Professional Documents
Culture Documents
1 Materials 60 %
2 Construction (Labour & Contractor) 25 %
3 Administrative Overhead 6 %
4 Design, Drawing, Consultancy 6 %
5 Contingency 3 %
100 %
Land value excluded
PROJECT BUDGETING
Design, Drawing,
Consultancy Contingency
Administrative 6% 3%
Overhead
6%
Construction
(Labour &
Contractor) Materials
25% 60%
1
Page
Sample project @ 4500 BDT/SFT
1 Materials 270000000
2 Construction (Labour & 112500000
Contractor)
3 Administrative Overhead 27000000
4 Design, Drawing, Consultancy 27000000
5 Contingency 13500000
450000000
Design, Drawing,
Consultancy, Contingency,
Administrative
27000000 13500000
Overhead,
27000000
Construction
(Labour &
Materials,
Contractor),
270000000
112500000
2
Page
Construction Cost-Head Breakdown (Excluding land and Material)
Categories
Likelihood
1 (rare)-5 (very frequent)
Impact
1 (very low)-5 (very high)
Type of Risk
Design risks
D1 Design errors and omissions 4 5
D2 Design process takes longer than anticipated 3 4
D3 Stakeholders request late changes 3 3
D4 Failure to carry out the works in accordance with the contract 3 3
External risks
Ex1 New stakeholders emerge and request changes 2 4
Ex2 Public objections 1 3
Ex3 Laws and local standards change 1 3
Ex4 Tax change 1 4
Environmental risks
Construction risks
C1 Construction cost overruns 4 4
C2 Technology changes 2 4
5
Page
BOQ
Chart -2
2nd
Sl. No LEVEL AREA 1st Phase Phase
Semi Basement Up to
Mat 8108 8108 0
Up to Floor of GF Where
basement note covers 7338 7338 0
Up to Basement Floor
Slab 8108 8108 0
Up to Mezzanine Slab 12101 12101 0
Ground Floor Slab 15446 15446 0
1st Floor Slab 15446 15446 0
2nd FLOOR Slab 15446 15446 0
3rd FLOOR Slab 15446 15446
4th FLOOR Slab 15446 15446
5th FLOOR Slab 15446 15446
6th FLOOR Slab 0 0
7th FLOOR Slab 0 0
Roof Floor Slab 3595 3595
total 131926 81993 49933