Engine transport

for power plant

COMMERCIAL PROPOSAL

Client: Les Centaures Routiers

Contact: Eric FOUA Email: efoua@lcr-ci.com

Date: 18/07/15 Pages: 16

Our ref: LCR-03-PC-00 Revisions: 00


Page 2 of 16

Subject: Heavy transport by road

Dear Sir,
Thank you for your kind request of quotation, which I can answer to you as follows:

Introduction

Abnormal Load Engineering SA (ALE) and Les Centaures Routiers (LCR) has been invited to
tender for the transportation of heavy engines for power generation in Cotonou.

This proposal is based on the following Client supplied documents, mail (PDF and Plan)

The offer is valid and open for acceptance for 30 days from date of this proposal

Rates are valid until 21/08/15

The project location will be Godomey in Cotonou, Benin and we have foreseen the equipment to
arrive on site June 16. The equipment will come from Spain.

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 3 of 16

Scope of work

The scope consists of the transport of 7 engines from Man, model 18V48/60TS

Item Weight (mT) Length (mm) Width (mm) High (mm)


7 Man Engine 320 12600 4750 6500

We considered after study and calculation at those engines with a high center of gravity have to
be transported with 20 axles lines of Self Propelled Modular Transport (SPMT).

We considered a total work of 15 days if the distance of the site does not exceed 20 kilometres
of the port gate.
As described in technical data below, SPMT trailers do not exceed a speed of 5 km/per hour,
that´s why we considered 2 days per motor, Loading, lashing, transport, unlashed, unload and
come back to port for next engine.
We assumed also 1 full day for set up and dismantled all equipment.

Technical Drawings are included at the end of the proposal, showing the configuration and
calculation of centre of gravity and load capacity of the main items.
This configuration have been chosen for the height of the centre of gravity, the size and the
weight of the Item, to rich the best safety configuration.

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 4 of 16

Inclusions and exclusions

The following concepts are included within the scope of ALE:


• Preparation and internal tests of ALE trailers
• Transport means for ALE equipment to jobsite and return
• Rental of our equipment for the periods included in our schedule
• Qualified personnel for assembling, disassembling and operation of our
equipment
• Transport, accommodation and lodging of our personnel
• Personal protection equipment
• Standard lashing to the trailers
• Coordination logistics of the operations
• Engineering according our scope
• Issue of method statements, calculations and drawings for road transport
• Safety documentation. Risk assessments.
• Quality documentation.
• Definition of amount of lines needed

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 5 of 16

The following concepts are excluded and will be supplied by others without costs for ALE.

• Cutting and welding devices with operators to handle


• Unskilled personnel to assist ALE activities
• All Risk insurance including ALE and subcontractors as co-insured
• Safety at the jobsite and custody of our equipment on site
• Removal and installation of obstacles. Way free of interferences during the
transportation
• Accesses to the jobsite
• Safety courses if necessary
• Drawings of the equipment to move
• Setting Out Cog lines
• Topography, if needed
• Engineering studies of the structures in the road
• Reinforce of the cargo if needed
• Saddles
• Road works if needed
• Stevedores and riggers
• Temporary importation and re- exportation of our equipment
• Clearances,Taxes, duties, port cost etc…
• Bank guaranties if necessary.
• Permits, road permits
• Port storage or intermediate storage costs
• Support and beams for transport and storage

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 6 of 16

Equipment to be supplied

- 20 axles lines of Self Propelled Modular Transport (SPMT)


- 1 big power pack
- 1 container tools and spare parts

Manpower

1 Supervisor
1 Operator/foreman

This proposal include a total of 30 man days on site.

Schedule

A detailed schedule will be developed following Contract Award.

As per your indication we have taken June 2016 as the starting date. (Operational)

Assembly of our trailers 1/2 days


Mobilisation/demobilisation 48 days
On duty 15 days
Disassembly of our equipment 1/2 days

This proposal consider 15 days of our trailers on-site


We have assumed 6 days per week 10 hours per day.

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 7 of 16

Pricing and rates

Based on the information we received from you and the scope, exclusions and schedule above
mentioned we can give you our summarized quote for the above mentioned works being:

Description Offer
Transport of the 23 Items 337.000 €uros

*Excluding taxes, duties etc.

The rates for equipment and personnel outside the given scope are follows:

Item Value
SPMT (20 axles) 3200 Euros Per day
Supervisor 600 Euros Per man/per day
Operator 500 Euros Per man/per day

Other details to be agreed on further stages.

Payterms: 30 days after invoicing

Conditions :

We have assumed 7 items will be transported consecutively and without any standby

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 8 of 16

Standard Insurance Cover

Description Cover

Employers Liability GBP 10,000,000 any one occurrence

Public/Products Liability GBP 2,000,000 any one occurrence

Excess Public/Products Liability GBP 3,000,000 in excess of 1st layer P/PL


any one occurrence

Motor GBP 20,000,000 for private car & GBP


5,000,000 all other vehicles

Engineering Plant GBP 2,500,000 any one occurrence

Damage to Goods GBP 250,000 any one occurrence

Quality Assurance / Quality Control

Management System

The Quality Management System conforms to the requirements of and is accredited to BSEN
ISO 9001:2008; 14001; 18001

It is externally assessed by the Lloyds Register.

The scope of the system covers transportation, installation and lifting of heavy, indivisible
items worldwide.

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
Page 12 of 16

Quality Plan

ALE produces a Quality Plan for each project. This is developed and issued following contract
award in agreement with the Client.

