You are on page 1of 6

Flotation Plant Design and Production Planning Through

Geometallurgical Modelling
D Bulled1 and C McInnes1

ABSTRACT This paper will focus on the application of geometallurgical


modelling concepts to flotation circuit design and production
The key to successful flotation plant design, production planning and
mine/mill optimisation is a solid understanding of the resource to be
forecasting.
processed. As advocated by the authors of this paper, the main components The first section of this paper describes the method of
of geometallurgical modelling of an orebody and its associated flotation quantifying pulp chemistry parameters. A key to practical
plant are: geometallurgical modelling is having a proven and affordable
1. an ore sampling program and subsequent laboratory testing of these test that provides the required data from small amounts of
samples in order to extract process model parameters; available exploration drill core. This makes it possible to conduct
enough tests to attain metallurgical validity for insertion in the
2. geostatistical distribution throughout the resource model of the
geological model. The first section of the paper covers the
process parameters;
various modes for carrying out the MinnovEX Flotation Test
3. calibration of the plant via benchmarking (for existing operations); (MFT) and the information attained from these tests.
and
Furthermore, the authors recognise that a flotation circuit does
4. plant simulation using a system of process models and the distributed not operate in isolation, but rather is strongly influenced both by
metallurgical parameters (from step two) as the data set. the feed ore delivered to the mill and by the manner in which the
It is important that the grinding and flotation models are linked. For preceding grinding circuit processed that ore. In other words, a
example, a laboratory test conducted on a drill core sample, intended to link is required through geometallurgically enabled comminution
represent a portion of the orebody, is conducted at a specific grind and flotation simulation tools. (‘Geometallurgically enabled’
(represented by a P80). However, when that ore is actually processed
refers to the ability to conduct fully integrated flotation, or
through the plant it may well be (and in many cases most likely will be)
at another P80. Additionally, the flotation plant residence time will often
grinding, circuit simulations on the large datasets that arise when
be determined solely by the grinding circuit capacity and feed slurry the geometallurgical approach towards design or production
density. In the case of SAG mill – ball mill circuits, the fluctuations in forecasting is used.) Considering just the flotation characteristics
tonnage and grind are known to be high. The modelling approach of the feed ore presents a partial picture; also of significant
described in this paper allows for changes in the measured flotation importance is knowledge of how the rock behaved in the
kinetic parameters in order to reflect the expected grind as determined by grinding circuit from a throughput and grind perspective. The
the comminution process. second section of the paper demonstrates this concept through a
step-by-step example that tracks various blocks of ore from pit
INTRODUCTION through grinding to flotation feed.
The third section of the paper briefly discusses precision
Many mineral extraction operations are challenged on a daily analysis. A benefit of a statistical approach to geometallurgical
basis with feed ore variability that impacts the throughput of the modelling is that the precision of a design or production plan can
grinding section and the subsequent concentrate grade and be quantified through error analyses. With modelling tools,
recovery that can be produced. A key to maximising the value of laboratory tests and geostatistics, there are quantifiable sources
a mining and processing facility is to develop a prior of error at each step. This section of the paper provides an
understanding of the characteristics of the feed ore over the overview of error sources in each step of the geometallurgical
life-cycle of the operation from design and financial evaluation modelling process (Lozano and Bennett, 2003).
of the project, through to monthly and yearly production
forecasts and on-going circuit troubleshooting and optimisation.
BENCH-SCALE FLOTATION TESTS
This is achieved through the application of geometallurgical
modelling of an orebody. Geometallurgical modelling can be defined as an approach that
The main components of geometallurgical modelling are: measures metallurgical variability within an orebody and
quantifies the effect of this variability on the comminution and
1. an ore sampling program and subsequent laboratory testing metallurgical response of the ore, as it pertains to full-scale
of these samples in order to extract process model production. The geometallurgical approach surpasses the resource
parameters; model as it encompasses not only the variability of alteration,
2. geostatistical distribution throughout the resource model of lithology and metal grades, but also metallurgical process specific
the process parameters; characteristics that influence the grinding and mineral recovery
characteristics of the ore (Bennett and Lozano, 2004).
3. calibration of the plant via benchmarking (for existing
operations); and Since the success of the approach hinges on how well the
variability of the ore is represented, it is obvious that, for
4. plant simulation using a system of proven process models geometallurgical modelling purposes, many data points from
and the distributed metallurgical parameters (from step small-scale tests are more valuable than a small number of
two) as the geometallurgical data set. detailed investigations. Therefore, a standard low-cost test that
can be performed on a small mass of drill core material is
essential. In order to maintain the integrity of the
1. MinnovEX Technologies Inc, 1140 Sheppard Avenue W #6, Toronto geometallurgical model, it is also important that the parameters
ON M3K 2A2 Canada.
from each test are primary† characteristics that can be distributed
† Primary data is defined as ore-specific parameters, which in the case across an ore block model using standard geostatistical methods.
of flotation describe the inherent floatability of the ore regardless of Describing the floatability of an ore through a set of pulp kinetic
the plant flow sheet, equipment or operating targets and conditions. parameters for each of the mineral component of the ore means

