means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. All kinds of soil.
C.P.W.D spec DSR code Clause 2.8&2.26.1
Total 438.32 CUM 280 122728.2
Earth work in excavation by mechanical
means (Hydraulic excavator) / manual means in foundation trenches or drains (exceeding 1.5 m in width or above 10 1.2 sqm on plan), including dressing of sides and ramming of bottoms, lift above 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. All kinds of soil Above 1.5m depth including ramp and lift pit Main building, lift, sump septic tank
Total 321.43 CUM 380 122144
Providing Anti Termite treatment using approved chemicals like Alderin E-300 or 1.3 equivalent in plinth area and 1m width of outside perimeter as specified, including cost of all materials and labour charges etc., complete as directed. (Plinth area only will be measured for payment)
Below PCC Slab 315.56
Total 315.56 SQM 200 63112
Providing and Back Filling with red
earth/murrum in layers not exceeding 15 cm, amply watered and consolidated to the correct level and thereafter flooding 1.4 the surface with water for atleast 24 hours, allowed to dry and then rammed, consolidated, after making good any settlement, including the cost of all materials, conveyance, lead, lift, labour, watering, ramming etc complete as directed. 142.00
Total 142.00 CUM 1250 177504
B CONCRETE
Unless otherwise specified the following
will apply for all items of plain and NOTE : reinforced cement concrete. Rates applied is inclusive of the following but excluding cost of reinforcements and inserts like bolts, plates, sleeves, pipes etc.
All form work, drip moulds, centering and
1 shuttering. Shuttering shall be steel or plywood as directed.
2 Adequate protection to edges and corners
from damage during construction.
Work either straight, curved, plain,
3 tapered, circular, sloping or grid pattern for beams and slabs.
4 Keeping the work watered for atleast 21
days after casting. 5 Roughing/hacking concrete surface where required after removing of centering or shuttering to receive plaster.
6 Building and placing in position any insert
supplied.
7 Machine mixing and consolidation using
vibrators of approved type.
8 Coarse sand shall be used for concrete
work.
9 Coarse aggregate shall be crusher broken
granite, basalt or trap of sizes specified.
The Contractors are particularly advised
10 to study relevant drawings carefully before quoting.
The Contractors shall submit drawings
11 showing the scheme of formwork (shuttering) for beams and slabs etc., and this shall be obligatory.
All concrete used for reinforced concrete
12 work (structural concrete) shall be of design mix
13 Minimum cement content for 43 grade
controlled concrete shall be as follows :-
b) M - 20 -300Kg
c) M - 25 300Kg
d) M - 30 -320Kg
e) M - 35 -340Kg
f) M - 40 -360Kg
2 PLAIN CEMENT CONCRETE .
Providing and laying in position cement
concrete of specified grade excluding the cost of centering and huttering - All work up to plinth level : 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) C.P.W.D spec DSR code Clause 4.1.10 Below Footing 29.22 Below Plinth Beam 10.64 PCC Slab 31.56
Total 71.42 CUM 5800 414233.22
3 REINFORCED CEMENT CONCRETE
Providing and laying cement concrete
conforming to specified grade (IS 456- 2000) with 20mm and down size graded aggregate of granite as per specifications, excluding to cost of reinforcement, but including providing rigid water tight centering and shuttering fixed in position, compacting with vibrators, curing etc.,
including labour for careful removal of
formwork supports, scaffolding, hacking the exposed surface to receive plaster wherever necessary etc., complete as per drawings and specifications for the following items of work :
Providing and laying in position specified
grade of reinforced cement concrete, 3.1 including the cost of centering, shuttering, finishing and excluding the cost of reinforcement - All work up to plinth level :
1:2:4 (1 cement : 2 coarse sand : 4
graded stone aggregate 20mm nominal size)
Centering and shuttering including
strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. Footing 101.11 CUM Column upto Plinth Beam 11.06 CUM Plinth Beam 20.83 CUM
Total 132.99 CUM 8920.00 1186309.41
Reinforced cement concrete work in rcc
3.2 wall, including the cost of centering, shuttering, finishing and excluding the cost of reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).including Centering and shuttering including strutting, propping etc. and removalof form for :Walls (any thickness) (average 0.15 thick & form work 13.32 m2 for 1 m3)
Lift 5.76
TOTAL 5.76 CUM 9295 53531.76
Providing and laying in position machine
batched and machine mixed design mix 3.3 M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but including the cost of centering, shuttering, finishing and excluding the cost of reinforcement,
including admixtures in recommended
proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/recoverable separately). All works above plinth level .
