Professional Documents
Culture Documents
1
NATIONAL IRANIAN OIL COMPANY
2
NATIONAL IRANIAN OIL COMPANY
Table of Content
1. Purpose
2. Scope
3. Responsible Persons
4. Type of Permits
5. References
3
NATIONAL IRANIAN OIL COMPANY
1.0 Purpose
The purpose of this Procedure is to describe Gas Freeing and Inerting of vessels and pipe work prior
to bringing in and out of service and thereby to ensure a safe and controlled working environment.
To ensure the safety of personnel and that correct Procedures are applied for:
It is vital that inerting operations are carried out in conjunction with the information in other related
documents and procedures particularly; Work Permits, Process and Electrical Isolations, and Entry
into Vessels and Confined Spaces.
2.0 Scope
This document is applicable for the Commissioning and Start-Up periods and is intended for the use
of employees of CONSORTIUM and his subcontractors who may be concerned with the operation of,
or work on the equipment and installations in South Pars Phases 17&18 project
3.0 Responsible Persons
3.1 Commissioning & Start-Up Manager
The Commissioning & Start-Up Manager is responsible for ensuring that Gas Freeing and Inerting
operations are carried out by Authorized Responsible Persons in accordance with this procedure.
3.2 Area Authority (Process / Utility / Shift Superintendents) The Area Authorities are responsible
for:
• Ensuring that all safety precautions and safeguards are fully implemented.
• Selection of the correct Procedures.
• Facilitating preparatory works in connection with work permits.
• Informing the relevant personnel of intended isolations.
• Appointing of competent persons to act as Performing Authority with responsibility for
performing the tasks.
• Ensuring that all necessary safety requirements and equipment which have been specified in
the Permit have been provided by Task Supervisors and Performing Authorities.
4
NATIONAL IRANIAN OIL COMPANY
To allow a person to enter a vessel (with or without breathing apparatus) reference should be made
to the following:
It is vital that in determining the success, or otherwise, of an inerting operation that a sample is taken
from inside the vessel or pipe work to determine the suitability of the atmosphere to proceed further.
This Procedure is mainly focused upon inerting a vessel using an inert gas. In some situations,
inerting is performed by filling the vessel with water and then draining and introducing an inert gas at
the same time. This is the preferred option.
4.2 Principles of Inerting
The following principles are always to be respected:
5
NATIONAL IRANIAN OIL COMPANY
• By sweeping.
• By alternate pressurization and depressurization.
When measuring the hydrocarbon or inert gas content of the vessel / plant, use Table 1 for reference.
In the case of pipe work, the inerting gas is introduced at one end and the hydrocarbon gas is vented
at the other end. Ideally the hydrocarbon gas and inerting gas will be of different densities. It is
therefore necessary to inject the inert gas at such a location to ensure that all the hydrocarbon gas is
removed (see Figure 1).
6
NATIONAL IRANIAN OIL COMPANY
TABLE 1
INERTING GAS END POINTS FOR INERTING OUT COMBUSTIBLE GAS END POINTS FOR INERTING OUT OF
OF SERVICE SERVICE
Combustible Gas Inert Gas Combustible Gas Inert Gas
Purging end points with
20% safety margin. %- Purging end points with 20%
minimum of inerting gas safety margin. %-maximum of
required so that the combustible gas allowed to be left
mixture will be non- after inerting so that the mixture
flammable when air is will be non-flammable when air is
added in any amount. added in any amount.
Note:
• If in doubt as to the composition of the hydrocarbon, take the figure for natural gas.
• For H2S, take the figure for natural gas.
The inerting gas should be injected slowly to minimize any turbulence and mixing at the interface.
7
NATIONAL IRANIAN OIL COMPANY
This method is economical with respect to the amount of inerting gas used. In theory the amount of
inerting gas required will equal the volume of the pipe work although in practice it is necessary to use
20% extra.
If the densities of the hydrocarbon and inerting gases are similar it is recommended that the injection
rate should be increased to allow proper mixing. In this case the amount of inerting gas required will
be in the order of three times the volume of the pipe work.
FIGURE 1
8
NATIONAL IRANIAN OIL COMPANY
The following Graph 1 can be used as a guide as to the total quantity of inert gas that should be
necessary.
GRAPH 1
9
NATIONAL IRANIAN OIL COMPANY
Example: A vessel or pipe work has a hydrocarbon content of 100%. It is to be inerted with nitrogen.
From Table 1 the maximum final hydrocarbon content is to be 2% (98% nitrogen). The ratio of initial
to final hydrocarbon concentration is therefore 100/2 = 50. From Graph 1: it is necessary to use a
nitrogen volume of four times that of the vessel or pipe work.
4.3.3 Other Information
• Care must be taken to avoid vacuum conditions occurring unless these are within the design
limits of the plant in question.
• Before entering any enclosed spaces the atmosphere inside must be tested.
• For gas freeing of large vessels e.g. oil storage tanks etc., this is not always practicable. In
such cases the vessel is filled with water and drained two or three times, each time allowing
air to enter, before the atmosphere inside the vessel is tested.
• For hot work inside, or on the outside, of vessels or pipe work that has previously contained
hydrocarbons, inerting and cleaning must be done to remove any deposits of hydrocarbon
substances. Steaming should also be considered.
• For hot work inside a vessel, a Gas Test must be carried out immediately before the work and
a permanent gas detector complete with suitable alarms must be used for the duration of the
work.
• To carry out Gas Tests inside a vessel, the gas tester must wear the following:
- Breathing Apparatus.
- Safety Harness and Lifeline.
- A permanent watch/standby man is to be immediately outside the vessel whenever
someone is inside (working or testing).
The crucial factor to be measured after inerting is that the oxygen percentage in the vessel/ plant is
less than 2% before any hydrocarbons / combustible gas are introduced back into the vessel.
10
NATIONAL IRANIAN OIL COMPANY
GRAPH 2
Example: A vessel or pipe work has contained 100% air (21% oxygen) and needs to be inerted to 2%
oxygen. The ratio of initial to final concentration of oxygen is therefore 21/2 = 10.5.
5.0 References
• Permit to Work Procedure, (Doc. TOT-1718-999-9020-0013).
• Commissioning General Leak Testing & Inerting Procedure
(Doc. No.: SIRC-00-CO-PR-0006)
• Confined Space Entry, (Doc. No. TOT-1718-999-9020-0020).
• Process & Mechanical Isolation, (TOT-1718-999-9020-0019)
• Total South Pars Gas Field Development Phases 2&3, Gas Freeing & Inerting
11