2 Drum safety valve and line safety valve floating 10:00PM/30-11-18 12:00AM/31-11-18 2 Hrs Tool box set
3 WHRB 1 all manhole door opening 6:00 AM/31-11-18 9.00 AM/31-11-18 3 Hrs Tool box set
7 LHS Gauge Glass body leakage to be arrested 09:00AM/31-11-2018 12.00 PM/31-11-18 3 HRS Tool box set & myca sheet
11 WHRB 1 Tunnel damper gear box servecing 09.00 AM/31-11-18 12.00 AM/31-11-18 3 HRS Tool box set + Greass
12 WHRB 2
14 Drum safety valve and line safety valve floating 9.00 AM/31-11-18 11.00 AM/31-11-18 2 Hrs Tool box set
15 WHRB -2 all manhole door opening 11.00AM/31-11-18 01.00 PM/31-11-18 2 Hrs Tool box set
19 Boiler -2 tube cleaning with water jet 6.00PM/31-11-18 6.00AM/01-11-18 12 Hrs High pressure water jet machine.
20 LHS Gauge Glass valve body leakage to be 9:00AM/01-11-2018 12:00PM/01-11-2018 3 HRS Tool box set & molycote
arrested .
Primary superheater I/L line at thermocouple Tool box set ,Cutting set and
21 3:00PM/01-11-2018 05:00AM/01-11-2018 2 HRS
threaded joint leakage to be arrested welding machine
22 WHRB -2 Tunnel damper gear box servecing 05.00 PM/01-11-18 07.00 PM/01-11-18 3 HRS Tool box set & EP-2 grease
24 Turbine
25 STG Stop 6:00AM/31-10-2018 6:00AM/03-11-2018 72HRS F -Rod
32 Barring Gear oil seal leakage arresting work 09:00PM/01-11-2018 05:00PM/01-11-2018 9HRS special tools
33 Turbine fore Brg. RTD - 220 to be checked 4:00PM/01-11-2018 10:00PM/01-11-2018 6 HRS Tool box set
35 Turbine Auxillaries
41 CEP 1&2 Strainer Cleaning Work 10:00AM/02-11-2018 2:00PM/02-11-2018 4HRS Tool box set
44 Cooling Tower Basin Cleaning Work 09:00AM/01-11-2018 08:00PM/01-11-2018 24 HRS Rope-4,bucket-10, Mug-10 no
45 Lub Oil Cooler Cleaning Work 9:00AM/02-11-2018 06:00PM/02-11-2018 8 HRS Tool box and PVC brush
46 Generator Air Cooler Cleaning Work 2:00PM/31-11-18 8:00PM/31-11-18 6 HRS Tool box and PVC brush
47 DM Plant
49 Scaff Folding work for Degesher tower opening 9.00 AM/02-11-18 11.00 AM/02-11-18 2 HRS
50 Acid make Up Line Flushing Work 6.00 AM/01-11-18 7.00 AM/01-11-18 1 HRS
51 MB Acid Injection Line Flushing Work 6.00 AM/01-11-18 7.00 AM/01-11-18 1 HRS
Work Time
Teams Alotted (hrs)
Samir Samanta 28 Hrs
Apu Bera 26 Hrs
Tapas Paul 27 Hrs
Supradip Paria 33 Hrs
3 (general) + 2 (G shift
Mechanical other job) + 2 ( with IBR
Welder) + 20 (CT basin 1 fitter cum grinder (with
cleaning) IBR) +1 (other job) 1 IBR 1
DM Plant 6 (N pit cleaning)
Electrical 2
Instrumentation 1 1
Total 36 2 1 2
Manpower status 2/11/2018
THERMAX TML
Tapas fitter-1 , boiler Tunnel damper should be open and ID fan filed operator
operator-1,helper-2 shouled be stop condition.
Apu -(Fitter), field Boiler shutdown required,ID fan should be shift inchrage
operator -1,helper-2 stop.
Spare parts
Samir (1 Fitter) + 2-Helper Tunnel damper should be close condition. Mechanical Eng. required .
TL Natural cooling process shift incharge
Supradip fitter-1 , boiler Tunnel damper should be open and ID fan Mechanical Eng.
operator-1,helper-2, shouled be stop.
Apu (Fitter) ,field Boiler shutdown required,ID fan should be shift inchrage
operator -1,helper-2 stop.
Samir (1 Fitter) + 2-Helper Out side agency TG Shutdown required Mechanical Eng.
Instrument tech.-1+
Out side agency TG Shutdown required C& I Eng.
helper-1
1- fitter ,2-helper out side agency CEP suction valve should be closed . fileld operator
Out side agency with MCW pump should be stop condition ,TG Spare fills
fitter +15 helper,5 no Shutdown required And scaffolding also DM plant HOD required.
rigger required inside cooling tower .