You are on page 1of 22

RULE 2 infrastructure projects is not absolute.

The prohibition will not apply when the matter


is of extreme urgency involving a constitutional issue, such that unless a TRO is
Luvimin Cebu Mining Corp. v Cebu Port Authority issued, grave injustice and irreparable injury will arise. Irreparable injury and grave
injustice was found to have been caused to the petitioners by CPA's premature
Doctrine: Pursuant to RA 8975, only the Supreme Court can issue a temporary
takeover of the port.
restraining order, writ of preliminary injunction, or writ of mandatory injunction
when what is involved is a national project. An exception is when the issuance will CPA moved for reconsideration but was denied. CPA appealed to the CA. CA ruled
result in grave injustice and irreparable injury. that RTC gravely abused its discretion in issuing the writ of preliminary injunction.
The CA ratiocinated that an injunctive writ cannot be issued to enjoin the respondents
Ponente: Justice Reyes
from taking over the port facility because the two projects implemented by the CPA
Concurred by: Justices Velasco Jr., Peralta, Villarama Jr., and Jardeleza are considered as national government projects as defined in Section 2 (a) of R.A. No.
8975 against which no injunctive writ can lie pursuant to Section 3 of the same law.
Facts: On October 28, 1997, the Cebu Port Authority issued a Certificate of The CA further decreed that no irreparable injury was caused to the petitioners
Registration and Permit to Operate to Luvimin Cebu Mining Corp. to operate a because whatever loss they will likely suffer can be measured by way of damages
private port at Brgy. Talo-ot, Cebu. On March 1, 2006, CPA rescinded the (actual or compensatory, exemplary, attorney's fees and costs of litigation).
registration/permit on the following grounds: Petitioners' motion for reconsideration was likewise denied.

a) A Foreshore Lease Agreement is a prerequisite for a port license and the FLA Issues:
application of petitioner is still pending with DENR
a) Sec. 3 of RA 8975 cannot be applied because the wharf in Talo-ot Port was never a
b) Said FLA application was denied by DENR in 1999. Instead petitioner should apply national government project
for a special land use which is Other Lawful Purposes
b) The exceptional circumstance in Sec. 3 of RA 8975 is present because the
c) No permit is still granted from the OLP application petitioners' constitutional right over the property was violated
Thus, CPA declared the registration/permit as defective and took possession of the Held:
port facility. Petitioners then filed a complaint for Injunction with Damages before the
RTC. Petitioners allege that they were not given prior warning and that the unilateral a) No. CA correctly ruled that RTC abused its discretion in issuing a writ of
cancellation of their permit/license denied them due process of law as they had preliminary injunction, violating Sec. 3 and 4 of RA 8975:
already built a RORO facility on the land using their own money. They also claim that
Section 3. Prohibition on the Issuance of Temporary Restraining Orders, Preliminary
they had already secured an ECC from DENR and that the CPA's invasion of their
Mandatory Injunctions. — No court, except the Supreme Court, shall issue any
right to operate a wharf is material and substantial, which warrants the issuance of a
temporary restraining order, preliminary injunction or preliminary mandatory
writ of injunction to prevent serious damage.
injunction against the government... to restrain, prohibit or compel the following acts:
RTC issued an Order directing the issuance of a TRO and set the hearing for
(d) Termination or rescission of any such contract/project;
preliminary injunction.
xxxx
CPA opposed. It asserted that it has an on-going infrastructure project at the Talo-ot
Port which forms part of the Nautical Highway envisioned by former President Gloria This prohibition shall not apply when the matter is of extreme urgency involving a
Macapagal-Arroyo. Considering that it is a national project, only the Supreme Court constitutional issue, such that unless a temporary restraining order is issued, grave
can restrain the same pursuant to Republic Act (R.A.) No. 8975. In addition, an injustice and irreparable injury will arise.
injunctive writ is moot and academic since they have already taken over the port by
implementing two projects: a) repair of the RORO ramp and b) construction of an Section 4. Nullity of Writs and Orders. — Any temporary restraining order,
office and other facilities. preliminary injunction or preliminary mandatory injunction issued in violation of
Section 3 hereof is void and of no force and effect.
Petitioners then argued that the case falls within the exception in Sec. 3 of RA 8975.
RTC issued an Order granting petitioners' application for the issuance of a writ of The prohibition covers national government projects defined in Section 2 of the same
injunction. RTC reasoned that it was premature for the CPA to take over the port's law.
premises without giving the petitioners the opportunity to iron things out or be given
proper notification for them to vacate. The RTC also held that the prohibition in R.A. The term infrastructure projects means "construction, improvement and
No. 8975 on the issuance of restraining orders by courts against government rehabilitation of roads, and bridges, railways, airports, seaports..."
On the other hand, the project by petitioner is covered by RA 6957, as amended by RA Issue: There are 2 primary issues in this case, first is the procedural issue which is our
7718 which covers those by private entities. The contract arrangement between topic for today. Whether or not the petitioners in the case have a legal standing. And
petitioner and CPA is such that the private entity undertakes the construction, the substantive issue talks about the legality of the service contract.
financing, operation and/or maintenance of a given infrastructure facility subject to
its eventual transfer to the concerned government entity upon completion, after a
fixed number of period or after the private entity has recouped its investments.
Ruling: Under the rules of court. It requires that the parties to a suit be either natural
This is affirmed in the Certificate of Registration and Permit to Operate granted to or juridical person or entities authorized by law. It further requires that action be
petitioner such that upon the expiration of said certificate, the port facility shall brought in the name of the real party in interest even if it is filed by a representative.
become the property of CPA. In other words, the Talo-ot Port is a national
infrastructure project, the termination or rescission of which cannot be enjoined by an
injunctive writ issued by any lower court. Hence, the respondents alleged that the stewards have no legal standing since the
party that they represent are the resident marine mammals who are neither natural or
b) No. The petitioners cannot claim exception. No constitutional issue of due process
juridical persons.
is involved because the petitioners were not deprived of any property or property right
when their Certificate of Registration and Permit to Operate was cancelled. The
petitioners were given a mere privilege to operate a private facility in Talo-ot Port, not
a property right. They also had no vested right to operate the private port since their However. The stewards contend that they have legal standing since they will be
certificate can be withdrawn at any time. Sufficient notice was also afforded the benefited or injured by the decision of the case and based their right in the case of
petitioners when it was stated in the certificate that it may be terminated should they oposa v factoran wherein the court allows the petitioner to bring a suit in behalf of the
be found to be non-compliant with the rules. future generations for the faithful performance of environmental laws.

Petition is denied.

Resident Marine Mammals v Reyes The court passed the rules of procedure for environmental cases which allow a citizen
suit and permit any Filipino citizen to file an action before our courts for violations of
our environmental laws. It means that locus standi in environmental cases has been
given a more liberalized approach.
Facts: Herein petitioners, resident marine mammals are the toothed whales, dolphins,
porpoises and other cetacean species which inhabit the waters in and around the
Tanon Strait (islands of Negros and Cebu) They are joined by Gloria ramos and Rose
Osorio collectively know as the stewards who seek the protection of these marine Although the case was filed before the passage of the rules of procedure for
species. environmental cases, the court held that the rules shall be applied retroactively. And
therefore the court ruled that the need to give the stewards a legal standing has been
eliminated by the passage of rules of procedure for environmental cases for it allows
any filipino citizen, as a steward of nature, to bring a suit to enforce environmental
In this case, the petitioners seek to nullify the service contract which permits
laws. The court also justified that herein petitioners, the stewards are real parties and
exploration, development and exploitation by Japan petroleum exploration within the
not just a representative
Tanon Strait. As we have discussed in NIPAS act, tanon strait is a protected seascape.
Originally the contract was entered by the government with JAPEX for geophysical Torrecampo v MWSS
survey and exploration. However it was converted into a service contract by the DOE
and JAPEX. JAPEX had started its operations through conducting a survey and Doctrine: Torrecampo, in seeking the issuance of a writ of injunction, seeks judicial
exploration of the areas. While in the second sub-phase of the project, JAPEX apply review of a question of Executive policy, a matter outside this Court's jurisdiction.
for Environmental impact assessment since it knew that the areas the contract covers Torrecampo failed to show that respondents committed grave abuse of discretion that
are within the protected seascapes. Thereafter, JAPEX obtain a Environmental would warrant the exercise of this Court's extraordinary certiorari power.
Compliance Certificate.
Ponente: Justice Carpio

Concurred by: Justices Nachura, Peralta, Abad and Mendoza

Facts: On June 30, 2009, Torrecampo reported that personnel and heavy equipment
from DPWH entered Brgy. Matandang Balara to implement the C-5 Road Extension
Project over Lot Nos. 42-A-4, 42-A-6, and 42-A-4. Torrecampo alleged that if the Torrecampo's relevant claims:
MWSS and the DPWH are allowed to continue and complete the C-5 Road Extension
Project, three aqueducts of the MWSS which supply water to eight million Metro a) Only the SC may issue a restraining order and/or writ of preliminary injunction
Manila residents will be put at great risk. Torrecampo insisted that the RIPADA area, against government projects
consisting of Pook Ricarte, Pook Polaris and Pook Dagohoy is a better alternative to
b) Present suit is not premature
subject lots. Torrecampo then filed the present petition before the Supreme Court.
The Court issued a status quo order. Pertinent provisions of the Resolution reads: c) The implementation of the road project violates RA 8975
Atty Alfredo Villamor, Jr., as counsel for Torrecampo, alleges that the project would MWSS claims:
result to grave injustice and irreparable injury to petitioner and the 8 million
residents of Metro Manila whose water supply are sourced from the aqueducts found a) Petition does not present a justiciable matter
underneath the area where the road project is to be implemented. He also alleges that
the petition raises the fundamental right to health, and that this petition for b) Petition failed to allege Torrecampo's right that warrants an issuance of an
injunction has to be filed directly with the Supreme Court rather than with the lower injunction under RA 8975
court pursuant to Sec. 3 of RA 8975. DPWH relevant claims:
The OSG claims that the present case does not fall within the exceptions under Sec. 3 a) MWSS did not object to the DPWH project
of RA 8975. He also clarified that the proposed C-5 Road Extension Project shall not
be undertaken pending completion by the DPWH of studies and tests on safety b) DPWH's determination of the location of the project in accordance with its
concerns which includes the aqueducts. specialized skills and technical expertise should be accorded with finality and respect

Atty. Agra for respondent MWSS finds the petition for injunction premature as the c) Torrecampo is not entitled to an injunction
project is yet to be implemented since for it to be implemented, it has to pass prior
review by the MWSS first which the MWSS can only do after DPWH has submitted its Held: No, the petition by Torrecampo must fail. He is not entitled to an injunction. He
detailed study and tests. seeks judicial review of a question of Executive policy, a matter outside this Court's
jurisdiction. Torrecampo failed to show that respondents committed grave abuse of
Thus, the Court resolved to lift the status quo order considering that no grave injustice discretion that would warrant the exercise of this Court's extraordinary certiorari
or irreparable injury would arise. power.

