the transformer against an
intersect as low as possible to maximize primary fuse with a fusing ratio of 1.0 arcing phase-to-ground fault, since the
protection for the transformer against will provide protection for a primary fuse will operate at as low as
secondary-side faults. delta/grounded-wye connected trans- 230 per cent of the full-load current of
The through-fault protection curve former against phase-to-ground sec- the transformer. A primary fuse with a
for a delta/grounded-wye connected ondary faults producing currents as low fusing ratio only slightly higher than 1.0,
transformer can be used to illustrate as 230 per cent of the full-load current of though, may have a total-clearing cur-
these principles for primary-side fuses. the transformer, as reflected on the pri- rent in excess of 290 per cent of the full-
See Figure 2. The total-clearing curves mary side. When the fusing ratio is 2.5, load current of the transformer, and thus
for primary fuses with a fusing ratio of however, protection for the transformer may not provide protection for the trans-
1.0, 1.5, or 2.0 all pass below the ANSI is provided only when secondary faults former against a phase-to-ground fault
Point of the delta/grounded-wye con- produce primary-side line currents under arcing conditions. A primary fuse
nected transformer’s through-fault pro- exceeding 670 per cent of the trans- with a fusing ratio only slightly higher
tection curve. The total-clearing curve former full-load current.
for primary fuses with a fusing ratio of
2.5 or 3.0 pass completely above and to
the right of the through-fault protection
curve and, thus, would not provide any
protection for the transformer for a
phase-to-ground secondary fault. Since
the object of primary fusing is to provide
protection for the transformer against all
types of secondary faults, primary fuses
having total-clearing curves that pass
above the ANSI Point would be consid-
ered unacceptable.
PROTECTION AND CONTROL

Table 3: Relationship Between Per-Unit Primary-Side Line Current and Per-Unit


than 1.0 will, however, protect the trans-
Secondary-Side Line Current for Various Types of Secondary Faults
former against permanent or metallic
phase-to-ground secondary faults as well Transformer Connection Ratio of Per-Unit Primary-Side Line
as other types of secondary faults, includ- Current to Per-Unit Secondary-Side Line Current *
ing arcing phase-to-ground secondary
faults that escalate to multiphase sec- Type of Fault Three-Phase Phase to Phase Phase-to-Ground
ondary faults.
Tip: You can determine if the prima-
ry fuse will protect against an arcing sec- 1.0 1.0 1.0
ondary-side fault by referring to Table 2
which lists primary-side line current val-
ues for various types of secondary-side 1.0 1.0 Not applicable
faults and for various transformer con-
nections and impedances, expressed in
percent of the transformer full-load cur- 1.0 1.15 0.58
rent. The desired protection is obtained if
the current value at which the total-clear-
ing curve of the primary fuse intersects *Primary-side and secondary-side line current values are expressed in per unit of their respec-
the transformer through-fault protection tive values for a “bolted” three-phase secondary fault.
curve is less than the values shown in
Table 2. in philosophy is due in large part to the tions because these small links must pass
realization that most overhead distribu- the surge current during an arrester oper-
Small-kVA Overhead tion transformer failures occur due to ation. Therefore, to provide better over-
Distribution Transformers lightning-induced surges and not sec- voltage protection without increasing
In the past, the fusing philosophy ondary-side faults. nuisance fuse operations, it is necessary
applied to small-kVA single-phase over- One way to provide better overvolt- to increase the fuse link rating to with-
head distribution transformers was simi- age protection is to relocate the arrester stand these surges. The only apparent
lar to the fusing philosophy applied to from the cross-arm and mount it directly downside to the use of larger fuse ratings
larger transformers, that is, the smallest to the transformer tank. This location is a reduced level of overload, secondary-
practical fuse link rating was used, sub- eliminates 3 to 4 feet of lead connecting fault, and internal-fault protection pro-
ject only to loading considerations. the arrester to the transformer tank, vided for the transformer. However, fur-
Recently, however, this philosophy has which reduces the L x di/dt voltage surge ther analysis reveals that very little pro-
changed to one of protecting the system seen by the transformer when the arrester tection is given up by standardizing on
from a failed transformer and protecting operates. larger fuse ratings. Consider the follow-
against catastrophic failure of the trans- Moving the arrester to the trans- ing:
former rather than protecting the trans- former tank, however, makes small-rated - Overload protection for the trans-
former itself from overcurrents. This shift fuse links susceptible to nuisance opera- former is difficult to justify as the

Phone: 905-355-3046 • Fax: 905-355-5480 • email: gary@steacydismantling.com • www.steacydismantling.com