Centenary of Flotation Symposium Brisbane, QLD, 6 - 9 June 2005 809


D BULLED and C McINNES

that both the concentrate grade and recovery can be calculated • the quantitative effect of grind on Kavg and Rmax; and
simultaneously using fundamental flotation modelling methods.
• a standard set of Rmax and Kavg values at a single grind-size
The MinnovEX Flotation Test (MFT) has been developed to (described by P80 and the Rosin-Rammler slope, or ‘m’
satisfy both of the above requirements. It is a standard value) common for the full set of drill core samples, together
bench-scale test that is used to measure the primary floatability with Rmax-slope parameters, all of which may be distributed
characteristics of a sample of ore. The philosophy behind MFT across the mine block model (Rmax-slope is the change in
work for samples is to have a test program that is simple, quick Rmax per one micron change in P80).
and can be done at the lowest possible cost – therefore allowing
as many tests as possible to be performed on individual drill core Table 1 summarises an example set of pulp kinetic parameters
samples to characterise the flotation properties of the ore. that would be determined for a typical copper porphyry material.
The objective of the MFT is to measure the pulp kinetics for A typical set of pulp kinetic parameters derived from an MFT
each of the mineral species in the ore at a set (pre-determined) performed on a drill core sample ground to 128 µm is shown on
reagent suite. The MFT is designed to determine the kinetics of the left side of the table. The kinetic parameters from each MFT
mineral separation in the pulp phase exclusively, while froth need to be reconciled to a standard grind before the parameters
effects in the plant are later accounted for through Flotation are distributed across a mine resource model. Therefore, the
Economic Evaluation Tool (FLEET) modelling. Further details terms Rmax-slope and Kavg-slope are used to correct the set of test
on the MFT can be found elsewhere (Dobby, Kosick and kinetic parameters to a set of standard kinetic parameters, as
Amelunxen, 2002; Dobby and Savassi, 2005). shown on the right side of the table.
In order to perform multiple tests in a quick and cost-effective
manner, the MFTs are carried out in two forms: the full MFT and Reconciliation between drill core testwork and
the mapping MFT. Once sufficient information about the kinetics flotation circuit simulation
of the mineral components in the orebody is known (through
completion of sufficient full MFTs), then the method can be The Rmax-slope and Kavg-slope parameters presented in Table 1
simplified for mapping purposes. The simplification resides provide the link between drill core flotation testwork results and
mainly in reduced degree of screen analysis, which thereby FLEET flotation circuit simulation on a block-by-block basis for
reduces the number of samples submitted for chemical analyses. design and/or production forecasting studies.
This can significantly lower the overall test cost, with little A geometallurgical model is created by following the steps
compromise in the quality of the results. Hence, more drill core outlined in Figure 1 (Dobby et al, 2004).
samples can be tested at the same project cost – ultimately The importance of accounting for the effect of grind-size on
leading to overall better accuracy in both design and production recovery from the initial grind at which the MFT test is
forecasting. performed to the ultimate prediction of flotation circuit recovery
At the commencement of a drill core test program, a decision and grade per ore block is illustrated in a step-by-step example.
would be made on the proportion of full MFTs and mapping
MFTs. This decision is based on the prerequisite that sufficient Step 1
full tests are performed per mineralogy/ore type, in order to
calibrate the key interpolation relationships needed for the The drill core samples for metallurgical testwork are selected over
mapping MFT parameter extraction. When the mineralogy/ore the region of interest within the resource. A grid pattern over the
type is simple, the split is typically around 15 per cent full MFTs area of interest (for example, the first five years of operation) is
to 85 per cent mapping MFTs. In more complex orebodies, with preferred, ensuring, as a minimum, that all major geological
more variable lithology, alteration and/or mineralogy, the features of the resource are represented. More complex geological
proportion of full tests to mapping tests has to be increased. conditions will dictate a greater number of samples. Clearly, the
The pulp kinetic parameters are determined from the MFT joint involvement of geological, mineralogical and metallurgical
results by applying a comprehensive parameter extraction staff in sample selection is required.
methodology that decouples true flotation and entrainment, and
then models the MFT according to fundamental flotation Step 2
principles (Dobby and Savassi, 2005). The analysis of each MFT
Bench-scale laboratory testwork is carried out on each of the drill
yields the following information, for each mineral (or minor
core samples. For SAG hardness tests (MinnovEX SPI) typically
element) of interest:
2 kg of drill core is required. For ball mill hardness measurements,
• the maximum recovery (Rmax) and cumulative frequency 1.2 kg for MinnovEX Modified Bond tests or 10 kg for full Bond
distribution of rate constants for each mineral species at the tests is required (Kosick, Bennett, 1999). Since full Bond tests are
test grind (described by Kavg and alpha, the latter being a only carried out on five to ten per cent of the samples, with
descriptor of the spread of rate constants); Modified Bond tests performed on the remaining samples, the core