Under PP 1395 by Pres. Arroyo, certain parcels of the RIPADA are serve two Torrecampo raises a violation of the residents' right to clean and potable water to
purposes: demand that this Court determine whether the Tandang Sora area is a better
alternative to the RIPADA area for the C-5 Road Extension Project. However, such
a) An access highway for the new road alignment of the C-5 Road Extension Project inquiry on issues raised by Torrecampo would delve into matters that are exclusively
b) Housing facilities for deserving and bona fide occupants within the wisdom of the Executive branch, not the Judiciary. The Court can only
determine whether there was grave abuse of discretion amounting to lack or excess of
On December 3, 2007, MMDA Chairperson Fernando wrote to MWSS Administrator jurisdiction attributed to the respondents. However, in this case the DPWH still has to
Jamora and proposed that certain MWSS properties be utilized for the construction of conduct the proper study to determine whether a road can be safely constructed on
medium rise building for the families to be displaced by the C-5 Road Extension land beneath which runs the aqueducts. Without such study, the MWSS, which owns
Project. MWSS rejected such proposal. the land, cannot decide whether to allow the DPWH to construct the road. Absent
such DPWH study and MWSS decision, no grave abuse of discretion amounting to
Between December 2007 and June 2008, certain correspondences took place lack of jurisdiction can be alleged against or attributed to respondents.
regarding the construction of MRBs. On March 12, 2009, MWSS issued a resolution
allowing DPWH to use the 60 Meter Right-of-Way for preliminary studies in the Petition is denied.
implementation of the c-5 Road Extension Project. DPWH then entered said
properties and conducted the necessary complete study. DPWH then released a Alvarez V. Picop Resources, Inc.
memorandum stating the properties to be affected by the road project, which included CHICO-NAZARIO, J.
those of MWSS and which MWSS allowed entry of the DPWH.
Doctrine: Accordingly, the prohibition in PD 605 against the issuance of preliminary
Issue: Whether respondents should be enjoined from commencing with and injunction in cases involving permits for the exploitation of natural resources was
implementing theC-5 Road Extension Project which affected MWSS properties. inapplicable to this case. Statutes such as PD 605, PD 1818 and Republic Act 8975
merely proscribed the issuance of temporary restraining orders and writs of Certain Area from the Operation of Proclamation No. 369 Dated February 27, 1931,
preliminary injunction and preliminary mandatory injunction. They could not, under and Declaring the Same as Mineral Reservation and as Environmentally Critical
pain of violating the Constitution, deprive the courts of authority to take cognizance of Area.” The excluded area consisted of about 8,100 hectares of respondent’s TLA No.
issues raised in the principal action, as long as that action and the relief sought were 43. On January 21, 2003, Picop filed a Petition for the Declaration of Nullity of the
within their jurisdiction. aforesaid presidential proclamation, as well as of the implementing order, DAO No.
2002-35 (“nullity case”). Initially, the RTC issued a Temporary Restraining Order
FACTS: In 1952, Bislig Bay Lumber Co., Inc. (BBLCI), the predecessor of Paper (TRO) enjoining respondents in that case from implementing the questioned
Industries Corporation of the Philippines (Picop) was granted Timber License issuances. Subsequently, however, it dismissed Picop’s Petition for not stating a cause
Agreement (TLA) No. 43. The Agreement covered an area of 75,545 hectares in of action. On reconsideration, it set for hearing respondent’s application for
Surigao del Sur, Agusan del Sur, Compostela Valley, and Davao Oriental. The late preliminary injunction. Thus, these consolidated Petitions have been brought before
President Ferdinand E. Marcos allegedly issued, sometime in 1969, a Presidential the Court, assailing (1) the grant of a writ of mandamus to compel the DENR to issue
Warranty confirming that TLA No. 43 “definitely establishes the boundary lines of an IFMA in favor of Picop; (2) the immediate execution of the writ; and (3) the non-
[BBLCI’s] concession area.” Upon its expiry in 1977, this Agreement -- as amended -- dismissal of the nullity case.
was renewed for another 25 years, to “terminate on April 25, 2002.” On December 23,
1999, the Department of Environment and Natural Resources (DENR) promulgated ISSUE: 1. Whether the mandamus case should be dismissed, because (1) it lacked a
DENR Administrative Order (DAO) No. 99-53 or the “Regulations Governing the cause of action; and (2) its subject matter pertained to the exclusive administrative
Integrated Forest Management Program (IFMP).” In a letter dated August 28 2000, domain of the DENR secretary
Picop signified its intention to convert TLA No. 43 into an Integrated Forest
Management Agreement (IFMA), pursuant to DAO No. 99-53. During the RULING: (Whether Outright Dismissal Whether Outright Dismissal Was Proper)
performance evaluation of Picop, the DENR found that respondent had violated the
The Petition filed before the trial court was one for mandamus with a prayer for the
rules and regulations governing TLA No. 43. Some of these violations were the non-
issuance of a writ of preliminary prohibitory and mandatory injunction, with
submission of a five-year forest protection plan and a sevenyear reforestation plan;
damages. Specifically, the Petition sought to compel the DENR secretary to (1) sign,
nonpayment of overdue forest and other charges in the total amount of
execute and deliver the IFMA documents to Picop; (2) issue the corresponding IFMA
P167,592,440.90 as of August 30, 2002; and failure to secure a clearance from the
number assignment; and (3) approve respondent’s harvesting of timber from the area
National Commission on Indigenous Peoples (NCIP), considering the presence of
of TLA No. 43. Petitioner contended that these acts related to the licensing, regulation
indigenous peoples in the area, as well as a Certificate of Ancestral Domain Claims
and management of forest resources, a task that belonged exclusively to the exclusive
covering part of the area. Meanwhile, Picop received from the DENR secretary a
administrative domain of the DENR. Picop, however, alleged grave abuse of discretion
letter. By virtue of this letter, Picop claimed that “the TLA has been converted.” The
on the part of the DENR secretary. Thus, it behooved the Court to determine whether
DENR believed, however, that respondent’s application for an IFMA should undergo
the department head had indeed gravely abused his discretion. An outright dismissal
the process as provided in DAO No. 99-53. Thus, petitioner required Picop to submit
of the case would have prevented the Court’s resolution of the issue. For the same
the following to the DENR: 1. Certificate of Filing of Amended Articles of
reason, the Petition could not be dismissed outright on the ground of lack of cause of
Incorporation issued on 12 August 2002 that extended PICOP’s corporate term for
action. A motion to dismiss on that basis would hypothetically admit the truth of the
another fifty (50) years; 2. Proof of Payment of forest charges; 3. Proof of Payment of
allegations in the Complaint. In ruling upon the DENR secretary’s Motion to Dismiss,
Reforestation Deposit; 4. Response to social issues, particularly clearance from the
the allegation of respondent that it had a contract with the government should thus be
NCIP; and 5. Map showing reforestation activities on an annual basis. Upon
hypothetically admitted. Necessarily, petitioner’s argument that there was no such
evaluation of the documents subsequently submitted, the DENR noted as follows: a)
contract should be considered in the trial of the case. Petitioner countered that he had
PICOP did not submit the required NCIP clearance; b) The proof of payments for
not yet exercised his exclusive jurisdiction over the subject matter of the case -- either
forest charges covers only the production period from 1 July 2001 to 21 September
to approve or to disapprove Picop’s application for IFMA conversion. Hence, he
2001; c) The proof of payment of reforestation deposits covers only the period from
argued that respondent’s immediate resort to the trial court was precipitate, in
the first quarter of CY 1999 to the second quarter of CY 2001; d) The map of the areas
violation of the doctrine of exhaustion of administrative remedies. The Court of
planted through supplemental planting and social forestry is not sufficient compliance
Appeals ruled that the doctrine of exhaustion of administrative remedies could be
per Performance Evaluation Team’s 11 July 2001 report on PICOP’s performance on
disregarded when there were circumstances indicating the urgency of judicial
its TLA No. 43, pursuant to Section 6.6 of DAO 79-87; and e) PICOP failed to respond
intervention. In this case, it cited the employment by Picop of a sizeable number of
completely to all the social issues raised. Insisting that the conversion of its TLA No.
workers and respondent’s payment of millions in taxes to the government.
43 had been completed, Picop filed a Petition for Mandamus (“mandamus case”)
against then DENR Secretary Heherson T. Alvarez before the Regional Trial Court The issue of whether there was indeed an urgency of judicial intervention (as to
(RTC) of Quezon City. The RTC granted the Petition in its October 11, 2002 Decision, warrant the issuance of a writ of mandamus despite the exclusive jurisdiction of the
which was later affirmed by the Court of Appeals (CA). Meanwhile, on November 25, DENR) was ultimately connected to the truth of Picop’s assertions, which were
2002, President Gloria Macapagal-Arroyo issued Proclamation No. 297, “Excluding a hypothetically admitted in the Motion to Dismiss filed by the DENR. In other words,
the issue still boiled down to whether petitioner had committed grave abuse of Lara received a Stoppage Order from Cagayan Governor Alvaro T. Antonio (Gov.
discretion in not executing the IFMA documents and in not approving respondent’s Antonio), directing him to stop his quarrying operations for the following reasons: (a)
harvesting of timber from the area of TLA No. 43. Hence, the mandamus case could the ISAG Permit was not in accordance with Republic Act No. (RA) 7942, otherwise
not have been subjected to outright dismissal. Another issue raised by the DENR known as the "Philippine Mining Act of 1995," and its implementing rules and
concerned Section 1 of Presidential Decree (PD) No. 605 which, according to the CA, regulations; (b) Lara's failure to pay sand and gravel fee under Provincial Ordinance
had been partly repealed by Republic Act 8975. Republic Act 8975 was not intended No. 2005-07; and (c) [Lara's] failure to secure all necessary permits or clearances
to set forth in full all laws concerning the prohibition on temporary restraining orders, from the local government unit concerned as required by the [ECC].
preliminary injunctions and preliminary mandatory injunctions. This law prohibited
lower courts from issuing such orders in connection with the implementation of Lara maintains that the MGB and DENR-EMB had already authorized him to extract
government infrastructure projects. On the other hand, PD 605 prohibited the sand and gravel from the Permit Area, as evidenced by the ISAG Permit and ECC,
issuance of these orders in any case involving licenses, concessions and the like, in thereby dispensing with the need to secure any permit from the local government. In
connection with the natural resources of the Philippines. When the licenses, any case, he contends that the only reason why he failed to secure such permits was
concessions and the like also entailed government infrastructure projects, however, because the local government officials deliberately refused to process his applications
the provisions of Republic Act 8975 were deemed to apply. Thus, PD 605 was without any legitimate reason whatsoever.
modified in this sense. In Datiles and Co. v. Sucaldito, the Court held that the
Issue:
prohibition in PD 605 “pertains to the issuance of injunctions or restraining orders by
courts against administrative acts in controversies involving facts or the exercise of WON Lara is entitled to continue his quarrying operations.
discretion in technical cases, because to allow courts to judge these matters could
disturb the smooth functioning of the administrative machinery. But on issues Ruling:
definitely outside of this dimension and involving questions of law, courts are not
prevented by Presidential Decree No. 605 from exercising their power to restrain or No.
prohibit administrative acts.” While there were indeed questions of fact in the present In order for an entity to legally undertake a quarrying business, he must first comply
Petitions, the overriding controversy involved was one of law: whether the with all the requirements imposed not only by the national government, but also by
Presidential Warranty issued by former President Marcos was a contract within the the local government unit where his business is situated.
purview of the Constitution’s Non Impairment Clause. Accordingly, the prohibition in
PD 605 against the issuance of preliminary injunction in cases involving permits for Section 138(2) of RA 7160:
the exploitation of natural resources was inapplicable to this case. Moreover, as the
Court held in Republic v. Nolasco, [1] statutes such as PD 605, PD 1818 and Republic SECTION 138. Tax on Sand, Gravel and Other Quarry Resources.
Act 8975 merely proscribed the issuance of temporary restraining orders and writs of
The permit to extract sand, gravel and other quarry resources shall be issued
preliminary injunction and preliminary mandatory injunction. They could not, under
exclusively by the provincial governor, pursuant to the ordinance of the sangguniang
pain of violating the Constitution, deprive the courts of authority to take cognizance of
panlalawigan.
issues raised in the principal action, as long as that action and the relief sought were
within their jurisdiction. Provincial Ordinance No. 2005-07
Province of Cagayan vs. Lara SECTION 2H.04. Permit for Gravel and Sand Extraction and Quarrying. No person
shall extract ordinary stones, gravel, earth, boulders and quarry resources from public
Facts:
lands or from the beds of seas, rivers, streams, creeks or other public waters unless a
Lara obtained an Industrial Sand and Gravel Permit (ISAG Permit) from the Mines permit has been issued by the Governor (or his deputy as provided herein) x x x.
and Geosciences Bureau (MGB) of the Department of Environment and Natural
A plain reading of the afore-cited provisions clearly shows that a governor's permit is
Resources (DENR), authorizing him to conduct quarrying operations in a twenty-
a pre-requisite before one can engage in a quarrying business in Cagayan. Records,
hectare area situated in Cagayan (Permit Area) and extract and dispose of sand,
however, reveal that Lara admittedly failed to secure the same; hence, he has no right
gravel, and other unconsolidated materials from the Permit Area. For the same
to conduct his quarrying operations within the Permit Area. Consequently, he is not
purpose, Lara obtained an Environmental Compliance Certificate (ECC) from the
entitled to any injunction.
DENR Environmental Management Bureau (EMB).
Special People vs Canda
Because of Refusal of ENRO Adap to issue and Order of Payment, Lara deposited the
amount of P51, 500.00 with the Treasurer’s Office corresponding to the extraction fee Facts:
and other fees.
The petitioner was a proponent of a water-resource development and utilization Accordingly, the Court is called upon to resolve, firstly, whether the appeal directly to
project in Barangay Jimilia-an in the Municipality of Loboc, Bohol that would involve this Court from the RTC was proper, and, secondly, whether the petition for
the tapping and purifying of water from the Loboc River, and the distribution of the mandamus was the correct recourse.
purified water to the... residents of Loboc and six other municipalities.seeking to be
exempt from the requirement of... the Environmental Compliance Certificate (ECC) Held
under Section 4 of Presidential Decree No. 1586
RTC dismissed the petition for mandamus. Mandamus was an improper remedy for
Upon evaluating the nature and magnitude of the environmental impact of the petitioner,
project, respondent Nestor M. Canda, then Chief of EMB in Bohol, rendered his
We dismiss the present recourse because the petitioner failed to exhaust the available
findings in a letter dated December 4, 2001, as follows:
administrative remedies, and because it failed to show that it was legally entitled to
The project is located within a critical area; hence, Initial Environmental Examination demand the performance of the act by the respondents.
is required.
Accordingly, the petitioner should have appealed the EMB Regional Director's
The project is socially and politically sensitive therefore proof of social acceptability decision to the EMB Director who exercised supervision and control over the former.
should be established. Proper indorsement from the [Protected Area Management
It is relevant to mention that the DENR later promulgated Administrative Order No.
Bureau or] PAMB should be secured.[2] (Emphasis supplied)...
2003-30[23] in order to define where appeals should be taken
The petitioner appealed Canda's findings to respondent EMB Region 7 Director
Another reason for denying due course to this review is that the petitioner did not
Bienvenido L. Lipayon (RD Lipayon), claiming that it should also be issued a CNC
establish that the grant of its application for the CNC was a purely ministerial in
because the project was no different from the Loboc-Loay waterworks project of the
nature on the part of RD Lipayon. Hence, mandamus was not a proper remedy.
Department ofPublic Works and Highways (DPWH) that had recently been issued a
CNC. The foregoing considerations indicate that the grant or denial of an application for
ECC/CNC is not an act that is purely ministerial in nature, but one that involves the
RD Lipayon required the petitioner to submit certain certifications from different
exercise of judgment and discretion by the EMB Director or Regional Director, who
government agencies to enable the EMB to determine whether the project was within
must determine whether the... project or project area is classified as critical to the
an environmentally critical area or not.
environment based on the documents to be submitted by the applicant.
Petitioner failed to secure a certification from the Regional Office of the Mines and
The petitioner errs on two grounds.
Geosciences Bureau (RO-MGB), the petitioner filed a petition for mandamus and
damages in the Regional Trial Court (RTC) in Loay, Bohol,[12] alleging that it was Firstly, RD Lipayon had not yet fully exercised his discretion with regard to the CNC
now entitled to a CNC as a matter of right after having complied with the certification application when he made his finding.
requirements; and that the EMB had earlier issued a CNC to the DPWH for a similar
waterworks project in the same area. Secondly, there is no sufficient showing that the petitioner satisfactorily complied
with the requirement to submit the needed certifications.
RD Lipayon and Canda aver that the act complained of against them involved an
exercise of discretion that could not be compelled by mandamus that the petitioner's WHEREFORE, the Court DENIES the petition for review on certiorari; and ORDERS
proposed project was located within an environmentally critical area, and the the petitioner to pay the costs of suit
activitiesto be done were so significant that they would create massive earth
movement and environmental degradation; that the petitioner violated the rule
against forum shopping; and that the petitioner had no cause of action against them
for failure to exhaust administrative remedies.