Extra for providing richer mixes at all floor
levels. Note:- Excess/less cement over the specified cement content used is payable recoverable separately
Providing M-30 grade concrete instead of
M-25 grade BMC/RMC. (Note:- Cement content considered in M-30 is @ 340kg/cum)
Centering and shuttering including
strutting, propping etc. and removal of form for :base slab(any thickness) (average 0.15 thick & form work 6.67 m2 for 1 m3)
C.P.W.D spec DSR code Clause ,5.33.1,
5.34.1,5.9.6 Sump Tank 13.29 Rain Water Harvesting Tank 7.38 Sewage Treatment Plant 41.63
Total 62.29 CUM 10370.00 645984.63
Providing and laying in position machine batched and machine mixed design mix M-25grade cement concrete for 3.4 reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but including the cost of centering, shuttering, finishing and excluding the cost of reinforcement, including admixtures in recommended proportions as per IS: 9103
to accelerate, retard setting of concrete,
improve workability without impairing strength and durability as per direction of Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/recoverable separately)All works above plinth level
Extra for providing richer mixes at all floor
levels. Note:- Excess/less cement over the specified cement content used is payable recoverable separately
Providing M-30 grade concrete instead of
M-25 grade BMC/RMC. (Note:- Cement content considered in M-30 is @ 340kg/cum)
Centering and shuttering including
strutting, propping etc. and removalof form for columns (9.99 m2 for 1m3 of concrete column 30 x60 column assumed) Add for using extra cement in the items of design mix over and above the specified cement content therein Add 150ml admixture for each bag of cement For COLUMNS C.P.W.D spec DSR code Clause ,5.33.2, 5.34.1,5.9.6,5.35 Ground Floor 18.41 First Floor 18.41 Second Floor 18.41 Third Floor 18.41 Fourth Floor 18.41 Fifth Floor 18.41 Sixth Floor 8.27 water tank column, beam, slab, wall 18.71
Total 137.43 CUM 10750.00 1477361.8
Reinforced cement concrete work in 3.5 beams, including the cost of centering, shuttering, finishing and excluding the cost of reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).including
Centering and shuttering including
strutting, propping etc. and removal of form for beam : (11.02 m2 for 1 m3 of concrete average size of beam 23 x 55) For BEAMS C.P.W.D spec DSR code Clause 5.3 & 5.9.5
Ground Floor 32.83
First Floor 32.83 Second Floor 32.83 Third Floor 32.80 Fourth Floor 32.80 Fifth Floor 34.46 Sixth Floor 12.50
Total 211.07 CUM 10650.00 2247854.55
Reinforced cement concrete work in
suspended floor slabs, roof slab , balcony 3.6 slabs,canopies, lofts, including the cost of centering, shuttering, finishing and excluding the cost of reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).(12mm thick slab)
Centering and shuttering including
strutting, propping etc. and removal of form for slab: (8.33 m2 of 1 m3 of concrete) For SLABS C.P.W.D spec DSR code Clause 5.3 & 5.9.3 Ground Floor Roof 40.00 First Floor Roof 39.82 Second Floor Roof 39.82 Third Floor Roof 39.82 Fourth Floor Roof 39.82 Fifth Floor Roof 39.18 Sixth Floor Roof 16.02 Lift Floor Roof 2.49
Total 256.96 CUM 10550.00 2710953.8475
Reinforced cement concrete work in lintel beam including the cost of centering, 3.7 shuttering, finishing and excluding the cost of reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).
Centering and shuttering including
strutting, propping etc. and removal of form for Lintels, beams (8.69 m2 for 1 m3 of concrete) For LINTEL BEAM C.P.W.D spec DSR code Clause 5.3 & 5.9.5
Ground Floor 2.06
First Floor 6.15 Second Floor 6.15 Third Floor 6.15 Fourth Floor 6.15 Fifth Floor 6.15 Sixth Floor 1.63 Terrace Floor 1.25 Lift Room 0.63
Total 36.33 CUM 10640.00 386501.67
Reinforced cement concrete work in
staircases and spiral stair cases including 3.8 the cost of centering, shuttering, finishing and excluding the cost of reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size). including
Centering and shuttering including
strutting, propping etc. and removal of form for stair :( 7.33 m2 for 1 m3 of concrete.assuming 15 cm thick waist slab) Stairs, (excluding landings) except spiral- staircases For STAIR C.P.W.D spec DSR code Clause 5.3 & 5.9.7
Ground Floor 3.56
First Floor 3.56 Second Floor 3.56 Third Floor 3.56 Fourth Floor 3.56 Fifth Floor 3.56 Sixth Floor 3.56
Total 24.94 CUM 10500.00 261912
REINFORCEMENT FOR RCC
Providing and fixing steel reinforcement.
Rate includes labour charges for cutting, bending, cranking, fabricating and tying in position steel bars conforming to IS 434 and IS 1786 for RCC works including cost of soft drawn annealed binding wire of not less than 20 gauge, PVC / NYLON coverblocks of required thickness, all leads, lifting and handling charges, cost of tools, tackle, scaffolding, wastages, rolling margins, chairs , hooked ends etc., complete as per specifications, drawings and directions of the consultant.
Steel reinforcement for R.C.C. work
4 including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Using Thermo-Mechanically Treated bars C.P.W.D spec DSR code Clause 5.22.6 4.a Footing 16.18 4.b Column Below Plinth Beam 1.66 4.c Plinth Beam 2.50 4.d Sump,Rain Water ,Sewage,Lift 6.81 4.e Ground Floor 10.31 4.f First Floor 11.08 4.g Second Floor 11.08 4.h Third Floor 11.08 4.i Fourth Floor 11.08 4.j Fifth Floor 11.23 4.k Sixth Floor 4.23 4.l Lift Floor Roof 3.37 4.m Water Tank 1.87