TABLE 1
Typical set of pulp kinetic parameters derived from an MFT.

Testwork grind m = 0.93 Stanrdard grind for FLEET simulation m = 0.70


P80 = 128 P80 = 100
Kinetics at testwork conditions Kinetics at standard grind
Mineral Rmax Kavg Alpha Mineral Rmax Kavg Alpha Rmax slope Kavg slope
CuSulf 91.7 1.5 1.3 CuSulf 92.9 1.5 1.3 -0.041 -0.004
Pyrite 96.0 2.8 3.2 Pyrite 95.8 2.8 3.2 0.002 0.004
Au 71.5 1.0 1.2 Au 73.6 1.0 1.2 -0.058 -0.002
Ag 80.0 0.6 4.3 Ag 81.9 0.6 4.3 -0.065 -0.001
NSG 3.9 0.3 10.0 NSG 2.8 0.3 10.0 0.023 0.001

810 Brisbane, QLD, 6 - 9 June 2005 Centenary of Flotation Symposium


FLOTATION PLANT DESIGN AND PRODUCTION PLANNING THROUGH GEOMETALLURGICAL MODELLING

Step 1
Selecting the Drillcore samples for Metallurgical testwork

Step 2
Communition and Flotation testwork

Step 3
Extraction of ore-specific primary parameters for
geostatistical distribution

Step 4
Population of the mine block model using Geostatistics to
distribute the extracted parameter

Step 5 Step 6
CEET simulation to predict TPH FLEET simulation to predict final
and P80 on a block-by-block basis concentrate grade and recovery
on a block-by-block basis

Production planning/ Mine/Plant Optimisation


Design Mode
forecasting Mode Mode

FIG 1 - Creating a geometallurgical model.

TABLE 2
A selection of typical grindability and floatability parameters for three random drill core samples.

Drill core label SPI BWi MFT grind Rmax_cusulf Rmax_cusulf Rmax_cusulf
(min) (kWh/t) (microns) (at test grind) (%) (at std grind)† (%) slope
DC-1 28 12.4 65 81.0 77.6 -0.090
DC-2 35 11.7 108 94.3 94.6 -0.023
DC-3 91 15.0 128 91.7 92.9 -0.041

† A standard target grind of 100 µm had been selected.