Issue

WHETHER OR NOT, AFTER PETITIONER'S DUE COMPLIANCE WITH THE


REQUIREMENTS MANDATED BY RESPONDENTS FOR THE ISSUANCE OF THE
CERTIFICATE OF NON- COVERAGE (CNC) APPLIED FOR BY PETITIONER, IT IS
NOW THE RIPENED DUTY OF RESPONDENTS, THROUGH RESPONDENT EMB
REGIONALDIRECTOR, TO ISSUE SAID DOCUMENT IN FAVOR OF PETITIONER
RULE 4 NCIP Compliance Certificate was issued to 168 FPMC as proof that there was free and
prior consent from the indigenous cultural communities affected. Also, the One Stop
Alecha vs. Atienza Shop Committee of the DENR-MGB-RIX screened the subject mining application to
ensure that the covered areas do not fall within any reservation or declared protected
Facts:
area.
Cebu Ore and Mineral Resources Corporation (Cebu Ore) filed an application for the
Factual considerations relating to mining applications properly rest within the
approval of the Mineral Production Sharing Agreement (subject mining agreement),
administrative competence of the DENR. Its factual findings are accorded great
covering an area of about 8,100 hectares located in the municipalities of Midsalip and
respect and even finality by the appellate courts because it possesses the specialized
Bayog, Zamboanga del Sur. Cebu Ore later on assigned to 168 FPMC its rights over
knowledge and expertise in its field. (XPN: Grave abuse of discretion which was not
the mining agreement. Jose L. Atienza, Jr., then DENR Secretary, granted the mining
proved in this case).
agreement to 168 FPMC.
RULE 7 AND 8
Alecha, et. al. filed a petition for cancellation of the mining agreement alleging that
168 FPMC failed to secure the Free and Prior Informed Consent (FPIC) of the [RULE 7: WRIT OF KALIKASAN] -- LNL Archipelago Minerals Inc. vs Agham Party
Indigenous Peoples (IP) concerned for the approval of the mining agreement. They List
also alleged that the contract area under the mining agreement was located in the J. Carpio
volcanic cones of Mt. Sugarloaf Complex, a known key biodiversity area and forest
reserve, thus rendering it exempt from any mining application. Lastly, they submitted
that the proposed operation would destroy the lives of the Zamboanga Peninsula
residents. Doctrine: The following requisites must be present to avail of this remedy: (1) there is
an actual or threatened violation of the constitutional right to a balanced and
168 FPMC denied the allegations and insisted that it had observed the FPIC process. healthful ecology; (2) the actual or threatened violation arises from an unlawful act or
It submitted the National Commission on Indigenous Peoples (NCIP) Compliance omission of a public official or employee, or private individual or entity; and (3) the
Certificate (Certification Precondition) as proof of its compliance with the FPIC actual or threatened violation involves or will lead to an environmental damage of
process. The 168 FPMC also claimed that the nearest volcanic cones of Mt. Sugarloaf such magnitude as to prejudice the life, health or property of inhabitants in two or
Complex cones are located 9 kilometers away from the contract area. more cities or provinces.