28 Electricity Today Issue 7, 2003


economics of overhead distribution systems necessitate For a phase-to-phase
the loading of transformers significantly beyond their secondary fault not involving
nameplate ratings. ground on a delta/grounded-
- Where covered secondary conductor is used, secondary wye connected transformer,
faults are rare. With covered conductor the possibility of the per-unit primary-side line
faults due to mid-span tree, animal, or human contact is current in one phase is the
significantly reduced. same as that resulting from a
- The rare faults that do occur on the secondary conductor three-phase secondary fault,
will generally not sustain the arc. These faults tend to be while the secondary-side line
self clearing due to the low 120/208-volt driving voltage. current is only 0.87 per unit
In addition, when aluminum secondary conductor is used, of the three-phase secondary
faults tend to burn back the conductor which further helps fault-current value (hence,
to extinguish the arc. the ratio, as listed in Table 3,
- A bolted fault at the service drop of the nearest house will is 1.0 0.87, or 1.15). To com-
be low enough in magnitude, due to the impedance of the pensate for the line-current Figure 3: Application of 15%
conductor, that a primary fuse — even one with a low fus- differential inherent to the current margin between time-
ing ratio — would not likely detect the fault. delta/grounded-wye connect- current curves of primary fuse
Perhaps a greater concern than secondary-fault protection ed transformer, it is generally and low-voltage current-limiting
is the need to protect overhead distribution transformers from recommended that a 15 per fuse.
catastrophic failure due to internal faults that begin as low-cur- cent margin in terms of cur-
rent faults, and then quickly escalate to the full available fault rent (or an equivalent margin in terms of time) be maintained
current. One recent paper[4] studied internal transformer faults between the total-clearing curve of the feeder protective
and concluded that this type of fault signature is indeed com- device and the minimum-melting curve of the primary fuse.
mon. Interestingly, the authors also concluded that small rated This is illustrated in Figure 3 for a low-voltage feeder circuit
fuses in general, and even surge-tolerant fuses with dual-ele- breaker.
ment melting characteristics in particular, are no better at Tip: The only exception to this recommendation is Class invo
detecting internal winding faults than are larger rated fuses E-2 high-voltage industrial control equipment, where the 15 ed
having the same lightning surge-withstand characteristics. In per cent current margin is not required since the point of influ- prot
addition, fuse limiters or backup current-limiting fuses were ence of this margin (where the curves for this device and the the
found to be very effective at minimizing the energy into the primary-side device are the closest to each other) occurs at tect
faulted transformer, and are recommended when surge tolerant approximately 20 seconds, before which time a medium-volt- trem
fuses are used. Lastly, pressure relief devices are clearly rec- age phase-to-phase ungrounded fault would likely have prop- low
ommended to limit tank pressure during an evolving fault agated to ground. This current margin is therefore not required dura
should a high-current fault develop. to ensure proper coordination for faults involving ground in occu
this type of equipment. dista
COORDINATE WITH OTHER PROTECTIVE DEVICES Occasionally, it may be deemed necessary to coordinate form
In addition to protecting the transformer against faults, the transformer primary fuse with a main secondary-side pro- clea
internal or otherwise, it is also important that the primary fuse tective device. In this case, the primary fuse will operate to prot
coordinate with overcurrent protective devices on both the pri- protect the transformer against a fault located between the
mary side and the secondary side of the tran sformer. The fol- transformer and the main secondary protective device and will not
lowing sections describe how proper coordination is achieved further serve as a backup to the main device - operating in the tain
both between the primary fuse and secondary-side protective event the main secondary protective device either fails to oper- rent
equipment, and between the primary fuse and source-side pro- ate due to a malfunction, or operates too slowly due to incor- lent
tective devices. rect (higher) ratings or settings. coor
The method for establishing coordination between the age
Coordination Between the Primary Fuse and 480/277Y- transformer primary fuse and the main secondary protective rent
Volt Secondary-Side Overcurrent Protective Devices device is essentially the same as that described previously for circu
Coordination between the transformer primary fuse and a feeder circuit breaker or fuse, except for the handling of the rent
the feeder protective device is typically checked for the level current margin (or equivalent time margin) for the phase-to- curr
of fault current and for the type of fault (i.e., three-phase, phase secondary fault not involving ground on a delta-wye faul
phase-to-phase, or phase-to-ground) producing the most connected transformer. For this particular fault, the point of whe
demanding conditions possible for the transformer in each influence of the 15 per cent current margin (or equivalent time brea
application. From the standpoint of coordination, the most margin) typically occurs at a relatively low current (and long
demanding conditions possible are those where the per-unit duration) for low-voltage circuit breakers and low-voltage cur- have
line current on the primary side of the transformer is greater rent-limiting fuses. The probability of occurrence of a low- time
than the per-unit line current on the secondary side of the trans- magnitude long-duration phase-to-phase secondary fault not the
former. For this situation, the primary-side device carries more with
current, relatively, than does the secondary-side overcurrent com
protective device. Accordingly, an allowance must be made seco
before checking for proper coordination between the two is re
devices. Table 3 lists the ratio of per-unit primary-side line cur- seco
rent to per-unit secondary-side line current for the same trans- tion
former connections and types of secondary faults discussed prim
earlier. tran