requirement is 12 kg for up to ten per cent of the samples and only complete set of parameters, but only a selection for illustrative
about 4 kg for the other 90 per cent. purposes – the full set of floatability parameters per sample
The MFT requires no additional drill core as this test is would be as per Table 1.
performed on the products from the SPI and Bond dry grinding Although a standard grind of 100 µm had been selected, it can
tests. At the outset of the testwork program, a standard grind-size be seen that the actual grind-sizes (P80) at which the three tests
for the feed for the MFT is selected. Based on initial hardness were performed were 65, 108 and 128 µm, respectively. DC-1 is
information for each drill core sample (SPI and BWi), an the softest of the three samples and as a result, the laboratory
estimate is made of the required grinding time to attain the mill over-ground this sample. Likewise, DC-3 is a much harder
standard grind-size for the MFT, and each sample is wet ground sample, and the desired grind was not attained in the specified
in a laboratory mill for the specified length of time. MFTs are grinding time. Even when attempts are made to account for the
then carried out on all samples, with product streams analysed Bond value in selecting the lab grind time, these differences
either according to the full MFT or mapping MFT protocols. often occur. However, a unique aspect of the MFT is that the
kinetic parameters measured at each test grind can be reconciled
Step 3 to the standard grind through the Rmax_slope function.

The primary ore parameters, shown in Table 1, which describe Step 4


fundamental grindability and floatability of the ore samples, are
extracted from the lab data according to model fitting techniques The grindability parameters and floatability parameters at
(Dobby and Savassi, 2005). Table 2 provides a case study standard grind are distributed throughout the blocks in the region
selection of typical parameters measured for three random drill of interest in the mine resource model using geostatistical
core samples (we will follow the three samples through the next techniques (involving the consideration of sample location, ore
few steps of the process). Note that this table does not show the type and grade). An outcome is illustrated in Figure 2.

Centenary of Flotation Symposium Brisbane, QLD, 6 - 9 June 2005 811


D BULLED and C McINNES

2. For Block 2, neither the SAG mill nor the Ball mill has
become the limiting element due to this blocks’ lower BWi.
Throughput therefore can be maximised up to a limit
typically set by some constraint external to the grinding
circuit (typically tailings pumps or concentrate filter
capacity dictates this limit on maximum throughput). At
this maximum throughput of 5250 tph the grinding circuit
can produce a grind of 109 µm.
3. Block 3 comprises the hardest ore and the grinding circuit
is SAG mill limited. The maximum tonnage that can be
treated through the SAG mill is only 4436 tph before the
mill would overload. At this lower tonnage, the ball mill
circuit produces the finer grind of 89 µm.

Step 6
FIG 2 - Sample region of a mine resource model. The tonnage and P80 results from the grinding simulation become
input values to the flotation circuit simulation. Similar to Step 5,
Early in a project development, often there will be insufficient the FLEET software tool calculates final concentrate grade and
samples tested to develop a geostatistical distribution. In this recovery on a block-by-block basis based on the tonnage and
situation, the distribution of parameters is made along either a grind feeding the flotation circuit for the block, and the
regional basis or ore type basis. floatability characteristics attributed to that block. Table 4
provides the set of feed parameters for the same three blocks of
Figure 2 is a sample region of a mine resource model,
ore discussed in Step 5.
demonstrating areas of higher and lower theoretical recovery of
copper sulfide minerals, after geostatistical distribution of the The kinetic parameters at standard grind (100 µm) are
Rmax_cusulf parameter across the resource model. distributed through the mine block model. However these values
are adjusted on a block-by-block basis according to their
Rmax-slope values and the P80 value calculated for that block. The
Step 5 slope values are also distributed across the block model and are
At this stage, each block in the geometallurgical model has been therefore available on a block-by-block basis. The actual Rmax
attributed the interpolated ore-specific parameters, necessary for values used in the FLEET simulation are adjusted according to
grinding simulation. Within a web-based simulation platform, the difference in P80 between the standard grind and the block
the grinding simulation software ‘mines’ the resource model on a grind and the slope for that block.
block-by-block basis, calculating the grinding circuit throughput It is important to make the correction for the difference in
(TPH) and product grind (P80) for each block. Example grinding grind-size between that produced in the MFT to that attributed to
simulation results for the three blocks of ore (samples) listed in each block of ore, to achieve accurate design and production
Table 2 are given in Table 3. (In this table is assumed that DC-1 forecasting. Table 5 highlights this by showing the original test
was located in Block 1, DC-2 in Block 2 and DC-3 in Block 3, grind for a drill core sample compared to its associated block
and a typical SAG – ball mill circuit was used for the grind, and the impact that this has on the prediction of ultimate
simulation.) recovery (Rmax) for that block. Modelling is conducted by
utilising the kinetic parameters of all minerals.
Note the following:
1. In this scenario, Block 1 comprises soft ore, therefore ERROR ANALYSIS FOR GEOMETALLURGICAL
affording the opportunity to maximise tons by producing a
MODELLING
coarser grind. A limit of 120 µm (based on coarse fraction
results of flotation tests) has been set on how coarse the The following discussion is most applicable to production
grind is allowed to become, thereby limiting the throughput forecasting at an operating concentrator. A statistical approach to
for Block 1 to 5185 tph. geometallurgical modelling presents the user with an opportunity