DENR dismissed the petition. The DENR Secretary also held that the Certification FACTS:
Precondition was the best evidence that 168 FPMC complied with the FPIC process.
Petitioner LNL Archipelago Minerals, Inc. (LAMI) is the operator of a mining claim
Issue: located in Sta. Cruz, Zambales. LAMI embarked on a project to build a private, non-
commercial port in Brgy. Bolitoc, Sta. Cruz, Zambales. A port is a vital infrastructure
WON DENR Secretary gravely abused his discretion when he dismissed the petition to the operations of a mining company to ship out ores and other minerals extracted
for cancellation of the 168 FPMC mining agreement. from the mines and make the venture economically feasible. Brgy. Bolitoc, about 25
kilometers away from the mine site, makes it an ideal location to build a port facility
Ruling:
LAMI secured the following permits and compliance certificates for the port project:
No. (1) Department of Environment and Natural Resources (DENR) Environmental
Compliance Certificate5 (ECC) The Bolitoc community – the barangay, its officials
We find that the DENR Secretary did not gravely abuse his discretion in taking and residents – gave several endorsements12 supporting the project. Even the
judicial notice of the documents submitted for 168 FPMC's application for the mining Sangguniang Bayan of Sta. Cruz gave its consent to the construction of the port
agreement that showed compliance with the FPIC process and all the legal
requirements for the approval of the mining agreement. However, LAMI allegedly encountered problems from the local government of Sta.
Cruz, headed by Mayor Luisito E. Marty (Mayor Marty). Mayor Marty unduly favored
DENR Secretary took judicial notice of the documents submitted for the approval of some mining companies in the municipality and allegedly refused to issue business
the subject mining agreement which were already in his possession by reason of his and mayor’s permits despite the necessary national permits and licenses secured by
office and were either posted in a conspicuous place, published in a newspaper of the other mining companies. DENR Environmental Management Bureau in Region
general circulation, or its contents announced through the radio. The DENR Secretary III (DENR-EMB R3) received a letter from Mayor Marty inquiring if the ECC the
merely confirmed the 168 FPMC's allegation in its Answer that it had complied with DENR issued in favor of LAMI allowed LAMI to cut trees and level a mountain. The
the legal process laid down by law and obtained the consent of the IPs concerned for DENR PENRO team found that LAMI violated some of its conditions under the ECC.
the approval of the mining agreement. Accordingly, a Notice of Violation (NOV) was issued against LAMI for violation of
certain conditions of the ECC with a cease and desist order from further constructing prejudice the life, health or property of inhabitants in two or more cities or provinces.
and developing until such time that the ECC conditions were fully complied. DENR- The writ is available against an unlawful act or omission of a public official or
EMB R3, Mines and Geosciences Bureau (MGB) R3 and PENRO Zambales, conducted employee, or private individual or entity.
an investigation to determine whether mitigating measures done by LAMI were
sufficient. The composite team found that LAMI’s activities in its property would not The following requisites must be present to avail of this remedy: (1) there is an actual
result to any environmental damage to its surrounding communities. Thereafter, the or threatened violation of the constitutional right to a balanced and healthful ecology;
DENR-EMB R3 lifted the cease and desist order after LAMI was found to have (2) the actual or threatened violation arises from an unlawful act or omission of a
complied with the requirements. public official or employee, or private individual or entity; and (3) the actual or
threatened violation involves or will lead to an environmental damage of such
Respondent Agham Party List (Agham), through its President, former Representative magnitude as to prejudice the life, health or property of inhabitants in two or more
Angelo B. Palmones (Rep. Palmones), filed a Petition21 for the issuance of a Writ22 of cities or provinces.
Kalikasan against LAMI
In the present case, Agham, in its Petition for a Writ of Kalikasan, cited two laws
Agham alleged that LAMI violated: (1) Section 6823 of PD No. 705,24 as amended by which LAMI allegedly violated: (1) Section 68 of the Revised Forestry Code, as
Executive Order No. 277,25 or the Revised Forestry Code; and (2) Sections 5726 and amended; and (2) Sections 57 and 69 of the Philippine Mining Act.
6927 of Republic Act No. 7942,28 or the Philippine Mining Act of 1995 (Philippine Section 2(c), Rule 7, Part III of the Rules of Procedure for Environmental Cases
Mining Act). Agham added that LAMI cut mountain trees and flattened a mountain provides: Section 2. Contents of the petition. - The verified petition shall contain the
which serves as a natural protective barrier from typhoons and floods not only of the following: (c) The environmental law, rule or regulation violated or threatened to be
residents of Zambales but also the residents of some nearby towns located in violated, the act or omission complained of, and the environmental damage of such
Pangasinan. magnitude as to prejudice the life, health or property of inhabitants in two or more
cities or provinces.
This Court remanded the petition29 to the Court of Appeals for hearing, reception of
evidence and rendition of judgment. LAMI stated further that there is no The Rules are clear that in a Writ of Kalikasan petitioner has the burden to prove the
environmental damage of such magnitude as to prejudice the life, health, or property (1) environmental law, rule or regulation violated or threatened to be violated; (2) act
of inhabitants in two or more cities and provinces. The Court of Appeals decided the or omission complained of; and (3) the environmental damage of such magnitude as
case in favor of petitioner. Thus, for failing to comply with the requisites necessary for to prejudice the life, health or property of inhabitants in two or more cities or
the issuance of a Writ of Kalikasan, the Court of Appeals resolved to deny the petition. provinces.
Agham filed a Motion for Reconsideration with the Court of Appeals. In an Amended
Decision, the Court of Appeals reversed and set aside its original Decision and granted It is well-settled that a party claiming the privilege for the issuance of a Writ of
the petition for WRIT OF KALIKASAN. Hence, the instant petition. Kalikasan has to show that a law, rule or regulation was violated or would be violated.
In the present case, the allegation by Agham that two laws – the Revised Forestry
The Issues: The issues for our resolution are (1) whether LAMI violated the Code, as amended, and the Philippine Mining Act – were violated by LAMI was not
environmental laws as alleged by Agham, and (2) whether LAMI flattened any adequately substantiated by Agham. Even the facts submitted by Agham to establish
mountain and caused environmental damage of such magnitude as to prejudice the environmental damage were mere general allegations.
life, health or property of inhabitants in two or more cities or provinces. ----- W/N the
petition for Writ of Kalikasan should be granted. Second, Agham’s allegation that there was a "mountain" in LAMI’s port site was
earlier established as false as the "mountain" was non-existent as proven by the
RULING: NO -- The present case involves the extraordinary remedy of a Writ of testimonies of the witnesses and reports made by environmental experts and persons
Kalikasan which is under the Rules of Procedure for Environmental Cases.42 Section who have been educated and trained in their respective fields.
1, Rule 7, Part III of the said Rules provides: Section 1. Nature of the writ. – The writ
is a remedy available to a natural or juridical person, entity authorized by law, Last, the alleged scraping off or leveling of land at LAMI’s port site is deemed
people’s organization, non-governmental organization, or any public interest group insignificant to pose a detrimental impact on the environment. the cut and fill
accredited by or registered with any government agency, on behalf of persons whose operations of LAMI only affected the port site but not the surrounding area and that
constitutional right to a balanced and healthful ecology is violated, or threatened with the environmental effect was only minimal and insignificant and temporary and
violation by an unlawful act or omission of a public official or employee, or private nature, and it does not in any way affect or cannot affect the Province of Pangasinan
individual or entity, involving environmental damage of such magnitude as to as alleged.
prejudice the life, health or property of inhabitants in two or more cities or provinces.
In sum, the SC finds that In sum, SC finds that LAMI did not cause any environmental
The Writ of Kalikasan, categorized as a special civil action and conceptualized as an damage that prejudiced the life, health or property of the inhabitants residing in the
extraordinary remedy covers environmental damage of such magnitude that will municipality of Sta. Cruz, the province of Zambales or in the neighboring province of
Pangasinan. Agham, as the party that has the burden to prove the requirements for liability by placing blame on the construction activities on the roads surrounding
the issuance of the privilege of the Writ ofKalikasan, failed to prove (1) the West Tower.
environmental laws allegedly violated by LAMI; and (2) the magnitude of the
environmental damage allegedly caused by LAMI in the construction of LAMI' s port On November 15, 2010, West Tower Condominium Corporation (West Tower Corp.)
facility in Brgy. Bolitoc, Sta. Cruz, Zambales and its surrounding area. Thus, the interposed the present Petition for the Issuance of a Writ of Kalikasan on behalf of the
petition for the issuance of the privilege of the Writ of Kalikasan must be denied. residents of West Tower and in representation of the surrounding communities in
Barangay Bangkal, Makati City. West Tower Corp. also alleged that it is joined by the
WEST TOWER CONDOMINIUM CORPORATION, on behalf of the Residents of West civil society and several people's organizations, nongovernmental organizations and
Tower Condominium and in representation of Barangay Bangkal, and others, public interest groups who have expressed their intent to join the suit because of the
including minors and generations yet unborn,Petitioners, vs. FIRST PHILIPPINE magnitude of the environmental issues involved.1
INDUSTRIAL CORPORATION, FIRST GEN CORPORATION and their RESPECTIVE
BOARD OF DIRECTORS AND OFFICERS, JOHN DOES, and RICHARD DOES, In their petition, petitioners prayed that respondents FPIC and its board of directors
Respondents. (VELASCO, JR., J.) and officers, and First Gen Corporation (FGC) and its board of directors and officers
be directed to: (1) permanently cease and desist from committing acts of negligence in
Facts: Before the Court is the Petition for the Issuance of a Writ of Kalikasan filed the performance of their functions as a common carrier; (2) continue to check the
following the leak in the oil pipeline owned by First Philippine Industrial Corporation structural integrity of the whole 117-kilometer pipeline and to replace the same; (3)
(FPIC) in Makati City. make periodic reports on their findings with regard to the 117-kilometer pipeline and
their replacement of the same; (4) rehabilitate and restore the environment, especially
Respondent FPI C operates two pipelines since 1969, viz: ( 1) the White Oil Pipeline Barangay Bangkal and West Tower, at least to what it was before the signs of the leak
(WOPL) System, which covers a 117-kilometer stretch from Batangas to the Pandacan became manifest; and (5) to open a special trust fund to answer for similar and future
Terminal in Manila and transports diesel, gasoline, jet fuel and kerosene; and (b) the contingencies in the future. Furthermore, petitioners pray that respondents be
Black Oil Pipeline (BOPL) System which extends 105 kilometers and transports prohibited from opening the pipeline and allowing the use thereof until the same has
bunker fuel from Batangas to a depot in Sucat, Parañaque. These systems transport been thoroughly checked and replaced, and be temporarily restrained from operating
nearly 60% of the petroleum requirements of Metro Manila and parts of the provinces the pipeline until the final resolution of the case.
of Bulacan, Laguna, and Rizal.
On November 19, 2010, the Court issued the Writ of Kalikasan2 with a Temporary
In May 2010, however, a leakage from one of the pipelines was suspected after the Environmental Protection Order (TEPO) requiring respondents FPIC, FGC, and the
residents of West Tower Condominium (West Tower) started to smell gas within the members of their Boards of Directors to file their respective verified returns. The
condominium. A search made on July 10, 2010 within the condominium premises led TEPO enjoined FPIC and FGC to: (a) cease and desist from operating the WOPL until
to the discovery of a fuel leak from the wall of its Basement 2. Owing to its inability to further orders; (b) check the structural integrity of the whole span of the 11 7-
control the flow, West Tower's management reported the matter to the Police kilometer WOPL while implementing sufficient measures to prevent and avert any
Department of Makati City, which in turn called the city's Bureau of Fire Protection. untoward incident that may result from any leak of the pipeline; and ( c) make a
report thereon within 60 days from receipt thereof.
What started as a two-drum leak at the initial stages became a 15-20 drum a day
affair. Eventually, the sump pit of the condominium was ordered shut down by the They alleged... that: petitioners had no legal capacity to institute the petition; there is
City of Makati to prevent the discharge of contaminated water into the drainage no allegation that the environmental damage affected the inhabitants of two (2) or
system of Barangay Bangkal. Eventually, the fumes compelled the residents of West more cities or provinces; and the continued operation of the pipeline should be
Tower to abandon their respective units on July 23, 2010 and the condo's power was allowed in the interest of maintaining... adequate petroleum supply to the public.
shut down.
Verified Return... claiming that not all requirements for the issuance of the Writ of
Petitioner FPIC initially disowned any leak from its oil pipeline. Thus, the residents of Kalikasan are present and there is no showing that West Tower Corp. was authorized
West Tower shouldered the expenses of hauling the waste water from its basement, by all those it claimed to represent.
which eventually required the setting up of a treatment plant in the area to separate
fuel from the waste water. On October 28, Issues:

2010, the University of the Philippines-National Institute of Geological Sciences (UP- 1. Whether petitioner West Tower Corp. has the legal capacity to represent the other
NIGS), which the City of Makati invited to determine the source of the fuel, found a petitioners and whether the other petitioners, apart from the residents of West Tower
leak in FPIC's WOPL about 86 meters from West Tower. and Barangay Bangkal, are real parties-in-interest;

A day after, or on October 29, 2010, FPIC admitted that indeed the source of the fuel
leak is the WOPL, which was already closed since October 24, 2010, but denied
2. Whether a Permanent Environmental Protection Order should be issued to direct Resolution. We deemed it proper to require said certification from the DOE
the respondents to perform or to desist from performing acts in order to protect, considering that the core issue of this case requires the specialized knowledge and
preserve, and rehabilitate the affected environment; special expertise of the DOE and various other administrative agencies. On October
25, 2013, the DOE submitted the certification pursuant to the July 30, 2013
Resolution of the Court. Later, however, on August 5, 2014, DOE Secretary Carlos
3. Whether a special trust fund should be opened by respondents to answer for future Jericho I. Petilla submitted a letter recommending certain activities and the timetable
similar contingencies; for the resumption of the WOPL operations after conducting a dialogue between the
concerned government agencies and FPIC.
4. Whether FGC and the directors and officers of respondents FPIC and FGC may be Propriety of the Creation of a Special Trust Fund
held liable under the environmental protection order.
A reading of the petition and the motion for partial reconsideration readily reveals
Ruling: that the prayer is for the creation of a trust fund for similar future contingencies. This
is clearly outside the limited purpose of a special trust fund under the Rules of
Petitioners as Real Parties-in-Interest
Procedure for Environmental Cases, which is to rehabilitate or restore the
We agree with the CA that petitioners who are affected residents of West Tower and environment that has presumably already suffered. Hence, the Court affirms with
Barangay Bangkal have the requisite concern to be real parties-in-interest to pursue concurrence the observation of the appellate court that the prayer is but a claim for
the instant petition. Organizations that indicated their intention to join the petition damages, which is prohibited by the Rules of Procedure for Environmental Cases. As
and submitted proof of juridical personality including the Catholic Bishops' such, the Court is of the considered view that the creation of a special trust fund is
Conference of the Philippines, Kilusang Makabansang Ekonomiya, Inc., Women's misplaced. The present ruling on petitioners' prayer for the creation of a special trust
Business Council of the Philippines, Inc., Junior Chambers International Philippines, fund in the instant recourse, however, is without prejudice to the judgment/s that
Inc. - San Juan Chapter, Zonta Club of Makati Ayala Foundations, and the may be rendered in the civil and/or criminal cases filed by petitioners arising from the
Consolidated Mansions Condominium Corporation, as petitioners in the case, the same incident if the payment of damages is found warranted.
Court already granted their intervention in the present controversy in the adverted
Liability of FPIC, FGC and their respective Directors and Officers
July 30, 2013 Resolution. This is so considering that the filing of a petition for the
issuance of a writ of kalikasan under Sec. 1, Rule 7 of the Rules of Procedure for The Court will refrain from ruling on the finding of the CA that the individual
Environmental Cases does not require that a petitioner be directly affected by an directors and officers of FPIC and FGC are not liable due to the explicit rule in the
environmental disaster. The rule clearly allows juridical persons to file the petition on Rules of Procedure for Environmental cases that in a petition for a writ of kalikasan,
behalf of persons whose constitutional right to a balanced and healthful ecology is the Court cannot grant the award of damages to individual petitioners under Rule 7,
violated, or threatened with violation. Sec. 15(e) of the Rules of Procedure for Environmental Cases. As duly noted by the
CA, the civil case and criminal complaint filed by petitioners against respondents are
Propriety of Converting the TEPO to PEPO or its Lifting in light of the DOE
the proper proceedings to ventilate and determine the individual liability of
Certification of the WOPL's Commercial Viability
respondents, if any, on their exercise of corporate powers and the management of
With respect to leak detection, FPIC claims that it has in place systems that seeks to FPIC relative to the dire environmental impact of the dumping of petroleum products
regulate and check the pipelines in place. stemming from the leak in the WOPL in Barangay Bangkal, Makati City. Hence, the
Court will not rule on the alleged liability on the part of the FPIC and FGC officials
The CA, however, observed that all of these tests and measures are inconclusive and which can, however, be properly resolved in the civil and criminal cases now pending
insufficient for purposes of leak detection and pipeline integrity maintenance. Hence, against them.
considering the necessary caution and level of assurance required to ensure that the
WOPL system is free from leaks and is safe for commercial operation, the CA Segovia v Climate Change Commission
recommended that FPIC obtain from the DOE a certification that the WOPL is already
Doctrine: Mandamus lies to compel the performance of duties that are purely
safe for commercial operation. This certification, according to the CA, was to be
ministerial in nature, not those that are discretionary, and the official can only be
issued with due consideration of the adoption by FPIC of the appropriate leak
directed by mandamus to act but not to act one way or the other.
detection systems to monitor sufficiently the entire WOPL and the need to replace
portions of the pipes with existing patches and sleeves. Sans the required certification, Ponente: Justice Caguioa
use of the WOPL shall remain abated.
Facts: To address the clamor for a more tangible response to climate change, Former
The Court found this recommendation of the appellate court proper. Hence, We Pres. Arroyo issued AO 171 which created the Presidential Task Force on Climate
required FPIC to obtain the adverted DOE Certification in Our July 30, 2013 Change (PTFCC). It was reorganized through EO 774, which contained the Road
Sharing Principle: “Those who have less in wheels must have more in road.” In 2009, It is well-settled that a party claiming the privilege for the issuance of a writ of
AO 254 was issued mandating DOTC to formulate a nation Environmentally kalikasan has to show that a law, rule or regulation was violated or would be violated.
Sustainable Transport Strategy, which similarly included the Road Sharing Principle. In this case, there was none. The correlations made by the petitioners on the current
Later, Congress passed the Climate Change Act which created the Climate Change state of air quality, alleging that it was a result of failure to implement the
Commission and absorbed the functions of the PTFCC. Then, petitioners requested environmental laws lacks merit. On the contrary, respondents have shown that they
the CCC to implement the Road Sharing Principle but did not receive a response. were indeed able to implement the law through different projects and actions.
Hence, this petition.
Similarly, the writ of continuing mandamus cannot issue.
The petitioners filed for the issuance of writs of kalikasan and continuing mandamus
to compel the implementation of the Climate Change Act, Clean Air Act, EO 774, AO First, the petitioners failed to show they suffered personal injury.
254 and AO 171. They contend that respondents’ failure to implement the foregoing
Second, the Road Sharing Principle is precisely as it is denominated – a principle.
resulted in the violation of their right to a healthful and balanced ecology.
Unless there were specific provisions in the law requiring the implementing agencies
Issues: to take a specific course of action to implement the principle, then they cannot be
compelled to do so, and failure to do so will not make them liable. Mandamus lies to
WoN the petitioners have standing compel the performance of duties that are purely ministerial in nature, not those that
are discretionary, and the official can only be directed by mandamus to act but not to
WoN the petition should be dismissed for failure to adhere to the doctrine of the act one way or the other. The duty being enjoined in mandamus must be one
hierarchy of courts according to the terms provided in the law itself. Thus, the recognized rule is that, in
the performance of an official duty or act involving discretion, the corresponding
WoN a writ of kalikasan and/or continuing mandamus should issue
official can only be directed by mandamus to act, but not to act one way or the other.
Held:
In this case, what the petitioners are seeking is to compel the performance not of a
For the writ of kalikasan, yes. For the writ of continuing mandamus, no. The RPEC ministerial act, but a discretionary act.
liberalized the requirements on standing, allowing the filing of citizen suits for the
Rule 8
enforcement of rights and obligations under environmental laws. However, while in a
petition for the issuance of a writ of kalikasan, it is sufficient that the person filing INTERNATIONAL SERVICE FOR THE ACQUISITION OF AGRI-BIOTECH
represents the inhabitants prejudiced by the environmental damage subject of the APPLICATIONS, INC.,
writ, a petition for the issuance of a writ of continuing mandamus is only available to vs. GREENPEACE SOUTHEAST ASIA (PHILIPPINES)
one who is personally aggrieved by the unlawful act or omission.
PERLAS-BERNABE, J.:
No. A direct resort to the Supreme Court for the issuance of a writ of kalikasan may be
allowed by way of exception where its necessity is dictated by public welfare. Thus, it Respondents' petition for Writ of Kalikasan was already mooted by the expiration of
is ultimately within the Court’s discretion whether or not to accept the petitions the Biosafoty Permits and the completion of the field trials subject of these cases, and
brought before it. with none of the exceptions to the mootness principle properly attending, the Court
grants the instant motions for reconsideration and hereby dismisses the aforesaid
No. Both petitions must fail.
petition. With this pronouncement, no discussion on the substantive merits of the
For a writ of kalikasan to issue, the following requisites must concur: same should be made.