seco
29 does
over
PROTECTION AND CONTROL
involving ground locat- Coordination Between Primary-Side and Source-Side
ed between the feeder Overcurrent Protective Devices
protective devices and After the transformer primary fuse has been selected to
the main secondary pro- provide the maximum degree of protection for the transformer
at tective device is ex- and to coordinate with secondary-side protective devices, it is
lt- tremely remote. Such necessary to consider coordination with source-side protective
p- low-magnitude long- devices. To achieve coordination with a source-side protective
ed duration faults typically device, the total-clearing time of the primary fuse must be less
in occur on a feeder some than the minimum-melting time of a source-side fuse, or the
distance from the trans- minimum-operating time of a source-side relay, for all currents
te former, and thus are up to the maximum available fault current at the location of the
o- cleared by the feeder primary fuse. In establishing such coordination, no adjust-
to protective device. ments must be made to the total-clearing curve of the primary
he Accordingly, it is Figure 4: Coordination between pri- fuse.
ill not necessary to main- mary fuse and low-voltage main-sec- Certain adjustments, however, must be made to the mini-
he tain the 15 per cent cur- ondary circuit breaker can often be mum operating time-current curves of source-side protective
r- rent margin (or equiva- obtained by lowering the short-time devices. Specifically, the minimum response curves for
r- lent time margin) when pickup current and/or the short-time source-side relays must be adjusted for overtravel and toler-
coordinating low-volt- delay setting. ance, and minimum-melting curves of source-side power fuses
he age main secondary cur- must be adjusted to reflect the assumed prefault load, elevated
ve rent-limiting fuses with the primary fuse. For medium-voltage ambient temperature and, for certain types of fuses, damage-
or circuit breakers, the point of influence of the 15 per cent cur- ability.
he rent margin (or equivalent time margin) occurs at a very high Earlier it was recommended that the smallest practicable
o- current — on the order of the maximum three-phase secondary ampere rating or setting for the primary fuse be selected in
ye fault-current level. Accordingly, this margin must be retained order to maximize transformer protection. Such a selection
of when coordinating medium-voltage main secondary circuit will also greatly facilitate coordination with source-side pro-
me breakers with the primary fuse. tective devices since the lower total-clearing time-current
ng Since main secondary circuit breakers or fuses typically curve associated with the primary fuse will more easily fit
ur- have high ampere ratings or settings, difficulties are some- below the time-current curve of the source-side protective
w- times experienced in simultaneously obtaining protection for device.
ot the transformer against secondary-side faults in accordance If difficulties in coordination with source-side protective
with the through-fault protection curves discussed earlier, and devices are encountered, the ratings of the primary fuse should
complete coordination between the primary fuse and the main be restudied to verify that the smallest practicable ampere rat-
secondary protective device. If this situation is encountered, it ing has indeed been selected. This may involve a reconsidera-
is recommended that the ampere rating or settings of the main tion of the ratings and settings of the secondary-side protective
secondary protective device be investigated to see if a reduc- devices with which coordination was previously obtained.
tion is possible, rather than accepting a larger than necessary
primary fuse ampere rating, which would result in reduced PROTECT LOAD-SIDE CONDUCTORS AND CABLES
transformer protection. The final principle to be considered when selecting a
This point is illustrated in Figure 4 for a low-voltage main transformer primary fuse is that it must protect the conductors
secondary circuit breaker, wherein a transformer-primary fuse or cables between the primary fuse and the transformer against
does not coordinate with the main secondary circuit breaker damage due to excessive overcurrents. In general, the size of
over the full range of applicable currents. Coordination the conductor or cable is
between the two devices has not been obtained with the short- determined by considering
time pickup current of the main secondary circuit breaker set its ampacity, as well as its
at 12,000 amperes (4X), and with the short-time delay setting behavior under short-cir-
on the “Maximum.” Clearly, by reducing the short-time pick- cuit conditions. Selection
up setting from 4X to 3X or even 2.5X, and by reducing the of the conductor size from
