Professional Documents
Culture Documents
ABSTRACT - The report presents the structures' analysis of the railway station’s building in the
permafrost and high seismic activity. Fеаturе of the is that besides saving permafrost bу the fist principle of
construction, рile foundation construction of high raft using performs the function of seismic isolation. The
building considered in the report represents the two-storeyed frame and panel building. The bearing vertical
designs (columns) are made of monolithic reinforced concrete with a section of 400 x 400 mm. Designs of
interfloor overlappings and coverings are executed from ferroconcrete the plates 220 mm thick connected
monolitno. The design of the pile base is presented in the form of ferroconcrete piles with a high grillage.
Length of piles is 10 meters. Research was carried out on the elementary models and on the models
considering spatial work of the building. In researches various programs complexes were used. During the
executed research criteria at which the pile base can be used as a seismoisolation element are established.
For increase of reliability of behavior of the building at an earthquake the special damping elements are
entered into a design of the base. The analysis settlement and theoretical researches of the considered
seismoprotection type is presented in the report.
Keywords: transport frame-panel building, piles foundation with high grillage, permafrost,
seismicity
1 INTRODUCTION
2 INVESTIGATION METHODOLOGY
Investigation was carried out upon the example of transport large-panel building with rigid
structural system, which is constructed in permafrost regions according to permafrost keeping
principle. The building is two-storeyed, framed-panel, with plane sizes of 18 х 42 m. Load-bearing
vertical structures are designed in the form of columns with cross-section of 40 х 40 cm made of
cast-in-situ reinforced concrete. Floors and revetment are made of precast concrete slabs, 22 cm
thick, joined monolithically. Foundation is in the form of piles with high grillage. Piles foundation
components were considered as elements of yielding brace between the base and superstructure of
the building, and this allowed to realize the seismic isolation principle. At that, it was assumed that
the seismic isolation efficiency can be achieved only in case, if seismic load upon the building is
decreased by two times or more [2]. Thereupon, it was necessary to define, what pile design was to
be used, and its free length, needed for provision of seismic isolation function. Piles with different
cross-sections 30 х 30 and 40 х 40 cm, made of precast concrete, were considered. Piles are
rigidly connected with grillage, thickness of grillage was taken equal to 40 cm. Grillage is a cast-in-
situ reinforced concrete slab, upon which building's superstructure is placed.
Investigation was carried out on the basis of different calculation models, taken in the form
of single-mass and multiple-mass models with rigid fixing in the base. Seismic loads were
determined within linear-spectrum calculation procedure with consideration of relevant normative
documents for 7, 8 and 9 point intensity zone. Calculated pile length varied from 2.5 to 8 m.
In the process of investigation it was revealed that with the increase of pile's free length the
building natural period increases, and this leads to significant reduction of seismic load upon the
building. This expected result testifies to the positive effect, which is achieved in case of seismic
isolation. At that, as is known [2], efficient tuning of seismic isolation should be within the limits of
Т ≈ 2 s. Such period can be provided only in case of significant pile's free length (5 m and more).
However, increase of pile's free length, in its turn, leads to increase of reinforcement area [3].
It is possible to obtain the most acceptable results at 7-point seismicity and reinforced
concrete piles with cross-section of 40 x 40 cm, that is to achieve the effect, at which it is possible
to keep the bearing capacity of piles and achieve their significant yielding simultaneously. During
investigation it was found that with the increase of pile foundation yielding the increase of stresses
in piles and grillage junctions, as well as relative displacements at grillage level are observed. In
case of earthquake intensity over 7 points the keeping of seismic isolation effect with provision of
bearing capacity can be achieved only by changing of pile design, for instance, by using tubular
elements or additional introduction of energy-absorbing components, for instance, in the form of
dry friction dampers, into pile foundation structure.
3 CONCLUSIONS
Carried out investigations show that the pile foundation with high grillage, which is used for
the realization of principle I – keeping of permafrost, van be used simultaneously as a seismic
isolation component. At that, the pile foundation design should provide their significant yielding
and bearing capacity simultaneously. It is revealed that piles free length should reach 6 m, at that,
reinforcement ratio is within the limits from 3 to 4%.
Investigations showed that in case of ordinary reinforce concrete piles of 40 x 40 cm size
and seismic intensity of 7 points it is possible to obtain the expected seismic isolation effect with
keeping of bearing capacity. However, in case of earthquake intensity of 7 and more points increase
2
of reinforced concrete pile flexibility leads to significant increase of reinforcement area. Thereupon
the most appropriate variant is the use of other pile design or introduction of additional energy
absorbing component in the form of dry friction dampers into pile foundation structure. In case of
use of pile foundation with high pile grillage as seismic isolation components one should pay
special attention to their joints with grillage, as the increase of pile foundations flexibility leads to
increase of stresses in connection joints and requires special design solution.
References