1. There is an actual or threatened violation of the constitutional right to a balanced Background:


and healthful ecology;
The instant case arose from the conduct of field trials for "bioengineered eggplants,"
2. The actual or threatened violation arises from an unlawful act or omission of a known as Bacillus thuringiensis (Bt) eggplant (Bt talong), administered pursuant to
public official or employee, or private individual or entity; and the Memorandum of Undertaking (MOU) entered into by herein petitioners
University of the Philippines Los Baños Foundation, Inc. (UPLBFI) and International
3. The actual or threatened violation involves or will lead to an environmental damage Service for the Acquisition of Agri-Biotech Applications, Inc. (ISAAA), and the
of such magnitude as to prejudice the life, health or property of inhabitants in two or University of the Philippines Mindanao Foundation, Inc. (UPMFI), among others. Bt
more cities or provinces. talong contains the crystal toxin genes from the soil bacterium Bt, which produces
the CrylAc protein that is toxic to target insect pests. The CryAc protein is said to be
highly specific to lepidopteran larvae such as the fruit and shoot borer, the most and buried following the conditions of the Biosafety Permits; and (e) the
destructive insect pest to eggplants. precautionary principle could not be applied as the field testing was only a part of a
continuing study to ensure that such trials have no significant and negative impact on
From 2007 to 2009, petitioner University of the Philippines Los Banos (UPLB), the the environment.
implementing institution of the field trials, conducted a contained experiment on Bt
talong under the supervision of the National Committee on Biosafety of the In a Decision35 dated May 17, 2013, the CA ruled in favor of respondents and directed
Philippines (NCBP) to identify and evaluate potential hazards involved in initiating petitioners to pemanently cease and desist from conducting the Bt talong field
genetic engineering experiments or the introduction of new species and genetically trials.36 At the outset, it did not find merit in petitioners' contention that the case
engineered organisms and recommend measures to minimize risks"; should be dismissed on the ground of mootness, noting that the issues raised by the
and (b) ''formulate and review national policies and guidelines on biosafety. latter were "capable of repetition yet evading review" since the Bt talong field trial was
just one of the phases or stages of an overall and bigger study that is being conducted
On March 16, 2010 and June 28, 2010, the Bureau of Plant Industries (BPI) issued in relation to the said genetically-modified organism.37 It then held that the
two (2)-year Biosafety Permits for field testing of Bt talong after UPLB's field test precautionary principle set forth under Section 1,38 Rule 20 of the Rules of Procedure
proposal satisfactorily completed biosafety risk assessment for field testing pursuant for Environmental Cases39 is relevant, considering the Philippines' rich biodiversity
to the Department of Agriculture's (DA) Administrative Order No. 8, series of 2002. and uncertainty surrounding the safety of Bt talong. It noted the possible irreversible
Consequently, field testing proceeded in approved trial sites in North Cotabato, effects of the field trials and the introduction of Bt talong to the market, and found the
Pangasinan, Camarines Sur, Davao City, and Laguna. existing regulations issued by the DA and the Department of Science and Technology
(DOST) insufficient to guarantee the safety of the environment and the health of the
Facts: On April 26, 2012, respondents Greenpeace Southeast Asia (Philippines)
people.40
(Greenpeace), Magsasaka at Siyentipiko sa Pagpapaunlad ng Agrikultura
(MASIPAG), and others (respondents) filed before the Court a Petition for Writ of Aggrieved, petitioners filed their respective petitions for review on certiorari before
Continuing Mandamus and Writ of Kalikasan with Prayer for the Issuance of a this Court.
Temporary Environmental Protection Order (TEPO)18 (petition for Writ
of Kalikasan) against herein petitioners the Environmental Management Bureau Issues:
(EMB) of the Department of Environment and Natural Resources (DENR), the BPI
and the Fertilizer and Pesticide Authority (FPA) of the DA, UPLBFI, and ISAAA, and (a) the case should have been dismissed for mootness in view of the completion and
UPMFI, alleging that the Bt talong field trials violated their constitutional right to termination of the Bt talong field trials and the expiration of the Biosafety Permits;
health and a balanced ecology considering, among others, that:
(b) the Court should not have ruled on the validity of DAO 08-2002 as it was not
(a) the Environmental Compliance Certificate (ECC), as required by Presidential
raised as an issue
Decree No. (PD) 1151, was not secured prior to the field trials;

(b) the required public consultations under the Local Government Code (LGC) were
not complied with; Ruling: respondents petition for Writ of Kalikasan, were mooted by the undisputed
expiration of the Biosafety Permits issued by the BPI and the completion and
(c) as a regulated article under DAO 08-2002, Bt talong is presumed harmful to
termination of the Bt talong field trials subject of the same.82 These incidents
human health and the environment, and that there is no independent, peer-reviewed
effectively negated the necessity for the reliefs sought by respondents in their petition
study showing its safety for human consumption and the environment.
for Writ of Kalikasan as there was no longer any field test to enjoin.
On May 2, 2012, the Court issued a Writ of Kalikasan against petitioners (except
UPLB) and UPMFI, ordering them to make a verified return within a non-extendible
period of ten (10) days, as provided for in Section 8, Rule 7 of the Rules of Procedure The Supreme Court of the Philippines upheld a lower court decision invalidating an
for Environmental Cases. Thus, in compliance therewith, ISAAA, EMB/BPI/FPA, administrative order governing import and release of genetically-modified organisms
UPLBFI, and UPMFI filed their respective verified returns, and therein maintained (GMOs) in the Philippines. The Court addressed a range of issues, from standing and
that: (a) all environmental laws were complied with, including the required public mootness to application of the precautionary principle. On the procedural claims by
consultations in the affected communities; (b) an ECC was not required for the field the petitioners that the case was moot and “academic” because all field trials had been
trials as it will not significantly affect the environment nor pose a hazard to human suspended, the Supreme Court found the paramount public interest in the case and
health; (c) there is a plethora of scientific works and literature, peer-reviewed, on the the fact that the legal issues were capable of repetition yet evading review justified the
safety of Bt talong for human consumption; (d) at any rate, the safety of Bt talong for Court’s review of the case. Page 38. The Court also noted the petitioners were
human consumption is irrelevant because none of the eggplants will be consumed by warranted in seeking judicial review because the biotechnology administrative
humans or animals and all materials not used for analyses will be chopped, boiled, framework does not provide “a speedy, or adequate remedy.”
In view of the great significance of the points involved in these matters, relating to the
protection and conservation of the forests throughout the country, the Court formed
The decision explains the current controversy over GMOs and, in particular, the opinion that the matters required a further indepth hearing to examine all the
genetically-modified food crops for human consumption. Drawing on research and aspects relation to the National Forest Policy.
case studies from around the world, and the testimony of expert witnesses, the
Supreme Court found there to be no consensus on the safety of Bt talong to humans It considered that certain interim directions were necessary to oversee the
and the environment, stating “[t]hese divergent views of local scientists reflect the enforcement of forest laws across the nation. The Court examined in detail all the
continuing international debate on GMOs and the varying degrees of acceptance of aspect of the National Forest Policy, the forest conservation act, 1980, which was
GM technology by states . . . .” The Court also cautioned that the “uncertainties enacted with a view to check further deforestation.
generated by conflicting scientific findings or limited research [are] not diminished by
extensive use at present of GM technology in agriculture.” Section 2 of the Forest Conservation Act specifies that no state government or other
authority may allow the use of any forest land for any non-forestry purpose without
prior approval from the Central Government.