TABLE 3
Typical CEET simulation results for three blocks of ore.

Spatial location SPI (min) Bwi (kWh/t) TPH P80 (microns) Case Note (see text)
Block 1 x1 y1 z1 28 12.4 5185 120 Ball-mill limited 1.
Block 2 x2 y2 z2 35 11.7 5250 109 Downstream limited 2.
Block 3 x3 y3 z3 91 15.0 4436 89 SAG limited 3.

TABLE 4
Typical FLEET feed values for three blocks of ore.

Spatial location TPH P80 Rmax_cusulf Rmax_ cusulf Actual Rmax_ cusulf used
(microns) (at std grind) (%) slope in FLEET simulation
Block 1 x1 y1 z1 5185 120 77.6 -0.090 75.8
Block 2 x2 y2 z2 5250 109 94.6 -0.023 94.3
Block 3 x3 y3 z3 4436 89 92.9 -0.041 93.4

812 Brisbane, QLD, 6 - 9 June 2005 Centenary of Flotation Symposium


FLOTATION PLANT DESIGN AND PRODUCTION PLANNING THROUGH GEOMETALLURGICAL MODELLING

TABLE 5
The actual Rmax_cusulf used in FLEET simulations, compared to the values established from the MFT test.

Grind at which MFT test Rmax_cusulf value extracted Grind-size attributed to the Actual Rmax_cusulf value for
was performed (microns) from MFT test results (%) block of ore after CEET that block, used in FLEET
simulation (microns) simulations (%)
Block 1 (DC-1) 65 81.0 120 75.8
Block 2 (DC-2) 108 94.3 109 94.3
Block 3 (DC-3) 125 91.7 89 93.4