We hope to have given you an acceptable proposal and like come over to your jobsite in order to
discuss and agree final terms and conditions.

Kind regards.

Find below data sheet, Technical drawings and calculation for the engines to transport and
Generators.

All business is undertaken subject to the Company's General Conditions of Contract


and to the availability of our equipment. Copies of these will be supplied on application.

Client: LCR Our ref: LCR-03-PC-00


Proposal: Comercial Date: 18/07/15
Scope: Road transport Revision: 00
EQUIPMENT DATA SHEET - SPMT

The development of self propelled modular


transporters (SPMT’s) is a major advance in the
technology of moving very large loads.
This new generation of heavy transport equipment
combines state of the art design with proven
components. The 4 and 6 axle line transporter units
can be operated independently or assembled into
any combination.
Individual transporters can be hydraulically and
electronically linked to provide a support platform
matched to the characteristics of the load and the
route.
Programmable, 360 degree electronic steering
achieves extremely accurate load positioning even
under arduous site conditions.
The SPMT transport system is an unrivalled method
for the safe and effective transport of the largest
loads.

Self Propelled Modular Transporter


Key features of the SPMT system include:
2 FILE UNIT • Hydraulically driven for movement in any
Carrying Capacity 36t / Axle direction.
• Multi-axle, high torque drive units, maximising
the tractive effort.
• 25 to 50 percent of all axles driven.
• Multi power modules capable of being
interlinked.
• Advance coupling system to reduce rigging
time.
• In cab or remote control option.
4 FILE UNIT
• Single point control for multi transfer operation.
Carrying Capacity 72t / Axle
• 3, 4 or multi suspension.

SIDE ELEVATION

www.ale-heavylift.com
TRANSPORT CALCULATION Proj.Nº Ref.Nº Doc.Nº Rev.
Client: LES CENTAURES ROUTIERS (LCR) LCR-003 LCR-003-01 0
Project: ROAD TRANSPORT By Chk by Date Page
Subject: TRANSPORT GENERAL ARRANGEMENT J.E.C. E.F. 16/07/2015

TRANSPORT CALCULATION ALE-SingleTrailer-7.4

DATE: * Schematic graph.

PL = 320 t PayLoad
HCoG = 4.560 mm Height CoG of cargo and supports (saddles, beams, etc.).
Trailer type = Scheuerle Gen 3
TH = 1.500 mm Height of trailer.
AL = 10 Number of axle lines.
F= 4 Number of files.
TW = 5.330 mm Transport width.
TL = 14.000 mm Transport length.
HP = 3 Number of hydraulic points.

CoG of load is symmetrical on the trailer. TCoG = 2.665 mm TCoG = 0 mm


LCoG = 7.000 mm LCoG = 0 mm

Supports on trailer. S(n) [mm] = 3000 ; 11000

Transverse spaced and longitudinal bed.


n 1 2 3 4 5 6 7 8
After F(n) = 2
ST [mm] = 470
After AL(n) =
SL [mm] =
WSL [t] =

O. type = 1 Trailer operation type.

CHECKING TRAILER STABILITY: CHECKING CHASSIS:

Hydraulic transverse = 16,5 % (9,4°) → Ok! 800,00


Hydraulic longitudinal = 60,7 % (31,3°) → Ok! 600,00
400,00
200,00
Geometric trans. with slope = 14,6 % (8,3°) → Ok! 0,00
-200,00
Geometric long. with slope = 47,9 % (25,6°) → Ok! -400,00
-600,00
-800,00

SUMMARY LOADS PER AXLE:


0 14000
Group1 Group2 Group3 Group4
Load per axle [t] = 7,87 8,55 9,15 0,00
u.c. [%] = 44 47 51 0 u.c. [%] = 11
TRANSPORT CALCULATION Proj.Nº Ref.Nº Doc.Nº Rev.
Client: LES CENTAURES ROUTIERS (LCR) LCR-003 LCR-003-01 0
Project: ROAD TRANSPORT By Chk by Date Page
Subject: TRANSPORT GENERAL ARRANGEMENT J.E.C. E.F. 16/07/2015

TRANSPORT CALCULATION ALE-SingleTrailer-7.4

LOAD TABLE:

Total Group1 Group2 Group3 Group4


Number of axles 40 16 12 12 0
PayLoad [t] 320 128 96 96 0
Transport weight. [t] 80 32 24 24 0
Engine weight. [t] 7 -6 3 10 0
Auxiliary steel weight. [t] 11 4 3 3 0
Maximum overload [t] 0 0 0 0
Total load [t] 418 158 127 134 0
Load per axle [t] 7,87 8,55 9,15 0,00
Load per axle at ground level [t] 9,87 10,55 11,15 0,00
Ground bearing pressure* [t/m2] 5,80 6,20 6,55 0,00
Group pressure [bar] 123 132 139 0
* Whitout overloads
OFF VALVE:

TIPPING LINES:

0 2000 4000 6000 8000 10000 12000 14000 16000


0

F-1

1000
Group3 (51%)

2000 F-2

CoG HCoG Group1 (44%)


3000
F-3

4000
Group2 (47%)

F-4
5000
1 2 3 4 5 6 7 8 9 10

6000

STABILITY LIMIT:
The transverse operational limit for this configuration is ± 194mm
The longitudinal operational limit for this configuration is ± 350mm

COMMENTS:

….
….
….
….
….
….
….
….
….