Invoking the precautionary principle, the Supreme Court blocked further field trials of RULE 2,7,8
Bt talong until regulatory systems governing the import and release of GMOs are
strengthened. “When these features - uncertainty, the possibility of irreversible harm, Dolot vs Paje
and the possibility of serious harm - coincide, the case for the precautionary principle
Facts:
is strongest. When in doubt, cases must be resolved in favor of the constitutional right
to a balanced and healthful ecology.” The Court proceeded to nullify DAO 08-2002 On September 15, 2011, petitioner Maricris D. Dolot (Dolot), together with the parish
and enjoined applications for contained use, field testing, propagation and priest of the Holy Infant Jesus Parish and the officers of Alyansa Laban sa Mina sa
commercialization, and importation of any GMOs until a new administrative order is Matnog (petitioners), filed a petition for continuing mandamus, damages and
adopted. attorney’s fees with the RTC of Sorsogon, docketed as Civil Case No. 2011-8338.4 The
petition contained the following pertinent allegations: (1) sometime in 2009, they
protested the iron ore mining operations being conducted by Antones Enterprises,
All told, with respondents' petition for Writ of Kalikasan already mooted by the Global Summit Mines Development Corporation and TR Ore in Barangays Balocawe
expiration of the Biosafoty Permits and the completion of the field trials subject of and Bon-ot Daco, located in the Municipality of Matnog, to no avail; (2) Matnog is
these cases, and with none of the exceptions to the mootness principle properly located in the southern tip of Luzon and there is a need to protect, preserve and
attending, the Court grants the instant motions for reconsideration and hereby maintain the geological foundation of the municipality; (3) Matnog is susceptible to
dismisses the aforesaid petition. With this pronouncement, no discussion on the flooding and landslides, and confronted with the environmental dangers of flood
substantive merits of the same should be made. hazard, liquefaction, ground settlement, ground subsidence and landslide hazard; (4)
after investigation, they learned that the mining operators did not have the required
permit to operate; (5) Sorsogon Governor Raul Lee and his predecessor Sally Lee
issued to the operators a small-scale mining permit, which they did not have authority
to issue; (6) the representatives of the Presidential Management Staff and the
Department of Environment and Natural Resources (DENR), despite knowledge, did
not do anything to protect the interest of the people of Matnog;5 and (7) the
T.N. Godavarman VS. Union of India & Ors respondents violated Republic Act (R.A.) No. 7076 or the People’s Small-Scale Mining
Act of 1991, R.A. No. 7942 or the Philippine Mining Act of 1995, and the Local
2 SCC 267 (1997) Government Code.6 Thus, they prayed for the following reliefs: (1) the issuance of a
writ commanding the respondents to immediately stop the mining operations in the
Verma, J.Kirpal., B. Municipality of Matnog; (2) the issuance of a temporary environment protection
FACTS order or TEPO; (3) the creation of an inter-agency group to undertake the
rehabilitation of the mining site; (4) award of damages; and (5) return of the iron ore,
In 1995, T.N. Godavarman Thirumulkpad filed writ petition with the Supreme Court among others.7
of India to protect the Niligris Forest Land from Deforestation by illegal timber
operations. The case was referred by the Executive Judge to the RTC of Sorsogon, Branch 53
being the designated environmental court.8 In the Order9 dated September 16, 2011,
the case was summarily dismissed for lack of jurisdiction.
The petitioners filed a motion for reconsideration but it was denied in the The Court also finds that the RTC erred in ruling that the petition is infirm for failure
Resolution10 dated October 18, 2011. Aside from sustaining the dismissal of the case to attach judicial affidavits. As previously stated, Rule 8 requires that the petition
for lack of jurisdiction, the RTC11 further ruled that: (1) there was no final court should be verified, contain supporting evidence and must be accompanied by a sworn
decree, order or decision yet that the public officials allegedly failed to act on, which is certification of non-forum shopping. There is nothing in Rule 8 that compels the
a condition for the issuance of the writ of continuing mandamus; (2) the case was inclusion of judicial affidavits, albeit not prohibited. It is only if the evidence of the
prematurely filed as the petitioners therein failed to exhaust their administrative petitioner would consist of testimony of witnesses that it would be the time that
remedies; and (3) they also failed to attach judicial affidavits and furnish a copy of the judicial affidavits (affidavits of witnesses in the question and answer form) must be
complaint to the government or appropriate agency, as required by the rules attached to the petition/complaint

Issues: WoN Final Decision is needed for Continuing Mandamus

WoN RTC SORSOGON has Jurisdiction Continuing mandamus is a writ issued by a court in an environmental case directing
any agency or instrumentality of the government or officer thereof to perform an act
The RTC cannot solely rely on SC A.O. No. 7 and Admin. Circular No. 23-2008 and or series of acts decreed by final judgment which shall remain effective until judgment
confine itself within its four corners in determining whether it had jurisdiction over is fully satisfied. (Emphasis ours)
the action filed by the petitioners.
The final court decree, order or decision erroneously alluded to by the RTC actually
None is more well-settled than the rule that jurisdiction, which is the power and pertains to the judgment or decree that a court would eventually render in an
authority of the court to hear, try and decide a case, is conferred by law.16 It may environmental case for continuing mandamus and which judgment or decree shall
either be over the nature of the action, over the subject matter, over the person of the subsequently become final.
defendants or over the issues framed in the pleadings.17 By virtue of Batas Pambansa
(B.P.) Blg. 129 or the Judiciary Reorganization Act of 1980, jurisdiction over special Under the Rules, after the court has rendered a judgment in conformity with Rule 8,
civil actions for certiorari, prohibition and mandamus is vested in the RTC. Section 7 and such judgment has become final, the issuing court still retains
Particularly, Section 21(1) thereof provides that the RTCs shall exercise original jurisdiction over the case to ensure that the government agency concerned is
jurisdiction – performing its tasks as mandated by law and to monitor the effective performance of
said tasks. It is only upon full satisfaction of the final judgment, order or decision that
in the issuance of writs of certiorari, prohibition, mandamus, quo warranto, habeas a final return of the writ shall be made to the court and if the court finds that the
corpus and injunction which may be enforced in any part of their respective regions. judgment has been fully implemented, the satisfaction of judgment shall be entered in
(Emphasis ours) the court docket.34 A writ of continuing mandamus is, in essence, a command of
continuing compliance with a final judgment as it "permits the court to retain
A.O. No. 7 and Admin. Circular No. 23-2008 was issued pursuant to Section 18 of B.P.
jurisdiction after judgment in order to ensure the successful implementation of the
Blg. 129, which gave the Court authority to define the territory over which a branch of
reliefs mandated under the court’s decision
the RTC shall exercise its authority. These administrative orders and circulars issued
by the Court merely provide for the venue where an action may be filed. The Court
does not have the power to confer jurisdiction on any court or tribunal as the
allocation of jurisdiction is lodged solely in Congress.18 It also cannot be delegated to
another office or agency of the Government.19 Section 18 of B.P. Blg. 129, in fact,
explicitly states that the territory thus defined shall be deemed to be the territorial
area of the branch concerned for purposes of determining the venue of all suits,
Braga v. Abaya RULE 4-7-8
proceedings or actions
Brion, J.
The RTC need not be reminded that venue relates only to the place of trial or the
geographical location in which an action or proceeding should be brought and does Doctrine: Petition for Writ of Kalikasan cannot be invoked absent clear showing of the
not equate to the jurisdiction of the court. It is intended to accord convenience to the threatened environmental damage to 2 cities/municipalities, especially when project
parties, as it relates to the place of trial, and does not restrict their access to the is still under negotiation. Same rule applies with petition for Writ of CM due to
courts.22Consequently, the RTC’s motu proprio dismissal of Civil Case No. 2011-8338 absence of definite proponent who may be compelled under law.
on the ground of lack of jurisdiction is patently incorrect. It should have referred the
case to the appropriate venue which is the RTC of Irosin Facts:

WoN lack of JA is a ground for the immediate dismissal of the case. An urgent petition for a Writ of Continuing Mandamus and/or Writ of Kalikasan with
a prayer for issuance of TEPO
Filed against DOTC and Phil. Ports Authority assailing their modernization project of
the Sasa Wharf in Davao under the Public-Private Partnership Scheme (PPP)
RULE 9
Petitioner alleges that:
Monge v. People of the Philippines
DOTC issued the notice of public bidding despite failure to comply with the Local
Government Code which requires consultations with Sanggunian of Davao City TINGA, J.,

Failure to procure and ECC under PD 1586 Facts

Respondent, through OSG:

Invoked the prematurity of petition On 20 July 1994, petitioner Monge and Potencio were found by barangay tanods
Serdan and Molina in possession of and transporting three (3) pieces of mahogany
Project is still under bidding and thus there is no proponent yet of the project to lumber in Barangay Santo Domingo, Iriga City. Right there and then, the tanods
which the complaint may be filed against demanded that they be shown the requisite permit and/or authority from the
Department of Environment and Natural Resources (DENR) but neither petitioner
Even if there is, the proponent is not the government but the private party nor Potencio was able to produce any. Petitioner fled the scene in that instant whereas
Potencio was brought to the police station for interrogation, and thereafter, to the
Issue: WON petition is meritorious & writs prayed for can be granted
DENR-Community Environment and Natural Resources Office (DENR-CENRO).The
Held: DENR-CENRO issued a seizure receipt for the three pieces of lumber indicating that
the items, totaling 77 board feet of mahogany valued at P1,925.00, had been seized
Petition is not meritorious because it is PREMATURE. The project has not yet even from Potencio.
reached the construction stage.
At the 26 November 1996 arraignment, petitioner entered a negative plea.
Writ of Continuing Mandamus cannot be resorted to when:
Trial ensued. On 17 June 1997, Serdan testified on the circumstances of the
The respondent is NOT the person obliged to perform the duty under the law; or apprehension but for failing to appear in court for cross examination, his testimony
was stricken out. On 16 January 1998, Potencio was discharged to be used as a state
When the period for respondent to perform its legal duty has not yet expired witness on motion of the prosecutor.Accordingly, he testified on the circumstances of
Writ of Kalikasan cannot be granted the arrest but claimed that for a promised fee he was merely requested by petitioner,
the owner of the log, to assist him in hauling the same down from the mountain.
Condition sine qua non for this writ: Such magnitude that would negatively affect Potencios testimony was materially corroborated by Molina. Petitioner did not contest
health and cause environmental damage the allegations, except that it was not he but Potencio who owned the lumber. He
lamented that contrary to what Potencio had stated in court, it was the latter who
Petitioner failed to identify particular threats from the project itself; failed to show hired him to bring the log from the site to the sawmill where the same was to be sawn
clear environmental risk that threatens to prejudice the inhabitants of 2 or more into pieces.
cities/municipalities because bidding process itself cannot conceivably cause any
environmental damage Issue: Whether or not the petitioner is guilty for the possession and transportation of
mahogany lumber?

Ruling:

Yes. The petioner is guilty for the possession and transportation of mahogany lumber.
Petitioner and Potencio were caught in flagrante delicto transporting, and thus in
possession of, processed mahogany lumber without proper authority from the DENR.
Section 68 of P.D. No. 705, as amended by E.O. No. 277, criminalizes two distinct and
separate offenses, namely: (a) the cutting, gathering, collecting and removing of
timber or other forest products from any forest land, or timber from alienable or
disposable public land, or from private land without any authority; and (b) the
possession of timber or other forest products without the legal documents required
under existing laws and regulations.
It is thus clear that the fact of possession by petitioner and Potencio of the subject Duplicity of charges simply means a single complaint or information charges more
mahogany lumber and their subsequent failure to produce the requisite legal than one offense, as Section 13 of Rule 11020 of the 1985 Rules of Criminal Procedure
documents, taken together, has already given rise to criminal liability under Section clearly states:
68 of P.D. No. 705, particularly the second act punished thereunder.
Duplicity of offense. – A complaint or information must charge but one offense,
John Eric Loney, Steven Paul Reid and Pedro Hernandez vs People of the Philippines except only in those cases in which existing laws prescribe a single punishment for
(Ponente: Carpio) various offenses.