to estimate precision on production forecasts. For the model to be make the model accurate. In this case, ‘tuning’ refers to model
used for production planning, it can only be considered rigorous adjustments made based on the performance of the plant over an
and definitive if accompanied by an associated precision model. extended period, such as a month or a quarter, for which kinetic
A complete geometallurgical modelling study comprises the data has been estimated (Dobby et al, 2004). If we do a good job
following main components (Dobby et al, 2004): here the accuracy error will be minimal – retaining only an
intrinsic precision error from the model quality.
• a bench-scale laboratory testwork program;
Thus, in a more simplified sense one can think of the error in
• geostatistical distribution over the resource model of the production forecasts that use this approach as being precision
parameters extracted from the bench-scale test; based when referring to the dataset, with some intrinsic precision
• plant benchmarking for model calibration; and error built into the process models. Accuracy related error may
be introduced with the process models. We can reduce the
• circuit simulation using the distributed metallurgical precision error through more samples and the accuracy error with
parameters and a system of process models, calibrated plant benchmarking and periodic model tuning based on
according to plant measurements. extended periods of plant operation.
A summary of the main error sources is given in Table 6. The precision errors on a predicted plant performance (tonnage,
There are two types of error to consider. One is precision related recovery and concentrate grade) for an extended period such as a
and the other is accuracy related. Consider the errors listed in month, quarter or year can be made with this approach. Estimates
Table 6. are made for test error (through repeat MFTs), block estimation
errors (from geostatistical analysis) and model precision for use
within a Monte Carlo simulation. The resulting precision estimate
TABLE 6 on the stated performance indicators of tonnage, recovery and
Error sources for production forecasting. grade provide metallurgical staff and management with a realistic
assessment on the quality of the stated performance. Clearly, in
1 Testing error • loss of sample today’s demand for accurate production forecasting, this is of
• minor difference in test execution (operator significant value, allowing all involved to recognise the precision
induced) of the estimates, and to plan accordingly.
• natural variability in test repeatability (test For a properly conducted study using a well developed model,
nugget effect) the largest error source will be in the block estimation error. If
• transposition at logging or during the test, etc the precision is deemed unacceptable, then the geometallurgical
2 Block • directly proportional to the number of samples approach provides a means to quantify the precision
estimation within the search radius defined by the improvement gained by increasing the number of samples tested.
error variogram(s) (may be more than one variogram
if there is anisotropy in the deposit for the CONCLUSIONS
parameter – common)
It is the authors’ belief that the geometallurgical modelling
3 Process model • from lack of, or incomplete tuning approach for flotation circuits, as described in this paper, is a step
error • incorrect process assumptions forward in quantifying the impact of ore variability on the
(eg P80_Ave or t/hMAX ) metallurgical performance of industrial flotation circuits. The
quantification of ore variability linked with geometallurgically
enabled process models opens the opportunity for more accurate
When flotation technicians are well trained in the MFT, then circuit design and the most reliable production forecasting
the testing error is considered to be mainly precision related, due method that is currently available. Finally, there is considerable
to normal operator variations and assay precision (in some cases, opportunity to apply these geometallurgical technologies to
incorrect assumptions about the element-to-mineral conversion optimisation studies and advanced process control to maximise
will introduce a bias). the value from mine to mill.
With respect to the block estimation error, there is much in the
literature about which geometrical, geostatistical, or simulation REFERENCES
(in a geostatistical sense) technique should be used for a variety Bennett, C and Lozano, C, 2004. The architecture of the geometallurgical
of common estimation challenges. Picking an appropriate model, in Proceedings Procemin, Santiago, Chile, pp 1-8.
technique is essential to avoiding both a bias (accuracy) and Dobby, G, Bennett, C, Bulled, D and Kosick, G, 2004 Geometallurgical
unnecessary precision-based error. If we assume that good modelling – the new approach to plant design and production
judgement has been exercised here then the error is almost forecasting/planning, and mine/mill optimization, in Proceedings
completely precision based. 36th Annual Meeting of the Canadian Mineral Processors, Ottawa.
Dobby, G, Bennett, C and Kosick, G, 2001. Advances in SAG circuit
For the process model error, both inaccuracy and imprecision design and simulation applied to the mine block model, in
are introduced here. For a given circuit the raw model may be Proceedings SAG 2001, Volume 4, pp 221-234 (Department of
inaccurate (biased). However, the benchmarking and periodic Mining and Mineral Process Engineering, University of British
tuning process is designed to eliminate this systematic bias and Columbia: Vancouver).

Centenary of Flotation Symposium Brisbane, QLD, 6 - 9 June 2005 813


D BULLED and C McINNES

Dobby, G, Kosick, G and Amelunxen, R, 2002. A focus on variability Kosick, G and Bennett, C, 1999. The value of orebody power requirement
within the orebody for improved design of flotation plants, in profiles for SAG circuit design, in Proceedings 31st Annual Meeting
Proceedings 33rd Annual Meeting of Canadian Mineral Processors, of the Canadian Mineral Processors, Ottawa.
Ottawa. Kosick, G, Bennett, C and Dobby, G, 2002. Managing company risk by
Dobby, G S and Savassi O N, 2005. An advanced modelling technique for incorporating the mine resource model into design and optimization
scale-up of batch flotation results to plant metallurgical performance, of mineral processing plants, in Proceedings 104th Annual General
in Proceedings Centenary of Flotation Symposium, pp 99-104 (The Meeting of the CIM, Vancouver.
Australasian Institute of Mining and Metallurgy: Melbourne). Lozano, C and Bennett, C, 2003. Geometallurgical modelling applied to
production forecasting, plant design and optimization, in
Proceedings Procemin (T11), pp 1-11, (Universidad de Chile).

814 Brisbane, QLD, 6 - 9 June 2005 Centenary of Flotation Symposium

You might also like