short-time delay setting from “Maximum” to “Minimum,” the standpoint of its contin-
coordination between the main secondary circuit breaker and uous current-carrying
the primary fuse will be obtained. (The time-current curve for capability is easily done by
the main secondary circuit breaker adjusted to reflect lower reference to ampacity
short-time pickup and short-time delay settings is illustrated tables found in sources
by solid lines.) Lack of complete coordination of the type illus- such as the National
trated in Figure 4 can frequently be corrected by making such Electrical Code. Similarly,
adjustments. conductor or cable sizes
Tip: If it is not practicable to reduce the ampere rating or capable of withstanding
settings of the main secondary-side protective device, as dis- available short-circuit cur-
cussed in the example above, incomplete coordination rents can easily be selected
between the primary-side protective device and the main sec- Figure 5: Damage curve for rub-
ber-insulated aluminum conduc- from industry-accepted
ondary-side device should be accepted in order to obtain bet- curves, such as those con-
ter transformer protection. Even if these circumstances are tors with initial temperature of
75°C and final temperature of tained in the IEEE Buff
encountered, coordination will typically be given up over only Book, or those distributed
one or two very small ranges of current. 200C.
by conductor or cable man-
ufacturers. As a general rule, power fuses, which operate in as the primary fuse in any case. The pre-
little as one cycle for high-magnitude faults, will protect con- dominant cause of failure of small
ductors or cables one or more sizes smaller than will relay- overhead distribution transformers is
actuated circuit breakers. This is illustrated in Figure 5 for rub- insulation failure due to lightning-
ber-insulated aluminum conductors with initial temperature of induced overvoltages. These transform-
75°C and final temperature of 200°C. As noted in Figure 5, for ers are inexpensive and readily avail-
a 10,000-ampere fault, the circuit breaker will protect cables able.
sized 1/0 or larger. By comparison, a power fuse will protect Thus, a larger fuse rating, used in
cables two sizes smaller, or #2 AWG. combination with a tank-mounted
surge arrester, can provide better trans-
SUMMARY former protection than the smaller fuse
This series of articles should be useful as a reference link ratings traditionally recommended.
source detailing the often contradictory factors that must be
considered when selecting a transformer-primary fuse. The REFERENCES
first article showed that the industry “standard” points used to [1] J. R. Dunki-Jacobs, “The Effects 1977, Dallas, Texas, C
represent inrush currents are sufficiently conservative such of Arcing Ground Faults on Low- 77CH1229-4-lA.
that a fuse having a smaller ampere rating can often be used in Voltage System Design,” article [3] L. E. Fisher, “Resistanc
cases where the initial fuse selection does not properly coor- reprinted from the May/June 1972 Voltage Alternating Curr
dinate with other protective devices, or where the degree of issue of IEEE Transactions on IEEE Transactions on In
transformer protection is not acceptable. Industry and General Application. General Applications, V
As detailed in the second article, secondary-fault protec- [2] J. R. Dunki-Jacobs, “State of the November/December 19
tion is critical on small three-phase power transformers used Art of Grounding and Ground 607-616.
on industrial, commercial, and institutional power systems, Fault Protection,” article reprinted [4] J. M. Lunsford and T.
and small-to-medium size three-phase power transformers from the 1977 Conference Record “Detection of and Prot
used in utility substations, because of the expense and long of the IEEE 24th Annual Internal Low-Current
lead times involved in repairing or replacing these transform- Petroleum and Chemical Industry Faults In Overhead D
ers. Small-kVA overhead distribution transformers, on the Conference, September 13-14, Transformers,” present
other hand, will not likely see secondary faults, and the rare 1977, Dallas, Texas, Catalog No.
faults that do occur will not likely be detected and cleared by 77CH1229-4-lA.
[3] L. E. Fisher, “Resistance of Low-
Voltage Alternating Current Arcs,”
IEEE Transactions on Industry and
General Applications, Vol. IGA-6,
November/December 1970, pages
607-616.
[4] J. M. Lunsford and T. J. Tobin,
“Detection of and Protection for
Internal Low-Current Winding
Faults In Overhead Distribution
Transformers,” presented at the
IEEE Power Engineering Society
1996 Summer Power Meeting, July
28 - August 1, 1996, Denver,
Colorado.
Carey Cook and James Niemira are
with S&C Electric Company, Chicago.ET

Electricity Today Issue 7, 2003

You might also like