Doctrine: Duplicity of charges means a single complaint or information charges more In short, there is duplicity (or multiplicity) of charges when a single Information
than on offense. The filing of several charges is proper. A single act or incident might charges more than one offense.21
offend two or more entirely distinct and unrelated provisions of law thus justifying the
prosecution for more than one offense. The only limit is double jeopardy. Under Section 3(e), Rule 11722 of the 1985 Rules of Criminal Procedure, duplicity of
offenses in a single information is a ground to quash the Information. The Rules
Facts: Loney, Reid and Hernandez are the President, CEO and Senior Manager and prohibit the filing of such Information to avoid confusing the accused in preparing his
Resident Manager for Mining Operation of Marcopper in Marinduque. Marcopper defense.23 Here, however, the prosecution charged each petitioner with four offenses,
built concrete plug at the tunnels discharging tons of tailing into Boac and Makalupnit with each Information charging only one offense. Thus, petitioners erroneously
rivers. invoke duplicity of charges as a ground to quash the Informations. On this score
alone, the petition deserves outright denial.
DOJ then filed separate charges against the petitioners in MTC Marinduque for
violation of Art. 19 of PD 1067 or the Water code of the Philippines, Section 8 of PD As early as the start of the last century, this Court had ruled that a single act or
984 or the National Pollution Control Decree, Section 108 of RA 7942 or the incident might offend against two or more entirely distinct and unrelated provisions
Philippine Mining Act of 2005 and Art. 365 of the RPC for reckless imprudence of law thus justifying the prosecution of the accused for more than one offense.24 The
resulting in damage to property. only limit to this rule is the Constitutional prohibition that no person shall be twice
put in jeopardy of punishment for “the same offense.”25 In People v. Doriquez,26 we
Petitioners moved to quash the information saying that the (1) information was held that two (or more) offenses arising from the same act are not “the same” —
duplicitous for it charges more than one offense for a single act, (2) that Loney and
Reid were not yet officers when this incident took place and (3) that the informations x x x if one provision [of law] requires proof of an additional fact or element which the
contain allegations which constitute legal excuse or justification. other does not, x x x. Phrased elsewise, where two different laws (or articles of the
same code) define two crimes, prior jeopardy as to one of them is no obstacle to a
MTC: partially granted the quashing of the informations for violation of PD 1067 and prosecution of the other, although both offenses arise from the same facts, if each
PD 984 but maintained violation of RA 7942 and RPC. MTC then issued a crime involves some important act which is not an essential element of the
consolidated order in so far as the offense against RPC. With such, petitioners filed a other.27 (Emphasis supplied)
petition for certiorari with RTC-Marinduque assailing the Consolidated Order.
Here, double jeopardy is not at issue because not all of its elements are
RTC: granted appeal but denied the petition for certiorari. Consolidated Order was present.28 However, for the limited purpose of controverting petitioners’ claim that
affirmed and ordered the reinstatement of the informations pertaining to the violation they should be charged with one offense only, we quote with approval Branch 94’s
of PD 1967 and PD 984. Petitioners filed a petition for certiorari with the CA alleging comparative analysis of PD 1067, PD 984, RA 7942, and Article 365 of the RPC
grave abuse of discretion reiterating the defense that the informations were made out showing that in each of these laws on which petitioners were charged, there is one
from a single act. essential element not required of the others.
CA: affirmed RTC People vs. Dator
Issues: Whether all the charges filed against petitioners except one should be quashed Facts:
for duplicity of charges and only the charge for Reckless Imprudence Resulting in
Damage to Property should stand. Police officers confiscated pieces of lumber from an Isuzu cargo for failure of the
driver, accused Benito Genol, to show the required documents for the proper
Ruling: No duplicity. Duplicity of charges means a single complaint or information transport of the pieces of lumber consisting of forty-one (41) pieces of Dita lumber
charges more than on offense. The filing of several charges is proper. A single act or and ten (10) pieces of Antipolo lumber with a total volume of 1,560.16 board feet.
incident might offend two or more entirely distinct and unrelated provisions of law
thus justifying the prosecution for more than one offense. The only limit is double Pastor Telen, owner of lumber, testified that the lumber will be used in renovating his
jeopardy. residence. Boy Leonor, who was the Officer in Charge of CENRO Maasin, Southern
Leyte allegedly allowed Telen to cut the aging Dita trees only. According to Telen, WON the seizure of the vessel, its equipment and dynamites therein was valid.
Leonor assured him that a written permit was not anymore necessary before he could
cut the Dita trees, which are considered soft lumber, from the private land of his HELD:
mother, provided the same would be used exclusively for the renovation of his house
YES. Search and seizure without search warrant of vessels and aircrafts for violations
and that he shall plant trees as replacement thereof, which he did by planting
of the customs laws have been the traditional exception to the constitutional
Gemelina seedlings.The trial court convicted Pastor Telen of violation of Sec 68 of PD
requirement of a search warrant, because the vessel can be quickly moved out of the
No. 705 which Telen appealed.
locality or jurisdiction in which the search warrant must be sought before such
Issue: warrant could be secured; hence it is not practicable to require a search warrant
before such search or seizure can be constitutionally effected. The same exception
WON Legal Documents / Permit is still required for cutting/transporting the soft should apply to seizures of fishing vessels breaching our fishery laws. They are usually
lumber. equipped with powerful motors that enable them to elude pursuing ships of the
Philippine Navy or Coast Guard. Under our Rules of Court, a police officer or a private
Held: individual may, without a warrant, arrest a person(a) who has committed, is actually
committing or is about to commit an offense in his presence; (b) who is reasonably
The Supreme Court upheld the conviction.
believed to have committed an offense which has been actually committed; or (c) who
The fact of possession by the appellant of the subject lumber, as well as his is a prisoner who has escaped from confinement while serving a final judgment or
subsequent failure to produce the legal documents as required under existing forest from temporary detention during the pendency of his case or while being transferred
laws and regulations constitute criminal liability for violation of Presidential Decree from one confinement to another. In the case at bar, the members of the crew of the
No. 705, Section 68. two vessels were caught in flagrante illegally fishing with dynamite and without the
requisite license. Thus their apprehension without a warrant of arrest while
The appellant stands charged with the crime of violation of Section 68 of PD No. 705, committing a crime is lawful. Consequently, the seizure of the vessel, its equipment
a special statutory law, and which crime is considered mala prohibita. In the and dynamites therein was equally valid as an incident to a lawful arrest.
prosecution for crimes that are considered mala prohibita, the only inquiry is whether
or not the law has been violated. The motive or intention underlying the act of the MUSTANG LUMBER, INC VS. CA
appellant is immaterial for the reason that his mere possession of the confiscated
(J. Davide, Jr., 1996) [RULE 11 – ARREST]
pieces of lumber without the legal documents as required under existing forest laws
and regulations gave rise to his criminal liability.

Under the DENR Administrative Order No. 78, Series of 1987, a certification from the DOCTRINE: Search of a moving vehicle is one of the five doctrinally accepted
CENRO concerned to the effect that the forest products came from a titled land or tax exceptions to the constitutional mandate[34] that no search or seizure shall be made
declared alienable and disposable land must still be secured to accompany the except by virtue of a warrant issued by a judge after personally determining the
shipment. This the appellant failed to do, thus, he is criminally liable under Section 68 existence of probable cause. The other exceptions are (1) search as an incident to a
of PD No. 705 necessitating prior acquisition of permit and “legal documents as lawful arrest, (2) seizure of evidence in plain view, (3) customs searches, and (4)
required under existing forest laws and regulations.” consented warrantless search.[35]
Roldan vs. Arca (nasa book ito)

FACTS: FACTS: On 1 April 1990, Special Actions and Investigation Division (SAID), acting on
information that a huge pile of narra flitches, shorts, and slabs were seen inside the
Respondent company filed a case against Roldan, Jr. for the recovery of fishing vessel
lumberyard of Mustang Lumber, conducted a surveillance at Mustang lumberyard.
Tony Lex VI which had been seized and impounded by petitioner Fisheries
The team saw a truck loaded with lauan and almaciga lumber coming out of the
Commissioner through the Philippine Navy. The CFI Manila granted it, thus
lumberyard. Since the driver could not produce the required invoices and transport
respondent company took Possession of the vessel Tony Lex VI.- Petitioner requested
documents, the team seized the truck together with its cargo and impounded them at
the Philippine Navy to apprehend vessels Tony Lex VI and Tony Lex III, also
DENR compound. On 3 April 1990, RTC Valenzuela issued a search warrant. On same
respectively called Srta. Winnie and Srta. Agnes, for alleged violations of some
day, the team seized from the lumberyard narra shorts, trimmings and slabs, narra
provisions of the Fisheries Act. On August 5 or 6, 1965, the two fishing boats were
lumber, and various species of lumber and shorts. On 4 April 1990, team returned to
actually seized for illegal fishing with dynamite.
lumberyard and placed under administrative seizure (owner retains physical
ISSUE: possession of seized articles, only an inventory is taken) the remaining
lumber because Mustang Lumber failed to produce required documents
upondemand. Upon recommendation of SAID Chief Robles, DENR Sec Factoran and a long fishing net already spread over the water. The team boarded the vessel and
suspended Mustang Lumber¶s permit and confiscated in favor of the gov¶t the seized apprehended her captain, a Filipino, and a crew composed of three Filipinos and three
articles. Mustang Lumber filed for a TRO against Factoran and Robles, and Chinese. Also arrested were 17 Chinese fishermen aboard F/V Sea Lion.
questioned the validity of the April 1 and 4 seizure. RTC held that the warrantless
seizure on April 1 is valid as it comes within the exceptions where warrantless seizure
is justified (search of a moving vehicle), and April 4 seizure was also valid pursuant to
Various charges were thereafter filed as follows: (1) Violation of Section 97[7] of
the search warrant issued on April 3. CA affirmed. Mustang lumber filed a petition for
Republic Act (RA) No. 8550[8] against all those arrested, docketed as I.S. No. 2004-
review on certiorari.
032; (2) Violation of Section 90[9] of the same law against the captain of F/V Sea
Lion, the Chief Engineer, and the President of the corporation which owned said
vessel, docketed as I.S. No. 2004-061; and (3) Violation of Section 27(a) and (f)[10] of
ISSUES: a) WON the search and seizure on April 4 was valid. RA 9147[11] and of Section 87[12] of RA 8550 against all those arrested and the
President of the corporation which owned the vessel, respectively docketed as I.S.
Nos. 2004-68, 2004-69, and 2004-70.
HELD: Yes. The search and seizures made on April 1, 3, 4 were all valid. valid. (1) The Provincial Prosecutor of Palawan nevertheless found probable cause for the
April 1 search was conducted on a moving vehicle, which could be Lawfully conducted remaining charges[13] but only against the 17 Chinese fishermen.[14] This was after
without a search warrant. (2) The search on April 4 was a continuation of the search it was found out that the crew of F/V Sea Lion did not assent to the illegal acts of said
on April 3 done under and by virtue of the search warrant issued on 3 April 1990 by 17 Chinese fishermen who were rescued by the crew of the F/V Sea Lion from a
Exec Judge Osorio. Under ROC Rule 126 Sec 9, a search warrant ahs a lifetime of 10 distressed Chinese vessel. The prosecutor concluded that the crew, unarmed,
days. Hence, it could be served at any time within the said period, and if its object or outnumbered and hampered by language barrier, acted only out of uncontrollable fear
purpose cannot be accomplished in 1 day, the same may be continued the following of imminent danger to their lives and property which hindered them from asserting
day or days until completed, provided it is still within the 10-day period. their authority over these Chinese nationals. The Fishing Vessel F/V Sea Lion 1 as well
as the fishing paraphernalia and equipments used by the accused in committing the
crime [are] hereby ordered confiscated in the favor of the government.
DISPOSITIVE: Petition is denied. CA did not commit any reversible error in affirming
Petitioner contends that F/V Sea Lion should be released to it because it is the
RTC judgment. Search and seizure done was valid
registered owner of said vessel and her captain and crew members were not among
those accused of and convicted in Criminal Case Nos. 18965 and 19422. To buttress
its contention, petitioner invokes Article 45 of the Revised Penal Code which provides:

RULE 12
ART. 45. Confiscation and forfeiture of the proceeds or instruments of the crime. -
SEA LION FISHING CORPORATION, PETITIONER, VS. PEOPLE OF THE Every penalty imposed for the commission of a felony shall carry with it the forfeiture
PHILIPPINES, RESPONDENT. of the proceeds of the crime and the instruments or tools with which it was
committed.
DEL CASTILLO, J.:

Such proceeds and instruments or tools shall be confiscated and forfeited in favor of
When an instrument or tool used in a crime is being claimed by a third-party not the Government, unless they be the property of a third person not liable for the
liable to the offense, such third-party must first establish its ownership over the same. offense, but those articles which are not subject of lawful commerce shall be
Facts: destroyed. (Emphasis supplied.)

In response to fishermen's report of poaching off Mangsee Island in Balabac, Petitioner also claims that it was denied its right to due process of law when it was not
Palawan, a combined team of Philippine Marines, Coast Guard and barangay officials notified of the judicial proceedings relative to the confiscation of the fishing vessel. It
conducted search and seizure operations therein. There they found F/V Sea Lion argues that such notification was necessary considering that the provincial prosecutor
anchored three nautical miles northwest of Mangsee Island. Beside it were five boats was duly informed of its claim of ownership of the F/V Sea Lion.
Issue:

Whether the forfeiture of F/V Sea Lion in favor of the government was proper The public prosecutor filed, on 24 March 2000, a motion for reconsideration. Instead
of deciding the pending motion, respondent Judge deferred its resolution until after
Ruling: the arraignment of the accused and the pretrial of the case would have been had.
Yes. The government was correct when it forfeited F/V Sea Lion since its motion was
only filed after the judgment has been rendered and it failed to seek all remedies given
the sufficient time to do so. Special Prosecutor Romeo B. Senson filed an administrative complaint against
respondent Judge for Gross Misconduct with Prayer for Preventive Suspension
The lack of any factual basis for the third-party claim of ownership was not cured at asseverating that the release of the evidence had exposed said evidence to tampering
all when the petitioner filed its motion for reconsideration before the trial court. At and that the deferment of the resolution of the motion for reconsideration virtually
that point, evidence should have been adduced to support the petitioner's claim (so resulted in the undue archive of the case.
that a new trial or reopening of the trial on the confiscation aspect should have been
prayed for, rather than a mere motion for reconsideration.) There is firstly the factual
issue - to be proved by proper evidence in order to be properly considered by the court
- that the vessel is owned by a third party other than the accused. Article 45 required In his comment, respondent contended that Republic Act No. 8550, the law under
too that proof be adduced that the third party is not liable for the offense. After the which the accused were charged with having transgressed, did not provide for the
admission by the accused through their guilty plea that the vessel had been used in seizure of the fishing paraphernalia pending trial and that the prosecution still could
the commission of a crime, we believe and so hold that this additional Article 45 prove the guilt of the accused beyond reasonable doubt even without the evidence
requirement cannot be simply inferred from the mere fact that the alleged owner is being presented since it had sufficient witnesses for the purpose.
not charged in the same case before the court.[

The lower court had jurisdiction over the case and the petitioner was not denied of
ISSUE: Whether the judge’s order in granting the motion is valid.
due process and gets it failed to comply with the other requirements provided in the
law.

SENSON v PANGILINAN RULING: NO, Evidently, the seizure of the fishing paraphernalia has been made as
being an incident to a lawful arrest. Rule 127, Section 12, of the Rules of Court
J. VITUG (RULE 12 – CUSTODY AND DISPOSITION OF SEIZED ITEMS)
provides:

DOCTRINE: All criminal actions commenced by a complaint or information are


SEC. 12. Search incident to lawful arrest.- A person lawfully arrested may be searched
prosecuted under the direction and control of the prosecutor. The seized items
for dangerous weapons or anything which may be used as proof of the commission of
ordered released by respondent Judge have not yet been offered in evidence; hence,
an offense, without a search warrant.
the prosecution, not the court, could still be deemed to be in the legal custody and to
have the responsibility over such items.

All criminal actions commenced by a complaint or information are prosecuted under


the direction and control of the prosecutor. The seized items ordered released by
FACTS: On 14 March 2000, several persons were apprehended for violation of Section
respondent Judge have not yet been offered in evidence; hence, the prosecution, not
86 of Republic Act No. 8550, also known as The Philippine Fisheries Code of
the court, could still be deemed to be in the legal custody and to have the
1998[1] by members of the Philippine National Police. The items seized from those
responsibility over such items.
arrested included (a) 1 unit fish net, … etc. On the same day, Criminal Case No.15019
against them was filed. Three days later, Danilo Alayon and Norma Villarosa,
asserting to be the co-owners of the M/B King Fisher that was used in the illegal
fishing activity, filed an Urgent Motion for Custody of Fishing Net, alleging that the The outcome of the criminal action will dictate the disposition of the seized
fish net which costs no less than P600,000.00 was left unattended at the beach property. If found to be contraband, i.e., articles the possession of which, without
exposed to the elements and movements of the sea which could cause its early more, constitutes a crime and the repossession of which would subject defendant to
deterioration and ultimate loss. Respondent Judge, despite the vigorous objection of criminal penalties and frustrate the express policy against the possession of such
the public prosecutor, granted the motion. objects, they will not be returned, but shall be confiscated in favor of the State or
destroyed, as the case may be. If not contraband, the property shall be returned Tally Sheets.
without undue delay to the person who appears from the evidence to be the owner or
rightful possessor.

WHEREFORE, the Court finds respondent Judge Heriberto M. Pangilinan GUILTY of Such omission is punishable under Sec. 68 of Presidential Decree (P.D.) No. 705
gross ignorance of the law, and he is hereby ordered to pay a fine of Ten Thousand otherwise known as the Revised Forestry Code. Thus, petitioner Atty. Robles issued a
(P10,000.00) Pesos with a warning that another infraction by him will be dealt with temporary seizure order and seizure receipt for the narra lumber and the six-wheeler
severely. truck.

Factoran VS. Court of Appeals On January 20, 1989, petitioner Fulgencio S. Factoran, then Secretary of
Environment and Natural Resources issued an order for the confiscation of the narra
G.R. No. 93540 lumber and the six-wheeler truck

FACTS

On August 9, 1988 two police officers of Marikina Police Station, Sub-Station III, Private respondents neither asked for reconsideration of nor appealed the said order
intercepted a six-wheeler truck carrying 4,000 board feet of narra lumber as it was to the Office of the President. Consequently, the narra lumber and six-wheeler truck
cruising along Marcos Highway. They apprehended the truck driver, private were forfeited in favor of the government and were later on advertised to be sold at a
respondent Jesus Sy, and brought the truck and its cargo to the Personnel public auction on March 20, 1989.
Investigation Committee/Special Actions and Investigation Division (PIC/SAID) of
DENR Office in Quezon City. There, petitioner Atty. Vicente Robles of the PIC/SAID
investigated them, and discovered the discrepancies in the documentation of the
On March 17, 1989, private respondents filed a complaint with prayer for the issuance
narra lumber.
of the writs of replevin and preliminary injunction and/or temporary restraining
order for the recovery of the confiscated items, and to enjoin the panned auction sale
of the subject narra lumber, respectively.
What were declared in the documents were narra flitches, while the cargo of the truck
consisted of narra lumber. In the documents, the plate numbers of the truck supposed
to carry the cargo bear the numbers BAX-404, PEC-492 or NSN-267, while the plate
On the same day, the trial court issued an order directing the parties to desist from
of the truck apprehended is NVT-881. Considering that the cargo is lumber, the
proceeding with the planned auction sale and setting the hearing for the issuance of
transport should have been accompanied by a Certificate of Lumber Origin, scale
the writ of preliminary injunction on March 27, 1989.
sheet of said lumber and not by a Certificate of Timber Origin. The Log Sale Purchase
Agreement presented is between DSM Golden Cup International as the Seller and
Bonamy Enterprises as the buyer/consignee and not with Lily Francisco Lumber
Hardware. On March 20, 1989, private respondents filed and Ex-Parte motion for Release and
Return of Goods and Documents (Replevin) supported by an Affidavit for Issuance of
Writ of Replevin and Preliminary Injunction and a Replevin Bond in the amount of
P180,000.00. The trial court granted the writ of replevin on the same day and
These are in violation of Bureau of Forestry Development (BFD) Circular No. 10
directed the petitioners "to deliver the xxx [n]arra lumber, original documents and
which requires possession or transportation of lumber to be supported by the
truck with plate no. NJT 881 to the custody of the plaintiffs and/or their
following documents:
representatives x x x".
Certificate of Lumber Origin (CLO) which shall be issued only by the District Forester,
or in his absence, the Assistant District Forester;
On March 22, 1989, the trial court issued a writ of seizure. However, petitioners
Sales Invoice;
refused to comply therewith. Sheriff David G. Brodett of Branch 80 of the RTC of
Delivery Receipt; and Quezon City, reported that the petitioners prevented him from removing the subject
properties from the DENR compound and transferring them to the Mobile Unit
compound of the Quezon City Police Force. He then agreed to a constructive On April 25, 1990, petitioners filed a motion for reconsideration of the foregoing
possession of the properties. On that same day, petitioners filed a Manifestation decision but it was subsequently denied by the Court of Appeals in its Resolution
stating their intention to file a counterbond under Rule 60 of the Rules of Court to dated May 18, 1990.
stay the execution of the writ of seizure and to post a cash bond in the amount of
P180,000.00. The trial court did not oblige the petitioners for they failed to serve a
copy of the Manifestation on the private respondents. Petitioners then made
Hence this petition.
immediately the required service and tendered the cash counterbond but it was
refused, petitioners' Manifestation having already been set for hearing on March 30,
1989.
ISSUE:

On March 27, 1989, petitioners made another attempt to post a counterbond but was
also denied for the same reason. Whether or not the RTC was correct in the issuance of a writ of replevin and the Court
of Appeals in dismissing the petition and lifting the preliminary injunction.

On the same day, private respondents filed a motion to declare petitioners in


contempt for disobeying the writ of seizure. The trial court gave petitioners 24 hours RULING:
to answer the motion. Hearing was scheduled on March 30, 1989.

No, Pursuant to Sec. 8 of P.D. No. 705, all actions and decision of the Director are
On March 29, 1989, petitioners filed with the Court of Appeals a Petition for subject to review, motu propio or upon appeal of any person aggrieved thereby, by the
Certiorari, Prohibition and/or Mandamus to annul the orders of the trial court dated Department Head whose decision shall be final and executory after the lapse of 30
March 20, 1989 and March 27, 1989. days from the receipt by the aggrieved party of said decision unless appealed to the
President. The decision of the Department Head may not be reviewed by the courts
except through a special civil action for certiorari or prohibition.
On March 30, 1989, the Court of Appeals granted petitioners temporary relief in the
form of a temporary restraining order (TRO).
It was observed by the Court that herein respondents never appealed the confiscation
order of the petitioner Secretary to the Office of the President.
On September 11, 1989, the Court of Appeals converted the TRO into a writ of
preliminary injunction upon filing by petitioners of a bond in the amount of
P180,000.00. The doctrine of exhaustion of administrative remedies is basic. Courts, for reasons of
law, comity and convenience, should not entertain suits unless the available
administrative remedies have first been resorted to and proper authorities have been
given an appropriate opportunity to act and correct their alleged errors, if any,
On March 30, 1990, the Court of Appeals lifted the writ of preliminary injunction and
committed in the administrative forum.
dismissed the petition. It declared that the complaint for replevin filed by the private
respondents complied with the requirements of an affidavit and bond under Sec. 1
and 2 of Rule 60 of the Revised Rules of Court, issuance of the writ of replevin was
mandatory. It was pointed out by the Court in Paat vs. Court of Appeals that the enforcement of
forestry laws, rules and regulations and the protection, development and management
of forest land fall within the primary and special responsibilities of the DENR. It held
that assumption of the trial court of a replevin suit constitutes an encroachment into
As for the contempt charges against the petitioners, the Court of Appeals believed that
the domain of the administrative agency's prerogative. The doctrine of preliminary
the same were sufficiently based on a written charge by private respondents and the
jurisdiction does not warrant a court to arrogate unto itself the authority to resolve a
reports submitted by the Sheriff.
controversy the jurisdiction over which is initially lodged with an administrative body
of special competence.
However, herein petitioners did not a motion to dismiss on the ground of non- Finally. The writ or seizure and the writ of replevin was issued by the trial court in
exhaustion of administrative remedies. Thus, it is deemed waived. grave abuse of its discretion. Thus, disobedience thereto cannot constitute indirect
contempt of court which presupposes that the court order thereby violated was valid
and legal. Without a lawful order being issued, no contempt of court could be
committed.
Nonetheless, the Court finds the petition impressed with merit.

The instant petition is granted. The decision of the Court of Appeals dated March 30,
First. A writ of replevin does not issue as a matter of course upon the applicant's filing
1990 and its Resolution dated May 18, 1990 were set aside. Respondent presiding
of a bond and affidavit, as the Court of Appeals has wrongly put it. The mere filing of
judge of the RTC of Quezon City was permanently enjoined from enforcing the Orders
an affidavit, sans allegations therein that satisfy the requirements of Section 2 Rule 60
dated March 20, 1989 and March 22, 1989, or if said orders had already been issued,
of the Revised Rules of Court, cannot justify the issuance of a writ of replevin.
said respondent judge was directed to render judgement of forfeiture of replevin bond
Wrongful detention of the properties sought in an action for replevin must be
filed by private respondents. Finally, the said respondent judge is hereby permanently
satisfactory established. If only mechanistic averment thereof is offered, the writ
enjoined from further acting on the Motion for Contempt filed by private respondents
should not be issued.
against petitioners.

In the case at bar, the taking of the subject property was within the administrative
authority of the Secretary as provided by Section 68-A of P.D. No. 705. Thus, it is not
wrongful and does not warrant the issuance of a writ of replevin prayed for by the
private respondents.

Second. By virtue of the confiscation order by petitioner Secretary, the subject


properties of private respondents were held in custodia legis and hence, beyond the
reach of replevin. Property lawfully taken by virtue of legal process is deemed to be in
custodia legis. So basic is this doctrine that it found inclusion in the 1997 amendments
introduced to the Rules of Civil Procedure.

Third. Petitioner Secretary's authority to confiscate forest products under SEction 68-
A of P.D. No. 705 is distinct and independent of the confiscation of forest products in
a criminal action provided for in Section 68 of P.D. No. 705.

Fourth. SEction 80 of P.D. No. 705 which requires the delivery of the seized forest
products within six (6) hours from the time of the seizure to the appropriate official
designated by law to conduct preliminary investigations applies only to criminal
prosecutions provided for in Section 68 and not to administrative confiscation
provided for in Section 68-A.

Fifth. Nothing in the records supports private respondents' allegation that their right
to due process was violated as no investigation was conducted prior to confiscation of
their properties.

You might also like